Forwards Safety Insp Repts 50-277/87-11 & 50-278/87-11 on 870409.Util Does Not Satisfy All Applicable Requirements of 10CFR50,App R.Enforcement Conference Will Be Scheduled to Discuss Violation & Corrective Actions
ML20215L865
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/06/1987
From: Johnston W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Gallagher J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20215L867 List:
References
NUDOCS 8705120405
Download: ML20215L865 (2)


See also: IR 05000277/1987011

Text

. . _ _ _. . _ _ .. m._

.;

.-

MAY 0 6 W

Docket Nos. 50-277 License Nos. OPR-45

50-278 DPR-56

, Philadelphia Electric Company-

ATTN: Mr'. J. W. Gallagher

Vice President

Nuclear Operations '

2301 Market-Street

Philadelphia, Pennsylvania 19101

,

Gentlemen:

Subject: Inspection Report Nos. 50-277/87-11 and 50-278/87-11

^

This refers to the special safety inspection conducted by Messrs. A. Krasopoulos

and S. Pullani of this office on April 9,1987 at the Philadelphia Electric

Company Headquarters of activities authorized by NRC License Nos. OPR-45 and-

OPR-56 and to the discussions of our findings held by Mr. A. Krasopoulos with

Mr. W. Boyer of your staff at the conclusion of-the inspection. -The inspection

was conducted to review, and determine the status of, numerous examples of a

violation of fire protection _ requirements (10 CFR 50, Appendix R)' identified by

your staff during a confirmatory review of the Fire Protection Program. This

review was committed to in _ Confirmatory Action Letter 86-07 dated April 11,

-1986 following a previous NRC inspection of the fire protection program .

(Reference: Inspection Nos. 50-277/86-08; 50-278/86-08). The examples identified

by your. staff were described in your letters' dated May 22, 1986, September 17, 1986

and October 31, 1986.

During the inspection, the inspector evaluated the circumstances associated

with five of the examples. Based on this review, the NRC has determined that

i you do not currently satisfy all of the applicable requirements of'10 CFR 50

Appendix R. We are considering the violation for appropriate enforcement

action and will schedule an enforcement conference with you to discuss the

(

examples of the violation, their causes and your corrective actions.

No reply to this letter is required. Your cooperation with us in this matter

is appreciated.

Sincerely,

j

8705120405 870506

gDR ADOCK 05000277 Original SisacW

PDR *

William V. Johnston, Acting Director

'

'

Division of Reactor Safety

'

Enclosure: Combined NRC Region I Inspection Report

Nos. 50-277/87-11 and 50-278/87-11

l OFFICIAL RECORD COPY CIR PB 87-11 - 0001.0.0 ,

'

,

04/30/87

.- - - - . - - _ . . - - . . . -. -_ .-. --- - . - . - - - ,

'

-,

Philadelphia Electric Company 2.

cc w/ enc 1:

R. S. Fleischmann, Manager, Peach Bottom Atomic Power Station

John S.-Kemper, Senior Vice President, Engineering and Production

Troy 8. Conner, Jr., Esquire

W. H. Hirst, Director, Joint Generation Projects Department,

Atlantic Electric

G. Leitch, Nuclear Generation Manager

Eugene J. Bradley, Esquire, Assistant General Counsel (Without Report)

Raymond L. Hovis,. Esquire

Thomas Magette, Power Plant Siting, Nuclear Evaluations

W. M. Alden, Engineer in Charge, Licensing Section

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

Commonwealth of Pennsylvania

bec w/ enc 1:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

Section Chief, DRP

Robert J. Bores, DRSS

.

,

RI:DRS

co

RI:jRS clof n

RI:DRS N

Krasopoulos/ms Anderson Durr M"I 4 'eds

(

4/?o/87 W

Al

f/$/87 M /87 Tfl f $b

0FFICIAL RECORD COPY CIR PB 87-11 - 0002.0.0

04/30/87