ML20215F338
| ML20215F338 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 10/08/1986 |
| From: | Gagliardo J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Goldberg J HOUSTON LIGHTING & POWER CO. |
| Shared Package | |
| ML20215F341 | List: |
| References | |
| NUDOCS 8610160159 | |
| Download: ML20215F338 (3) | |
See also: IR 05000498/1986013
Text
y
,
'
'
.
.
OCT
8 1986
.
In Reply Refer To:
Dockets:
50-498/86-13
50-499/86-13
Houston Light.ing & Power Company
ATTN:
J. H. Goldberg
Group Vice President, Nuclear
P. O. Box 1700
llouston, Texas 77001
m
Gentlemen:
This refers to the inspection conducted by Messrs. D. R. Carpenter,
R. G. Taylor, B. A. Breslau, and H. F. Bundy of this office during the period
April 5 through June 30, 1986, of activities authorized by NRC Construction
Permits CPPR-128 and 129 for the South Texas Project, Units 1 and 2, and to the
discussion of our findings with members of your staff at the conclusion of the
inspection.
Areas examined during the inspection included:
site tours, licensee action on
previous inspection findings, allegations, receipt, storage and handling of
equipment and material at permanent plant warehouse, plant procedures,
emergency procedures, preoperational test procedure review, licensee program
for review of NRC IE bulletins, notices and generic letters, operational
staffing, preoperational test witnessing, biofouling of cooling water heat
exchangers, and preoperational test results review. Within these areas, the
inspection consisted of selective examination of procedures and representative
records, interviews, with personnel, and observations by the inspectors.
The
inspection findings are documented in the enclosed inspection report.
Within the scope of the inspection, no violations or deviations were
identified.
We.h' ave'also examined actions you have taken with regard to previously
identified inspection findings.- The status of these items is identified in
paragraph 3 of the enclosed report.
Should you' have ariy questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
hot
159 061oos
Original Signed By
o
ocx oS00049s
J. E. Gagliardo
J. E. Gagliardo, Chief
Reactor Projects Branch
Enclosure: (see next page)
RGTayI[o[fC:RhC
RP8/(
C:RPB /
AC$
F
PB/C
ndy/cg
y
slau
r GLC
table
JEGagl
MEEmerson
<J/ f/86 '{/p/86
y/f /,
'\\f6/86
/p/86
i
tV86
A
h y
t
.
e-
-
.
'
.
,
.
..
Houston Lighting & Power Company
-2-
Enclosure:
Appendix - NRC Inspection Report
-50-498/86-13
50-499/86-13
cc w/ enclosure:
Houston Lighting & Power Company
ATTN:
M. Wisenberg, Manager,
Nuclear Licensing
P. O. Box 1700
Houston, Texas
77001
Brian Berwick, Esquire
Asst. Attorney General
Environmental Protection Div.
P. O. Box 12548, Capitol Station
Lanny Alan Sinkin
Citizens Concerned About
Nuclear Power, Inc.
Christic Institute
1324 North Capitol Street
20002
Charles Bechhoefer, Esquire
Chairman, Atomic Safety & Licensing
Board
U.S. Nuclear Regulatory Commission
20555
Dr. James C. Lamb, III
.
313 Woodhaven Road
Chapel Hill, North Carolina
'27514
Frederick J. Shon
Administrative Law Judge
Atomic Safety and Licensing Board
U.S. Nuclear Regulatory Commission
20555
Alvin H. Gutterman
Newman & Holtzinger, P.C.
1615 L St., N.W.
Suite 1000
20036
Texas Radiation Control Program Director
bec:
(see next page)
,
-
a
.,
.
.
Houston Lighting & Power Company
-3-
s
bec to DMB (IE01)-
..
bec~distrib. by RIV:
- RPB
DRSP-
- Resident Inspector-0PS
. R. D. Martin, RA
- Resident Inspector-CONST.
- Section Chief (RPB/C)
- R&SPB
- MIS SYSTEM..
c
- RIV File
'
- D. Weiss, LFMB (AR-2015)
- RSTS Operator
R. Pirfo, ELD' '
- R. G. Taylor, RPB/C
- RSB'
- B. A. Breslau, RPB/C
M. E. Emerson, AC (2)
- w/766
.
-l
i
i
-.
, ,
. _ _ . -
. , , _ , . _ _ _ _ . , _ _ .
._,.___..__.m.___..__--..-...
. . . - . . , _ _ - . , _ . . _ _ . . , _ _ . _ . . _ _ _ . , _
.