ENCLOSURE 1
'i 1
q Georgia. Power Company Docket Nos.: 50-321 and 50-366 Hatch Nuclear Plant License Nos.:- DPR-57 and NPF-5 j
I L
During' the Nuclear Regulatory Commission (NRC) inspection conducted on
{
June 1-5, 11, 12 and 15, 1987, a violation of NRC requirements was identified.
The violation involved failure to calculate lower limits of. detection for plant
' effluents' according to plant technical specifications'.
In accordance with the
" General Statement of Policy and Procedure for NRC Enforcement Actions,'E
-i 10 CFR Part 2,' Appendix C (1986), the violation is listed'below:
Technical Specifications 4.15.1.1 (Unit 1) and 4.11.1.1.1 (Unit 2) i require that radioactive liquid effluents shall be sampled and analyzed according to the sampling analyses programs of' Tables 4.15.1 (Unit 1).
j and 4.11.1-1 (Unit 2).
Footnotes to Tables 4.15.1-1 and 4.11.1-1 define j
the lower limit of detection -(LLD) per Table. 4.16.1-1.(Unit.1)
Specification 4.16.1.
Technical Specifications 4.15.2.1.2 (Unit 1)-- and 4.11.2.1.2 " (Unit 2) require :that dose rates due.to radioactive materials other than noble
~
. gases in gaseous effluents shall be determined by obtaining representative.
i samples and performing analyses in accordance with the sampling and analysis program specified 'in Tables 4.15.2-1 (Unit 1) and 4.11.2-1 (Unit 3
.2).
Footnotes to Tables 4.15.2-1 and 4.11.2-1 define the lower limit of j
detection per Table 4.16.1-1 (Unit 1) Specification 4.16.1.
1 Technical Specification Table.4.16.1-1 (Unit 1) requires that the " delta T" used in the LLD equation be defined as the elapsed time between the midpoint of the sample collection period and the time of counting for plant effluents.
Contrary to the above, the licensee's methodology to calculate effluent LLD's was incorrect in that the elapsed time, " delta T," was calculated using the end' point of the sampling period instead of the midpoint.
.l This is a Severity Level V violation (Supplement IV).
l 8706300400 870624
' DR ADOCK 0500 1
. v.
,}",
. Docket Nos.: 50-321-and 50-366
. Georgia Power Company.'
2:
- Hatch Nuclear _. Plant- '
-License Nos.:
~Since; Georgia.-Power has: completed corrective actions regarding this item, a
. written response will not be required.-
FOR THE-NUCLEAR REGULATORY COMMISSION kk uglas M. C 11 ns, Chi fi Emergency Preparedness ~ nd.
1 Radiological: Protection Branch Division of Radiation Safety 1
and Safeguards-f Dated gt Atlanta,-: Georgia' this-
~ day of June 1987 I