. 55 ARSONS Daniel L. Curry, %ce President. Nuciear services Parscms Energ & Chemicalo Group Inc.
2G75 Morgantown Road
- Reading. Pennsylvania 19607 * (610) 855-2366
- Fax: (610) 855-2602 April 6,1998 Docket No. 50-336 Parsons NUM2-PPNR-1325-L U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Millstone Nuclear Power Station Unit No. 2 Independent Corrective Action Verification Program (ICAVP)
Gentlemen:
Pursuant to your recent request, attached please find the Millstone Unit 2 ICAVP Bi-Weekly Report for week ending April 3,1998.
Please call me at (610) 855 2366 if you have any questions.
Sincerely,
/$P Daniel L. Cury Parsons ICAVP Project Director DLC:cvb Attachments 1.
Bi-Weekly Report ec:
E. Imbro (2) - USNRC H. Eichenholz - USNRC R. Laudenat - NNECo J. Fougere - NNECo Rep. Terry Concannon - NEAC Project Files
()
9804130375 980406
^
PDR ADOCK 05000336 P
PDR PAGE1 Encompass g
PPNR1325. doc
(
PARSONS l
Daniel L Curry, vice Preent. Nuc.iear services Pars *>ns Enctgy & Chemicais Group Inc 2675 Morgantown Road
- Reading. Pennsylvania 19607 + (610) 855-2366
- Far (610) 855-2602 April 6,1998 Doc. ID: NUM2-PPNU-1324-L Mr. Richard Laudenat Northeast Nuclear Energy Company Millstone Nuclear Power Station Unit 2 P. O. Box 128 Waterford, CT 06385 Re:
Millstone Unit 2 ICAVP Bi Weekly Progress Report
Dear Mr. Laudenat:
The following represents a bi-weekly progress report for work completed on Millstone Unit 2 ICAVP for the week ending April 3,1998.
Project Schedule: Forecasted discovery completion dates noted in Tier summaries presented below.
i Tier 1 - System Vertical Slice Reviews HPSI system discovery complete. Corrective Action Review and DR closcout still pending.
AFW system review is moving forward with recent receipt of CST information. Discovery complete forecast to be June 15,1998.
t RRC system review in progress. Forecast discovery complete June 5,1998.
EDG system review in progress. Forecast discovery complete June 12,1998.
i impact of programs associated with EQ, HELB, SBO are on-hold pending receipt ofinformation from e
NNECo. Current information indicates:
=> SB0 target date has slipped to April 7,1998. Schedule for completing SB0 effort is 8 weeks after receipt ofinformation.
l
=> HELB/EQ - limited information will be available from NNECo by mid-May, final information is expected mid-November. Schedule options associated with this change are still being evaluated.
Impact of delayed accident reanalysis on Tier 1 systems review is under evaluation.
=
Tier 2 - Accident Mitigation System Review Closure of preliminary DRs, UIRs and RAls is required to complete Tier-2 review. See Attachment B for
=
details.
Design inputs have been received for 8 of the 12 DDEv being reanalyzed by NNECo. Design inputs for the remaining 4 DBEv are scheduled to be transmitted to Parsons by April 15,1998.
Short term (April) staffing reductions initiated based upon slippage of projected reanalysis completion dates.
Tier 2 schedule revised based on NNECo " Accept Analysis" date of April 30,1998. Tier 2 discovery complete forecast as June 19,1998.
b l
Mr. Richard Laudenat Northeast Nuclear Energy Company NUM2-PPNU-1324-L April 6,1998 '
Analysis review - 29 Design Basis Events (DBEv) 28 DBEv Analyses Reviewed 1
11 DBEv Validations in Progress 10 DBEv Discovery Complete Tier 3 - Process Review Tier 3 discovery complete date forecasted for April 22, ; ' (Completion date of outstanding Tier 3 e
RAls plus one week.). This does not include vendor techmcal manual reviews.
Report preparation in progress for completed sample areas.
EWR reviews completed during this report period.
Reviews in progress for specification revision, drawing revision, NCRs and ASME Section XI Repairs.
Vendor manual review on hold until NNECo can identify the population of Unit 2 manuals to be updated and the NNECo schedule for updates and validation of procedures.
Other Activities:
)
Phone conferences completed on March 24,26,31 and April 2,1998.
e Discrepancy Reports See Attachment A for details RAI (Status)
- Totalissued 1320 l
41 greater than 2 weeks / total outstanding 94 Tier 1 EQ Program (RAI-l105)
HPSI (RAI-766, RAI-921, RAI-1054, RAI-l179) e AFW Calculations (RAI-1087)
RRC (RAI l125) e Tier 2 Validation (RAI-l 115, RAI-1251, RAI 1314) l Tier 3 (RAI-l168, RAI-1234, RAI-1241, RAI-1267) l l
Should you have any questions on the contents of this progress report, do not hesitate to contact me at (610) 855-2366.
Sincerely, fM k<S Daniel L. Curry Project Director DLC/cyb Attachment cc:
J. Fougere M. J. Akins R. T. Glaviano E. Imbro (USNRC)
J. L. Caldwell J. F. Hilbish E. A. Blocher W. L. Dobson Project Records 2 of 2 Encompass Letter PPNU1324. Doc
2 Attachment A to April 3,1998 Bi-weekly Report Discrepancy Report Summary and Status 489 Preliminary DR Numbers issued by Parsons 412 Preliminary DRs approved of which 15 determined to be invalid 100 Responses received to date from NU 35 DRs CLOSED 56 DRs OPEN 09 DRs IN-PROGRESS (Awaiting revised response from NU on 5 DR's)
I l
Of the 35 Valid and Closed Discrepancies resolutions 15 Confirmed Discrepancies 12 Previously Identified by NNECo 8 Non-discrepant Conditions Of the 15 Confirmed Discrepancies 0 - Level 1 0 - Level 2 0 - Level 3 15 - Level 4 l
l l
r I
(
l Attachment B: Tier-2 AMSR Validation Open Items (Status as of 4/03/98)
This attachment lists information needed to complete validation of the Critical Design Characteristics associated with the FSAR Chapter 14 Accident Analyses.
Preliminary Discrepancy Reports - Provide completion schedule and closure package for the listed DRs.
DR-027 Enclosure Building Ventilation System DR-033 HPSI Flow DR-045 Deboration During Startup DR-202 MSSV Accumulation DR-205 Pressurizer Safety Valve Accumulation DR-313 RPS RC Low Flow Trip Setpoint NNECo Identified Items - Provide completion schedule and closure package for the listed items.
Note: the listed items may have related UIRs, CRs, etc.
i UIR-288 RCS Pressure Uncertainty UIR-929 Pressurizer Level Revised FSAR Chapter 14 Analyse _s - The below table lists events being reanalyzed by NNECo and identifies information needs to complete the Tier-2 validation.
Event.
Design NNECo Accept ~
Analysis Revised Inputs Ana!/ s (ECD) 14.1.3 Increase in Steam Flow 27 Feb 98 Rs 15 Apr 98 RAI(later)
I 14.1.5 Main Steam Line Break (RCS Analysis)
'27 Feb 98 R?
15 Apr 98 RAI(later)
L14.2!14 sLoss'ofExternalLoads 4
?27 FebL98 R4 Completek
'23 Mar 98'R (14.2'.'41 J Closure ofMain Steam Isolation.Valvei 27 Feb 98 R4 Complete?
23 Mar 98 Rt 14.2.7 Loss of Normal Feedwater Flow 27 Feb 98 R?
31 Mar 98 RAI(later) 14.4.1 Startup Rod Withdrawal Accident
-24 Mar 98.R
15 Apr 98 RAI(later) 14.4.6 CVCS Malfunction Causing RCS RAI-l115 30 Apr 98 RAI (later)
Deboration 14.6.5.1 Large Break LOCA (RCS Analysis)
RAI-l115 30 Apr 98 RAI(later) 14.6.5.2 Small Break LOCA RAI-l115 15 Apr 98 RAI(later) 14.6.3 Steam Generator Tube Rupture RAI-1115 31 Mar 98 RAI(later) 14.8.2.'l 1 iContainment' Analysis (MSLB)
Received Interim" 6 Mar 98 R1 (14.8.2.1) Containment High Pressure Trip During RAI-1) 15 15 Apr 98 RAI (later)
MSLB 14.8.2.2 E Containment' Analysis (LOCA) -
Received Complete' 6 Mar 98 R :
RC Pump Coastdown Curve RAI-l115 15 Apr 98 RAI (later) l Note: R = Documents received by Parsons on indicated date Reauests for AdditionalInformation RAls: 1251 & 1314 (New Item)