Technical Assistance for Preservice Insp, Monthly Ltr Rept for Aug & Sept 1986
ML20215M891
Person / Time
Site: South Texas, Comanche Peak, 05000000
Issue date: 10/20/1986
From: Poucher F
ROCKWELL INTERNATIONAL CORP.
To: Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CON-FIN-A-0700, CON-FIN-A-700 86ETEC-DRF-2081, NUDOCS 8611030417
Download: ML20215M891 (3)


Text

e

. '*o

(%

( ' oct 2 7ses Energy Technology Engineering Center Rocketdyne Division l

Rock well lnternational Corporation Rockwell canoga park.ca$fo~mYaME International J

(818)700-8200 Operated for U.S. Department of Energy In Reply Refer to:

86ETEC-DRF-2081 October 20, 1986 Mr. T. F. Westerman, Chief Reactor Safety Branch U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011

Subject:

Monthly Letter Report on ETEC Technical Assistance to U.S. NRC, Region IV, for Preservice Inspection, FIN A0700

Dear Mr. Westerman:

Enclosed is a monthly business letter which summarizes the work performed by ETEC on the subject program during the months of August & September 1986.

Sincerely yours, F. W. Poucher Programs Manager Energy Programs Energy Technology Engineering Center

/gb

Enclosure:

as noted cc:

(w/ encl.)

R. Ireland, NRC, Region IV D. M. Meyer, NRC, Region IV M. E. Long, ETEC S0 D. Tomlinson, NRC, Region IV h

e6110 M N g 6

hh A

__~ __. -.

(

s Attachment to: 86ETEC-DRF-2081 Page 1 of 2 4

MONTHLY REPORT Technical Assistance for Preservice Inspection FIN: A0700 NRC Dockets:

50-498/50-446 Contract No. DE-AC03-76-SF00700 Principal Investigator::

R. Fuhrer Period of Performance: 05-30-86 tc 09-30-86 Reporting Period: August & September 1986 I.

PROJECT STATUS Task Order A - Review of Preservice Inspection Activities A.

Task

Description:

This task establishes a team of qualified 4

individuals to perform and report the review results of Preservice Inspection Activities at the South Texas Project, Unit 1, and at Comanche Peak, Unit 2.

These reviews are accomplished in,accordance with four NRC supplied inspection modules.

i B.

Efforts Completed During This Period: Assembled and furnished supplemental information (

Reference:

86ETEC-DRF-1764, dated September 04,1986) to be incorporated into the Draft Report which was previously transmitted under 86ETEC-DRF-1438, i

July 23, 1986.

C.

Problems or Delays Encountered:

None D.

Plans for the Next Reporting Period:

Provide services as i

necessary to finalize the review report for the South Texas Project, Unit 1.

I II.

FINANCIAL STATUS l

i.

A.

Total Cost of the Project:

l The status of the total cost of the project is as follows:

Total Projected Funds Obligated Balance of Funds l

Project Cost To Date By Fiscal Year FY 86 FY 87 l

$50,000

$50,000 0

0 i

1

. ~.

The total amount of funds expended during the months of August & September 1986 and cumulative expenditures through September are as follows:

Period YTD FY Cumulative 1.

Direct Labor Staff Effort 0.3 1.7 1.7 (Staff Months) 2.

Funds Direct Salaries 1,071 6,532 6,627 Materials and Services (Excluding ADP)

ADP Support Subcontracts 9,334 9,334 9,334(a) 2,396 2,396 Travel Expense Indirect Labor Costs 1,017 7,684 7,731 Other General & Administrative 676 1,458 1,462 Fee 280 2,985 2,985 TOTALS:

12,378 30,389 30,535(61%)

Note:

(a)

Final Subcontractor costs have not yet been billed.

III. FEE RECOVERY COST STATUS - Not applicable to this FIN A0700 l