Forwards Insp Rept 50-309/86-13 on 860729-0910.No Violation Noted.Concern Expressed Re Slow Followup of Identified Contamination Problem W/Sand from Excavation Project
ML20215J717
Person / Time
Site: Maine Yankee
Issue date: 09/26/1986
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Randazza J
Maine Yankee
Shared Package
ML20215J719 List:
References
NUDOCS 8610270161
Download: ML20215J717 (2)


See also: IR 05000309/1986013

Text

N

.

.

SEP 2 61986

Docket / License: 50-309/DPR-36

Maine Yankee Atomic Power Company

ATTN:

Mr. J.B. Randazza

Vice President

Nuclear Operations

83 Edison Drive

Augusta, Maine

04336

Gentlemen:

Subject:

Inspection Report No. 50-309/86-13

This transmits the July 29 through September 10, 1986, routine inspection findings

of Messrs. C. Holden and J. Robertson at the Maine Yankee Atomic Power Plant,

Wiscasset, Maine.

Those findings were based on observations of activities, inter-

views, and document reviews, and have been discussed with Mr. Garrity of your staff.

Within the scope of this inspection, no violations were observed.

However, we are

'

concerned about the apparent slow followup of an identified contamination problem

with sand from an excavation project.

Once we became involved, your corrective

action was prompt and aggressive. We will continue to review this area in upcoming

inspections.

We have received your letter dated April 25, 1986, which provides a response to

our March 31, 1986 Inspection Report 50-309/86-01 as well as your letter dated May

20, 1986, in response to our April 18, 1986 Inspection Report 50-309/86-02.

Thank

you for informing us of the corrective and preventive actions documented in those

letters.

These actions will be examined during a future inspection of your program.

No reply to this letter is required.

Your continued cooperation with us in this

matter is appreciated.

Sincerely,

pr*E" SLgued ByY

ef

-

&

dward C. Wenzinger, Chief

Projects Branch No. 3

Division of Reactor Projects

Enclosure:

NRC Region I Inspection Report No. 50-309/86-13

1

8610270161 860926

g M j/

DR

ADOCK 0500

9

I

i

,

'

. ,

..

Maine Yankee Atomic Power Company

2

SEP 2 61986

cc w/ encl:

C.E. Monty, Presiden't

C.D. Frizzle, Assistant Vice President / Manager of Operations

J.H. Garrity, Plant Manager

P.L. Anderson, Project Manager

G.D, Whittier, Licensing Section Hdad

J. A. Ritsher, Attorney (Ropes and Gray)

Public Document Room (PDR)

local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of Maine (2)

bcc w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl.)

DRP Section Chief

M. McBride, RI, Pilgrim

H. Eichenholz, SRI, Yankee

P. Sears, LPM, NRR

File RI-86-A-0102

p:

)

RP

P

RI:DRP

@, &

i

roth/meo

Iripp

Wenzinger

9/19/86

y

et /2,6

0FFICIAL RECORD COPY

,