ML20215E711
ML20215E711 | |
Person / Time | |
---|---|
Site: | South Texas |
Issue date: | 09/26/1986 |
From: | HOUSTON LIGHTING & POWER CO. |
To: | |
Shared Package | |
ML20215E704 | List: |
References | |
NUDOCS 8610150469 | |
Download: ML20215E711 (245) | |
Text
, _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
l l-PART A I l
l HOUSTON LIGHTING AND POWER COMPANY QUALITY ASSURANCE PR03 RAM DESCRIPTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION i
l REVISION 15 September 26, 1986 I Date
$$01$ K J
[
A
n-
,( it r
i
' HOUSTON LIGHTING & POWER COMPANY QUALITY ASSURANCE PROGRAM DESCRIPTION Table of Contents
.SECTION TITLE PAGE 1.0 Organization 6-2.0 Quality Assurance Program 17-3.0 Design Control 19 4.0 Procurement Document Control 22 4
5.0 Instruction, Procedures, and Drawings 24 6.0 Document Control 24 7.0 Control of Purchased Material, 25 Equipment and Services 8.0 Identification and Control of 28 Materials, Parts and Components 9.0 Control of Special Processes 28 10.0 Inspection 30
- 11.0 Test Control 31 12.0 Control of Measuring and Test Equipment 32 13.0 Handling, Storage and Shipping 33 14.0 Inspection, Test and Operating. Status 34 15.0 Nonconforming Materials, Parts 34 or Components 16.0 Corrective Action 35 17.0 Quality Assurance Records 35 18.0 Audits 36 2
e y I v
HOUSTON LIGHTING & POWER COMPANY QUALITY ASSURANCE PROGRAM DESCRIPTION List of Tables NUMBER TITLE 1 ANSI Standard and Regulatory Guide Compliance 4
2 HL&P Manuals Used to Implement the Quality Assurance Program List of Figures NUMBER TITLE 1 South Texas Project Management Organization 2 Construction Management Organization 3 Nuclear Licensing Organization 4 Nuclear Assurance Organization 5 Nuclear Training Organization 6 Lines of Communication HL&P & BEC/ Westinghouse /ESI/ECI/ Contractors 3
f QUALITY ASSURANCE PROGRAM DESCRIPTION South Texas Project Electric Generating Station Quality Assurance During Design and Construction Houston Lighting & Power Company (HL&P), as a licensee and as Project Manager for itself and the other owners, has quality assurance responsibility for design, engineering, procurement, fabrication, construction, and operation associated with the South Texas Project Electric Generating Station (STP). Although HL&P has delegated certain of its quality assurance authority to its contractors, it nevertheless retains the responsibility for the quality assurance program controlling all aspects of the STP. HL&P reviews and approves this QAPD and all changes thereto prior to-implementation. Additionally, HL&P establishes quality assurance requirements for the Project in a Project Quality Assurance Plan. The Project Quality Assurance Plan specifies requirements applicable to prime contractors and HL&P. The HL&P Quality Assurance staff monitors the performance of HL&P staff and contractors to assure compliance with the Project Quality Assurance Plan.
HL&P has contracted with Westinghouse Electric Corporation (Westinghouse)for the design, fabrication, and quality assurance services for the nuclear steam supply system and with Bechtel Energy Corporation (BEC) for plant design, procurement, engineering, construction management, quality assurance services and other related services, including quality assurance services for Westinghouse items upon receipt at the Project site. HL&P has contracted with Ebasco Services, Inc. (ESI) for quality assurance and quality control and with Ebasco Construction Inc. (ECI) for construction services for its scope of work. This quality assurance program description addresses the HL&P quality assurance program (Part A), the quality assurance program of BEC (Part B), and the quality assurance program of Ebasco (Part C). The Westinghouse quality assurance program is described in WCAP-8370,
" Westinghouse Nuclear Energy Systems Division Quality Assurance Plan" and is not included in this program description.
4
q l
l 4
PART A l 1
' HOUSTON LIGHTING & POWER COMPANY
- -QUALITY ASSURANCE-PROGRAM DESCRIPTION South' Texas Project Electric Generating Station .)
Quality Assurance During Design and Construction ;
Houston Lighting & Power Company (HL&P), as a licensee and as Project Manager for itself and the other owners, has the Quality Assurance (QA)
I responsibility for design, engineering, procurement, fabrication, 4
construction, preoperational testing and operation of the South Texas Project 4
(STP) Electric Generating Station.
1 HL&P's Project Quality Assurance Plan requires that HL&P, its prime contractors, subcontractors and vendors comply with the criteria established by 10CFR50, Appendix B. It is the intent of HL&P to comply with ANSI N45.2 and the applicable daughter standards and implementing Regulatory Guides as 1 indicated in Table 1. Furthermore, HL&P will assure through programmatic direction that the prime contractors and all their subcontractors and suppliers performing nuclear safety-related work comply with 10CFR50, Appendix B; ANSI N45.2, and the Regulatory Guides as referenced herein consistent with their scope of work.
i Programmatic direction is defined as the role of the owner in establishing the program requirements and ensuring the adequacy of the Prime Design, Engineering and Construction Management Quality Assurance Program. The programmatic direction consists of review and approval of the system features initially and continued monitoring of those systems if the systems need
, strengthening. The assurance of compliance by first level nuclear safety-related suppliers and contractors will be accomplished through the Engineer / Construction Manager's review and approval of the supplier's/ contractor's Quality Assurance Program.
The system monitoring is achieved through audits and surveillances of work in 1
progress.
The HL&P Quality Assurance Program is implemented in two phases: the-design and construction phase as defined by the Project Quality Assurance Plan and the operational phase, including preoperational testing and startup, as defined by the Operational Quality Assurance Plan. The Project Quality 4
Assurance Plan is described herein. The Operational Quality Assurance Plan is described in Chapter 17.2 of the FSAR.
The combination of these Quality Assurance programs augmented by definitive procedures provide HL&P with the assurance that its quality commitments are met.
i 4
5
1.0 Organization 1.1 .The organization charts shown in Figures 1 through 6 illustrate:
. (a) groups within HL&P having quality responsibilities (engineering, procurement, construction) and (b) Quality Assurance interdepartmental relationships for the South Texas Project.
1.2 The Project Quality Assurance Manager, South Texas Project, is t responsible for providing the programmatic direction, and
, administering policies, goals, objectives and methods which are i described in the Project Qualjty Assurance Plan. The HL&P Group
- i. Vice President Nuclear, reviews and approves the Project Quality Assurance Plan and has ultimate responsibility for Quality i Assurance activities. The Project Quality Assurance Plan describes i specific Quality Assurance controls to be established by HL&P and
] the prime contractors on the South Texas Project.
1.3 Two levels of control have been implemented by HL&P to monitor the effectiveness of the Quality Assurance Programs at the Scuth Texas Project.
- a. Corporate level control - Corporate level control is achieved through the direct involvement of the HL&P Group Vice President, Nuclear, and Technical Services audits and vendor
! surveillance as described below. The Group Vice President, Nuclear, regularly meets with QA management and receives
! reports on the status of the QA Programs to aid him in 4
evaluating the overall effectiveness. Technical Service audits and vendor surveillance are conducted under the direction of the General Manager, Nuclear Assurance to evaluate the overall program effectiveness of HL&P Project Quality Assurance, Westinghouse and its suppliers. Technical i,
Service audits of the Architect Engineer / Construction Manager's activities may be performed as requested by the r Project Quality Assurance Manager.
- b. Project level control - Project level control is achieved through Project Quality Assurance Program approval and j monitoring of the effectiveness of implementation by HL&P,
- prime contractors and subcontractors. The Project QA staff l under the direction of the Project Quality Assurance Manager prepares the Project Quality Assurance Plan and reviews and approves the Project Quality Program Manual for the Architect Engineer / Construction Manager. The monitoring is implemented by scheduled Project audits performed by qualified auditors.
Additional monitoring is accomplished by Project QA personnel performing unscheduled selected surveillance of in-process
- work. HL&P Project Quality Assurance also maintains the-capability to perform inspection verifications of in-process or completed work if determined to be necessary by the Project i
Quality Assurance Manager. If necessary the inspections are performed by personnel qualified in accordance with ANSI N45.2.6.
I 6
1
)
l
)
1.4 Group Vice President, Nuclear The Group Vice President, Nuclear, is responsible for management of nuclear projects and operating nuclear plants and for all nuclear activities within HL&P related to design, engineering, 1 construction, operation, and quality assurance. The Group Vice President, Nuclear, provides technical guidance and administrative ;
direction to:
- a. General Manager, South Texas Project
- b. Manager, Nuclear Engineering
- c. Manager, Engineering Assurance
- d. Manager, Nuclear Licensing
- e. Vice President, Nuclear Plant Operations (Description of responsibilities is contained in Chapter 17.2,FSAR)
- f. General Manager, Nuclear Assurance The Group Vice President, Nuclear, reports to the Chairman of the Board and Chief Executive Officer.
1.5 General Manager, South Texas Project The General Manager, South Texas Project reports to the Group Vice President, Nuclear.
He has overall responsibility for the engineering, construction, procurement, cost, schedule, and startup of the South Texas Project. He has authority to "Stop Work" for cause in all activities of the Project.
1.5.1 Deputy Project Manager The Deputy Project Manager reports to the General Manager, South Texas Project.
He has overall responsibility for the engineering, construction, startup, procurement, cost and schedule activities of the South Texas Project acting for the Manager, STP in his absence and/or stead. He has "Stop Work Authority" for cause in all activities on the Project.
1.5.2 Startup Organization NOTE: The detailed discussion of the startup organization is contained in the Operations Quality Assurance Plan (0QAP).
7
_.,_.._1 _
s 1.5.3 Manager, Nuclear Purchasing The Manager, Nuclear Purchasing reports to the General Manager, STP/ Deputy Project Manager for project direction and to the Manager, Generation Construction Purchasing, for technical direction. He is responsible for.overall' coordination and administration of purchasing, contracts administration and subcontracting activities for the South Texas Project. 'He directs the development and' implementation of procedures, vendor selection, contract negotiations and preparing purchase orders for those contracts issued directly by HL&P.
1.5.4 Supervisor, Project Services and Administration The Supervisor Project Services and Administration i
reports to the General Manager STP/ Deputy Project Manager. He is responsible for assuring proper review, I
coordination, distribution and control of all Project
' procedures, maintenance of the STP forms control program, maintaining a controlled required reading program for the STP Project Team and the review of non-project procedures to ensure consistency with Project 4
requirements and objectives.
- 1.5.5 Construction Manager 1' The Construction Manager reports to the General Manager STP/ Deputy Project Manager. He is responsible for providing technical direction and administrative guidance 1 to HL&P and its prime contractors in the area of
- construction, construction control and reviewing
- documents, drawings and specifications related to i construction. He provides direction to Site Security, Administrative Services and to the Construction organization. He has the authority to "Stop Work" for
, cause in all activities related to construction.
! 1.5.6 Construction Superintendent The Construction Superintendent reports to the Construction Manager. He is responsible for ensuring that the prime contractors comply with all contractual and construction requirements. He monitors the prime
- contractors construction in the areas of evaluation and analysis of construction plans and schedules, work methods, craft performance, staffing, equipment utilization and progress. He recommends "Stop Work" for cause 1n construction items within his area of
~
responsibility.
4 I
8 i
l
. - - _ _ _ - _ _ _ _ , , _ , . _ _ - - _ . _ . . . _ ~
1.5.7 Manager, Engineering The Manager, Engineering reports to the General Manager STP/ Deputy Project Manager. He directs the engineering personnel in the performance of the owner's review of the design and engineering work performed by the prime contractors. He ensures that adequate engineering planning, coordination of solutions to problems and work priorities are established by the prime contractors. He has "Stop Work Authority" for cause in the engineering and design activities on the project. ,
1.5.8 Principal Engineer, Site Engineering The Principal Engineer, Site Engineering reports to the Manager, Engineering; additionally for matters relating to the Licensing of the South Texas Project, he receives direction from the Manager, Nuclear Licensing. He is responsible for coordinating the site engineering interface in the technical resolution of all site related engineering problems, reviewing field change requests, site initiated design change notices and for monitoring the activities of the prime contractors construction engineering groups. He assists in the release and interpretation of design documents., He can recommend "Stop Work" for cause in the engineering and design within the area of his responsibility.
1.5.9 Principal Engineer, Operations Support Engineering The Principal Engineer, Operations Support Engineering reports directly to the Manager, Engineering. He implements the Engineering Program to support initial fuel load, spare parts procurement and transition to the operational phase of the plant.
1.5.10 Principal Engineers - Service, Systems and Programs The Principal Engineers - Service, Systems and Program report to the Manager, Engineering for project and technical direction. They direct home office engineering personnel by assuring that the owner's review is performed in accordance with the Project Quality Program; directing the review of design criteria, conceptual design, and detailed design, ensuring the required engineering plans, schedule control logs and status and forecast reports to satisfy project team planning and schedule requirements are developed. They also ensure the resolution of critical problems requiring special engineering support and attention by their division including responsibilities for overseeing, coordinating 9
and administering the South Texas Project effort, review and approve as delegated by the Manager, Engineering the issue of design drawings, engineering specifications, engineering related studies,.and recommendations for purchase in accordance with appropriate procedures.
1.5.11 Project Cost / Scheduling Manager )
The Project Cost / Scheduling Manager reports to the General Manager, STP/ Deputy Project Manager. He is responsible for directing and monitoring the cost and scheduling control and reporting activities for the project. He is responsible for the development and implementation of the material control program by the Construction Manager / Constructor.
1.5.12 Cost / Scheduling / Materials, Manager The Cost / Scheduling / Materials Manager reports to the Project Cost / Scheduling Manager. He is responsible for ;
overseeing, coordinating and administering the cost, scheduling and materials control activities for the project.
1.5.13 Manager, Records Management / Document Control and Information Processing The Manager, Records Management / Document Control and Information Processing reports to the General Manager, STP/ Deputy Project Manager. The Manager, RM/DC/IP is responsible for managing the Records Management personnel and interfacing with the prime contractors and all Project organizations with respect to the establishment of systems that control, collect, store and transfer records related to the South Texas Project.
1.5.14 Manager, Records Management / Document Control The Manager, Records Management / Document Control reports to the Manager, Records Management / Document Control and Information Processing. The Manager RM/DC is responsible for the Records Management and Document Control activities associated with the design and construction phase of the project.
1.5.15 Manager, Project Records Review Program The Manager, Project Records Review Program reports to the Manager, Records Management / Document Control and 10
Information Processing. He .is responsible for reviewing a sampling of safety related installation records for technical adequacy, identification of records discrepancies, returning of discrepant records to'the originating group for correction, and HL&P final acceptance of the records.
1.6 Manager, Nuclear Licensing The Manager, Nuclear Licensing reports to the Group Vice President, Nuclear. -He is responsible for the planning, coordination, direction, and control of the Nuclear Licensing Department activities, and for providing technical direction, as necessary, to ensure that STP Licensing activities are accomplished in an effective and timely manner consistent with HL&P policy. The Manager Nuclear Licensing provides the primary interface with the NRC.
1.7 Manager, Engineering Assurance.
The Manager, Engineering Assurance reports to the Group Vice President, Nuclear. He is responsible for the planning, scheduling, ar.d execution of appropriate independent technical reviews of HL&P Project and Contractor Engineering activities.
- 1.8 General Manager, Nuclear Assurance l
The General Manager, Nuclear Assurance, has the authority and i responsibility to identify, initiate, recommend, or provide I solutions to quality related problems and verify the implementation -
and effectiveness of the solutions. He has the authority to "Stop Work" for cause in the design, construction, and operation phase of the nuclear plant. The minimum requirements established for this position are:
a) A college degree in a field of engineering or science, or i
equivalent experience.
b) Familiarity with nuclear power generation facilities and the
- related operations, c) Knowledge of the industry's quality assurance standards and regulatory requirements.
i
- d) Management experience and familiarity with HL&P corporate organizations.
The General Manager, Nuclear Assurance, provides technical guidance and administrative direction to: l e) Project Quality Assurance Manager j
!l l
11
.m--w,,-,---,s--n9-.ye-,_.m.-,,-, -- mm, n r m.n,w-g,-,-w_w.
j._ _
I f) General Supervisor, Technical Services 4-
..g) Operations Quality Assurance Manager (The responsibilities of the Operations Quality Assurance Manager are described in Chapter 17.2, FSAR).
The General Manager, Nuclear Assurance, reports to the Group Vice President, Nuclear.
1.8.1 Project Quality Assurance Manager, South Texas Project The Project Quality Assurance Manager, South Texas Project has .the responsibility to identify, initiate, recommend, or provide solutions and authority to solve quality related problems and to verify the implementation and effectiveness of the solutions. He has the authority to "Stop Work" for cause of any quality-related activity during the design and construction phase of the South Texas Project. The Project Quality Assurance Manager, 4
South Texas Project, must, as a minimum, have:
a) A college degree in a field of engineering or science, or equivalent experience.
b) Familiarity with nuclear power generation facilities j and related operations.
i c) Knowledge of the QA standards and regulatory requirements.
d) Management experience and familiarity with HL&P corporate organizations.
The major responsibilities of the Project Quality j Assurance Manager, STP are:
e) Develop and administer QA policies, goals, objectives, and methods which ensure the proper
- planning, development, implementation, coordination a
- id administration of the Project Quality Assurance Plan.
- f) Provide programmatic direction on QA related matters j of HL&P, and contractor management.
g) Direct the onsite audit and surveillance activities; direct audits /surveillances of the Engineer / Construction Manager's QA program
- implementation in the design office.
t 1
4 12
-- -ce.,, e=a-.. . , - - * ~ g - .- ,,-,,w----,. ,.._,.,,.,g.4,.,,.wwwy.,4, .,,---.e-w-,-,.,---e-,m....,-,-ww,-~,ew--,,w,, r-wre ewn n - v e. -
h) Coordinate activities relating to auditing and ven6 e surveillance in conjunction with the HL&P General Supervisor. Technical Services.
The Projoct Quality Assurance Manager reports on all Quality Assurance matters directly to the General Manager, Nuclear Assurance.
1.8.2 Project QA Supervisor, Quality Control The Project QA Supervisor, Quality Control reports directly to the Project Quality Assurance Manager, South Texas Project. He is responsible for technical direction and administrative guidance to the HL&P Quality Control personnel, coordinating inspection of selected fabrication and construction activities, ensuring proper nonconformance identification and assuring that the personnel performing inspections are properly certified.
He as the authority to "Stop Wark" for cause on any quality related activity during the design and construction phase at the South Texas Project at the site.
1.8.3 Project QA Supervisor, Design / Procurement The Project QA Supervisor, Design / Procurement reports directly to the Project Quality Assurance Manager, South Texas Project. He is responsit,le for providing technical direction and administrative guidance to HL&P Design / Procurement Quality Assurance personnel, coordinating the resolutions of vendor problems identified by HL&P QA, coordinating with site QE personnel for input to vendor surveillance / audit activities and providing programmatic direction to the Engineer /Censtruction Manager regarding design control, vendor surveillance and auo! ting functions. He has authority to "Stop Work" for cause on any quality related activity during the design and construction phase of the South Texas Project at the Design office.
1.8.4 Deputy Project Quality Assurance Manager The Deputy Project 'sality Assurance Manager reports directly to the Prop t Quality Assurance Manager, South Texas Project. He is responsible for technical direction and administrativo guidance to the site Quality Engineering personnel, providing programmatic direction i to prime contractors and interfacing with the NRC. He has the authority to "Stop Work" for cause on any quality related activity during the design and construction phase of the South Texas Project at the site.
i 13
1.8.5 Project QA Supervisor - Analysis 1
~
.The Project QA Supervisor - Analysis reports to the i Deputy Project QA Manager. He is responsible for assisting in development of QA programs and procedures, provides input for responses to NRC Inspection and-Enforcement Reports, performs special studies, 4
investigations and analysis of quality programs as requested, provides quality engineering input into trend
_ analysis, technical analysis and corrective action and participates in audits as requested. He has authority to "Stop Work" for cause on any quality related activity during the design and construction phase of the prcject at the site.
1.8.6 Project QA Supervisor - Audits j The Project QA Supervisor - Audits reports to the Deputy Project QA Manager. He is responsible for coordinating, i scheduling and participating in audits of HL&P i Engineering / Construction Management, t.onstructor and i
other contractors, supports specials task force efforts and project team studies when' requested. He has authority.to "Stop Work" for cause on any quality related i
+
activity durirg the design and construction phase of the project at the site.
1.8.7 - Project QA Supervisor - Surveill'ances ' '
The Project QA Supervisor - Surveillances reports to the .
Deputy Project QA Manager._ He is responsible for coordinating surveillances of HL&P and contractors, supporting special task force efforts and project team studies as requested and participating in audits as requested. He has authority to "Stop Work" for cause on any quality related activity during the design and construction phase of the project at the site.
1.8.8 Project QA Supervisor, Quality Systems / Administration l
, The Project QA Supervisor, Quality Systems / Administration l reports directly to the Project Quality Assurance i i Manager, South Texas Project. He is responsible for i providing technical direction and administrative guidance to the Quality Systems / Administration personnel, developing and administering the HL&P Project QA Plan, evaluating the Engineer / Construction Manager and
- Constructor QA programs, administering the HL&P STP QA personnel training and certification program, administrative control of HL&P STP Project Quality
, Assurance Procedures and providing mechanisms to correct
/
14
-r-w.. .w.---,y.w. - - ,, ..--..-..~,-,-.-,,m,__,,._,w eve-w,,,y-n_-,_,w-.. .%..w.,.-,,--,-~,.._..- . . - - - - - - . . , , - , - -_ . , .
the QA programs as necessary. He has the authority to "Stop Work" for cause on any quality related activity during the design and construction phase of the South Texas Project at the site..
1.8.9 General Supervisor, Technical Services The General Supervisor, Technical Services is responsible for directing all HL&P Technical Service auditing ,
vendor surveillance and vendor. evaluation activities. He has the authority to "Stop' Work"-for cause on any quality-related activity of the South Texas Project.
The General Supervisor, Technical Services must, as a minimum have:
a) A college degree in a field of engineering or science, or equivalent experience.
4 b) Familiarity with nuclear power generation facilities and the related operations.
c) Knowledge of the industry QA standards and regulatory requirements.
d) Management experience and familiarity with HL&P corporate organizations.
The major responsibilities of the General Supervisor, Technical Services are to provide administrative guidance and direction to the HL&P Vendor Evaluation and Surveillance Group.
The General Supervisor, Technical Services reports on all Quality Assurance matters directly to the General Manager, Nuclear Assurance.
1.9 Manager, Nuclear Training The Manager, Nuclear Training reports to the Vice President, Nuclear Plant Operations. He directs, coordinates, and administers the STP nuclear training efforts and provides direction to the prime contractors relative to training. The STPEGS Nuclear Training program includes the Quality Assurance Indoctrination for HL&P personnel associated with the safety related activities for the South Texas Project.
15
1.10 Manager, Nuclear Engineering The Manager, Nuclear Engineering reports to the Group Vice President, Nuclear. He is responsible for directing personnel in the performance of an owner's review of selected analyses. He is also responsible for overseeing and coordinating nuclear fuel plant design interface support to the STP Project Team.
1.11 The organizations or entities listed below may be delegated Quality l Assurance authcrity within their scope of work. HL&P has the responsibility to audit and monitor all of the below listed organizations' or entities'. performance to assure that their quality programs provide sufficient authority and organizational freedom for personnel performing QA functions and that they are effectively implemented.
- a) Houston Lighting & Power Company as a licensee and Project i Manager for itself and the other owners has the overall
- responsibility for design, engineering, procurement, construction, operation and quality assurance activities.
Bechtel Energy Corporation and Westinghouse Electric 4
Corporation have contractual responsibility to provide
, acceptable QA programs to HL&P. The contract provides HL&P the authority to audit and monitor BEC and Westinghouse performanco to assure that the QA programs provide for sufficient authority and organizational freedom to be j effectively implemented.
b) Bechtel Energy Corporation as the Architect / Engineer and Construction Manager provides HL&P with design, engineering, procurement, construction management and Quality Assurance ,
services.
c) Westinghouse Electric Corporation as the Nuclear Steam Supply System (NSSS) supplier provides HL&P with the NSSS design, engineering, procurement, fabrication, and quality assurance services.
d) Ebasco Services Inc. as the Constructor shall provide HL&P with construction quality assurance and quality control services under the direction and as approved by the Construction Manager.
e) ' Consultants - HL&P utilizes the services of qualified
. consultants to assist in the performance of quality tasks.
Figure 6 illustrates how these companies interrelate with HL&P for the South Texas Project.
16
l l
2.0 Quality Assurance Prcgram 2.1 The HL&P Project Quality Assurance Program for the South Texas Project has been developed in accordance with the criteria of 10CFR50 Appendix B, ANSI N45.2 and Regulatory Guides as reference herein, to provide programmatic direction on quality requirements for the prime contractors and subcontractors during design and construction. j 2.2 The nuclear safety-related structures, systems and components covered by this program are listed in Section 3.2 of the FSAR.
Westinghouse Electric Corporation provides quality assurance services for the items listed in Table 3.2.B-1 of the FSAR until -
delivery to the site. BEC and ESI provida quality assurance I services for the items listed in Table 3.2.A-1 of the FSAR within 1 the scope of their work. BEC provides quality assurance and quality control services for Westinghouse items (Table 3.2.B-1) upon receipt at the site until release for construction, after which ESI provides such services.
2.3 The HL&P Quality Assurance Program for the South Texas Project is described by the HL&P Project Quality Assurance Plan. The plan requires that written procedures, Training and Certification, issuance of specifications and drawings, and work and inspection planning be accomplished in advance of performing nuclear safety-related activities. HL&P Project Quality Assurance ensures through procedure reviews that this advance preparation is accomplished.
The Project Quality Assurance Plan for the South Texas Project has in the past been structured in accordance with the Regulatory Guides (RGs) and Industrial Standards that are addressed in the NRC publications " Guidance on QA Requirements During Design and Procurement Phase of Nuclear Power Plants," (The
- Gray Book) Revision 1 dated May 24, 1974 (WASH 1283) and " Guidance on QA Requirements During the Construction Phase of Nuclear Power Plants," (The Green Book) dated May 10, 1974 (WASH 1309).
Presently the regulatory guides and standards listed on Table 1 are '
in effect for the South Texas Project.
2.4 The HL&P Plans and Procedures Manuals, which are used to implement the quality related activities for each major HL&P organization, are listed in Table 2. Verification that plans and procedures are properly implemented is accomplished by HL&P Quality Assurance through audits, surveillance, and regular management assessment of the Quality Assurance Program.
a 17 <
.f 2.5 It is the policy of HL&P, acting as a licensee and Project Manager for the other owners for the South Texas Project, to assure that the design, fabrication,' construction, testing and operation of STP 4
are in conformance with Project specifications, procedures, codes and NRC regulations. It is the responsibility of each organization assigned to the STP to ensure that Project procedurd review mathods include provisions to ensure that the requirements stated in this program description are incorporated into Project !
procedures. . The Project Quality Assurance Plan identifies activities and establishes requirements for procedures which identify, initiate and verify the resolution of nuclear safety-related quality proble;s. The implementing procedures call for the resolution of quality problems at the lowest possible authorized level. However, if a dispute is encountered in the resolution of.a quality problem which cannot be resolved at lower levels, the General Manager, Nuclear Assurance, presents the l problem ultimately to the HL&P Group Vice President, Nuclear, for resolution.
2.6 The HL&P Nuclear Training Department is responsible for conducting a quality oriented indoctrination program for new HL&P personnel
, who have quality-related functions. The HL&P Project Quality Assurance Plan requires that prior to performing activities affecting quality the personnel are trained, as necessary, in the applicable procedures. The training provides a thorough understanding of the purpose, scope, policies, principles, and techniques of the specific procedures or instructions. When personnel perform special activities, a training and certification
- program is established and maintained. Refresher training is conducted as necessary to ensure that proficiency is maintained.
Bechtel is required to establish a training program for Bechtel and i administer the constructor's training program including refresher training as necessary, to ensure proficiency is achieved and main-tained. Quality Assurance audits and surveillances are performed to ensure compliance with these criteria.
2.7 The Project Quality Assurance Manager is directly responsible
- for assuring effective implementation of the Quality Assurance program. The qualifications for this positio's are defined in Section 1.8.1.
2.8 The HL&P Project Quality Assurance Plan requires BEC to review and
- approve procedures which control nuclear safety-related construction activities. It is the responsibility of BEC's Project Quality Assurance to determine that the contractor's procedures ,
L require proper equipment, environment and other prerequisites to
! perform the associated activity. The implementation of these t
requirements is verified through audits and surveillances performed i by either HL&P, BEC or ESI Quality Assurance.
1 i
18 h
2.9 All quality related activities implemented for the South Texas Project are audited annually at a minimum, or at least once within the life of the activity, whichever is shorter. These audits are performed by either HL&P, BEC, or ESI Quality Assurance personnel.
Selected areas are targeted and scheduled for more frequent auditing based on such factors as complexity, relative significance, past performance, etc. Supplemental audits will also be performed as described in Section 18.
2.10 The results of the South Texas Project Quality Assurance audit and surveillance activities are presented in a periodic report to the HL&P Group Vice President, Nuclear. Regular executive management review of these activities and the direct involvement of the HL&P Group Vice President, Nuclear, assures that an objective i program assessment of the South Texas Project Quality Assurance l programs is being performed.
l i
HL&P Project Quality Assurance reviews and documents approval of the BEC Project Quality Program Manual (PQPM); and audits and
. surveillances are performed by either HL&P Quality Assurance or Bechtel Quality Assurance to ensure compliance with the BEC PQPM.
, 2.11 HL&P and BEC Project Quality Assurance will establish and document a program for transferring responsibilities and controls for quality-related activities from BEC to HL&P during phaseout of
, design / construction 'and plant turnover. This program will be
! implemented prior to preoperational testing. This program will be in accordance with and consistent with the requirements of this section and/or 17.2 of the FSAR.
i 2.12 HL&P is committed to maintaining the Quality Assurance Program Description as an effective and meaningful document to provide programmatic direction to HL&P and the prime contractors on the South Texas Project. When changes are proposed to the QAPD for HL&P or its prime contractors and those-proposed changes reduce the commitments previously established in the QAPD, approval by the NRC will be obtained prior to implementation of the change (s),
i 2.13 When changes are made to the QAPD which alter the program for i HL&P or its prime contractors and those changes do not reduce the
- commitments previously established in the QAPD, appropriate l- notification will be made to the NRC within 90 days of i implementation, f 3.0 Design Control i HL&P has the overall responsibility for design and engineering of the South Texas Project and imposes the requirements of 10CFR50, Appendix B, Criterion III, Regulatory Guide 1.64 and ANSI N45.2.11 on the prime con-tractors and applicable subcontractors.
19
.---,--*,-,,,.m- , . , , - - ,.--,,.,,,,.w,----,w-,--ww- . , , - ,,,--e,-,--,,,e--,y--,--y-- ,~,-wm -,-.,,._,--w.-.-,,-.---, _.r..-,
,, ,,,,v-- 3~+. --wy--,
HL&P has assigned the authority to BEC and Westinghouse to perform the design, engineering and design verification.
HL&P, as appropriate, selects contractors / subcontractors to perform design related tasks. These tasks include.but.are not limited to the following:
New design Special design studies Design work outside the scope of prime contractors Changes to existing design performed by contractors no longer associated with the South Texas Project.
To be eligible to participate in design activities the contractor must
=
be approved to assure he has the capability to perform the design or requested task in accordance with specified requirements. When a contractor has been selected, the HL&P General Manager, STP, or designee shall ensure that all appropriate design background information with which to perform the task is provided.
HL&P Engineering performs reviews of selected elements of the completed design, design documents and specifications to ensure that contractual requirements are met.
The HL&P Manager, Engineering.is responsible for ensuring that l engineering activities are conducted in accordance with approved engineering procedures. The Engineering organization provides l programmatic direction and overview of the engineering activities. The i HL&P Engineering activities are conducted in accordance with Project I Engineering Procedures (PEP's).
When HL&P has direct responsibility or assumes direct responsibility for conducting design activities, these activities will be conducted in accordance with the requirements of this section and/or the FSAR Section 17.2.3.
HL&P contractors are required to provide the following design control measures in their quality assurance programs:
A design control system is established to document the methods of accomplishing and controlling essential design activities.
Design documents such as calculations, diagrams, specifications and
- drawings are prepared and records developed such that the final design is traceable to its sources.
20
. . . _ . . ~ . - -_ . - - - _ . ._. . . - - - - - - - . . . - __-. -.
Design activities, documents and interfaces are controlled to assure that applicable input such as design bases, regulatory requirements, codes and standards are incorporated into the final design.
Design input requirements, including design criteria, are documented and their selection reviewed and approved.
Design documents include an indication as to their importance to safety and shall specify the quality characteristics, including materials, parts, equipment and processes, that are essential to safety-related a;pects of structures, systems, and components.
Design documents also include, as appropriate, acceptance criteria for inspections and tests.
Design control measures are applied to safety-related items such as seismic, stress, thermal, hydraulic, radiation and accident analyses, as they apply to the development of design input or at they are used to analyze the design.
Safety-related designs, including Seismic C'ategory I designs, are verified for adequacy and accuracy through independent objective review of design documents by individuals competent in the subject activity. This verification may include the use of alternate or simplified solution methods or qualification testing, as appropriate.
Design changes, including engineering, vendor and construction originated changes, are controlled in a manner commensurate with
- the control imposed on the original design.
Document distribution is controlled such that all individuals using a design document or its results and/or conclusions for further 4
design work can be notified if the document is revised or cancelled.
Design documentation includes evidence that design control require-ments have been satisfi,ed.
Errors and deficiencies in approved design documents, including design methods (such as computer codes), that could adversely affect safety-related structures, systems and components are documented; and action taken to assure that all errors and defiaier,i6:; are corrected.
Deviations from specified quality standards are identified and j procedures are established to ensure their control.
G.h acurate definition of the atity classes, including systems designated as safM y w ht m 4 provided.
i 21
Quality Assurance audits are performed by either HL&P or BEC Quality Assurance personnel of HL&P, BEC and Westinghouse to ensure that design controls, requirements, specifications and documents are in accordance with the design control criteria.
In addition, HL&P Project Quality Assurance reviews selected quality / construction procedures to ensure that the quality requirements of the design specifications are incorporated. Quality Assurance audits and surveillances are performed by either HL&P or BEC Quality Assurance personnel to ensure that the work is accomplished in accordance with the design requirements and to ensure that field changes to the design are processed in accordance with the design control criteria.
4.0 Procurement Document Control To assure that nuclear safety-related items are purchased in a planned and controlled manner, the HL&P Project Quality Assurance Plan establishes basic requirements which are to be used by HL&P and prime contractors in preparing procurement procedures for the South Texas Project. BEC performs procurement activities for nuclear safety-related equipment, materials and services, exclusive of the NSSS contract, which is performed by Westinghouse. BEC will approve any Ebasco nuclear safety-related procurements. BEC, and as appropriate, Ebasco verify through contract, vendor surveillance and audit that their suppliers comply with the established requirements.
When HL&P has direct responsibility or assumes direct responsibility for procurement activities, these activities will be conducted in accordance with the requirements of this section.
The basic requirements are:
Written procedures are established clearly delineating the sequence of actions to be accomplished in the preparation, review, approval, and control of procurement documents.
A review of the adequacy of quality requirements stated in procurement documents is performed by qualified personnel knowledgeable in the QA requirements. This review is to determine all quality requirements are correctly stated; they can be inspected and controlled; there are adequate acceptance and rejection criteria; and the procurement document has been prepared in accordance with QA Program requirements.
Documented evidence of the review and approval of procurement documents is provided and available for verification.
t 22
L _
s S /
9 Procurement documents identify those quality assurance requirements which must be complied with and described in the supplier's QA a Program to meet 10CFR50, Appendix B; ANSI N45.2 and applicable ANSI standards and Regulatory Guides. This QA Program shall be reviewed
, for adequacy by qualified personnel knowledgeable in quality
- assurance.
Procurement documents contain or reference applicable desion bases; technical requirements, intlading regulatory requirements; component and material identification; drawings; specifications; codes and industrial standards, including their revision status; tests and inspection requirements; and instructions of such activities as fabrication, cleaning, erecting, packaging, handling, i shipping, storing and inspecting.
Procurement documents contain, as applicable, requirements which identify the documentation to be prepared, maintained, submitted and made available to the procuring agent for review and/or approval, such as drawings, specifications, procedures, inspection and test records, personnel and procedure qualifications and-material and test reports.
Procurement documents contain, as required, provisions for extending applicable requirements to lower tier subcontractors and suppliers, including purchaser's access to facilities and records. -
Procurement documents contain provisions for control of nonconfor-mances including 10CFR21 notification and for method of-acceptance of the item or service.
Procurement documents contain the requirements for the retention, control, submittal and maintenance of records.
Procurement documents contain the procuring agency's right of access to Vendor's facilities and records for source inspection and
- audit.
Changes and/or revisions to procurement documents are subject to at least the same review and approval rcquirements as the original document.
Purchase documents for spare or replacement parts of safety-related structures, systens and components are reviewed for adequacy of quality requirements by qualified personnel knowledgeable in quality assurance. The review is to determine the adequacy of the quality assurance requirements and acceptance criteria relative to the original design.
i The evaluation and selection of suppliers are determined by qualified personnel in accordance with written procedures acceptable to HL&P.
23
- - - e-, -
w --y + r- --v=, ic--w--w--,+"
Procurement documents, records and changes thereto are collected, stored, maintained and retrievable in a systematic and controlled manner.
HL&P Engineering is responsible for review of selected BEC Procurement Specifications.
Audits and surveillances are performed by either HL&P or BEC Quality Assurance personnel to verify that the requirements have been implemented and that they are effective.
5.0 Instructions, Procedures and Drawings The HL&P Project Quality Assurance Plan requires HL&P, the prime contractors and their suppliers to establish and implement a Quality Assurance Program which is in compliance with 10CFR50 Appendix B, ANSI N45.2 and applicable ANSI standards and Regulatory Guides. Each program is required to be effective in verifying that the defined activities are accomplished and documented in accordance with written procedures, instructions, and drawings and that they provide quantitative and qualitative acceptance criteria.
HL&P Project Quality Assurance reviews and approves the BEC South Texas Project Quality Assurance Program. To measure the effectiveness of the prime contractors' quality assurance programs, a monitoring program consisting of audits and surveillances has been established for the South Texas Project. HL&P Project Quality Assurance also audits HL&P Corporate organizations that perform functions for the South Texas Project. Additionally, HL&P Technical Services audits HL&P Project Quality Assurance and Westinghouse for compliance with their respective Quality Assurance Programs.
6.0 Document Control The HL&P Project Quality Assurance Plan and implementing procedures require that HL&P, the prime contractors and subcontractors implement a document control system for nuclear safety-related items for the South Texas Project. The established system ensures that design, engineering, procurement, fabrication, construction and QA/QC procedures, plans and changes thereto are reviewed and approved by procedurally authorized groups and that the documents are issued, maintained current and controlled by the use of controlled lists of document holders to ensure that superseded documents are replaced in a timely manner.
Measures are established and documented to control the issuance of documents, such as instructions, procedures and drawings, including changes thereto, which prescribe activities affecting quality. These measures assure that documents, including changes, are reviewed for technical adequacy and the inclusion of appropriate quality 24
r
- requirements, are approved for release by authorized personnel and are
= distributed to and used at.the location where the prescribed activity is performed. Changes to documents are reviewed and approved by the same organizations that performed the original review and approval unless other organizations.are specifically designated. The reviewing organizations have access to pertinent background information upon which j- to base their approval and shall have adequate understanding of the requirements and intent of the original document.
Those' participating in an activity are made aware of and use proper and current instructions, procedures, drawings and engineering requirements for performing the activity. Participating organizations have procedures for control of the documents and changes thereto to preclude
, the possible use of outdated or inappropriate documents.
Document Control measures provide for:
Identification of individuals or organizations responsible for preparing, reviewing, approving and issuing documents and revisions thereto; Identifying the proper documents to be used in performing the.
, activity; Coordination and control of interface documents; Ascertaining that proper documents are being used; l
Establishing current and updated distribution lists; I . -
A listing identifying the current revision of instructions, procedures, specifications, drawings and procurement documents.
The list is updated and distributed to predetermined responsible personnel.
Audits and surveillances are performed by either HL&P, BEC or ESI QA personnel to verify that document control systems are in place and effectively implemented.
7.0 Control of Purchased Material, Equipment and Services i The HL&P Quality Assurance Plan and implementing procedures require that HL&P, prime contractors and subcontractors define ar.d document-the system and requirements for the control of nuclear safety-related purchased material, equipment and services.-
i Control and verification of supplier's activities during fabrication, inspection, testing and shipment of materials, equipment and components is planned and performed as early as possible, as required to assure conformance to the purchase order or contractual requirements. These procedures provide for:
25
c l
Requiring the supplier to identify processes to be utilized in fulfilling procurement requirements.
Reviewing documents required to be submitted by the procurement requirements.
Specifying the characteristics or processes to be witnessed, )
inspected or verified and accepted based upon the fabrication i schedules; the method of surveillance and the extent of l documentation required; and those responsible for implementing these procedures.
Audits, surveillance and/or inspections which verify that the !
supplier complies with the quality requirements of his QA program.
Control and verification of organizations performing services is accom-plished by technical verification of data provided, surveillance and/or audit of the activity and review of objective evidence such as certifications, reports, etc. ,
The selection of suppliers is based on evaluation of their capability to I provide items or services in accordance with the requirements of the procurement documents prior to award of contract.
Procurement source evaluation and selection measures are implemented by HL&P and BEC which provide for the identification of the organizational responsibilities for determining supplier capability.
Measures for evaluation and selection of procurement sources, and the results thereof, are documented and include one ot more of (a) through (c) and also must include (d) below
- a. Evaluation of the supplier's history of providing an identical or similar product or service which performs satisfactorily in actual use. The supplier's history shall reflect current capability.
- b. Supplier's current quality records supported by documented qualitative and quantitative information which can be objectively evaluated. The records reviewed may include the ASME Section III Certificates of Authorization for N, NA, NPT and NV stamps.
- c. Supplier's technical and quality capability as determined by a direct evaluation of his facilities and personnel and the implementation of his approved quality assurance program. Reviews of ASME Nuclear Certificates of Authorization may be used to qualify the supplier in lieu of direct evaluation.
- d. Evaluation of bid documents including review for technical adequacy, quality assurance and commercial considerations.
26
Requiring the supplier to identify processes to be utilized in I fulfilling procurement requirements.
Reviewing documents required to be submitted by the procurement ,
requirements. '
Specifying the cl.4racteristics or processes to be witnessed, inspected or verified and accepted based upon the fabrication schedules; the method of surveillance and the extent of documentation required; and those responsible for implementing these procedures.
Audits, surveillance and/or inspections which verify that the supplier complies with the quality requirements of his QA program.
Control and verification of organizations performing services is accom-plished by technical verification of data provided, surveillance and/or audit of the activity and review of objective evidence such as certifications, reports, etc.
The selection of suppliers is based on evaluation of their capability to provide items or services in accordance with the requirements of the procurement documents prior to award of contract.
Procurement source evaluation and selection measures are implemented by HL&P and BEC which provide for the identification of the organizational responsibilities for determining supplier capability.
Measures for evaluation and selection of procurement sources, and the results thereof, are documented and include one or more of (a) through (c) and also must include (d) below:
- a. Evaluation of the supplier's history of providing an identical or similar product or service which performs satisfactorily in actual use. The supplier's history shall reflect current capability.
- b. Supplier's current quality records supported by documented qualitative and quantitative information which can be objectively evaluated. The records reviewed may include the ASME Section III Certificates of Authorization for N, NA, NPT and NV stamps.
- c. Supplier's technical and quality capability as determined by a i direct evaluation of his facilities and personnel and the implementation of his approved quality assurance program. Reviews of ASME Nuclear Certificates of Authorization may be used to qualify the supplier in lieu of direct evaluation.
- d. Evaluation of bid documents including review for technical adequacy, quality assurance and commercial considerations.
26
i 4
Procurement of spare or replacement parts for safety-related structures, systems and components is subject to QA program controls, to codes and standards and to technical requirements at_least equal to the invoked original technical requirements or any properly reviewed and approved revisions.
A receipt inspection is planned and implemented to assure:
Timely inspection of items upon receipt.
The material, component or equipment is properly identified and corresponds to the identification on the purchase document and receiving documentation.
Material, components, equipment and acceptance records satisfy the receiving inspection instructions prior to installation or use.
Specified inspection, test and other records are accepted and available at the South Texas Project prior to installation or use where required unless otherwise authorized by conditional release.
1 Items accepted and released are identified as to their inspection status prior to forwarding them to a controlled storage area or releasing them for further work or installation.
Coordination of receipt inspection with vendor surveillance activities to verify the required vendor inspection has been performed or a waiver documented.
Deficiencies if applicable have been resolved prior to shipment.
Supplier control and use of Certificates of Conformance,.when required by procurement documents, are evaluated by audits,-vendor inspections or tests to ensure they are valid. The supplier's records shall include a description of those nonconformances from the procurement requirements dispositioned " accept as is" or " repair," including evidence of acceptance by the purchaser's engineering organization.
Site receiving inspection ensures that, for nuclear safety-related items received at the South Texas Project, there is accompanying documentation
, that indicates review and concurrence by the appropriate prime contractor or designee, that the item complies with established requirements or has an authorized waiver prior to shiprnent. Audits and surveillances are performed by either HL&P or BEC Quality Assurance personnel to ensure compliance with these criteria.
~
HL&P Design Office Quality Assurance ensures by audits /surveillances of the AE/ Construction Manager's vendor surveillance function that source surveillance and inspection are performed in accordance with the quality 4 assurance program. In addition, audits and surveillances are performed
,. by either HL&P or BEC Quality Assurance personnel of activities 27
commencing with receiving inspection at the. site to ensure proper controls of purchased material and equipment are exercised and to ensure overall compliance.
8.0 Identification and Control of Materials, Parts and Components The HL&P Project Quality Assurance Flan requires that prime contractors and suppliers establish written procedures for the identification and control of materials, parts and components including partially assembled components. Prime contractor's and supplier's procedures shall include the documented verification of correct identification of materials, components and subassemblies, and that the method of identification does not affect the function or quality of the item prior to release of the items for assembly or installation. These procedures must:
Establish controls to identify and control materials (including consumables), parts and components (including partially fabricated subassemblies).
Provide specific identification and traceability controls when required by codes, standards or specifications.
Provide a method for identification and control of incorrect or defective items. This system includes verification and documentation prior to release for fabrication, assembling, shipping and installation.
1 All safety related items and material shall be controlled by one or more .
of the following: l 1
Uniquely identified and traceable.
Physically marked - items are not traceable but are readily l retrievable. 1 Physically identified as to type and user tested. l Identifiable as to type, by some physical characteristic or other administrative control.
BEC and ESI Quality Assurance verify that the above criteria are incor-porated into the quality / construction procedures during the
! review / approval cycle. Audits and surveillances are performed by either HL&P, BEC or ESI Quality Assurance personnel to verify compliance.
l 9.0 Control of Special Processes l The HL&P Project Quality Assurance Plan requires that written procedures be established by prime contractors and subcontractors for the activities associated with all special processes. For special processes ;
the qualification of personnel, procedures and equipment relating to I specific codes, standards, specifications and contractual requirements shall be documented and maintained current.
28
Special Processas - special manufacturing processes, metallurgical, chemical, material cleaning, welding, plating and other processes where :
assurance of the process quality is dependent largely on the inherent skill of the operator and cannot be assured by the inspection of articles alone.
Special processes for the South Texas Project include but are not limited to:
Welding Heat treating Cadwelding Nondestructive examination Chemical cleaning and flushing Coatings Organizational responsibilities are. defined in procedures for qualification of special processes, equipment and personnel. These responsibilities will include the provision to assure that special processes are performed by-qualified personnel using procedures qualified and approved in accordance with applicable codes, standards or other requirements.
Special processes are performed under controlled conditions by qualified personnel using procedures qualified and approved in accordance with applicable codes, standards or other requirements. For special processes not covered by existing codes or standards the specific equipment, personnel qualification and procedure qualification requirements are defined prior to application of the special process.
Records are maintained for the qualification of procedures, equipment and personnel associated with special processes. Records are in sufficient detail to clearly define the procedures, equipment or personnel being qualified; criteria or requirements used for qualification; and the individual approving the qualification.
HL&P Quality Assurance verifies that the special process control l criteria are met by BEC and ESI review and approval of special process procedures.
HL&P will retain the capability with a quality control group to perform, as directed by the PQAM, certain special process examinations (NDE) during the inspection verification process. Special process examinations performed during the inspection verification process will be accomplished using the same procedure that was used for the initial l
29 !
i
- examination. These examinations will be performed.by personnel qualified in accordance with SNT-TC-1A-80. Instances of recommendations
' within SNT-TC-1A-80 ('shoulds') will be considered mandatory require-ments ('shalls'.)._ This exception will be reflected in approved imple- 1 menting procedures.
~
Audits and surveillances of special process activities are performed by i
.either HL&P, .BEC or!ESI Quality Assurance personnel to ensure compliance l with all aspects of the Quality Assurance Program.
10.0 Inspection The HL&P Project Quality Assurance Plan requires the prime contractor for construction and subcontractors to establish and implement an inspection operation whose activities are independent from the group performing the activities being inspected. The training, qualifications and certifications of inspectors include criteria from appropriate coces, standards, and procedures. Inspector training shall be documented and kept current. Inspection activities relating to construction, fabrication, installation and testing are documented, kept i
, current and identify all mandatory inspection hold and test points and the criteria to be witnessed by authorized inspectors. Operations and inspections -(including rework, replaced items) are performed in predetermined, documented sequences. Deviations or deletions must be accomplished in accordance with approved and documented systems.
Inspection procedures include all required inspection operations defined by the specifications, drawings, codes and standards. These procedures-provide for the following:
- a. Identification of characteristics and activities to be inspected.
- b. A description of the method of inspection.
- c. Identification of the individuals or groups responsible for performing the inspection operation.
- d. Acceptance and rejection criteria.
- e. Identification of required procedures, drawings and specifications and revisions.
- f. Recording the identification of inspector and/or data recorder if applicable and the results of the inspection operation.
- g. Specifying necessary measuring and test equipment including accuracy requirements and verification of calibration.
- h. Evaluation of inspectico results.
30
4 i
Where direct inspections are imcossible or disadvantageous, in-process
- monitoring is specified in the inspection procedures and both direct and in-process monitoring are used when control is inadequate without both.
All required procedures, specifications and drawings are made available to the inspectors prior to performing inspection. If mandatory inspection hold points are required beyond which work cannot proceed without the specific consent of the designated representative, the specific hold points will be indicated in appropriate documents.
Inspection results are documented, evaluated and their acceptability determined by a responsible individual or group.
, BEC or ESI Quality Assurance verify that inspection control criteria are complied with by review and approval of the inspection procedures.
HL&P Quality Control may occasionally perform inspection verifications as deemed necessary by the Project Quality Assurance Manager.
Audits and surveillances of inspection activities are performed by either HL&P, BEC or ESI Quality Assurance personnel to ensure compliance with all aspects of the quality assurance program.
, The HL&P inspectors are trained and certified by a program conforming to 4
ANSI N45.2.6 and as applicable, SNT-TC-1A-80. Instances of recommendations within SNT-TC-1A-80 ('shoulds') will be considered 4
mandatory requirements ('shalls'). This exception will be reflected in approved implementing procedures.
11.0 Test Control The HL&P Project Quality Assurance Plan requires that a test control program be developed and documented by the prime contractors and 1
contractors for tests that they are responsible for, which demonstrates that the facility performs in accordance with the South Texas Project requirements and specifications. Preoperational testing and start-up testing requirements are established by the Operational Quality Assurance Plan, as described in Chapter 17.2 of the FSAR. The training,
- certification of personnel, calibration and certification of test equipment, system or component status, environmental conditions, inspection hold points and configuration of the items to be tested are i included in the procedures. Test results are documented, evaluated and the acceptance status determined by the authorized departments.
1 Test procedures or instructions provide for the following as required:
- ~
- a. The inclusion of requirements and acceptance limits contained in applicable design and procurement documents.
- b. Instructions for performing the test.'-
4 i
31
- c. Test prerequisites such as calibrated instrumentation, adequate I test equipment and instrumentation including their accuracy requirements, completeness of item to be tested, suitable and controlled environmental conditions and provisions for data collection and storage.
- d. Mandatory inspection hold points for witness by Owner and the contractor's inspector (as required),
- e. Acceptance and rejection criteria.
1
- f. Methods for documenting or recording test data and results.
- g. Provisions for assuring that test prerequisites have been met.
- h. Evaluation of results.
BEC and ESI Quality Assurance verify inclusion of adequate test control criteria by review and approval of test procedures. Audits and surveil-lances are performed by either HL&P, BEC or ESI Quality Assurance personnel to verify that the controls are implemented and effective.
The test control activities are an example of a case in which HL&P Project Quality Assurance monitoring activities and the Operational Quality Assurance monitoring activities will interface and in some instances overlap. HL&P Project Quality Assurance procedures will specifically define the responsibilities for this period.
12.0 Control of Measuring and Test Equipment The HL&P Project Quality Assurance Plan requires the establishment, documentation and implementation of a Measuring and Test Equipment Control System. The system is to include calibration techniques, accuracy, frequency and maintenance of all measuring instruments / test equipment used in the measuring, inspection and monitoring of nuclear safety-related items. Calibration and maintenance data shall be filed and kept current. Calibration standards are to be traceable to nationally recognized standards where standards exist. If standards do not exist, the basis for calibration of the equipment shall be documented. If measuring or test equipment is found to be out of calibration, missing or lost, an investigation is required to be performed to determine the validity of the use of the instrument and whether measurements or tests are required to be reperformed.
Reinspection when required will be documented.
Equipment is identified and traceable to the calibration test data and suitably marked to indicate calibration due date.
32
p Measuring and test equipment;is calitirated at specified intervals and based:on the required accuracy, purpose, frequency of use, stability characteristics, and other conditions affecting the measurement.
Calibration of this equipment is against standards .that have an accuracy of at least four times the required accuracy of the equipment being calibrated, or when this is not possible, have an accuracy that assures the equipment being calibrated will be within required tolerance and that the basis of acceptance is documented and authorized by responsible management.
Calibrating standards will, when possible, have greater accuracy than standards being calibrated. Calibrating standards with the same accuracy may be used if they can be shown to be adequate for the requirements and the basis of acceptance is documented and authorized by responsible management.
BEC and ESI Quality Assurance review and approve procedures for control of calibration of measuring and test equipment to ensure these criteria are incorporated. Audits and surveillances are performed by either HL&P, BEC or ESI Quality Assurance personnel to verify compliance.
In the conduct of its inspection verifications, as directed by the PQAM, HL&P Quality Control is required to use measuring and test equipment of the appropriate accuracy level which is controlled by procedures meeting the requirements of this section.
13.0 Handling, Storage and Shipping The HL&P Project Quality Assurance Plan requires that for nuclear safety-related items, written procedures be developed in accordance with design requirements, specifications and standards to control the cleaning, handling, storage, packaging, shipping and preservation to preclude damage and daterioration by environmental conditions. The activities are to be accomplished by appropriately trained and experienced personnel.
BEC and, as appropriate, ESI Quality Assurance review and approve quality construction procedures for receiving, handling, storage and
! cleaning to verify that the appropriate crf teria of Regulatory Guide i
1.38 and ANSI N45.2.2 are included. Periodic audits and surveillances
, are conducted by either HL&P, BEC or ESI Quality Assurance personnel to
- verify compliance with the procedures.
4 8
33
14.0 Inspection, Test and Operating Status The HL&P Project Quality Assarance Plan requires that the prime ;
contractor and construction contractors indicate the current inspection, '
test and operating status of nuclear safety-related items through the use of stamps, markings, tags or other suitable means. Procedures include the requirements for:
- a. Controlling the application and removal of inspection status indicators such as tags, markings, labels and stamps.
- b. Documenting the status of nonconforming, inoperative, or malfunctioning structures, systems and components to prevent inadvertent use.
- c. Defining, controlling and documenting the use, application and removal of inspection tags, labels or markings which identify the status of inspections or tests performed and attest to the acceptability of the structure, system or component.
- d. Controlling the altering of the sequence of required tests, inspections and other operations.
BEC and ESI~ Quality Assurance review and approve these procedures.
Audits and surveillances are performed by either HL&P, BEC or ESI Quality Assurance personnel to assure compliance.
15.0 Nonconforming Materials, Parts or Components The HL&P Project Quality Assurance Plan requires that HL&P maintains and the prime contractors' Quality Assurance Programs include a system which is documented by written procedures for the identification, segregation and disposition of nonconforming materials, parts and components. The procedures shall specify the preparation and handling of nonconformance documents, segregation requirements and which groups are responsible for review and disposition of the items. Documentation identifies the nonconforming item; describes the nonconformance, the disposition of the nonconformance and the inspection requirements; and includes signature approval of the disposition and final closeout. Nonconformances are corrected or resolution determined prior to initiation of the preoperational test program on the item. Rework, repairs and subsequent reinspection and tests are conducted in accordance with the original inspection and test requirements or accepted alternatives. These tests shall be performed in accordance with controlled procedures and contain mechanisms for providing information to the identifying group as to the disposition of the nonconformance. For NSSS items, the organization responsible for dispositioning of the nonconformance shall obtain concurrence of the Westinghouse Site Representative. HL&P Quality Assurance performs trend analysis of HL&P, BEC and ESI nonconformances.
Procedures are established by HL&P to report significant deficiencies during the design, construction and startup phase to HL&P executive managemeat and to the Nuclear Regulatory Commission in accordance with 10CFR50.55(e) and 10CFR21 where applicable. Either HL&P, BEC or ESI Quality Assurance personnel perform periodic audits and surveillances to assure compliance.
34
e ,
16.0 Corrective Action The HL&P Project Quality Assurance Plan for the South Texas Project requires that a system be established and docuinented by HL&P and the prime contractors which defines the responsibilities, authorities and methods used by specific groups involved in the evaluation of nonconformances and trending to determine the need for corrective action. The system includes measures to identify the cause of significant conditions adverse to quality, measures to ensure that the root causes are corrected, and measures to ensure that timely action is taken. Follow-up is performed to ensure the effectiveness of corrective action and that appropriate . levels of management are informed of the results. HL&P performs trend analysis of HL&P, BEC and ESI identified deficiencies to determine the need for corrective action. General categories of documents to be trended are: Nonconformance Reports; Standard Deficiency Reports; Deficiency Notices; Inspection Reports; and Audit Deficiency Reports. Specific documents to be trended, and the frequency of trending, are identified in approved procedures. Either HL&P, BEC or ESI Quality Assurance personnel perform audits and surveillances to assure compliance.
)
17.0 Quality Assurance Records The HL&P Project Quality Assurance Plan requires that a Quality Assurance record system be developed by HL&P and the prime contractors for the South Texas Project. The record system provides evidence that activities relating to quality are defined, implemented and that inspection and test documents contain a description of the type of observation, reference to nonconformance reports, evidence relating to status of observation, date and inspector identification.
Quality records shall include reviews, audits, reports, specifications, ;
nonconformance reports, analyses, personnel and equipment qualification procedures.
The HL&P Project Quality Assurance Plan requires that HL&P and prime contractors establish requirements to ensure that records generated during the design, procurement and construction are identifiable, retrievable and meet the requirements of 10CFR50, Appendix B, and ANSI N45.2.9 as endorsed by Regulatory Guide 1.88.
As an alternative to the ANSI N45.2.9 storage requirements, records may be maintained for the South Texas Project in a two-hour rated fire resistant file room meeting NFPA No. 232-1975 including the following provisions:
An automatic fire suppression system and an early warning fire detection system is utilized.
l 35 I
...,,,.._-__r.. . ,,.,m.. . , _ _ ~ , . _ . . , . , , , , _ , . . . . - , . . . _ . . - , - .-,- - -.
l i
Records are stored in fully enclosed metal cabinets.
Smoking and eating / drinking are prohibited within the records storage facility.
Work not directly associated with record storage or retrieval is prohibited within the records storage facility.
Ventilation, temperature and humidity control equipment is controlled where they penetrate fire barriers bounding the storage facility. :
Either HL&P, BEC or ESI Quality Assurance personnel perform audits and surveillances to assure compliance.
18.0 Audits The HL&P Project Quality Assurance Plan establishes the requirement that HL&P, prime contractors and subcontractors develop, document and implement audit activities which are structured in accordance with the ,
requirements of ANSI N45.2.12 for the South Texas Project. As required l by the ANSI standard, results of audits are presented for review to management of the audited organization and, in the case of HL&P performed audits the HL&P Group Vice President, Nuclear. Where indicated HL&P performs follow-up action.
HL&P has the ultimate responsibility for the auditing of quality related activities on the Project. HL&P Technical Services audits are performed primarily on the HL&P Project Quality Assurance group, and Westinghouse.
HL&P Project Quality Assurance is primarily responsible for audits of the Engineer / Construction Manager, constructor, subcontractors, HL&P Project team organizations, and the HL&P corporate organizations providing services to the Project. To the extent possible, audits are scheduled such that recurring audit areas are audited by different organizations on successive audits when deemed appropriate. Certain selected audit areas will be retained by HL&P in order to provide continued assurance that HL&P, Bechtel and Ebasco programs are maintained as required.
The prime contractors and subcontractors perform quality related audits of internal activities and suppliers of material, components and systems.
HL&P, BEC or ESI personnel perform supplemental audits when required, !
based on such factors as significant changes in the Quality Assurance l Program, results of trending programs or investigations into the root !
causes of problems. !
l l
36
'~
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE The STP Quality Assurance Program complies with the following ANSI Standards and associated Regulatory Guides except as noted:
STANDARD TITLE ANSI N45.2-1971 Quality Assurance Program R.G. 1.28 (Rev. 0, 6/72) Requirements for Nuclear Power Plants ANSI N45.2.1-1973 Cleaning of Fluid Systems and R. G. 1.37 (Rev. O, 3/73) Associated Components During (see notes 8 through 10) Construction Phase of Nuclear Power Plants ANSI N45.2.2-1972 Packaging, Shipping, Receiving, R.G. 1.38 (Rev. 0, 3/73) Storage and Handling of Items for (see Notes 11 through 16) Nuclear Power Plants ANSI N45.2.3-1973 Housekeeping During the Con-
- R.G. 1.39 (Rev. O, 3/73) struction Phase of Nuclear Power (see Notes 17 and 18) Plants ANSI N45.2.4-1972 Installation, Inspection and R.G. 1.30 (Rev. O, 8/72) Testing Requirements for (see Notes 19 and 20) Instrumentation and Electric Equipment During the Construction of Nuclear Power Generating Stations ANSI N45.2.5-1974 Supplementary Quality Assurance (see Notes 1 and 2) Requirements for Installation, Inspection and Testing of
, Structural Concrete and Structural C+- 1 During the Construction
- Phat of Nuclear Power Plants.
ANSI N45.2.6-1973 Qualif ;ations of Inspection, R.G. 1.58 (Rev. O, 8/73) Examination and Testing Personnel As modified by positions C.5, for the Construction Phase of C.6, C.7, C.8 and C.10 of Nuclear Power Plants Rev. 1 (see Note 34)
ANSI N45.2.8-1975 . Supplementary Quality Assurance Reg. 1.116 (6/76) Requirements for Installation, (see Notes 21 through 23) Inspection and Testing of Mechanical Equipment and Systems for the Construction Phase of Nuclear Power Plants 1
1
_ _ . . _ . _ , _ . . . - . - . _ , _ , - _ , _ . _ _ _ , , _ , . _ _ - - . ~ .
+ -
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (Continued)
ANSI N45.2.9-1974 Requirements for Collection, R.G. 1.88 (Rev. 2, 10/76) Storage and Maintenance of Quality (see Notes 24 through 26) Assurance Records for Nuclear Power Plants ANSI N45.2.10-1973 Quality Assurance Terms and R.G. 1.74 (Rev. O, 2/74) Definitions ANSI N45.2.11 1974* Quality Assurance Requirements for R G. 1.64 (Rev. 2, 6/76) the Design of Nuclear Power Plants (see Notes 3 through 7)
ANSI N45.2.12-1977 Requirements for Auditing of R.G. 1.144 (Rev. 1, 9/80) Quality Assurance Programs for (see Notes 32 and 33) Nuclear Power Plants ANSI N45.2.13-1976 Quality Assurance Requirements for R.G. 1.123 (10/76) Control of Procurement of Items and (see Notes 27 through 31) Services for Nuclear Power Plants ANSI N45.2.23-1978 Qualification of Quality Assurance R.G. 1.146 (Rev. O, 8/80) Program Audit Personnel for Nuclear Power Plants Exception Notes
- 1. ANSI N45.2.5-1974, Section 4.8 states " Pumped concrete must be sampled from the pump line discharge." In lieu of this statement, in-process strength samples of pumped concrete are taken at the delivery point. Correlation tests of air content, slump, and temperature are performed to verify theso plastic properties of the concrete at the placement point in accordance with the following frequency requirements:
- a. A minimum of 2 correlation tests are performed for each pumped placement exceeding 200 cu. yds.
- b. Otherwise, a minimum of 2 correlation tests per week are performed when any individual pumped placement during a week requires delivery of more than one truckload of concrete.
- c. During a week when a pumped placement exceeding 200 cu. yds is made, the correlation tests performed on that placement will satisfy the weekly requirement for performing two correlation tests as specified in Item b above.
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (Continued)
If the correlation test result shows a concrete property not meeting the specification limits and/or tolerances at the point of placement, the frequency of correlation testing 'shall be increased .to 100 cubic yards. If two consecutive correlation tests exceed the specified limit for slump, air ,
content, or temperature, the Constructcr shall document the condition, l notify Bechtel Site Engineering within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of completion of the !
placement and shall return to control of the concrete by in process testing at the point of placement per ANSI N45.2.5-1974.
" Correlation Tests," " Delivery Point," and " Placement Point" are as defined in ANSI N45.2.5-1978, Section 1.4.
- 2. Samples and frequency for cadweld testing is in accordance with ACI-359/-
ASME Section III, Division 2, issued for trial use and comment in 1973, including addenda 1 through 6, (see Sections 3.8.1.6.3 and 3.8.3.6.3 of the 4
STP Final Safety Analysis Report). '
- The following interpretations (Notes 3 through 7) of ANSI N45.2.11-1974 and Regulatory Guide 1.64, Rev. 2-6/76, apply to HL&P, their contractors and '
consultants working under HL&P's Quality Program.
- 3. Section 3.1, Design Input Requirements, General. This section implies that all necessary~ design input (as listed-in Section 3.2) should be available prior to the start of a design activity. In practice, certain design activities are initiated before the firm input requirements are available.
(For example, foundation designs prepared based on preliminary information or equipment sizes and mounting, embedded conduit run based on preliminary estimates of circuit requirements, etc.). - The design phase Quality Assur-ance program will be structured to ensure that all necessary design input is available before completion of final design of the work affected by the input, and that final design input is available for use -in. verification of the final design.
- 4. Section 4.1, Design Process, General. Paragraph 3 implies traceability back from final design to the source of design input. In practice, a literal interpretation of this is not always possible. For example, final design drawings do not identify the related calculations. This paragraph will be interpreted to mean that it shall be possible to relate the cri-teria used and analyses performed to the final design documents and that record files will permit location of analyses supporting specific design output documents.
- 5. Section 4.2, Design Analyses. This section implies a requirement for retention of all calculations. In principle, it is considered good prac-tice for the responsible engineer or engineering organization to retain all I
J
_ . , _ _ ._ _ ___-_. ~._ . _ _ _ _ _ ___ _ _ - _ _. _ _ ,. _-__ _ _ - _ _ -
i l
s
- l TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (continued). .
final calculations, and this will be done for all manual calculations covered by the program.' However, for computer programs only documentation of the design input, assumptions made in the analyses, results obtained,
- and evidence of verification will be retained since permanent retention of
'all versions of all computer programs is not considered practical or necessary if sufficient information is available for a competent individual to verify the results using the input and assumptions.
- 6. Section 10, Records. In-process documentation, relating to checking and coordination of drawings (for example, check and coordination prints) or copies of marked-up specifications used to solicit comments shall be retained until the drawing or specification is approved and issued for use outside of Engineering. Such in-process documents will be available for review / audit until the document is approved, but may be discarded once the document has been approved. In the first sentence of the second paragraph the phrase " final design documents" shall mean those documents which are ,
the latest revision that has been issued for use.
- 7. Regulatory Position, Section C-2: If, in an exceptional circumstance, .the originator's immediate supervisor is the only technically qualified individual available, the design verification or checking will be conducted by the supervisor with the following provisions:
- a. The other requirements of Regulatory Guide 1.64 will be met.
n
- b. The justification will be individually documented and approved by the next level of supervision.
- c. Quality Assurance audits will include review of the frequency and i
effectiveness of the use of the immediate supervisor to assure that this provision is used only in exceptional circumstances.
- 8. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more. pro-jects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or proce-dures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality. This is consistent with
- Section II, Paragraphs 2 and 3 of ANSI N45.2-1971 which provides for examination, measurement, or testing to assure quality or indirect control by monitoring of processing methods. However, final cleaning or flushing activities will be performed in accordance with procedures specific to the
( system.
, - , v- m y e - - - - , , - - , - - . - - --m---e, ---ww-,m-ve---+----,rr e--e- ,w -m e *----+e e--ve- - w w ww *w +ee-- 1-w,, +e e -w--e--
)
l l
l TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (continued)
- 9. Section 4, Preinsta11ation Cleanliness. This section states, " Items should not be delivered to the point of installation site sooner than necessary unless the installed location is considered a better storage area." As an alternate to this requirement, items may be delivered to the installation site sooner than absolutely necessary when determined to be advantageous for other considerations, for example, reduced handling or easier access, thereby reducing susceptibility to handling damage. In all such cases, equipment stored inplace will be protected in accordance with Section 5 of ANSI N45.2.1.
- 10. Section 3.1.2, HL&P interprets the lighting level of 100 footcandles to be guidance. It is HL&P's normal practice that the lighting level for deter-mining " metal clean" of accessible surfaces of piping and components is determined by the inspector. Typically he uses a standard two-cell-flashlight supplemented by other lighting as he deems necessary.
- 11. Section 2.7, Classification of Items. The four-level classification system may not be used explicitly. However, the specific requirements for each classification as specified in the standard will be applied to the items suggested in each classification and for similar items.
Classification differing from Section 2.7 will be considered acceptable provided no degradation is assured; for example, electric motors designed for outside service may be stored in Level C area rather than a Level B.
- 12. Section 6.2, Storage Areas. Paragraph 6.2.1 requires control and limited access to storage areas. In lieu of and to amplify this paragraph, the following will be applied:
Access to storage areas for Level A, B and C will be controlled by the individual (s) responsible for storage. While the above areas will be posted to limit access, other positive controls (other than that for the overall site area) or guards may not be provided. Level D areas will be posted with the storage level designation only.
- 13. Section 5.5, Correction of Nonconformances. This section provides for
" rework" and "use as is" dispositions for nonconforming items. As an l alternate, the " repair" disposition (as defined in ANSI N45.2.10-1973) will also be used.
l
- 14. Section 6.2.4, Storage of Food and Associated Items. Controlled areas, within storage areas, will be established for the storage of food, drink, and salt tablets. These areas will be controlled through normal super-vision and inspection.
- r
(
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE-
, (continued)
- 15. In Section 8, the control of documentation and records shall be in accord-ance with Section 17 of this Program Description.
- 16. Appendix A 3.4.2, Inert Gas Blankets. There may be cases involving large or complex shapes for which an inert or dry air purge flow is provided .
rather than a static gas blanket in order to provide adequate protection due to difficulty of prcviding a leakproof barrier. In these cases a positive pressure purge flow may be utilized as an alternative to the
- leakproof barrier.
- 17. Section 2.1, Planning. The required planning is frequently performed on a
. generic basis for application to many installations on one or more pro-jects. This results in standard procedures or plans for installation and '
inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless
.the work operations are unique. However, standard procedures or plans will be reviewed.for applicability in each case. Installation plans or proce-dures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
! - 18. Alternative equivalent zone designations and requirements may be utilized to cover those situations not included in the subject standard; for exam-ple, situations in which shoe covers and/or coveralls are requirad but material accountability is not. In addition, zones might be combined into the next more restrictive category in order .to reduce total number of zones.
- 19. Section 1.2, Applicability. The Standard is applied to the items and systems identified in Paragraph 1.1.1 and to additional systems depending on the nature and scope of the work to be performed and the importance of the item or service involved.
- 20. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more pro-jects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless
~the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or proce-dures are also limited in scope to thosa actions'or activities which are essential to maintain or achieve. required quality.
l.
- . . - , ~ _ , - _ - , -
.---,-,--,,-,,,.,,,,,..,..,,,----..,,.,.,--,,--,,,,,-~.y..,cr----, -,--p . - - .,-,y---.~---.--,--we---,,+.. 1-,
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (continued)
- 21. Section 1.1, Scope. The term "important items" will be interpreted to apply to those activities or quality attributes of an item or service that could affect a nuclear safety-related characteristic. For example, if a barrier is required for leakage control, but serves no structural function, the leaktight characteristic would be considered "important", but appear-ance, dimensional requirements, and structural features would not.neces-sarily be considered important; or if a pump casing is required for coolant.
boundary integrity, but the pump does not have to operate to provide for nuclear safety, those attributes which affect its operation would not be considered important from the standpoint of nuclear safety.
Section 2.1, Planning. The required planning is frequently performed on a .
generic basis for application to many installations on one or more pro-jects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or proce-dures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
- 22. Section 3.3, Process and Procedures. The terms " installation site",
" installation area", and " site" used in this standard shall be interpreted as follows:
- a. " Installation site" or " site" will be interpreted the same as
" construction site". When applied to documents, these may be at the i central-office or work area document control station,
- b. Installation area - Immediate proximity of location where work is to be perfonned.
- 23. Section 3.5(e), Site Conditions. This requirement will be applied only if subsequent correction of adjacent nonconformances could damage the item being installed.
Section 4.6, Care of Items. HL&P retains the authority and is the "Respon-sible Organization" for temporary usage of equipment or facilities unless specific (i.e. on a case by case basis) or general authority is granted in writing to the Construction llanager's organization.
- 24. Section 1.4, Definitions. Quality Assurance Records - A document is considered completed when it has finished full processing and has been issued for use in design, procurement, construction, or manufacturing.
l
-_ . , , - - . -. m. .-. . - _ , , . _ _ _ . . - _ . - - - . , _ , - - . . - _ . , _ . _ _ ~ . . - _ _ - . _ _ _ _ - _
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (continued) a
- 25. Section 1.4, Definitions. Authenticated Records - Those records which are clearly identified as a statement by the individual or organization holding responsibility. Handwritten signatures are not required if the document or printout is clearly identified as a statement by the reporting individual 3
or organization.
- 26. For Appendix A, an installation shall be considered to be in an "as con-structed" condition if it is installed within the tolerances established by Project Engineering indicated in the design output documents.
- 27. Section C.3 of the Regulatory Guide - A corrective action system may, depending upon complexity and/or importance to safety of the item or service provided, be imposed upon the supplier. When a corrective action i
system is imposed on a supplier, the applicable elements of-Section 9.0 of the standard will be included and its implementation will be verified.
- 28. Section C.4 of the Regulatory Guide - Applicable information concerning the
, method (s) of acceptance of an item or service will be made available to receiving inspection personnel.
- 29. Section 4.2.a of the Standard - When evaluation of a supplier is based solely on historical supplier data,'these data will primarily include r HL&P's or a prime contractor's records that have been accumulated in connection with previous procurement actions. Data that includes exper-1ence of users of identical or similar products of the prospective supplier and product operating experience will be used if they become available; however, such data are normally available only to those involved in plant
- operations.
- 30. Section 10.2.d.-of the Standard - The requirements of this section are
- interpreted as follows
- The person attesting to a certificate shall be an authorized and responsible employee of the supplier and shall be identified by the supplier.
- 31. HL&P's position relative to ANSI N45.2.13-1976, Section 10.2.f., Verifi-cation of the Validity of Supplier Certificates and the Effectiveness of i
the Certification System, is as follows: The verification of the validity i
of supplier certificates and the effectiveness of the certification system are accomplished as an integral part of the total supplier control and
- product acceptance program, and no separate HL&P system exists that ad-dresses itself solely to such verification. The degree of verification required will depend upo1 the type of item or service and their safety importance. The means of verification may include source witness / hold I
points, source audits, and document reviews; independent inspections at the time of material receipt; user tests on selected commodities, such as concrete components; and tests after installation on selected components and systems. All of these means verify whether or not a supplier has fulfilled procurement document requirements and whether or not a certifi-cation system is effective.
TABLE 1 ANSI STANDARD AND REGULATORY GUIDE COMPLIANCE (continued)
- 32. ANSI N45.2.12-1977, Section 4.5.1 states, "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed." This implies that the audited organiza-tion must provide the auditing organization with written notification detailing what corrective action was taken and when the corrective action was completed.
In actual practice, the audited organization will provide the auditing organization with documented corrective action including the date when the corrective action will be completed. The auditing organization will evaluate the corrective action response to determine if corrective action verification is necessary. If verification is necessary, the corrective action verification will be performed after the scheduled completion date and the results of the verification will be documented.
- 33. ANSI N45.2.12-1977, Section 1.3 states, "In no way shall the performance of audits by an organization diminish the responsibility of the audited organization or contractor for audit of his designated portion of the quality assurance program or the quality of his product or services". For the South Texas Project all quality related activities implemented for the South Texas Project are audited annually at a minimum, or at least once within the life of the activity, whichever is shorter. These audits are performed by either HL&P, BEC, or ESI Quality Assurance personnel.
- 34. As an alternate, compliance with ANSI N45.2.6-1978 and R. G. 1.58 (Rev. 1, 9/80) ir :ts entirety is acceptable.
l
TABLE 2 HL&P MANUALS USED TO IMPLEMEN1 THE QUALITY ASSURANCE PROGRAM Project Quality Assurance Plan Project Specific Quality Assurance Procedures Manual Standard Quality Assurance Procedures Manual Technical Services Procedures Manual Project Engineering Procedures Manual Interdepartmental Procedures Manual Project Licensing Procedures Manual Project Procurement Procedures Manual Project Management Procedures Manual Records Management Systems Procedures Manual Standard Site Procedures Manual
{
1.4 GROUP VICE PRESIDENT NUCLEAR 1.5 1s GENERAL MANAGER MANAGER SOUTH TEXAS NUCLEAR
- -PROJECT LICENSING 1.7 1.8 MANAGER GENERAL MANAGER ENGINEERING NUCLEAR ASSURANCE ASSURANCE 1.10 VICE PRESIDENT MANAGER NUCLEAR PLANT NUCLEAR OPERATIONS ENGINEERING 1.9 -
PROJECT & TECHNICAL DIRECTION MANAGER TECHNICAL DIRECTION NUCLEAR TRAINING PROJECT DIRECTION ..............
FIGURE 1
1.E GDEltAL MANMIDt EDUTH TDfAE MtDJECT ntPUTY MIDJECT MANA30t MmAGER I01 Nua.Ent tW
. , , . . . . _ 1.5.2 l 1.5.3 i u.s, ~- 3 f l ,
e l
- ggq t.,
- n ... CNt J 4 r r n g e ,- n s ,,,)
t l
l 1G4 1ss suPDtvtstut I PiqDECT 30tVICES CtmSTfluCT1th l me :UnneDt ameasTR4Txm I
i 1.5.7 1.5.13 i N aDi l N aut - - MaNr. ""
ENGDEDt!NG llDCtBENT CGdTRIL l
DFD. PIEXISSING I 1.5.3 1.5.9 .__L 5 L 1.5.14 1.5.6 WAL DEDEDt PitDCIPAt. ENGDEDt Pftt1 JECT MANMElt NUE SITE [FS. SUPPGtT CDET/3CEDtLD8ti IECWtBS MIBtT.
DesmEDtDec EusDeutDe NunoDt nocuMDet n NN l
1.5.10 1.5.10 1.5.12 1.5.15 MuMCPM. ENGDE:DI PRDCPM Di[ENEDt CD. "" '
MtoonANs CDRDS sTsims - P,RO M -
gyjgy -
j 1.5.10 I PsuMCFM. DNEMEUt
- sDtv!CEs i PROJECT & TECHNICAL DIRECTION
- TECHNICAL DIRECTION _ -
SUPDtVI!!NG PROJECT DIRECTION ..............
ENGDEDt STP t.XXNE3MG FIGURE 2
1.6 MANAGER NUCLEAR LICENSING SUPERVISING SUPERVIS!NG ENGINEER ENGINEER STP LICENSING SITE LICENSING SUPERVISOR PRINCIPAL ENGINEER ADMINISTRATIVE SITE SUPPORT ENGINEERING PROJECT & TECHNICAL DIRECTION TECHNICAL DIRECTION _
PROJECT DIRECTION ................
{
l FIGURE 3
= a a 4 + '. -
1.8 GDERAL MANAGER NUCLEAR ASSURANCE 1.8.1 1.8.9 tratATEMS PRGRCT GENDtAL GA GA StFDtVISGt NANAGDt NANAGER TEQ4GCAL SUtVICES 1_R 7 PROKCT QA SIFutVISGt StPERVISGt VDGER EVAL QUALITY SLRVOLLANCE CENTROL 1 R_1 1.8.8 PROKCT SA PRnKCT StPDtVISGt SUPOtVISOR N CUALITY SYSTEMS PftOCURDENT AFINISTRATION 1Rt IIEPUTY PROKCT QA NANAGElt 1.8.5 1.8.7 1.8.6 PROKCT PftDECT pit 0ECT SUPERVISGt StPDtVIst3t SLPDtVISGt ANALYSIS SURVE!LLANCES AUDITS PROJECT & TECHNICAL DIRECTION TECHNICAL DIRECTION ----
PROJECT DIRECTION ..............
FIGURE 4
14 MANAGER NUCLEAR TRAINING TRAINING TRAINING SUPERVISOR MANAGER NANAGER PROGRAN DESIGN
[PERATIENS STAFF TRAINING AND TRAINING DIVISION DIVISION EVALUATION OECTION e
O PROJECT & TECHNICAL DIRECTION TECHNICAL DIRECTION _ _ _
PROJECT DIRECTION ...............
4 FIGURE 5 4
a m w-w--..-n r--- , , - , -- - w-- --s- e- -v+,- ..-vg e,- +------we,--w--nm--vr--vw,m, w -~p-w-----wwww 1vn e'w"-m--nve~n~*,-* w~v-*' p-- --v ---*s-' w*-
I 1
i
~
RIAP BEC/nlESTINCuoUSE/ESI/ECA
((XHrTt/.t"f0ES) j i
CROUP BEC/ WESTINGHOUSE '
VICE. PRESIDENT (CCNTRACTORS)
NUCLEAR MANAGEMENT
.I T T I I VICE-PRESIDENT NUCLEAR ENGINEERING GENERAL MNAGER NUCLEAR ASSURANCE g.
AND CONSTRUCTION f I ,
GENERAL MANAGER PROJECT QA QUALITY AS$URAhCE PROJECT SOUTH TEXAS PROJECT h MANAGER O MANAGEMENT MNAGEMENT 1 1 DEPUTY PROJECT GA/QC PROJECT $UPERV150R(5)
MANAGER J >
LIwas or mi M ACATION EIAP AND BEC/nfESTINCEOUSE/ESI/ECI (CONTRACTOES)
I FIGURE 6 4
. . _ _ . --. _ _ . . ~ _ . _ . . - - . _ _ _ _ _ _ _ _ . _ . .-. . . . . . . . _ . . . . _ _ _ . _ . . , _ . _ . - _ _ . _ . _ . . _ _ _ _ . . _ . _ _ . _ _ _ _ _ . . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
PART B BECHTEL ENERGY CORPORATION QUALITY ASSURANCE PROGRAM DESCRIPTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION REVISION 15 September 26, 1986 Date t
QUALITY ASSURANCE PROGRAM DESCRIPTION PART B FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION (STPEGS)
INTRODUCTION This document describes the Quality Assurance Program applied by Bechtel* to the design, procurement, and construction management of the South Texas Project. This document serves as Bechtel's portion of the Quality Assurance Program Description, the compliance document which fullfills the requirements of Chapter 17 prescribed in the " Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants", Regulatory Guide 1.70, Rev. 2, September 1975. This document is periodically reviewed and revised as necessary.
Bechtel Energy Corporation is responsible for Engineering, Procurement and Construction Management activities at the South Texas Project. This activity
-includes receiving, storage, maintenance, receiving inspection and Quality Assurance functions. Bechtel Construction Management is responsible for management of the construction and quality assurance / quality control activitiesoftheConstructor/ Contractor (s). Construction Management consists of planning, scheduling, monitoring and evaluating the Constructor /
Contractor (s) construction and quality assurance / quality control activities.
-The construction, site engineering, and quality control activities defined in this document will be the responsibility of the Constructor / Contractor (s).
The Constructor / Contractor (s) will be responsible for submitting to Bechtel, for approval, a quality program which is- consistent and compatible with the applicable sections of this program.
- The Quality Assurance Program described in this document is consistent with the Bechtel overall goals and objectives of maintaining the competence of its service and quality of its end products at contractually required levels.
This Quality Assurance Program is applied by Bechtel to those safety-related structures, systems, and components (Q-List items) identified in appropriate sections of the safety analysis report for which Bechtel has the '
responsibility for design, procurement, and construction management. This document does not cover preoperational testing activities.
The term " Quality Assurance" has been defined as "all those planned or systematic actions necessary to provide adequate confidence that an item or facility will perform satisfactorily in service." Quality assurance is recognized as a function of the group performing the work and not the sole respcnsibility of a quality assurance group.
O The term Bechtel is employed in this document to identify the Bechtel Western Power Corporation (BWPC) and associated companies, including Bechtel Energy Corporation, which is contractually responsible for the Design and Construction Management of STPEGS.
000lV/000lv Quality is achieved through the use of skilled personnel, adequate planning, use of suitable tools and procedures, proper definition of job requirements, and appropriate supervision and technical direction. Quality is verified through surveillance, inspection, testing, checking, and review of work activities and documentation. It is Bechtel policy that the organization or group that performs the activity (i.e., Engineering, Procurement, Construction, etc.) is responsible for the generation of a quality product.
Quality control and quality verification are performed by individuals who are not directly responsible for performing the work activity. The separation of responsibilities by organization for performance of the work activities and for performance of quality control and quality verification is discussed in Section 1 of this document.
s In addition, it is Bechtel policy that a qu % ty assurance function consisting of program definition, program coordination, and the review, surveillance, and the audit of quality-related activities is assigned to a group which is independent of the organizations responsible for the work. This group called Quality Assurance is responsible for defining and coordinating the Quality Assurance Program and for monitoring and auditing program activities to verify compliance with established requirements and to review program adequacy. When the term Quality Assurance is applied to personnel titles or procedures, it refers to the personnel and practices of the Quality Assurance Group. The overall Bechtel Quality Assurance Program, which includes the activities of the organizations performing work as well as those performing quality control and quality assurance function, is also referred to as the Bechtel Quality Program.
The Bechtel Quality Program commits to comply with the requirements of NRC Regulations, " Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants and Fuel Reprocessing Plants," 10CFR50 Appendix 8. The program also commits to comply with the quality assurance requirements of the ASME Boiler and Pressure Vessel Code,Section III, for items covered by the Code.
The Bechtel program is committed to follow the regulatory positions contained in the following documents and ANSI Standard ANSI N45.2.5:*
Regulatory Guide 1.28 " Quality Assurance Program Requirements (Design and Construction) (formerly Safety Guide 28) (Rev. O, June 1972)"
Regulatory Guide 1.30 " Quality Assurance Requirements for Installation, Inspection, and Testing of Instrumentation and Electric Equipment (formerly Safety Guide 30) (Rev. O, August 1972)"
Regulatory Guide 1.37 " Quality Assurance Requirements for Cleaning of Fluid Systems and Associated Components of Water-Cooled Nuclear Power Plants (Rev. O, March 1973)"
Regulatory Guide 1.38 " Quality Assurance Requirements for Packaging, Shipping, Receiving, Storage and Handling of Items for Water-Cooled Nuclear Power Plants (Rev. O, March 1973)"
0Bechtel's position, as exceptions to and interpretations of this guidance for STPEGS, is contained in Appendix A of this document.
000lV/0001V Regulatory Guide 1.39 " Housekeeping Requirements for Water-Cooled Nuclear Power Plants (Rev. O, March 1973)"
Regulatory Guide 1.58 " Qualification of Nuclear Power Plant Inspection, Examination and Testing Personnel (Rev. 0, August 1973)"
Regulatory Guide 1.64 Quality Assurance Requirements for the Design of Nuclear Power Plants, (Rev. 2, June 1976)"
Regulatory Guide 1.74 " Quality Assurance Terms and Definitions (Rev. O, February 1974)"
Regulatory Guide 1.88 " Collection, Storage, ano Maintenance of Nuclear Power Plant Quality Assurance Records (Rev. 2, October 1976)"
Regulatory Guide 1.116 "QLality Assurance Requirements for Installation, Inspection and Testing of Mechanical Equipment and Systems (Rev. 0-R, June 1976)"
Regulatory Guide 1.123 " Quality Assurance Requirements for Control of Procurement of Items and Services for Nuclear Power Plants (Rev. O, October 1976)"
Regulatory Guide 1.144 " Auditing of Quality Assurance Programs for Nuclear Power Plants (Rev.1, September 1980)"
Regulatory Guide 1.146 " Qualification of Quality Assurance Program Audit Personnel for Nuclear Power Plants (Rev. O, August 1980)"
ANSI Standard " Supplementary Quality Assurance Requirements for N45.2.5-1974 Installation, Inspection, and Testing of Structural Steel During the Construction Phase of Nuclear Power Plants" The terms used in this document follow the definitions provided in ANSI N45.2.10-1973 as endorsed by Regulatory Guide 1.74, Rev. O, 2/74, supplemented by the following additional terms and definitions applicable to this document.
- 1. Administrative Direction (Administrative Supervision):
Responsibility for hiring, salary review, and assignment of an individual.
- 2. Approve: When used in context with Bechtel review of supplier documents, the word " approve" or words of like import, such as-
" review" and " accept", shall mean, unless the context clearly indicates otherwise, that the supplier shall, before implementing the information in the document, submit the document, obtain resolution of any comments, and obtain authorization to proceed, and shall not mean that a complete check will be performed. Authorization to proceed shall not constitute acceptance or approval of design details, calculations, analyses, test methods or materials developed or selected by the supplier and shall not relieve supplier from full compliance with contractual obligations.
000lV/000lv - --. . .-. ... - -
e
- 3. Contractor: Supplier of construction site services, materials, or equipment. On construction management jobs, contractors under direct contract to the client may provide construction site services.
4 Coordination: Bringing together and assuring communication between independent groups, including responsibility for identification of interface problems, reconciling a position, and arriving at agreement.
- 5. Corporate Control: Technical and administrative direction of a functional manager to his office counterpart.
- 6. Corporate Quality Policies - Guidance defining requirements and responsibilities for accomplishing Quality Program functions
-which may be modified, deleted by, or supplemented with project documents to meet specific project / owner requirements and the scope of the project.
- 7. Formulate: To be responsible for coordination of effort by affected organizations and preparation of documentation describing or defining a policy procedure.
- 8. Material Certificate of Compliance: Verification document which certifies conformance to the requirements of the applicable material specification.
- 9. Monitor: To watch over, observe, or examine a work operation.
Results of the observations and examination may be recorded; however, signoff responsibility is not included.
- 10. Project Direction: Directions or instructions concerned with project operations. Includes coordination and day-to-day direction of the activities of project entities receiving technical direction from others, but does not include authority to overrule prescribed procedures or technical decisions of such entities.
- 11. Project Design Office: Office assigned responsibility for management of the project.
- 12. Q-List Items: Safety-related structures, systems, and '
components.
- 13. Quality Assurance Group: The quality assurance group consists of the Manager of Quality Assurance, Quality Assurance Managers, and the quality assurance personnel within their department.
14 Quality Policy Statement: Corporate management direction provided in the foreword to this document.
0001V/000lV m
- 15. ~ Review:- Exa.nination of any form of documentation for the.
purpose of establishing acceptability to the requirements of the function represented by.the reviewer. Reviews may range from a-thorough' investigation to a spot check. Reviews are generally not holdpoints, but signoff evidence of review on the documents
.or records traceable to the documents is required.
16 . Surveillance: A broad-term pertaining to and including both monitoring and witnessing.
17 . Surveillance Inspection: Review, observation, or inspection of supplier personnel, material, equipment, processes, and test results at random or selected stages of manufacture for the purpose of determining-if an action has been accomplished or a document (s) prepared-in accordance with selected requirements of a contract document (s). Surveillance inspection does not take the place of supplier quality programs or assume any responsibility for such programs or product quality.
Surveillance inspection is intended to provide a degree of added confidence that supplier materials and equipment meet specific contract requirements. Such inspections will not relieve the supplier or construction contractor of any responsibility under the applicable contract, or act as waiver by Bechtel or Client of any of the conditions thereof.
For additional information, see Section 7, subsection 7.2, SURVEILLANCE INSPECTION.
18 . Technical Direction: Instructions and directions defining technical requirements for an activity. This may include furnishing prescribed procedures, technical requirements, design approaches, specifications, and design details.
19 . Technical Guidance: Providing advice representing a preferred
-method or approach to a function or activity. This may include
-establishi_ng general requirements or policy but not specific procedures or instructions.
- 20. Witness: To watch over, observe, or examine a specific test or work. operation which includes signoff responsibility.
Whenever an approved ANSI Standard or Draft (or portion thereof) is referenced herein without qualification, all requirements of the Standard as interpreted by Bechtel Quality Assurance Management must be incorporated in the program subject to the modifications contained in Appendix A of this document.
0001V/0001V SECTION 1 ORGANIZATION
' 1.1 BECHTEL ORGANIZATION i-Figure 1 provides an organization chart for the Becht31 Group of Companies.
-South Texas Project-Electric Generating Station (STPEGS) contractual comitments are executed by Bechtel Energy Corporation, a wholly owned subsidiary of Bechtel Western Power Corporation (BWPC).
1.2 BECHTEL WESTERN POWER CORPORATION Figure 2 provides more detailed definition'of the Bechtel Western Power Management.
- Bechtel-Western Power Corporation consists of the Los Angeles, San Francisco, ,
Houston offices (Figure 2A) and the Bechtel Energy Corporation.
, 1.2.1 Bechtel Western Power Management Group includes the President and 4 Vice President and Manager for each office, Vice President and
- Manager of Domestic Operations, Vice President and Manager of Functional Operations, and Manager of Quality Assurance.
l.2.2 The quality policy' statement for Bechtel Western Power Corporation is authorized (approved for use) by the President of Bechtel Western
} Power Corporation.
f 1.2.3 The BWPC President is resposible for Bechtel Quality Program functions implemented within the corporation.
1.3 BECHTEL FUNCTIONAL / SERVICE ORGANIZATIONS 1.3.1 Functional. Operations-The Vice President and Manager of Functional Operations is responsible for various functional operations, including Engineering, Construction, Startup
. and Procurement.
1.3.2 Procurement Procurement is a Bechtel service organization and is responsible for the procurement of equipment, materials, and services specified by the Bechtel Western Power Corporation. Procurement does not establish technical or quality requirements-contained in procurement documents nor does it initiate 2 or approve changes thereto. These functions are the responsibilities of Engineering. The functions of Procurement include:
i i
000lV/000lv i e
- --s - sp ~m*- 3- an.mve. v ~ r m , em a wa -,-.gn,g.w -,yv.n-- ,y- ,p,,4m.m.,-,r q.,,,,,,-m-e-,_,, ,,,_gg-,.rg, ,-pw g y g y ,, v--y m,- n - q c. , v,m m , , -
- 1. Purchasing of equipment, materials, and services. This includes purchases for delivery to the project site and contracting where the work involves field labor.
- 2. Surveillance inspection of equipment, materials, and review of associated quality verification records when required by procurement documents.
- 3. Traffic services to control the flow of materials and provide shipping arrangements necessary for efficient delivery to the jobsite.
- 4. Field procurement and material handling at the project site providing a fully integrated materials operation from purchase to issuance. It includes receiving, inspection for over, short, and/or damage, warehousing and inventory control, distribution, local purchasing, and contracting. This function is the responsibility of the Senior Field Procurement Representative at the jobsite.
Figure 3 identifies the organization of Procurement, Figure 4 identifies the organization of the Procurement Supplier Quality Department. Procurement is supported by the Procurement Services Group, which provides policies, manuals, and procedures to all Procurement organizations.
The Manager of Procurement is responsible for procurement of equipment, materials, and services for projects within a designated geographical area.
The Manager of Procurement reports to the Manager of Support Services, Norwalk office and receives functional guidance from the central procurement organization. The Manager of Procurement also provides administrative and technical direction to the Project Procurement Managers.
As shown in Figure 4, the Supplier Quality Manager receives technical direction from the Manager of Procurement Supplier Quality. Administrative direction is the responsibility of the Manager of Procurement. The following activities are the responsibility of the Manager of Procurement Supplier Quality and are accomplished with the assistance of the Supplier Quality Manager:
- 1. Prepare, maintain, and implement the Procurement Supplier Quality Department Manual
- 2. Prepare the training and development program; train and qualify Procurement Supplier Quality personnel
- 3. Perform surveys and quality program audits at suppliers and offsite contractors as required by project and corporate procedures
- 4. Prepare and implement inspection plans 000lV/0001V . .- - -- - - - - . - - ., - . . - . - _ - - -
- 5. Provide qualified personnel and perform surveillance of items; revicw quality verification documents and release items for shipment
- 6. Review supplier QA program
- 7. Coordinate Procurement Supplier Quality Department activities with other quality functions
- 8. Monitor the adequacy of inspection plans and procedures in use by Supplier Quality personnel 1.3.3 Materials and Quality Services The Materials and Quality Services Department (M&QS) is responsible for furnishing specialized metallurgical, quality control, and auditing services to Bechtel corporations. Figure 5 illustrates the organization of the Materials and Quality Services Department.
M&QS responsibilities are:
- 1. To develop and qualify welding and nondestructive examination (NDE) procedures
- 2. To qualify and certify Bechtel nondestructive examination personnel
- 3. To support Engineering and Construction in the preparation of special process procedures and the qualification of personnel using these procedures
- 4. To provide technical guidance to field welding, coating, and'NDE personnel
- 5. To support the corporations in the evaluation of supplier and contractor welding nondestructive examination and protective coating procedures and quality program manuals for ASME components and metal structures applications
- 6. To prepare and maintain the Bechtel Quality Assurance Manual for ASME Nuclear Components (BQAM-ASME) and provide liaison with the ASMI and authorized inspection agencies in matters associated with compliance with the ASME B&PV Code, BQAM-ASME, and the control of the ASME code Symbol Stamps
- 7. To assist Quality Assurance in audits of Bechtel field const uction which includes compliance with the Quality Assurance Manual for ASME,Section III, Nuclear Components und Bechtel and contractor field welding, nondestructive examination, and protective coatings programs
- 8. To assist Procurement with surveys, audits, and evaluations of selected materials and component suppliers and contractors 000lV/000lV 1
- 9. To consult with Engineering, Procurement, Construction, and Quality Assurance on quality control and failure analysis problems involving materials, welding, protective coatings, and nondestructive examination
- 10. To support Engineering in the preparation of specifications for piping, metal structures, ASME Code components, protective coatings, and the selection of materials 1.3.4 Quality Assurance The Manager of Quality Assurance provides technical and administrative direction to the Quality Assurance Group within the Bechtel Western Power Corporation. Figure 6 reflects the BWPC Quality Assurance Organization.
The Manager of Quality Assurance is responsible for:
- 1. Formulating BWPC Quality Assurance Policies
- 2. Approving quality assurance procedures and instructions which define responsibilities and functions of quality assurance personnel within the Bechtel Western Power Corporation
- 3. Approving quality-related procedures and manuals prepared by departments and projects for conformance to quality assurance policies
- 4. Formulating audit programs and conducting audits and reviews to assure Bechtel management and clients that the quality assurance programs of the division and its projects conform with policies and requirements of Bechtel and the client. Identifying the need for corrective action and assuring follow-up 000lV/000lV - _ . . __. _ -
- 5. Providing periodic reports to the Corporation President on the
. status and adequacy of corporation and project programs and advising of any problems requiring special attention
- 6. Providing and maintaining a qualified and suitably trained staff of quality assurance engineers to carry out required project and staff functions
- 7. Formulating programs for maintaining the professional competence of personnel within his organization and providing assistance in training and indoctrination programs for management, l engineering, and construction personnel whose activities affect quality
- 8. Coordinating the Quality Assurance Program within the BWPC, l reviewing and approving departmental quality procedures, direction of the corrective action program, development of project quality assurance programs, and coordinating quality-related activities of BWPC with outside services l 1.3.5 Engineering The Manager er Engineering provides technical and administrative direction to the Engineering Department and is assisted by the Chief Engineers. The Manager of Engineering is responsible for the management and technical direction of assigned projects and for assuring that the projects are provided with adequate personnel and are following corporate procedures for conduct of engineering activities. The Manager of Engineering provides administrative direction to the Project Engineering Manager.
The Chief Engineers are responsible for assigning the engineers, designers, and draftsmen required to perform engineering functions within their respective disciplines on projects and for maintaining a staff of specialists and other support personnel to provide technical guidance to the projects.
Chief Er.gineers provide administrative and technical direction to the engineers in their respective disciplines.
In addition to its design responsibilities, the Engineering Department is responsible for:
- 1. Preparing quality program related Engineering procedures and instructions
- 2. Developing and conducting quality program related indoctrination and training programs for Engineering Department personnel
- 3. Preparing specifications for supplier, contractor, or constructor quality assurance program requirements 000lV/000lV W_._e
l 1.3.6 Construction The Manager of Construction provides technical and administrative direction to the Construction Department personnel. The Manager of Construction is responsible for the management and technical direction of assigned projects, and for assuring that construction projects are provided with appropriate personnel and are following prescribed corporate practices and procedures for conduct of construction activities.
l.4 STPEGS ORGANIZATION AND FUNCTIONS
~ The Project Manager is responsible for project direction to reflect the contract, client requirements, Bechtel policies, and project procedures. The Project Manager is the leader of the Bechtel STPEGS team, including the Project Engineering Manager, Project Procurement Manager, Field Construction Manager, Project Quality Assurance Manager, and Project Cost / Schedule Manager.
The Project Manager provides direction to the Project Team to assure satisfactory performance. The STPEGS Team Organization and its relationship to the BWPC management team is shown in Figure 7.
1.4 .1 Project Quality Assurance The project quality assurance program is directed by the Project Quality Assurance Manager (PQAM) who is responsible to assure that Quality Assurance l or Quality Control ' actions listed below are accomplished in accordance with the requirements of the project:
- 1. Coordinate the functions of the project quality program, and serve as the focal point for project communication on matters relating to this program.
- 2. Coordinate project quality-related activities of Engineering, Procurement, Project Administration, Records Management System, and Construction.
- 3. -Audit and surveillance of project quality-related functions and adherence to procedures. Advise management of the status of program implementation. Conduct prescheduled project audits and supplemental audits- directed by the Project Quality Assurance Manager.
4 1
000lV/000lv 4 Review Supplier and Constructor / Contractor (s) quality assurance program requirements in procurement documents and conditional releases of nonconforming items at the construction site.
- 5. Review turnover packages and selected quality verification records prior to turnover to the Client.
- 6. Concur with evaluation of recommended supplier's quality assurance program, in accordance with subsection 7.1. Evaluate supplier's Quality Programs for jobsite originated safety related purchases when determined necessary by the Project Quality Assurance Manager.
- 7. Take stopwork action when warranted.
- 8. Identify quality problems, initiate oocumented action leading to a solution, and verify implementation of solutions.
- 9. Review project plans and schedules for quality-related activities to assure timely and effective implementation of the quality assurance functions for the project.
- 10. Provide periodic reports to the Manager of Quality Assurance and Project Manager evaluating the status of the project quality assurance program and advising of any problems requiring special attention.
- 11. Coordinate quality assurance functions within the project and witn groups such as M&QS and Procurement Supplier Quality.
- 12. Assure that quality assurance related procedures and manuals prepared by or used for the project meet project quality program requirements and initiate revisions when necessary.
- 13. Review, prior to use, Procurement Supplier Quality - quality plans and Quality Control instructions for clarity and the existence of the information described in Sections 7 and 10. In addi', ion, evaluate the adequacy of selected plans and instructions by performing an in-depth review of:
- a. Accuracy of translation of drawing and specification requirements.
- b. Basis for determining inspection level and sequence.
- c. Adequacy of inspection method.
This review provides assurance that the total quality program requirements inclusions are complete. Reviews of generic plans and instructions can be performed on a generic basis. In that case, the Project Quality Assurance Manager only verifies that the review of the generic plan or instructions has been performed.
000lV/000lV 14 . Review and approve Constructor / Contractor (s) quality programs.
- 15. Prepare quality assurance descriptions in Safety Analysis Reports.
16 . Review Nonconformance Reports and other quality problem related documents to identify significant deficiencies, and recommend approprit.te corrective action.
The field quality assurance program includes the capability to perform:
o Receiving inspection of permanent plant material and equipment.
o Maintenance and storage inspection of permanent plant equipment and material in Bechtel's custody.
o . Review of receiving and Bechtel QC documentation.
o Surveillance inspection of work performed by Constructor /
Contractor (s). This inspection supplements the quality programs of the Constructor / Contractor (s) who have responsibility for their work and their quality verification.
Surveillance inspection includes either selected physical inspection at prescribed hold points and observation or witness of inspections performed by the Constructor / Contractor (s):
o Reviewing quality control documentation.
o Reviewing Bechtel and/or Constructor / Contractor (s) quality documentation.
o Providing technical direction to testing laboratories and inspection Contractors.
'o Reviewing supplier quality verification document packages for completeness and traceability to the item (s).
o Identifying quality problems, initiating action leading to solutions, and verifying implementation of solutions.
o Reviewing Constructor / Contractor (s) quality verification documents.
o Reinspection of Constructor / Contractor (s) completed work may be imposed as deemed necessary.
The STPEGS Quality Assurance Organization is shown in Figure 8.
000lV/000lV _ _ _ . _
BWPC designated Chief Engineers coordinate and assist in the preparation of l certain generic " standard" and " guide" documents. Standard documents include design standards, standard details, standard specifications, and technical topical reports. Guide documents include design guides, guide key documents, and guide specifications. Generic " standard" and " guide" documents which are pre-engineered to a level suitable for STPEGS adoption are subject to checking, review, and design verification as described in this Section.
Standard or guide documents which have been qualified by a design verification need only be verified by STPEGS for their applicability to project requirements. The acceptability of any significant changes to the qualified standard document must also be verified and documented.
As a matter of policy, Bechtel uses accepted industrial standards, specifications, and materials. Prototype testing is encouraged for equipment suppliers whose components have not previously demonstrated adequate performance. Prototype testing is not normally applicable to STPEGS design work; however, selected design details may be verified by test. When prototype testing is used for design verification, the test requirements are specified by Bechtel.
Design changes, including field changes, are subjected to design control measures commensurate to those applied to the original design. Checking and review of design changes are performed by the Project Engineering team to the same level as that of the original design. Changes to design requirements or completed designs produced by Project Engineering, which may be proposed by suppliers, contractors, or Bechtel construction, must be reviewed and accepted by Project Engineering.
In the case of proposed changes to the original design, initiated at the construction site, the design changes shall be reviewed, accepted and documented by Bechtel Project Engineering. Acceptance of design changes by Bechtel Project Engineering is required prior to implementation. For design changes proposed by suppliers, acceptance of the design change by Project Engineering is required prior to shipment of the item to the jobsite.
In all cases, approval of the proposed design change by project engineering is required pric< to fuel load for STPEGS.
Certain design work may be performed by Bechtel Site Engineering providing it is in compliance with the design control features utilized by Bechtel Project Engineering in the design office.
Certain detailing work may be performed by selected contractors; however, the nature, scope and parameters will be identified in design disclosure documents for each contractor with checking of field sketches required by an individual other than the detailer.
000lV/000lv Suppliers are not allowed to change Bechtel design requirements or Bechtel I
. rGviewed supplier design documents without obtaining approval by Bechtel Project Engineering. Construction site changes to engineering design are documented by means of change notices or change requests which require authorization by Project Engineering. Significant or unique changes are authcrized individually; Project Engineering may give written authorization in the form of specifications or other instructions to field organizations to make routine changes. Field organizations have the authority to approve changes to design details in cases where the original design details were prepared by that field organization.
J t
l 000lV/000lv _- -- - . . ._. _ _ _ _ _ _ _ . _ _ _ _
SECTION 4 PROCUREMENT DOCUMENT CONTROL All' procurement actions for Q-List items and services, including off-the-shelf items and bulk commodities, whether performed by design office or field procurement groups, employ technical and quality requirements established by project engineering.
Project cngineering prepares (or provides) the technical and quality requirements appearing in procurement documents. These activities are governed by the same policies and procedures as those applied to design documents. Engineering and procurement department procedures delineate the sequence of quality-related action to be accomplished in preparation, review, approval, and control of procurement documents and changes thereto.
Project engineering is responsible for assuring that applicable regulatory requirements, design bases, supplier quality assurance program requirements, and other requirements which are necessary to obtain and verify quality are included or referenced in the procurement documents.
Specifications for suppliers and contractors are prepared by the project engineering team based on the project quality program requirements and generic or guide specifications. Project safety-related specifications are reviewed for appropriate quality program requirements by Project Quality Assurance.
Procurement documents include specific technical specifications for the equipment and services to be furnished which define specific codes, standards, tests, inspections, and records to be applied or furnished. The procurement documents also include quality assurance requirements either in separate specifications which define requirements for the supplier's quality assurance program or by incorporating appropriate requirements in the technical specifications and associated documents. Quality programs may be specified by invoking the appropriate sections and elements of ANSI N45.2-1971, as endorsed by Regulatory Guide 1.28, Rev. O. 6/72, appropriate supplementary ANSI Quality Assurance Standards, and the ASME Boiler and Pressure Vessel Code, as applicable, or by incorporating requirements equivalent to those of these standards. The procurement documents also establish provisions for surveillance, inspection, and audits (including access to the supplier's and subsupplier's facilities and records for audit), provide for extension of the applicable requirements to subtier procurements, include provisions for control and approval of supplier nonconformances, and establish requirements for preparation and delivery of documentation. Specific requirements for documents which must be submitted for review, approval, and/or verification are provided.
0031V/000lv Engineering Department Procedures provide for establishing quality assurance requirements in procurement documents. Technical quality requirements are reviewed by technical personnel. Programmatic aspects are reviewed by Quality Assurance as described above, and the review also assures that the document was prepared, reviewed, and approved in accordance with the approved procedures. Procurement documents normally contain general acceptance criteria. These are reviewed by suppliers, contractors, or Bechtel Quality Control upon receipt of the documents to verify and supplement acceptance criteria.
Evidence of review and approval of procurement documents is available for verification.
Appropriate project procedures provide details to accomplish the administrative actions in processing procurement documents in the design office and at the jobsite.
000lV/000lV __ __ _ -_._ __ -_.____ ._ _ _ _ _ . . _ __ ___
SECTION 5 INSTRUCTIO,15, PROCEDURES, AND DRAWINGS The documented instructions and procedures governing this program are identified in Section 2.
Procedures and manuals governing the activities of organizations and groups performing quality-related functions include procedures for the preparation and review of instructions, procedures, and drawings.
Documented instructions from Project Engineering to Construction, contractors, and suppliers is in the form of engineering specifications and addenda or change notices thereto, drawings, and drawing change notices. These documents contain, reference, or require procedures and instructions, as appropriate, and provide necessary acceptance criteria. When approved by Project Engineering, these documents are released for construction work.
Bechtel procurement documents require suppliers and contracto.s to submit specified drawings and procedures to Bechtel for acceptance prior to start of fabrication or construction. Bechtel reviews of these documents are performed to determine that interfacing design features are compatible with overall design and installation requirements and that procedures are acceptable.
Procedures for construction activities are contained in the project procedure manual. These procedures describe, define, or specify administrative and functional requirements-for performing construction activities. Procedures of this nature include training of personnel; jobsite housekeeping; storage, maintenance, and handling of items; document control; changes to design documents; reviewing supplier engineering documents; and field requisitioning of items and services, as applicable to the scope of work.
Field organizations prepare other procedures when engineering documents rcquire amplification to perform various discipline activities associated with fabrication, cleaning, erection, installation, test, repair, modification, etc., of items.
The requirements, procedures, and instructions for the Quality Control activities are contained in the Project Procedures Manual. The elements of this manual include qualifications, indoctrination, certification, and training; items; field procurement control; control of measuring and test equipment; inspection, exa documentation and records control; final inspection and turnover; and constructor and contractor control.
Assurance that work is accomplished in accordance with approved instructions, procedures, and drawings is obtained through the various levels of surveillance, inspection, and audit described in other sections of this document.
000lV/0001V l
SECTION 6 DOCUMENT CONTROL The program documents identified in Section 2 provide means for document control. These include procedures providing Engineering, Procurement Supplier Quality, and Construction controls for the review, approval, and release of documents and changes thereto.
Documents pertaining to quality-related items, as identified in this paragraph, are required to be controlled. The documents listed in Table I are on controlled distribution. Instructions, procedures, specifications, drawings, procurement documents, quality plans, design calculations, design criteria, field change requests, safety analysis reports, and inspection test procedures are identified by control registers or index lists. Nonconformance reports, audit finding reports, supplier deviation disposition request, standard deficiency reports, documentary evidence of design reviews, memoranda, and correspondence are identified by logs which provide for traceability of closecut action.
Document control centers for STPEGS are set up in the Design Office and the jobsite. Controlled documents are released, received, controlled, and distributed through these centers.
Engineering Department procedures prescribe the requirements for preparation, control, and distribution of design documents. Approved drawings and specifications prepared by Project Engineering are issued to organizations and individuals responsible for performing the work and to those responsible for inspection *. Control registers, issued periodically, identify the drawings, specifications, and other design output documents and their current status.
Transmittal forms are employed to forward drawings and specifications and require that signed receipts be returned from the addressee or by controlled entry of the acknowledgement into the computerized data base.
Changes made to approved design documents by Project Engineering or proposed by field organizations are reviewed and approved by Project Engineering in accordance with established procedures which provide that changes are reviewed in the same manner as the original issue.
Supplier-submitted documents, such as drawings, specifications, procedures, manuals, and other data, are controlled through the use of control logs which provide identification and status of supplier documents. Transmittal forms are used to return and show approval status of evaluated supplier documents.
Bichtel Procurement Supplier Quality Representatives are informed as to the current status of supplier documents, and copies of applicable supplier documents are formally transmitted to the construction site with provision for receipt acknowledgement, u Bechtel Procurement Supplier Quality Representatives receive copies of the transmittal notices listing the documents and their approval status but normally do not receive copies of the documents. These are available at the supplier's plant for the Supplier Quality Representative.
000lV/000lv The project construction organization at the jobsite employs standard prescribed procedures for control of the distribution of approved drawings, specifications, and other documents. These procedures include provisions for field receipt, review and distribution of approved documents, and for appropriate marking or destruction of obsolete documents.
Approved changes are promptly included in governing documents or controlled change notices provided for interim revision. Changes may not be implemented without appropriate documented approvals. When a specified number of change notices have been issued or after a designated period of time, change notices must be incorporated in the governing document.
Controls to ensure that work activities are conducted in accordance with the necessary procedures cr other documents take several forms. These controls include the following:
- 1. Procurement documents
- 2. Appropriate department or group manuals and procedures
- 3. Engineering compliance monitored by Quality Assurance
- 4. Supplier compliance monitored by Procurement Supplier Quality
- 5. Construction compliance monitored by Quality Control and Quality Assurance The Bechtel surveillance inspection program includes procedures governing the initial inspection visit which are designed to identify necessary documentation and verify that the controls are in place for preparation and approval of procedures prior to performance of work governed by the procedure. Construction inspection planning includes identification of documents required, and these must be available for use prior to performing inspections governed by the procedure.
Control of documents in the design office and at the jobsite are regularly audited by Quality Assurance personnel. In addition, Quality Control assures that construction work is performed in accordance with current approved design documents as an integral part of their quality verification inspection program.
0001V/0001V _ __- - - _ - _ _ _ - - . ._ _
SECTION 7 CONTROL OF PURCHASED MATERIAL, EQUIPMENT, AND SERVICES 7.1 SUPPLIER EVALUATION AND SELECTION Files of suppliers and contractors are maintained by Procurement. These files identify suppliers and contractors who have demonstrated their ability to provide quality material, equipment, or services, or who have been established as capable by survey. Suppliers' and contractors' quality history files contain information on scope of services and capability, and results of recent shop surveys and audits. Periodic reports identifying data contained in quality history files are issued by Procurement Supplier Quality to interested groups within the corporations.
The Materials and Quality Services Department reviews welding and nondestructive examination procedures for work involving compliance with the ASME Boiler and Pressure Vessel Code and for fabrication of metal structures and protective coating procedures. Materials and Quality Services reviews and evaluates these documents and provides Procurement with information for summary listings of the approved vendor information on file. This information is available to STPEGS for assistance in identification and evaluation of qualified sources.
Procurement Supplier Quality Department procedures include provisions for source surveys which may be used to supplement data in a supplier's quality history file. Requests for source survey are initiated by Purchasing or Engineering in cases where inadequate historical data is available to evaluate the supplier's capability to produce the commodity.
Prior to award, the following technical and quality requirements must be met:
- 1. Determination by Engineering that the source is responsive to the technical requirements of the specification
- 2. Determination by Engineering and Quality Assurance that the supplier or Constructor / Contractor (s) quality program is capable of meeting the specified requirements. This may be bcsed on evaluations by Procurement Supplier Quality for manufacturing suppliers or Quality Assurance for jobsite
. Constructor / Contractor (s), and field procurements.
In some instances it may be necessary to place a contract without fully satisfying these criteria. For these cases, the criteria shall be met prior to start of related work activities.
The quality program evaluation may be achieved by review of controlled program manuals previously submitted and evaluated by responsible Bechtel personnel; manuals and procedures submitted to Bechtel, or made available for Bechtel review in the bidders' facilities in connection with the specific procurement; or an evaluation of performance on previous Bechtel procurements.
000lV/000lV In addition, supplier program evaluation may be based on review of the supplier's quality history, source survey results, or analysis of bid for responsiveness to quality program requirements contained in the procurement documents. Responsibility for maintenance of quality program acceptance for inactive noncode procurement orders may be transferred to Houston Lighting &
Power. Bechtel may utilize the status of the HL&P quality program maintenance as evidence of an acceptable Quality Assurance program and may also use other HL&P approved noncode vendors without re-reviewing the QA program. This alternate method is contingent upon the QA requirements being previously established by Bechtel.
For work covered entirely by ASME Boiler and Pressure Vessel Code,Section III requirements, possession of the appropriate Certificate of Authorization constitutes an acceptable minimum requirement for bidder qualification. When an award is made, appropriate sections of 10 CFR 50 Appendix B, shall apply.
Evaluation of suppliers of standard off-the-shelf items which are produced to a manufacturer's standard quality program is based on published data (catalogues, etc.) for conformance to engineering requirements and the use of historical quality performance data and source surveys.
7.2 PROCUREMENT SURVEILLANCE For purchased items, the primary responsibility for quality rests with the supplier. Technical control of supplier work is provided by Project Engineering through review of specified supplier documents, including drawings and procedures. Engineering is also responsible for providing or accepting supplier-proposed resolutions to discrepancies encountered. Inspection of supplier's work is the responsibility of supplier's inspection department.
Bechtel Procurement Supplier Quality Representatives perform surveillance inspection of supplier's work which may include specific measurements and examinations performed by the Supplier Quality Representative but generally includes monitoring and witnessing of inspections and tests performed by the supplier's quality control organization. Bechtel Supplier Quality Representatives frequently spot-check the dimensions, surface finish, and protective coatings, visually examine welds, review test reports and radiographs, and other details.
Project Engineering identifies procurements (both design office and field) requiring source surveillance inspection and audit. Procurement may recommend additional items. Manufactured or fabricated Q-List items, such as vessels, heat exchangers, pumps, piping subassemblies, valves, electrical panels, etc.,
are included in surveillance inspection and audit programs. Items which are typically excluded from the surveillance inspection program include standard off-the-shelf items and bulk commodities where required quality can be adequately determined by receipt inspection or post-installation checkout or test. Also excluded are materials where important physical and chemical properties are independently verified on samples taken at the supplier's facilities or at the jobsite.
000lV/000lv For Q-List items, Bechtel Procurement Supplier Quality Representatives perform their surveillances in accordance with quality plans and instructions. These plans are prepared by Procurement Supplier Quality based on instructions in the Procurement Supplier Quality Department Manual and may be modified by Project Engineering. They provide for identification of witness and hold points, identification of the examinations and tests which are selected to be witnessed by the Bechtel Supplier Quality Representative, anc~ documentary evidence of completion of each witness and hold point operation, test, or examination. A supplier may not proceed with the work beyond a hold point without written agreement of waiver of hold points from Procurement Supplier Quality based on agreement from Project Engineering and the PQAE.
It is the responsibility of the Supplier Quality Representative to verify, to the extent required by his quality plan, that the supplier has met the quality requirements contained in the procurement documents before the material or equipment is released for shipment. This responsibility of the Supplier Quality Representatives is met through surveillance, which includes observations and checks at random of selected intervals (or points) of materials of construction, in-process fabrication, heat treatment, welding, examination, testing, dimensions, preparation for shipment, marking, tagging, and quality verification. Bechtel Supplier Quality Representatives do not perform nondestructive examinations or tests on material and equipment at suppliers' plants. Such examinations and tests are performed by the supplier and selectively witnessed or otherwise monitored by the Supplier Quality Representative.
Typical quality plans have sections that describe the scope and define application, establish responsibilities, describe preplanning activities to be performed prior to making initial contacts with a supplier, describe the activities to be performed during the initial, progressive, and final surveillance vis its, and describe reporting requirements.
Procurement se.veillance may be performed by resident or area Supplier Quality Representatives assigned to several suppliers. Reports documenting surveillances performed, tests witnessed, and discrepancies observed are prepared by the Supplier Quality Representative and distributed in accordance with project procedures. Bechtel Supplier Quality Representatives are responsible for assuring that their surveillances of material, equipment, and specified documentation conform to the requirements of the quality plan and/or instructions and for releasing inspected items for shipment. Bechtel Supplier Quality Representatives have the authority to refuse release of nonconforming material.
Consistent with the complexity of the surveillance assignment, the Supplier Quality Representative will review with the supplier the requirements of the applicable quality plan. During the initial visit, the Supplier Quality Representative will discuss the following:
- 1. The quality requirements of the procurement documents
- 2. The applicable requirements of the governing codes and standards
- 3. The requirements for Bechtel Engineering approvals 000lV/000lv
. - - - . . - - ~ _ . - .-. .-
- 4. The requirements fcr Bechtel survaillance at principal subsupplier plants
- 5. The requirements for qualification of welders, nondestructive
, examination personnel, and inspection, examination, and testing personnel
- 6. The requirements for Bechtel Supplier Quality witness and hold points, including release for shipment
- 7. The requirements for complete and accurate supplier quality verification documentation' prior to release for shipment
- 8. The supplier's responsibilities for the' quality of subtier-items
!- In addition, the Supplier Quality Representative will establish witness and hold points in accordance with the guidelines established by the applicable quality plans and procurement documents. During the course of progressive surveillance, the Supplier Quality Representative has the prerogative to make other surveillances and witness other examinations and tests necessary to determine the supplier's compliance with the requirements of the procurement documents.
- Surveillance of jobsite contractors is the responsibility of Quality Control l utilizing Quality Control Instructions and Inspection Records provided by procedures contained in the Project Procedures Manual.
i The Constructor at STPEGS is responsible for monitoring the effectiveness of his inspection program, j 7.3 RECEIVING INSPECTION
! Receiving inspection practices conform to the requirements of ANSI j' N45.2.2-1972 as endorsed by Regulatory Guide 1.38, Rev. O, 3/73, as
, interpreted by the positions contained in Appendix A of this document. These I are performed in accordance with Quality Control Instructions by Quality j
Control personnel.
Documentary evidence that the item conforms to procurement documents, required to be available at the jobsite prior to installation, or use as a conforming item, includes as follows:
1
- 1. For Bechtel procured
- and inspected items not covered by ASME
] Boiler and Pressure Vessel Code requirements, a certificate of j conformance** (signed by an authorized representative of the
! supplier identifying the specific technical requirements met by i the item by referencing the appropriate Bechtel specification I and other governing codes and standards) and acknowledgement
- that the Bechtel Procurement Supplier Quality Representative has reviewed the required documentation and has released the item.
j
- Also applies to cases of Bechtel client (applicant) procured items for which i Bechtel is acting as agent for the client, i
- The certificate of conformance conforms to ANSI N45.2.13-1976, as endorsed by Regulatory Guide 1.123 Rev. O, 10/76, as interpreted by the positions i contained in Appendix A of this document, i
0001v/0001v i
This may be obtained by having the certificate signed by the Bechtel Supplier Quality Represe$ative to verify that he has reviewed applicable supplier documentation supporting the certificate and released the items, or by receipt of a separate teletype or report from the Supplier Quality Representative indicating that his " inspection is complete and the item has been released.
Receipt of the certificate of conformance and the Bechtel Procurement Supplier Quality Representative release constitutes documentary evidence that materials and equipment conform to procurement requirements and may be installed. If the balance of the documentation package required by the procurement documents is received prior to or with the shipment, the certificate of conformance may be waived.
- 2. For Bechtel procured and inspected items covered by ASME Boiler and Pressure Vessel Code requirements, the same requirements prevail as above, plus the appropriate Code Data Report.
- 3. For Bechtel procured and noninspected items, all quality verification documentation required to be submitted with the procurement documents must be reviewed and verified (as a part of receiving inspection) at the jobsite by Quality Control
, personnel or Procurement Supplier Quality personnel.
- 4. For nuclear steam supply system supplier furnished items, appropriate certification from the NSSS supplier in accordance with his quality program
- 5. For cases when procurement documents do not require the supplier to furnish quality verification documentation, satisfactory receiving inspection results constitute the necessary documentary evidence that items conform to procurement documents.
Standard off-the-shelf items are visually inspected for identification and condition at receipt.
Complete quality verification record packages are requested for delivery prior to, or with, the shipment. Documented control measures, with provisions for follow-up, are provided to expedite receipt of quality verification packages 1 which are delayed beyond the time of shipment. Completed quality verification records packages received at the construction site are checked for completeness and traceability by quality control personnel or Procurement Supplier Quality personnel and audited by Quality Assurance. Project Engineering may elect to have selected quality verification documentation delivered to the design office for review by so specifying in procurement documents.
7.4 SUPPLIER AUDITS The supplier control program provides for periodic audits of selected suppliers' quality assurance programs as described in section 18. Design contractor and consulting program work is monitored by Project Engineering.
000lV/000lv -_. ._. . _. -__. _ _. .-. . _. -- .
SECTION 8 1
IDENTIFICATION AND CONTROL OF MATERIALS, PARTS, AND COMPONENTS l Identification requirements are determined during the generation of specifications and design drawings. Procurement documents provide the requirements for identification of purchased items.
]
l- Parts, components, subassemblies and equipment, and partially fabricated items may be identified by stenciled or etched markings, strip marking, imprinted i tape, color coding, and tags. Large quantities of small items, unless specifically required by code or standard, may be identified as to heat, '
, batch, lot, or specification by applying markings to bags, bins, tanks, or other suitable containers. Identification of installed or assembled items requiring traceability may be transferred to inspection records or as-built
- ' documents'if desired and is required if markings are hidden or subject to obliteration during fabrication or installation.
Organizations receiving materials, parts, or components verify that these are j properly identified and are accompanied by appropriate documentation.
i Provisions are made for handling and storing items to retain identification and to prevent intermixing.
t I
t i
1 1
r ,
f l
\
l l
000lV/000lv K
SECTION 9 CONTROL OF SPECIAL PROCESSES The requirements of the ASME Boiler and Pressure Vessel Code are invoked, as applicable, in the Bechtel program. Special processes requiring procedure and/or personnel qualification beyond those required by the code are identified in technical specifications by reference to appropriate industry codes and standards, where available, or by specific identification in the technical specification. Supplier and contractor special process qualification data are subject to review by Bechtel.
Special processes performed in the construction of STPEGS, including welding, nondestructive examination, protective coating, cleaning and flushing, are imposed on the constructor by applicable specifications. The requirements for welding and nondestructive examination comply with applicable portions of the ASME Bciler and Pressure Vessel code, American Welding Society Standards, and the Society of Nondestructive Testing (SNT-TC-1A-30 and supplements), as applicable. Cleaning and flushing procedures and personnel qualifications conform to the requirements of ANSI N45.2.1-1973, as endorsed by Regulatory Guide 1.37, Rev. O, 3/73, as interpreted by the positions contained in Appendix A of this document.
-Other unique special processes or work operations identified by Westinghouse Electric Corp., the nuclear steam system supplier or Project Engineering are properly qualified and performed by trained personnel in accordance with specified technical requirements.
Current qualification records of procedures, equipment, and personnel are maintained at the jobsite. Active files are maintained in the de:ign office, and copies of qualification records covering special processes and procedures are provided to the jobsite. STPEGS maintains up-to-date lists of personnel qualifications and/or applicable equipment qualifications for special processes. Controls are provided to assure that personnel qualification records are regularly reviewed, and the appropriate requirements for requalification are implemented. Implementation of these controls is verified by Quality Control personnel and audited by Quality Assurance with the assistance of Materials and Quality Services.
i b
000lV/0001v 1
, . - - , , . - , n-. , ,. - ~. .--.-. .., ,. ----.,e ---- ,- - - - - . . - - , ,..-,-n., --. ._-- - -- - .
SECTION 10 INSPECTION As described in Section 7, suppliers' and contractors' programs are subject to surveillance by Bechtel Procurement Supplier Quality Representatives and Quality Control Engineers as applicable.
The responsibilities for inspection of Bechtel construction work are identified in Sections 1 and 2. Quality verification inspection, witness of ttsting activities, and evaluation of test results are performed by Quality Control personnel who are independent of site engineering and craft supervision. Quality Control Engineers receive administrative and technical direction from the Project Quality Control Engineer. The overall inspection program is monitored by resident construction site Quality Assurance personnel and audited by Corporate Quality Assurance.
Inspection, witness of testing activities, and evaluation of test results are performed in accordance with procedures contained in the Project Procedures Manual supplemented by construction quality control instructions, or work operations and planning documents. Inspection planning includes receiving inspection, construction and installation inspection, and testing.
Quality control inrtruction and inspection rccords are prepared to cover onsite receiving, maintenance, installation, testing, and contracted work activities performed during the construction phase. These are the controlling documents used by Quality Control Engineers for performance of onsite quality verification activities. These identify what inspections are required, the inspection acceptance / rejection criteria, how and by whom the inspections are to be performed, and the sequence. They arc available prior to inspection.
Inspection and acceptance criteria are derived from engineering design documents, supplier information, and construction procedures. Standard inspection instructions to be used on STDEGS are approved by the Project Quality Control Engineer.
In addition, all work covered by the ASME Boiler and Pressure Vessel Code,Section III, is also subject to independent inspection by authorized Code Inspectors in accordance with the Code rules.
Inspection procedures or instructions and records provide the following information:
- 1. Reference to applicable documents such as drawings, specifications, and procedures
- 2. Identification of prerequisites and special process control requirements, such as perscnnel, procedure, or equipment qualification 000lV/000lV
- 3. Identification of characteristics to be inspected
- 4. Individuals or groups responsible for performing the inspection
- 5. Acceptance criteria (explicit or by reference) obtained froin specifications, drawings, supplier instructions, and conttruction standards
- 6. A description of the method of inspection and equipment to be used or reference to an appropriate procedure
- 7. Identification of frequency of inspection or sampling plan
- 8. Record of results of the inspection, including any special documentation, and sign-off by the inspector
- 9. Verification that all inspection operations are complete and acceptable The personnel qualification procedures include provisions to maintain and periodically review records of inspectors' qualifications to ensure that they are kept current.
Inspections of modifications, repairs, and replacements are performed either in accordance with the original inspection procedure, instruction or plan, or special procedures or plans appropriate to the work activity.
l l
I 000lv/000lv SECTZON 11 TEST CONTROL Tests required to qualify, demonstrate, or assure quality of procured items or completed construction are defined in engineering drawings, specifications, or test procedures.
CSnstruction tests are an extension of construction inspection. Construction testing is conducted to demonstrate that the equipment installation is complete and that the electrical systems are properly wired. Test plans or procedures, and test reports and records are used to demonstrate that completed tests have met test objectives.
System cleaning, flushing, instrument and control settings, and performance demonstration are part of the preoperational and startup test program.
Preoperational and startup testing is under the control of HL&P. Bechtel startup engineers may provide assistance to HL&P in the preparation of startup procedures and supervision of startup tests. Bechtel startup engineers are independent of the construction and HL&P's operating organization and are qualified to collect, analyze, and evaluate test results in accordance with the requirements of ANSI N45.2-1971, as endorsed by Regulatory Guide 1.28, Rev. O, 6/72.
000lV/000lv SECTION 12 CONTROL 0F MEASURING AND TEST EQUIPMENT The Bechtel Quality Control Program provides for calibration, maintenance, and control of measuring and test equipment used in construction. Procedures provide for unique identification of each instrument or equipment item r; quiring calibration or checking, establishment of calibration schedules based upon the elapsed time or usage cycles, and provisions for identification of calibration status by tags, labels, or markings applied to the item.
Records are maintained to show the status of items under the calibration program.
Inspection procedures require thet the inspector check calibration labels or tags as well as apparent proper functioning of the instrument prior to use to assure that the calibration period has not lapsed and the equipment is in proper working order.
The identification of measuring and test equipment used in performing tests is entered in the test records when the validity of the test result is critically dependent on the accuracy of the test equipment.
Calibration standards are traceable to nationally recognized standards, or the basis for calibration is properly documented. Calibration standards have an uncertainty (error) requirement of no more than 1/4 of the tolerance of the intended use of the equipment being calibrated. A greater uncertainty (error) is acceptable when limited by the state of the art.
Provisions for contractor's control of measuring and test equipment are included in procurement documents by specifying ANSI N45.2-1971, Section 13.
The Bechtel surveillance inspection program of contractor's activities includes review of this element in the contractor's program. Contractors are required to apply practices similar to those described for the Bechtel program.
Performance and adequacy of supplier, constructor, contractor, and Bechtel construction programs for control of measuring ano test equipment are verified by surveys or audits performed by Bechtel Procurement Supplier Quality, Quality Control, or Quality Assurance personnel, as applicable.
0001V/0001V SECTION 13 HANDLING, STORAGE AND SHIPPING The requirements for packaging, marking, and shipping are specified in procurement documents for Q-List items by reference to ANSI N45.2.2-1972 or by provision of specific technical requirements which meet the intent of this standard.
Procedures for equipment and system cleaning and flushing and cleanness control conform to the appropriate requirements of ANSI N45.2.1-1973 as endorsed by Regulatory Guide 1.37, Rev. O, 3/73, as interpreted by the positions contained in Appendix A of this document.
Fer supplier, constructor, or contractor work, special handling, storage, shipping, and preservation requirements are identified in technical specifications which either provide, or require the vendor or contractor to provide, the required procedures and instructions. The packaging, handling, and shipping practices of the suppliers are subject to review by Bechtel Procurement Supplier Quality Representatives at the source prior to shipment for compliance with requirements defined in procurement documents.
At the construction site, materials and equipment are received, inspected, stored, and maintained in accordance with standard field procedures supplemented by special procedures and requirements issued by project engineering or furnished by suppliers. Materials and equipment are physically inspected upon arrival at the jobsite and moved into prescribed storage areas or to the installation site if adequate protection is available. Imediate movement to the installation site is permitted if it would eliminate multiple handling and is compatible with the construction schedule. Special environmental conditions, such as inert gas, specific moisture content levels, and temperature levels prescribed in procedures or specifications, are controlled at the site.
Procedures are provided..as appropriate, for handling special items and for the care and maintenance of material handling equipment. Otherwise, standard material handling methods are used to ensure care and protection against physical damage. Special handling instructions and procedures for major or special items are included in procedures reviewed by Project Engineering or Bechtel construction specialists. Personnel responsible for handling these major or special items will be qualified to the extent required by these special handling instructions and procedures. Preparation for and performance of rigging operations involving major equipment, such as reactor vessels, steam generators, and pressurizers, are witnessed by Bechtel construction rigging specialists.
000lV/000lv SECTIO.'l 14 INSPECTION, TEST, Afl0 OPERATING STATUS Construction procedures and inspection instructions provide for identification of inspection status of receipt inspection or work-in-process by using work sequence plans, inspection records, physical locations, tags, markings, or other devices compatible with the item, system, or operation being inspected or tested. Progress of work is entered in records, and status identification is changed to reflect current conditions. At the completion of construction, a tagging system is employed to visually indicate the operating status of cquipment and systems which are in test or rework. Records of test results are prepared and maintained.
Work is performed according to prescribed sequences required to assure quality, and in accordance with the provisions contained in this report.
Inspection points may be deferred or waived without generation of a nonconformance report only when specifically provided for in the governing procedure. Inspection points can be deferred only when the element can be inspected at a later time in the sequence and a later hold point exists. In these cases, the inspection records or checklists are not completed until the inspection point is picked up at a later date. If physical control of the item is required to prevent its inadvertent use or installation beyond the point where the inspection can be performed, the item is tagged or otherwise id:ntified and conditionally released with a limit placed on future work operations.
Procedures or instructions include identification of the individuals or groups responsible for application and removal of status indicators.
Project Engineering and supervisory personnel are authorized to apply and remove identifying tags, markings, and labels on equipment in accordance with approved procedures. Quality Control personnel are the only ones authorized to direct application and removal of inspection status indicators. Bechtel, in cooperation with the plant owners' operating personnel, establishes a tagging procedure which delineates those authorized for applying and removing tags during preoperational testing phases.
0001V/000lv -4 5 -
SECT 20N 15 I
NONCONFORMNG ITEMS Suppliers and contractors are required to advise Bccatel of all nonconformance from prccurement documents or Bechte'.-approved designs for which the rGconrnended dispositica is " repair" or "use as is.' Bechtel reserv2s the right to accept or reject the disposition. Bechtel requires suppliers to submit proposed repair proceduro for major nonconformances for approval by project engineering prior to their use. Reports of nonconformances identified by Bechtel personnel are prepared by the supplier, Bechtel Procarement Supplier Quality Representatives, or Project Engineering to assure complete '
and adequate documentation. Copies of completed nonconformance reports are forwarded to the jobsite prior.to, or with, the release of the item; or identification of outstanding nonconformances are included in the Supplier Quality Reoresentative's release.
Nonconformances discovered during Bechtel receiving inspection or construction activitics are controlled and documented in accordance with a standard Quality Control procedure. The procedure provides for identification and documentation of the nonconformance and control of the item, identifies the '
authority for approval of proposed resolution, and provides for documentation of reinspection results. Important elements of the procedure include requirements to:
- 1. Tag and segregate whenever practical.
- 2. Determine interim disposition by field organizations.
- 3. Have Project Engineering approve dispositions.
- 4. Provide conditional release of nonconforming items upon approval of Quality Assurance.
- 5. Review completed nonconfornance reports by Quality Assurance to establish need for corrective action. Repetitive ncnconformances are reported to higher levels of management for review and resolution on a generic basis.
The authority for disposition of nonconforming items follows the rules for approval of design changes described in Section 3 of this document. Quality Assurance reviews dispositions to determine that they are fully responsive to the conditions described in the nonconformance report. Quality Control is responsible for verification of rework and repair dispositions, applying inspection processes at least equivalent to that applied to the original work. " Repair" or "use as is" dispositions on nonconformances to procurement requirements at a supplier's plant must be accepted by Project Engineering.
t 000lV/000lv - - - - . . _ _ - - - - - - - -- - - .- .
Nonconforming items discovered at final inspection which cannot be corrected by rework cr completion of originally prescribed processing are required to be identified, tagged, and/or segregated. Discrepancies in work not yet submitted for final inspection which can be corrected by rework or completion of work processes are not considered to be nonconformances. For construction work performed by Bechtel, no further work can proceed on the nonconforming item until an approved disposition is implemented, unless a conditional release is approved by Quality Assurance. Suppliers, and Constructor /
Contractor (s),a required by procurement documents, apply similar procedures involving their quality assurance functions. Bechtel Procurement Supplier Quality Representatives are instructed to withhold release for shipment until all nonconformances have been resolved or an interim disposition is approved by Project Engineering.
The program also provides for the participation of the ASE Authorized Inspector for nonconformance dispositions on Code covered items.
000lV/000lV -
SECTION 16 CORRECTIVE ACTION The corrective action program provides procedures for prompt identification
-and correction of conditions adverse to quality which may require corrective action. Corrective action, when initiated, shall be documented. A decision that corrective action is not required need not be documented.
Within the Bechtel program, the identification of situations which may need c:rrective action is accomplished through review of nonconformance reports, supplier surveillance activities, quality assurance surveillance and monitoring programs, and quality assurance audits. Corrective action is controlled and documented by means of Standard Deficiency Reports and the associated procedure. These provide for (a) the identification and reporting by any member of the project team of situations or occurrences which warrant corrective action, (b) determination of the cause and identification of the corrective action to be taken by the responsible organization, (c) reporting the cause and corrective action to proper level of management, (d) final verification by the Project Quality Assurance Engineer that corrective action has been taken, and (e) review by Quality Assurance management for implication or effect on other work.
Corrective action involving design documents, investigation of cause, and actions taken to preclude recurrence is applied to errors detected after the design document is issued for use. Such errors, detected after the design document is issued for use, are formally documented and are reviewed for corrective action. These are documented by design change notices, revision block entries, or reports, such as supplier discrepancy reports, field n:nconformance reports, startup reports, or feedback from utilities during operation of the plant. Significant problems are also reviewed for programmatic corrective action by Quality Assurance.
This program also provides for the evaluation of conditions reported which may require reporting to the NRC by HL&P in accordance with the requirements of 10 CFR 50.55(e).
000lv/000lv -4 8-
SECTION 17 QUALITY ASSURANCE RECORDS The requirements of ANSI N45.2-1971, as endorsed by Regulatory Guide 1.28, Rev. O, 6/72 are applied to Bechtel activities. Records produced as a result of the quality program are prepared and maintained by project groups, suppliers, and contractors as their work is being performed.
Project engineering records are retained by the project engineering team as work is performed. It is normal practice to microfilm documents at regular intervals, unless duplicate copies are available at an alternate location.
Provisions for collection of completed records in the design office, or at the jobsite, and the criteria for storage and retention reenmended in ANSI N45.2.9-1974, as endorsed by Regulatory Guide 1.88, Rev. 2, 10/76, as interpreted by the positions contained in Appendix A are applied to quality records.
Documentation of the design review process is prepared and maintained in accordance with Section 3 of this document. Design changes may be issued on an interim basis by means of change notices. However, these are ultimately incorporated in revisions to the governing documents, unless the change is a limited waiver (e.g., "use as is" on a nonconformance report) which does not generally apply to the design document. Copies of released drawings, ,
specifications, technical reports, and similar documents are placed in '
Engineering office files, Construction office files, and submitted to HL&P.
At the completion of engineering, final copies of these records are provided to HL&P. Bechtel Engineering retains control of design calculations and analyses. These are available for review by HL&P and appropriate regulatory bodies.
Supplier records which identify as-built status and verify quality of the work are requested from the supplier and placed in construction site quality record files. In some instances, with the agreement of Bechtel and HL&P, suppliers are permitted to retain custody of certain records if retention procedures and storage facilities are adequate and access is provided to HL&P.
Completed quality verification records, including nonconformance reports for
" repair" and "use as is" dispositions, are placed in quality record files.
HL&P and appropriate regulatory groups are provided access to these files while they remain in Bechtel custody. At the completion of the Bechtel assignment, these files are turned over to HL&P.
The requirements and guidelines for receipt, control, and retention of permanent quality assurance records contained in ANSI N45.2.9-1974, as endorsed by Regulatory Guide 1.88, Rev. 2,10/76, as interpreted by the positions contained in Appendix A of this document and ASME Boiler and Pressure Vessel Code,Section III, are employed for the control of construction site quality record files. Identification of the records and method of turnover to HL&P are established for STPEGS through agreement between Bechtel and HL&P.
000lV/000lv -4 9-
SECTION 18 AUDITS A comprehensive program of audits is conducted by STPEGS covering the various project activities to assure applicable portions of the Quality Assurance Program are adequately and effectively implemented.
The STPEGS audit program includes both nonitoring by Quality Assurance Personnel of daily activities conducted at the construction site or design office as well as formal periodic team audits performed by individuals independent of project activities being audited. The combination of project and corporate Quality Assurance management audits of Bechtel activities I satisfies the requirement for annual audits of the applicable elements of the Quality Assurance Program. Audit activities include the following:
- 1. Audits of Project Engineering activities by Quality Assurance personnel. These audits are planned, scheduled, and ~
documented. Results are reported to the Project Engineer, l Project Manager, and the immediate functional supervisor of the
! Design Office Project Quality Assurance Engineer.
- 2. Audits of field Construction activities (including contractors l for Bechtel Construction Management jobs) by Quality Assurance i personnel. These audits are planned, scheduled, and documented. Results are reported to the Field Construction Manager, Project Manager, and the immediate functional supervisor of the Site Project Quality Assurance Engineer.
. 3. Audits of Supplier activities by the Procurement Supplier Quality Department. HL&P may audit suppliers for inactive orders and Bechtel mty utilize the results of such audits.
- 4. Audits of Project En,ineering, Procurement, Construction, and Quality Control activities by Quality Assurance audit teams under the direction of the Quality Assurance Manager, assisted by Materials and Quality Service specialists and others as required. These audits are conducted at least annually and results are reported to the management of the function audited, cognizant project management, and corporate management. A I
summary of the results of these audits is reported by the Manager of Quality Assurance to the President of BWPC,
- 5. Audits of corporate engineering technical staff and selected functional operation activities are performed on an annual basis under the direction of the Manager of Quality Assurance. These audits cover those groups doing design and/or review outside direct control of the Project Engineer. Results of these audits are reported to the manager or supervisor of the function audited and corporate management. A summary of the results of these audits is reported to the Manager of Quality Assurance.
t 0001v/0001v _ _ _ _ _ _ _ _ _ _ _ _ _
- 6. Audits of Procurement and Materials and Quality Service activities conducted annually by Quality Assurance personnel under the direction of the Manager of Quality Assurance. These audits are conducted for the benefit of Bechtel Power Corporations, and Quality Assurance personnel participate in the audits. Results of these audits are reported to cognizant management of the audited group in each corporation.
The purpose of the audit program is to assure compliance with all aspects of the QA program. Specifically, the audit program includes:
- 1. Audits conducted to assure that specialists, consultants, suppliers, constructor, and contractors are following their required programs for activities affecting quality, including activities associated with site features which affect plant safety. ,
- 2. Audits of all quality-related procedures. Such procedures include essential steps in the preparation, review, and control of design output documents; preparation, review, and control of procurement documents; indoctrination and training programs; and requests for proposals and evaluation of bids.
Audit frequencies vary, depending upon the nature and importance of the activity being performed and results achieved. The preceding listing provides information on frequency of management audits. Audits of activities are initiated early enough in the project cycle to assure effective implementation of the Quality Assurance Program, typically within three to six months after the start of work on activities affecting quality, and continue at regular intervals throughout the duration of the activity.
Audit findings are documented, reviewed with supervision having responsibility in the audit area, and reported to management; management audit reports include assessment of overall program implementation and direct attention to significant problem areas.
Audit programs include provisions for identification of deficiencies, determination that corrective action is defined, and follow-up to verify that timely corrective action has been taken and is effective. Audits include selective review and evaluation of quality-related procedures, instructions, work practices, and examination of items and records. Records of audits are available to STPEGS.
0001V/0001V APPENDIX A BECHTEL POSITION ON QA NRC REGULATORY GUIDES AND ANSI STANDARDS Page Title A-2 Regulatory Guide 1.30, Revision 0, August 1972 (ANSI N45.2.4-1972, IEEE 336, Installation, Inspection, and Testing Requirements for Instrumentation and Electric Equipment During the Construction of Nuclear Power Generating Stations)
A-3 Regulatory Guide 1.37, Revision 0, March 1973, (ANSI N45.2.1-1973, Cleaning of Fluid Systems and Associated Components During Construction Phase of Nuclear Power Plants)
A-4 Regulatory Guide 1.38, Revision 0, March 1973 (ANSI N45.2.2-1972, Packaging, Shipping, Receiving, Storage, and Handling of Items for Nuclear Power Plants [During the Construction Phase])
A-5 Regulatory Guide 1.39, Revision 0, March 1973 (ANSI N45.2.3-1973, .
HousekeepingDuringtheConstructionPhaseofNuclearPowerPlants)
A-6 Regulatory Guide 1.58, Revision 0, August 1973 (ANSI N45.2.6-1973, Qualifications of Nuclear Power Plant Inspection, Examination, and TestingPersonnel)
A-9 Regulatory Guide 1.64 Revision 2, June 1976 (ANSI N45.2.ll-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants)
A-Il Regulatory Guide 1.88, Revision 2, October 1976 (ANSI N45.2.9-1974, Requirements for Collection, Stcrage, and Maintenance of Quality Assurance Records for Nuclear Power Plants)
A-12 ANSI N45.2.5-1974, Quality Assurance Requirements for Installation, Inspection, and Testing of Structural Concrete and Structural Steel During the Construction Phase of Nuclear Power Plants A-13 Regulatory Guide 1.116, Revision 0-R, June 1976 (ANSI N45.2.8-1975, Supplementary Quality Assurance Requirements for Installation, Inspection, and Testing of Mechanical Equipment and Systems for the ConstructionPhaseofNuclearPowerPlants)
A-14 Regulatory Guide 1.123 Revision 0, October 1976 (ANSI N45.2.13-1976, Quality Assurance Requirements for Control of Procurement of Items and Services for Nuclear Power Plants)
A-15 RegulatoryGuide1.144, Revision 1, September 1980(ANSI N45.2.12-1977 Requirements for Auditing of Quality Assurance Programs for Nuclear Power Plants) 0004V/000lv A-1
.a APPENDIX A Regulatory Guide 1.30, Revision 0,- August 1972 (ANSI N45.2.4-1972, IEEE 336 Installation, Inspection, and Testing Requirements for Instrumentation and Electric Equipment During the Construction of Nuclear Power Generating Stations)
The requirenents of the referenced standard will be applied to the Bechtel Quality Program for construction of safety-related items as interpreted in the regulatory position as modified and interpreted below.
- 1) Section 1.2, Applicability. The standard is applied to the items and systems identified in paragraph 1.1.1 and to additional systems depending on the nature and scope of the work to be performed and the importance of the item or service involved.
- 2) Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard. Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case.
Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
1 0004V/000lv A-2
APPENDIX A Regulatory Guide 1.37, Revision 0, March 1973 (ANSI N45.2.1-1973, Cleaning of Fluid Systems and Associated Components During Construction Phase of Nuclear Power Plants)
, The requirements of the referenced standard as modified in the regulatory i
position will be applied to cleaning activities specified or applied by 1
Bechtel to safety-related items as modified and interpreted below.
- 1) Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard. Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case.
Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality. This is consistent with Section II, Paragraphs 2 and 3 of ANSI N45.2-1971 which provides for examination, measurement, or testing to assure quality or indirect control by monitoring of processing methods. However, final cleaning or flushing activities will be performed in accordance with procedures specific to the system.
- 2) Section 4, Preinstallation Cleanliness. This section states,
" Items should not be delivered to the point of installation site sooner than necessary unless the installed location is considered a better storage area." As an alternate to this l requirement, items may be delivered to the installation site sooner than absolutely necessary when determined to be l
advantageous for other considerations, for example, reduced handling or easier access, thereby reducing susceptibility to handling damage. In all such cases, equipment stored in place will be protected in accordance with Section 5 of ANSI N45.2.1-1973.
- 3) Section 3.1.2, Bechtel interprets the lighting level of 100 footcandles to be guidance. It is Bechtel's normal practice that the lighting level for determining " metal clean" of accessible surfaces of piping and components is determined by the inspector. Typically he uses a standard two-cell flashlight supplemented by other lighting as he deems necessary.
4 4
0004V/000lV A-3
APPENDIX A Regulatory Guide 1.38, Revision 0, March 1973 (ANSI N45.2.2-1972, Packaging, Shipping, Receiving, Storage, and Handling of Items for Nuclear Power Plants
[During the Construction Phase])
The requirements of the referenced standard as modified and interpreted in the regulatory position will be applied to the Bechtel Quality Program during the construction phase as described in Section 13 of this report, subject to the following clarifications and as modified and interpreted below.
- 1) Section 2.7, Classification of Items. The four-level classification system may not be used explicitly. However, the specific requirements for each classification as specified in the standard will be applied to the items suggested in each classification and for similar items.
Classification differing from Section 2.7 will be considered acceptable provided no degradation is assured; for example, electric motors designed for outside service may be stored in a level C area rather than a level B.
- 2) Section 6.2, Storage Areas. Paragraph 6.2.1 requires control and limited access to storage areas. In lieu of and to amplify this paragraph, the following will be applied:
" Access to storage areas for Levels A, B, and C will be controlled by the individual (s) responsible for storage. While the above areas will be posted to limit access, other positive controls (other than that for the overall site area) or guards may not be provided. Level D areas will be posted with the storage level designation only."
- 3) Section 5.5, Correction of Nonconformances. This section provides for " rework" and "use as is" dispositions for nonconforming items. As an alternate, the " repair" disposition (as defined in ANSI N45.2.10-1973) will also be used.
- 4) Section 6.2.4, Storage of Food and Associated Items. Controlled areas, within storage areas, will be established for the storage of food, drink, and salt tablets. These areas will be controlled through normal supervision and inspection.
- 5) In Section 8, the control of documentation and records shall be in accordance with Section 17 of this document.
- 6) Appendix, A3.4.2, Inert Gas Blankets. There may be cases involving large or complex shapes for which an inert or dry air purge flow is provided rather than a static gas blanket in order to provide adequate protection due to difficulty of providing a leakproof barrier. In these cases a positive pressure purge flow may be utilized as an alternative to the leakproof barrier.
0004V/000lv A-4
APPENDIX A Regulatory Guide 1.39, Revision 0, March 1973 (ANSI N45.2.3-1973, Housekeeping During the Construction Phase of Nuclear Power Plants)
The requirements of the referenced standard will be applied to the Bechtel Quality Program for construction of safety-related items except as modified or interpreted below.
- 1) Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard. Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case.
Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
- 2) Alternative equivalent zone designations and requirements may be utilized to cover those situations not included in the subject standard; for example, situations in which shoe covers and/or coveralls are required but material accountability is not. In addition, zones might be combined into the next more restrictive category in order to reduce total number of zones.
0004V/000lV A-5
APPENDIX A Regulatory Guide 1.58, Revision 0, dated August 1973 (ANSI N45.2.6-1973, Qualification of Nuclear Power Plant Inspection, Examination and Testing Personnel)
The requirements of the referenced standard, as modified and interpreted in the regulatory position will be applied to the Bechtel Quality Program during the construction phase as described in Section 2.5 of this document, subject to the following clarifications:
- 1) Section 3.4, " Level III Personnel Capabilities," of ANSI N45.2.6-1978 specifies the capability requirements of Level III personnel. In addition, the individual should be capable of reviewing and approving inspection, examination, and testing procedures and of evaluating the adequacy of such procedures to accomplish tne inspection, examination, and test objectives.
a
- 2) Section 3.5, " Education and Experience-Recomendations," of ANSI N45.2.6-1978 states that the education and experience specified are recomendations and that other factors may provide reasonable assurance that a person can competently perform a particular task. The set of recommendations has been reviewed by the NRC staff and found to be acceptable with one exception.
In addition to the recomendations listed under Section 3.5 for Level I, II, and III personnel, the candidate should be a high school graduata or have earned the General Education Development equivalent of a high school diploma. Since only one set of recommendations is provided for the education and experience of personn21, comitment to comply with the regulatory positions of this Suide in lieu of providing an alternative to the recomendations of the standard means that the specified education and experience recomendations of the standard will be followed.
- 3) Section 4, " Performance," of ANSI N45.2.6-1978 states: "When a single inspection or test requires implementation by a team or group, personnel not meeting the requirements of this Standard may be used in data-taking assignments or in plant or equipment operation provided they are supervised or overseen by a j qualified individual participating in the inspection, examination, or test." These personnel should have sufficient training to ensure an acceptable level of competence in the performance of their activities.
- 4) An important concept that is not addressed directly in ANSI N45.2.6-1978, ANST (sic) Recommended Practice No. SNT-TC-1A-1975 (sic), or the ASME Boiler and Pressure Vessel Code is that occupational radiation exposure should be maintained as low as
- is reasonably achievable (ALARA). In all cases where
, inspection, examination, and testing personnel may be exposed to
! radiation fields during their activities in restricted areas, these personnel should receive instruction in radiation protection and radiation-dose- reduction considerations related to work they are expected to 0004V/000lv A-6
o APPENDIX A perform. Regulatory Guide 8.8, "Information Relevant to Ensuring that Occupational Radiation Exposures at Nuclear Power Stations will be As low As Is Reasonably Achievable," describes techniques, features, and recommendations to maintain occupational exposures ALARA.
- 5) Section 2.2, " Determination of Initial Capability," and Section 2.3, " Evaluation of Performance," of ANSI N45.2.6-1978 deal with the use of evaluation of job performance and determination of initial capability to perform the job. Use of the measures outlined in these sections to establish that an individual has the required qualifications in lieu of required education and 4
experience should result in documented objective evidence (i.e.,
procedures and record of written test) demonstrating that the individual indeed does have " comparable" or " equivalent" competence to that which would be gained from having the required education and experience.
- 6) As an alternate, compliance with ANSI N45.2.6-1978 as specified by Regulatory Guide 1.58 (Revision 1, 9/80) in its entirety is acceptable.
- 7) Revise Table I of ANSI N45.2.6-1973 in accordance with the attached Table I (page A-8).
NOTE:
Regarding inspection, test, and examination during fabrication before receipt
- at the construction site, Bechtel fulfills this requirement by specifying applicable requirements of ANSI N45.2.6 or the equivalent (the Standard
, N45.2.6 may not be listed as a requirement in procurement document) tailored to the nature of the procurement and commensurate with the degree of skill and i qualification necessary for inspection, test, and exan:ination. For example, l on simple inspections using go-no-go techniques or simple linear measurements i
within broad tolerance bands, the requirements of ANSI N45.2.6 would not l
apply; a satisfactory equivalent being routine inspection instructions and personnel assignments by supervision.
I 4
I i
l 0004V/000lV A-7
.--r-e ,7, ,,-, n, --. ,----,-.r-n,---m__._-.,,--. ---y-,r--y, , . - -,-,r.----,,mw --.----m-u-----m-w.,,,, g, , -~m, , --n-w--~-
APPENDIX A TABLE 1 MINIMUM LEVELS OF CAPABILITY FOR PROJECT FUNCTIONS Project function Level L-l L-II L-III Recording inspection, examination, and X X X testing data Implementing inspection, examination, and X X X testing procedures Planning inspections, evaluations, and tests; X X setting up tests, including preparation and setup of related equipment Evaluating the validity and acceptability of X X inspection, examination, and testing results Reporting inspection, examination, and testing X X results Supervising equivalent or lower level X X personnel Qualifying lower level personnel X X Evaluating the adequacy of specific X programs used to train and test inspection, examination, and testing personnel Reviewing and approving inspection X examination, and test procedures Evaluating the adequacy of activities X to accomplish inspection, examination, and test objectives l
l 1
0004V/000lV A-8
APPENDIX A Regulatory Guide 1.64, Revision 2 June 1976 (ANSI N45.2.ll-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants)
The requirements of the referenced standard as modified by the regulatory position will be applied to Bechtel Quality Program for safety-related items.
The following interpretations of the standard serve to clarify the Bechtel program in relation this regulatory guide.
- 1) Section 3.1, Design Input Requirements, General. This section implies that all necessary design input (as listed in Section 3.2) should be available prior to the start of a design activity. In practice, certain design activities are initiated before the firm input requirements are available. (For example, foundation designs prepared based on preliminary information or equipment sizes and mounting, embedded conduit run based on preliminary estimates of circuit requirements, etc.) The design phase Quality Assurance program will be structured to ensure that all necessary design input is available before completion of final design of the work affected by the input and that final design input is available for used in verification of the final design.
- 2) Section 4.1, Design Process, General. Paragraph 3 implies traceability back from final design to the source of design input. In practice, a literal interpretation of this is not always possible. For example, final design drawings do not identify the related calculations. This paragraph will be interpreted to mean that it shall be possible to relate the criteria used and analyses performed to the final design documents and that record files will permit location of analyses supporting specific design output documents.
- 3) Section 4.2, Design Analyses. This section implies a requirement for retention of all calculations. In principle, it is considered good practice for the responsible engineer or engineering organization to retain all final calculations, and this will be done for all manual calculations covered by the Bechtel program. However, for computer programs only documentation of the design input, assumptions made in the analyses, results obtained, and evidence of verification will be retained since permanent retention of all versions of all computer programs is not considered practical or necessary if sufficient information is available for a competent individual
! to verify the results using the input and assumptions.
I 1
I 0004V/000lV A-9
APPENDIX A
- 4) Section 10, Records. In-process documentation, relating to checking and coordination of drawings (for example, check and coordination prints) or copies of marked-up specifications used to solicit comments shall be retained until the drawing or specification is approved and issued for use outside of Bechtel Engineering. such in-process documents will be available for review / audit until the document is approved, but may be discarded once the document has been approved. In the first sentence of the second paragraph the phrase " final design documents" shall mean those documents which are the latest revision that has been issued for use.
- 5) Regulatory Position, Section C-2: If, in an exceptional circumstance, the originators' immediate supervisor is the only technically qualified individual available, the design verification or checking will be conducted by the supervisor with the following provisions:
- a. The other requirements of Regulatory Guide 1.64 will be met.
- b. the justification will be individually documented and approved by the next level of supervision,
- c. Quality Assurance audits will include review of the frequency and effectiveness of the use of the immediate supervisor to assure that this provision is used only in exceptional circumstances.
l l
0004V/000lv A-10
l APPENDIX A Regulatory Guide 1.88, Rev. 2, October 1976 (ANSI N45.2.9-1974, Requirements for Collection, Storage, and Maintenance of Quality Assurance Records for NuclearPowerPlants).
The requirements of the referenced standard, as modified and interpreted in the regulatory position, will be applied to the Bechtel Quality Program during the design and construction phase, as described in Section 17 of this document, subject to the following clarifications:
- 1) Section 1.4, Definitions. Cuality Assurance Records - A document is considered completed when it has finished full processing and has been issued for use in design, procurement, construction, or manufacturing.
- 2) Section 1.4, Definitions. Authenticated Records - those records which are clearly identified as a statement by the individual or organization holding responsibility. Hand-written signatures are not required if the document or printout is clearly identified as a statement by the reporting individual or organization.
- 3) for Appendix A, an installation shall be considered to be in an "as constructed" condition if it is installed within the tolerances established by Project engineering indicated in the design output documents.
l l
l 0004V/000lV A-11
APPENDIX A ANSI N45.2.5-1974, Quality Assurance Requirements for Installation, Inspection, and Testing of Structural concrete and Structural Steel during the Construction Phase of Nuclear Power Plants
- The requirements of the referenced standard will be applied to the Bechtel Quality Program for construction of safety-related items as follows:
- 1) Samples and frequency for cadweld testing is in accordance with ACI-359/ASME Section III, Division 2, issued for trial use and consnent in 1973, including addenda 1 through 6, (see Sections 3.8.1.6.3 and 3.8.3.6.3 of the STP Final Safety Analysis Report).
- 2) Section 4.8, states " Pumped concrete must be sampled from the pump line discharge." In lieu of this statement, in-process strength samples of pumped concrete are taken at the delivery point. Correlation tests of air content, slump, and temperature are performed to verify these plastic properties of the concrete at the placement point in accordance with the following frequency requirements:
- a. A minimum of 2 correlation tests are performed for each pumped placement exceeding 200 cu. yds.
- b. Otherwise, a minimum of 2 correlation tests per week are performed when any individual pumped placement during a i week requires delivery of more than one truckload of concrete.
- c. During a week when a pumped placement exceeding 200 cu.
yds is made, the correlation tests performed on that placement will satisfy the weekly requirement for performing two correlation tests as specified in Item b above.
If the correlation test result shows a concrete property not meeting the specification limits and/or tolerances at the point l Of placement, the frequency of correlation testing shall be increased to 100 cubic yards. If two consecutive correlation tests exceed the specified limit for slump, air content, or
, temperature, the Constructor shall document the condition,
! notify Bechtel Site Engineering within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of completion of l
the placement and shall return to control of the concrete by in-process testing at the point of placement per ANSI l N45.2.5-1974.
" Correlation Tests," " Delivery Point," and " Placement Point" are as defined in ANSI N45.2.5-1978, Section 1.4.
0004V/000lv A-12
~ ._ -.- . . - - _ - .. .
r APPENDIX A Regulatory Guide 1.116, Revision 0-R, June 1976 (ANSI N45.2.8-1975, Supplementary Quality Assurance Requirements of Installation, Inspection and Testing of Mechanical Equipment and Systems for the Construction Phase of NuclearPowerPlants).
The requirement of the referenced standard as modified and interpreted in the regulatory position will be applied to the Bechtel quality program for construction of safety-related items except as modified and interpreted below:
- 1) Section 1.1, Scope. The term "important items" will be interpreted to apply to those activities or quality attributes of an item or service that could affect a nuclear safety-related characteristic. For example, if a barrier is required for leakage control, but serves no structural function, the i leaktight characteristic would be considered "important," but appearance, dimensional requirements, and structural features would not necessarily be considered important; or if a pump casing is required for coolant boundary integrity, but the pump does not have to operate to provide for nuclear safety, those
- attributes which affect its operation would not be considered
- important from the standpoint of nuclear safety.
i
, 2) Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard. Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case.
Installatien plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
- 3) Section 3.3, Process and Procedures. the terms ' installation site," " installation area," and " site" used in this standard shall be interpreted as follows:
. a) " Installation site" or " site" will be interpreted the same i-as " construction site." When applied to documents, these may be at the central office or work area document control station.
b) Installation area - Immediate proximity of location where work is to be performed.
- 4) Section 3.5(e), Site Conditions. This requirement will be applied only if subsequent correction of adjacent nonconformances could damage the item being installed.
- 5) Section 4.6, Care of Items. HL&P retains the authority and is the " Responsible Organization" for temporary usage of equipment or facilities unless specific (i.e., on a c'ase by case basis) or general authority is granted in writing to the Construction l Manager's organization.
0004V/000lV A-13
APPENDIX A Regulatory Guide 1.123, Revision 0, October 1976 (ANSI N45.2.13-1976, Quality Assurance Requirements for control of Procurement of Items and Services for NuclearPowerPlants).
The requirements of the referenced standard as modified and interpreted in the regulatory position will be applied to the Bechtel Quality Program during the design and construction phases except as modified and interpreted below:
- 1) Section C.3 of the Regulatory Guide - A corrective action system may, depending upon complexity and/or importance to safety of the item or service provided, be imposed upon the supplier.
When a corrective action system is imposed on a supplier, the applicable elements of Section 9.0 of the standard will be included and its implementation will be verified by Bechtel.
- 2) Section C.4 of the Regulatory Guide - Applicable information i concerning the method (s) of acceptance of an item or service will be made available to receiving inspection personnel.
- 3) Section 4.2.a of the Standard - When evaluation of a supplier is based solely on historical supplier data, these data will 4
primarily include Bechtel's records that have been accumulated in connection with previous procurement actions. Data that includes experience of users of identical or similar products of
. the prospective supplier and product operating experience will be sed if they become available to Bechtel; however, such data are normally available only to those involved in plant operations.
- 4) Section 10.2.d of the Standard - The requirements of this section are interpreted as follows: The person attesting to a certificate shall be an authorized and responsible employee of the supplier and shall be identified by the supplier.
- 5) Bechtel's position relative to ANSI N45.2.13-1976, Section 10.2.f, Verification of the Validity of Supplier Certificates and the Effectiveness of the Certification system, is as follows: The verification of'the validity of supplier certificates and the effectiveness of the certification system are accomplished as an integral part of the total supplier control and product acceptance program, and no separate Bechtel system exists that addresses itself solely to such verification. The degree of verification required will depend upon the type of item or service and their safety importance.
i The means of verification may include source witness / hold points, source audits, and document reviews; independent inspections at the time of material receipt; user tests on selected coninodities, such as concrete components; and tests after installation on selected components and systems. All of these means verify whether or not a supplier has fulfilled ,
procurement document requirements and whether or not a certification system is effective.
- 0004V/000lV A-14
APPENDIX A Regulatory Guide 1.144, Revision 1, September 1530 (ANSI N45.2.12-1977, Requirements for Auditing of Quality Assurance P ograms for Nuclear Pcwer Plants)
The requirements of this standard will be applied to the Bechtel Quality Program as modified and interpreted below:
- 1) ANSI N45.2.12-1977, Section 1.3 states, "In no way shall the performance of audits by an organization diminish the responsibility of the audited organization or contractor for audit of his designated portion of the quality assurance program or the quality of his product or services." For the South Texas Project all quality related activities implemented for the South Texas Project are audited annually at a minimum, or at least once within the life of the activity, whichever is shorter.
These audits are performed by either HL&P, BEC, or ESI Quality Assurance personnel.
- 2) ANSI N45.2.12-1977, Section 4.5.1 states, "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed." This implies that the audited organization must provide the auditing organization with written notification detailing what corrective action was taken and when the corrective action was completed.
In actual practice, the audited organization will provide the auditing organization with documented corrective action including the date when the corrective action will be completed. The auditing organization will evaluate the corrective action response to determine if corrective action verification is necessary. If verification is necessary, the corrective action verification will be performed after the scheduled completion date and the result of the verification will be documented.
1 l
l l
0004V/000lV A-15
STPEGS - QAPD PART B APPENDIX B Project Quality Program Manual
^M 10CFR50 APP. 8 BA Section Section Description Section i 1 Organization 1 ll 2 Quality Assurance Program 2 Ill 3 Design Control 3 IV 4 Procurement Document Control 4 V 5 Instructions, Procedures and Drawings 5 VI 6 Document Control 6 Vil 7 Control of Purchased Material, Equipment 7 l
and Services Vill 8 Identification and Control of Material, Parts 8 and Compoments IX 9 Control of Special Processes 9 X 10 Inspection 10 XI 11 Test Control 11 XII 12 Control of Measuring and Test Equipment 12 Xill 13 Handling, Storage and Shipping 13 XIV 14 Inspection, Test and Operating Status 14 XV 15 Nonconforming Materials, Parts, or Components 15 l
XVI 16 Corrective Action 16 XVil 17 Quality Assurance Records 17 XVill 18 Audits 18 l
l R91SC F4 (STPEGS)
1 This chart identifies reporting relationships to, BECHTEL GROUP, INC.
organizations that may perform activities in acrordance with this manual and is not intended CHAIRM AN to identify att funtionat organizations or groups' EXECUTIV V CE PRESIDEN15 I I _ I I I BECHTEL CIVIL, B ECHTEL, INC. BECHTEL BECHTEL BECHTEL CONSTRUCTION, VICE PRESIDENT INC. WESTERN POWER EASTERN POWER IN C. AND RE P NS E CORPORATION g O CF CORPORATION PRESIDENT PRESIDENT PRESIDENT PRESIDENT PRESIDENT I I PROCUREMENT ENERG
- CORPORATION PRESIDENT PERSONNEL BECHTEL BECHTEL fN.
NATIONA NC. FACILITIES AND CORPO Tl N PRESIDENT MANAGEMENT PRESIDENT PRESIDENT SERVICES I
MATERIALS AND QUALITY SERVICES STP - QAPD PART B FIGURE 1 ORG-F4
BECHTEL WESTERN POWER CORPORATION This chart identifies reporting relationships for orgrnizations that may perform activities in NORWALK, CALIFORNIA l tccordance with this manual and as not intended BECHTEL WESTERN to identify all f untional organizations or groups.
POWER CORPORATION l
PRESIDENT I
I I I HOUSTON OFFICE NORWALK OFFICE SAN FRANCISCO
- VICE PRESIDENT V.P AND MANAGER OFFICE AND MANAGER V.P. AND MANAGER I
MANAGER $ E E MANAGERS O FUNCTIONAL DOMESTIC OPERATIONS PROJECT = OPERATIONS - OPERATIONS = m ENGINEERING VICE PRESIDENT -
V.P. AND MANAGER V.P. AND MANAGER AND MANAGER I
BECHTEL,1NC. O MANAGERS
. MANAggg op SUPPORT PROCUREMENT MANAGER OF MANAGER OF "
, , - BUSINESS DEVELOP' SERVICES CONSTRUCTION ENGINEERING i DOMESTIC =
CONSTRUCTION QUALITY , QUAllTY ASSURANCE "
MANAGER DOMESTIC ASSURANCE AMGER OF - - OF = = PROJECT l g STARTUP SUPPORT SERVICES MANAGERS PROCUREMENT =
CAD SUPPORT , PROJECT ,
MAnlAGERS MANAGER OF MANAGER OF F ROJECT MANAGER OF
! BUSINESS
$ =
TECHNICAL SERVICES PROCUREMENT
- - OPERATING PLANT SERVICES MANAGERS EPRUCOGEN/DIABLO DEVELOPME NT OPERATING "
i PLANT 5ERVICES MANAGEROF QUALITY ASSURANCE TECHNICAL
$ ReceivesFunctionalDirection SERVICES 4
from the Applicable Corporate Manager Q Receives Functional Coordination and Support from the Houston Of face Vice President and Mar.ager Receives Functional Guidance for Applicable San Francisco Organization STP - QAPD onu. PARTB FIGURE 2 1
HOUSTON OFFICE '
PLAN OF ORGANIZATION This chart is intended to reflect reporting relationships and not necessarily levels of responsibility, seniority of positions, or working relationships VICE PRESIDENT AND HOUSTON MANAGER 1
MANAGER OF PROJECT MANAGER OF PERSONNEL MANAGERS DE LOP ENT MANAGER OF QUALITY PROCUREM ENT ASSURANCE MANAGER STP - QAPD PART B TIGURE 2A ORG-F4 1
l i
PROCUREMENT SAN FRANCISCO This chart identifies reporting relationships for organizat ons that may perform activities in accordance with this manual and is not intended PROCUREMENT to identif y all f untional organizations or groups.
VICE PRESIDENT AND MANAGER I
I I I I MANAGER OF MANAGER OF ^^ ^
PROCUREMENT PROCUREMENT C NTRAL lNE 5 PROCUREMENT DEVELOPMENT r---- r--- l l PROCUREMENT l PROCUR MENT PROCUREMENT
- g MANAGERS g MANAGERS MANAGERS WES N POWER -
BECHTEL. INC. - "^ ^
l CORPORATION l CONTRACTS l-- BECHTEL l--
EASTERN POWER BECHTEL LTD. _ TRAFFIC AND l CORPORATION l (LONDON) LOGISTICS
-- BECHTEL -- BECHTEL -
l NATIONAL, INC. l CIVIL, INC. ER IONS (LOUISVILLE) 1 I E- TOKYO E- -
SER I EXPEDITING FIELD PROCUREMENT pp
-==- Functional Supporting g ,, QUALITY STP - QAPD PARTB FIGURE 3
PROCUREMENT SUPPLIER
,, QUALITY DEPARTMENT his chart identifies reporting relationships for orga nizations that may perform activities in tuordance with this manual and is not intended to identify all f untional organizations or groups. M N G ROF QUALITY I
i , , _._._._.q TECHNICAL ______ SUPPLIER SERVICES
,... FIELD SERVICES ...
F E QUALITY MANAGER MANAGER - SUPERVISORS E SUPPLIER
! l QUALITY -
l l MANAGERS PROJECT SUPPLIER QUALITY REGIONAL TECHNICAL SUPERVISORS AND SUPERVISORS l AUDIT TEAM SERVICES REPRESENTATIVES
' LEADERS SPECIALISTS PROJECT SUPPLIER
, l QUALITY REPRESENTATIVES TECHNICAL
- SERVICES AREA SUPERVISORS AND SUPERVISORS Administrative & Technical Direction REPRESENTATIVES
--- Technical Direction QUALITY l REPRESENTATIVES
...... Field Coordination 4 -.- Technical Direction and Program SUPPLIER -
Coordination QUALITY REPRESENTATIVES E Reports to Procurement Manager for Administrative Direction STP - 0APD PART C FIGURE 4 ORG F4
ORGANIZATION CHART OF THE MATERIALS AND QUALITY SERVICES DEPARTMENT RESEARCH AND DEVELOPMENT-MATERIALS AND QUALITY SERVICES MANAG ER l
l DEPARTME NT E SERVICES TECHNICAL SUPERVISOR
^ ^ ^
l I MATERIALS AND FABRICATION CODES AND CORROSION SERVICES STANDARDS MANAGER MANAGER MANAGER I
E GAITHERSBURG E HOUSTON E LONDON E LOS ANGELES OFFICE OFFICE OFFICE I
OFFICE MANAGER MANAGER MANAGER MANAGER E Reports to Technical Staff Assistant This chart > intended to reflec+ reporting relatic aships and not necessarily levels of resporsibility,seniorsty of postions, or working relationships.
STP-QAPD PARTB g FiliURE 5 I
THIS CH ART IS INTENDED TO REFLECT REPORTING RELAT.ONSHIPS AND NOT NECESSARILY LEVELS OF RESPONSIBILITY, SENIORITY OF POSITIONS,OR WORKING RELATIONSHIPS MANAGER OF QUALITY ASSURANCE I
MANAGER OF S.F.A.O. QUALITY ASSURANCE l
I I I I I _
QA MANAGER QA MANAGER QA MANAGER QA MANAGER PALO VERDE / QA ANA PROG. / AUDITS / VOGTLE / INT'L/
P'E C'L~ SOUTH TEXAS OPER. PLANT ALL . . ppO E 5 l TRAINING HOUSTON OFFICE SERVICES STP - QAPD
- PART B FIGURE 6 ORG F4
.___-_A
l.4.2 Project Engineering The Project Engineering Manager (PEM) is responsible t'or the conduct of cngineering on the STPEGS. The PEM may be aided by one or more assistants.
The PEM provides project direction to Project Engineering. The PEM is responsible for ensuring that engineering work under Bechtel cognizance is carried out in accordance with the project direction received from the Bechtel Project Manager and the technical direction received from the Engineering flanager.
The Group Supervisors are responsible for the quality and technical adequacy of the engineering work performed under their guidance and receive their technical direction in these matters from the Chief Engineers for their respective disciplines. The Group Supervisors are assigned a team of engineers, designers, and draftsmen by their respective Chief Engineers. The Project Engineering Manager, Project Engineers, group supervisors, engineers, designers, and draftsmen comprise the engineering team. The STPEGS engineering team organization is shown in Figure 9. The project engineering team is responsible for all Bechtel engineering design work performed by and for the project and for checking functions performed on the project. Special design suppcrt is furnished to the project engineer by specialty groups. The Project Engineer is responsible for such special design work conducted off the project and for requiring that it be subjected to the same degree of checking and control as that conducted on the project. Key design work is also reviewed off the project by personnel on the staff of the Chief Engineer.
The project engineering team has the following responsibilities:
- 1. Prepare calculations, drawings, and specifications which
, constitute the engineering designs
- 2. Assure that drawings, specifications, procedures and instructions produced conform to project requirements, Bechtel standards, applicable industry standards, regulatory agency requirements, and the design bases as defined in Safety Analysis Re p ts
- 3. Prepare specifications for Supplier and Constructor /
Contractor (s) Quality Assurance Pro 9eam i
- 4. Establish the need for procurement surveillance inspection and audit, and monitor results of same 4
- 5. Review and approve the design changes and approve nonconformance dispositions
! 6. Review drawings, procedures, test data, manuals and reports submitted to Engineering by suppliers and Constructor /
Contractor (s)
- 7. Indoctrinate Engineering personnel in the use of Engineering procedures
-8. Provide support to Construction management relative to storage and maintenance of permanent plant equipment 000lV/000lv . . ___ - - - _ __ -
1.4.3 Project Construction Management The Field Construction Manager is responsible for the project field construction performance. The Field Construction Manager is responsible for assurir19 that construction activities are performed in accordance with the design requirements as established by project engineering and other applicable requirements.
STPEGS construction management organization is shown in Figure 10.
The Constructor / Contractor (s) are assigned first-level responsibility for the control of the quality of their work. Their performance is coordinated and monitored by the Bechtel field organization. The Bechtel Quality Assurance organization performs documented audits and surveillances and has the capability to perform surveillance inspection.
In cases where the Constructor / Contractor (s) are responsible for quality verification inspection or other quality assurance functions, the contract documents incorporate the requirements for the Constructor / Contractor (s) quality assurance program. Constructor / Contractor (s) quality assurance and quality control personnel are required to have the appropriate authority, organizational freedom, and independence within their own organization.
Constructor / Contractor (s) program requirements are specified by incorporation of the requirements of Reg. Guide 1.28 (6/7/72) or the ASME Boiler and Pressure Vessel Code,Section III, as appropriate. In the event that the Constructor / Contractor (s) is unable to provide an acceptable program, Bechtel may assume quality verificatir,n inspection responsibilities or these may be contracted to another organization.
1.4.4 Project Pracurement The Project Procurertnt Manager receives technical and administrative direction from the Manager of Procurement, Houston and project direction from the Project Manager. The Project Procurement Manager provides direction for the STPEGS procurement activities and pro,iect direction to the Project Supplier Quality Supervisor.
The Project Supplier Quality Supervisor reports to the Houston Supplier l Quality Manager for technical and administrative direction and receives project direction from the Project Procurement Manager. The functions of the Project Supplier Quality Supervisors are:
- 1. Coordinate project procurement surveillance inspection activities with project engineering and Procuretent Supplier Quality
- 2. Comment on technical specifications prior to issuance for bids
- 3. Initiate supplier surveys, Supplier Quality assignments, and coordinate supplier audits with procurement Supplier Quality
- 4. Review and accept procurement surveillance inspection reports
- 5. Give project direction on project Supplier Quality assignments to the Bechtel Supplier Quality Representative 0001V/0001V r-STPEGS procurement organization is shown in Figure 11.
Field procurement functions are-performed by the Field Procurement. Manager at the Jobsite. The Field Procurement Manager receives technical and administrative direction from the BWPC Field Procurement Manager and project direction from the Field Construction Manager through the Material Control Manager.
s 0001v/0001V SECTION 2 QUALITY ASSURANCE PROGRAM 2.1 SCOPE The program described in this document is applied to the design, procurement, and construction management of those structures, systems, and components (items) whose satisfactory performance is required to prevent accidents which may cause undue risk to the health and safety of the public or to mitigate the consequences of such accidents if they were to occur. These items are defined as safety related and are identified in the safety analysis report for STPEGS.
2.2 POLICY The Bechtel Quality Program described in this document assigns the responsibility for quality to the organization responsible for performing the work and includes as a basic requirement that individuals responsible for verifying and checking are independent of the individual or group responsible for performing the work. Additionally, independent review, audit, and surveillance are performed by individuals not affiliated with the organizational entities responsible for performance of the work.
The President of Bechtel Western Power Corporation is responsible for the overall quality policy.
BWPC quality assurance department procedures are formulated by the Manager of Quality Assurance.
The Quality Program and Quality Assurance practices for STPEGS are formulated by the Project Quality Assurance Manager, approved by the Manager of Quality Assurance or designee and implemented through the Project Quality Program Manual, the Project Quality Assurance Procedures and various department / group procedures. The implementing procedures are approved for program compliance by the Manager of Quality Assurance or a designee (See Table I). The STPEGS quality program follows applicable corporate procedures, suitably modified to meet the scope of STPEGS, including delineated HL&P and project requirements.
The Project Quality Assurance Manager is responsible for coordinating the development of the project quality program and assuring that appropriate approvals are obtained. Project and Corporate Quality Assurance personnel monitor and/or audits project program activities for compliance with approved procedures and policies. Quality Assurance personnel have the responsibility and authority to carry out these functions, including identification of program problems, initiation of action to resolve such problems, and final verification that the action was taken and the problem satisfactorily solved.
000lV/000lv The Project Quality Program includes program documents and and procedures which define the responsibility and authority of each group within the project and identifies' documents to be prepared and their distribution. Bechtel project communication is assured through the close physical relationship of project participants and the requirements for formal documentation and reporting.
Communication between the Houston Lighting & Power QA organization and Bechtel depends on contractual relationships and complies with various interface agreements. The Project Quality Assurance Manager is the focal point for quality program communication. Formal quality assurance program reporting is performed either through the Project Manager or directly by the Project Quality Assurance Manager. In either case, the Project Quality Assurance Manager is responsible for coordinating preparation of quality program communication. Day-to-day communication on problems involving engineering, procurement, and construction may be carried out directly between the Bechtel group responsible for the activity and appropriate utility personnel.
However, the Project Quality Assurance Manager is furnished copies of this correspondence, as appropriate.
Supplier and contractor quality control includes provision of specifications by Engineering requiring suppliers and contractors to execute appropriate quality programs; surveillance inspection of suppliers by the Procurement Supplier Quality Department, or by Quality Control for onsite contractors; and surveillance and audit of these activities by Quality Assurance personnel, the Procurement Supplier Quality Department staff, and/or Materials and Quality Services.
Control of construction activities performed directly by Bechtel includes in-process technical guidance and monitoring of the work by field engineering personnel who are independent of direct construction craft supervision; quality verification inspection and surveillance and audits by Quality Assurance personnel supplemented by Materials and Quality Services personnel.
Quality-related activities, such as inspection and test, are performed with appropriate equipment and under suitable environmental conditions.
2.3 STOPWORK The program provides Quality Assurance personnel with stopwork authority over certain portions of project activity, and this authority is delineated in procedures. In addition, control of further processing of unacceptable work is provided by appropriate hold and release points as follows:
- 1. Design. Unsatisfactory work with respect to design documents prepared by Bechtel is controlled through the independent review process (prescribed by written procedures) and the refusal of the checker / reviewer to sign off the acceptance of the document which blocks its further processing and issue for use. Each non-Bechtel design document for which project engineering has an interface and reviaw responsibility is logged upon receipt and has affixed a standard Bechtel stamp which signifies the status of the document when it is returned to the originator. Any status other than permission to proceed automatically sets in motion follow-up and close-out actions.
000lV/000lv . - _ _ . -_ _ --
- 2. Procurement. Bechtel control over Supplier work is as follows:
the Procurement Supplier Quality Representative, when required by procurement documents, must authorize supplier release for shipment (for purchased items) and may recommend stoppage of work on selected activities through designated contractual channels in situations which, if uncorrected, would render the item unacceptable for release. In cases of gross deficiencies or violations, procurement documents provide contractural relief, including termination, and these measures can be used when necessary.
- 3. Construction. Quality Control has two primary r.iechanisms to control further processing of unacceptable work. These are the nonconforming material control system and the authority to refuse acceptance of completed work. Quality Control has authority to recommend stoppage in situations which, if uncorrected, would render the item nonconforming or unacceptable. In cases of contractor work, Quality Control exercises controls similar to Procurement in 2. above.
2.4 PROGRAM DOCUMENTATION Bechtel Western Power Corporation Quality procedures and instructions are contained in the documents listed in Table I. Appendix B of this document lists the Quality Programs for STPEGS work and identifies their scope and relationship to 10 CFR 50 Appendix B.
Figure 12 is a graphic presentation of the relationship of documents that comprise the quality program for STPEGS. Each of these documents is authorized by the manager responsible for the activity. (Copies of Bechtel standard documents in Table I are available for review by regulatory authorities and HL&P, and controlled copies of those designated by an asterisk are available upon request through HL&P to cognizant regulatory bodies.)
Corporate and Department procedures and practices form the basis for the l Quality Assurance Program on STPEGS. The STPEGS Project Quality Program Manual references the procedures and manuals which comprise the Project Quality Program. The procedures and instructions contained in these manuals, are supplemented where necessary by specific work instructions and checklists. These project manuals are controlled and maintained by the project team.
STPEGS has the responsibility for preparing and maintaining documentation defining project design criteria and applicable codes, standards, and regulatory requirements. Further, STPEGS has the responsibility for preparing and maintaining organization charts and documentation defining interface responsibilities among various Bechtel groups and other major non-Bechtel project participants, such as HL&P and Westinghouse Electric Corporation.
000lV/000lV c
2.5 PERSONNEL Bechtel personnel participating in the Quality Program are provided with )
specific indoctrination and training covering the project procedures applicable to their work. This is accomplished by reading applicable procedures, general discussions of specific procedures and individual training by project supervision and staff specialists. Similar programs are employed for indoctrination of individuals assigned to staff and specialist groups.
Records are maintained showing completion of indoctrination and training.
Indoctrination and trair.ing is conducted in accordance with written procedures.
In addition to the basic indoctrination and training programs and performance reviews, certain minimum education and experience guidelines have been established for various positions responsible for managing and directing program activities. While these are used for guidance in selecting candidates for these positions, they are not considered absolute requirements when other factors, such as the individual's demonstrated capability and staff technical support available to him, provide assurance that appropriate managerial and t:chnical skill will be applied.
The basic qualification requirements for key management positions in the quality groups are an advanced degree with five or more years of appropriate management and quality assurance experience, or a bachelor's degree with eight or more years of appropriate experience. Additinnal pertinent experience is considered in lieu of a bachelor's degree.
The basic qualification requirements for supervisory and project quality functions, such as Project Quality Assurance Manager (PQAM), Project Quality Assurance Engineer (PQAE), Project Quality Control Engineer (P0CE), etc., are an advanced degree with two or more years of appropriate supervisory and quality-related experience or a bachelor's degree with five or more years of appropriate experience. Additional pertinent (technical) experience is considered in lieu of a bachelor's degree. Records are maintained showing qualifications of key management, supervisory, and project personnel in quality groups.
The following specific qualification requirements are applied:
- 1. Personnel performing pressure boundary and structural welding and nondestructive examination are required to meet applicable qualification requirements of ASME Code, SNT-TC-1A-80*, or other appropriate codes and standards.
4
- 2. Quality Control Personnel - Quality Control personnel performing surveillance inspection of contractors work will be qualified in accordance with the provisions of Regulatory Guide 1.58, Rev. 0 (as interpreted by the positions contained in Appendix A of this document) or SNT-TC-1A-80*, as applicable.
- 3. Audit Personnel - Personnel performing audits will be qualified in accordance with the appropriate requirements of ANSI N45.2.23- 1978, as endorsed by Regulatory Guide 1.146, Rev. O, 8/60.
Instances of recommendations within SNT-TC-1A-80 ('should') will be considered mandatory requirements ('shall'). This exception will be reflected in appropriate implementing procedures.
0001V/000lV _- . - - . .
. - -_._. . . .=. . .- - . . . -_ .
1 4. Procurement Supplier Quality Representatives - A formal trairing i
program, developed.by the Procurement Supplier Quality Department, is required for Supplier Quality Representatives assigned nuclear plant purchase orders. This' program is defined in.the Bechtel Procurement Supplier Quality Manual (PSQM) and conforms to the applicable requirements of ANSI N45.2.6-1973, as endorsed by Regulatory Guide 1.58, Rev. O, 8/73, as interpreted by the positions contained in Appendix A of this. document.
2.6 . PROGRAM CONTROL l
I Personnel performing quality assurance and quality control functions are I
provided with several means for controlling adherence to the quality program j requirements. These include:
- l. Various levels of approvals described in Sections 1 and 2.2 of
- this document.
- 2. Stopwork as described in Section 2.3 of this document.
- 3. Inspection and review hold points for engineering documents, 2 supplier work and documentation, and construction activities as l
i described.in various sections of this document.
- 4. Nonconformance and corrective action procedures as described in Sections 15 and 16 of this document.
In all the above instances, decision of the assigned individual performing the ,
, quality assurance function is controlling, subject only to appeal by the line organization through their management and to the cognizant quality function
- management. In any case, personnel performing quality assurance and quality control functions have the authority to identify quality problems and initiate l- action leading to their. solution.
1 Resolution of disputes which are not resolved at lower levels is as follows:
[ The final authority on project quality program matters rests with the Project Quality Assurance Manager, subject only to appeal by the Project Manager to the Manager of Quality Assurance.
2.7 PROGRAM EVALUATION i
I The BWPC Manager of Quality Assurance meets regularly with the QA Manager of l Projects and the Project Quality Assurance Manager on the status of the project and problem areas. Reports to the President of BWPC on a quarterly basis regarding the evaluation of the status and adequacy of the program l-including any required revisions to the program or special attention required including any recommendation for corrective action.
l i 0001V/000lV l
2.8 MANAGEMENT REVIEW Management reviews of the status and adequacy of this quality assurance program are accomplished through periodic reports and presentations by Quality Assurance Management personnel to their respective managers, and through reviews of quality assurance management audit reports. Meetings are held on a regular basis at the corporate level.
The Bechtel Western Power Corporation Quality Assurance Program, including Functional Operations Quality Assurance Programs, are reviewed annually by individuals outside the quality assurance function. These reviews are performed by management above or outside the QA organization for BWPC
!4anagement. The results of these reviews are documented and submitted to corporate management.
Management reports contain summary data on the status of outstanding audit and corrective action items and identify the status of other significant quality program activities which may include items such as training and qualification programs; development of standard procedures, work plans, and other documents; status of industry standards; and other external issues of interest. These reports and discussions combined with other reports on overall corporate performance are used by BWPC management above the level of Manager of Quality Assurance to assess the scope, implementation, and adequacy of the STPEGS auality assurance program.
The status of the STPEGS quality assurance program is reported regularly to cognizant management by the Project Quality Assurance Manager. These reports identify quality problems and summarize results of project quality assurance activities. Project quality program status also is identified and evaluated through management audit reports which are conducted in accordance with the provisions of Bechtel Western Power Corporation Quality Assurance Department Procedures. Audit reports are reviewed by cognizant quality assurance management and copies are submitted to corporate management and cognizant department management. The Manager of Quality Assurance is responsible for monitoring these reports and other information received from STPEGS such as 50.55(e) reports and Part 21 reports, and for sumarizing this information in reports to corporate management. The Project Quality Assurance Manager's report of STPEGS includes review and evaluation of reports of HL&P and NRC audits and reviews.
000lV/000lv
' 2.9 - PREOPERATIONAL TESTING AND STARTUP The quality program described in this. report covers design, procurement, and construction activities. HL&P Lis responsible for the quality program during tha preoperation testing and startup phase. As defined in the scope of work for STPEGS, Bechtel, in conjunction with HL&P, performs advance planning for control of managerial and technical interfaces between Bechtel, HL&P, Westinghouse Electric Corp. (NSSS Supplier), and other contractors during prcoperational testing and startup.
t i
000lV/000lV . _ . _ _- .. .-,_ _,,_ __ _ , - . _
. . . . . _ _ . ,_ _ - . - . , . . - . = -_ .-.
SECTION 3 DESIGN CONTROL Engineering department policies, standards, design guides, procedures, and instructions are employed for control of engineering design work to meet technical and regulatory requirements. These controls identify responsibilities and provide procedures to assure that the design requirements are correctly translated into the final design. The controls also provide for preparation of appropriate documentation to permit review of the process used and of the results obtained. The controls provide for the identification and specification of appropriate quality standards and for control of changes and design interfaces.
Design criteria are assembled by the project during the initial stages of design. These criteria include the criteria contained in safety analysis reports and other STPEGS requirements. The design criteria are maintained current and serve as a basis for preparation of the final design.
The design control program incorporates measures for identification and
', control of design interfaces among the various engineering disciplines on the project, between the project and technical support groups within Bechtel, and of such external interfaces as Westinghouse Electric Corp. (the nuclear steam supply system supplier), other equipment suppliers, contractors performing design work, and HL&P. These measures include: (a) identification of technical responsibilities of the various design groups and provisions for
- coordination of design documents among them, (b) description of responsibilities of and provisions for coordination with other design and engineering support groups within Bechtel, and (c) definition of interfaces and control of consnunication with organizations external to Bechtel.
Essentially all engineering documents are prepared by project personnel and
, include drawings, specifications, design analyses, system descriptions, and technical reports. They'are verified or checked in accordance with Engineering Department Procedures. Project Group Supervisors (Figure 9) are responsible for all engineering work performed within their discipline and for approval of engineering documents prepared within their groups. Procedures and instructions for verification and checking of drawings, calculations, and specifications are included in the procedures pverning the preparation of these documents or in separate procedures or instructions. These procedures identify the positions responsible for verification or checking and require that design errors are identified and followed up through correction.
Verifiers and checkers on the project are required to verify the incorporation of required corrections. Documents cannot be released without verification or checking.
i When design verification or checking is accomplished by an individual, it is performed by a person other than the originator or the immediate supervisor of the originator, who has adequate qualifications to have originated the work.
If, in an exceptional circumstance, the originator's immediate supervisor is the only technically qualified individual available, the design verification or checking will be conducted by the supervisor with the following provisions:
- a. The other requirements of ANSI N45.2.ll-1974, as endorsed by Regulatory Guide 1.64, Rev. 2, 6/76, as interpreted by the positions contained in Appendix A of this document, will be met.
3 000lV/000lv i 4
- b. The justification will be individually documented and approved by the next level of supervision,
- c. Quality Assurance audits will include review of the frequency and effectiveness of the use of the immediate supervisor to assure that this provision is used only in exceptional circumstances.
Design work, including verification or checking, of specialist external to the project, such as M&QS, Geotechnical, Hydraulics, and Stress is performed in accordance with project procedures or specialist group procedures meeting the requirements of this document. Such work must be reviewed and accepted by responsible project personnel for applicability to STPEGS.
Key design documents for systems and structures important to safety are subject to design verification, which may be accomplished by:
- a. Critical design reviews, either individual or interdisciplinary
- b. Alternate calculations, or
- c. Qualification testing Design verification is performed for the following key documents: system descriptions, flow diagrams, piping and instrument diagrams, control logic diagrams, electrical single-line diagrams, structural systems for major facilities, site arrangement, and equipment location drawings.
Specifications, calculations, and computer programs in support of the key documents are verified. Documentation of the design verification is provided by a design verification report signed by the appropriate individual.
When design verification is accomplished by an interdisciplinary design review, the review team will be composed of individuals knowledgeable of the type of system of structure and the requirements thereof. They may or may not have participated directly in the design of that particular system or structure. An individual who has participated directly in the design shall not be responsible for the independent design verification of this discipline.
The above description of design verification of key design documents satisfies the requirements specified by ANSI N45.2.ll-1974, as endorsed by Regulatory Guide 1.64, Rev. 2, 6/76, as interpreted by the positions contained in Appendix A of this document.
Design documents other than key design documents, identified above, shall be checked for technical correctness and conformance to design input requirements.
Engineering Department Procedures establish the extent of checking, the duties of the checker, and the extent of his responsibility for which he attests with his signature or initials. The signature or initials of the checker and date affixed on the design document in accordance with the Engineering Department Procedure satisfies the requirements specified by ANSI N45.2.ll-1974, as endorsed by Regulatory Guide 1.64, Rev. 2, 6/76, as interpreted by the positions contained in Appendix A of this document. Traceability of charac-teristic signatures and initials to the individual will be provided.
000lV/000lV SOUTH TEXAS PROJECT BECHTE W 5 R POWE R MAN AGEMENT ORGANIZATION "8M?N viCE PRE 5aDENT PRE 51 DENY AND ANO MANAGE R EXECUTIVE 5PON50R I
HOUSTON PROGRAM UGHTING S POWE R MANAGE R I i.._._._._._._._._._._._._._._._._._._._._.,
[______ .
i*
i ADMsNs5TRATION & TECHNICAL l PROJE CT !
DaRECTON MANAGER
~~~~ l PROJECT DIRECTION l h PROGRAM DIRECTION l
- PROJE CT COORDINATON I DEPUTY PROJECT MANAGE R h.
1 I
-" i r , ................... ;
p _ _ _ _- ,i I I I : .
FIELD I PROJiCT PROJECT PPOJECT ASSISTANT PROJECT PROJE CT l OPE RATING 5E RVICES STARTUP COST tSCHEDULE MANAGER-PROJECT QUAUTY A550RANCE CONST RUCT ON MANAGE R MANAGE R MANAGE R SUPE RVISOR SUPPORT 5ERVICES MANAGER l I
l B r---'--- , r-------
I T--------
9 l
I n i PRO,E CT PROJECT PROJECT PROJECT PROJE CT CONTRACT 5 INFORMATON EFFECTIVENES$ MANAGE R PROCURE ME NT E NGINE E RING MANAGE R SE RVIC ES MANAGE R PROGRAM MANAGER MANAGE R -
I I I I I 1 I PROJEC7 PROJECT ENGINE ER PROJECT PROJECT PROJECT ENGINEE A PROJECT E NGINE E R PROJECT E NGINEER PROJECT ENGINE ERING G OTECHWAL ENG MERi% RECORDS ADMINIHRATON NUCLE AR t LIC E N5NG PHY5(AL SYSTE MS MANAGER 51TE SE RVICE S MANAGE R COMPL E TION MANAGE R MANAGE R STP - BAPD PART B FIGURE 7
SOUTH TEXAS PROJECT QUALITY ASSURANCE ORGAHlZATION This chart is intended to reflect reporting relationships and not
- PROJECT Ee*nforihf p$'ti s. Ywok'lity, ig QUALITY ASSURANCE relationships MANAGER I
I I I DESIGN OFFICE SITE SITE PROJECT QUALITY PROJECT QUALITY ASSURANCE ENGINEER PROJECT QUALITY ASSURANCE ENGINEER CONTROL ENGINEER I I I QUALITY ASSURANCE QUALITY ASSURANCE QUALITY CONTROL ENGINEERS ENGINEERS ENGINEERS STP - QAPD PART B FIGURE 8 oAG44
SOUTH TEXAS PROJECT ENGINEERING ORGANIZATION PROJE CT ENGINE E RING MANAGE R PROJECT E NGINE ERING MANAGE R StTE GEOTECHNICAL I SE RVICES I l MANAGER SITE COMPLE TION E NGtNE E RING E NGINE E RING E E E E E PROJECT ' #
PROJE CT PROJECT E NGINEE R p, p,gg E NGINE E R E NGINE E R ENGINEERING PHYSICAL NUCLE Arl/ LICE NSING COMPLE TON Od SY TEMS I I I I I I I I I I I I I I I ENGINEE RING ENGINEE RING ENGINEER;NG ENGINE ERING ENGINEERING R U 5UPE V 50R PROJECT E NGINEE RING IO '"O O ' O I" GROUP SUPE RVISOR GROUP $UPE RVISOR GROUP SUPE RVtSOR GROUP SUPE RVISOR GPOUP SUPE RVISOR QUAUTY GROUP SUPE RVtSOR GROUP SUPE RVISOR GROUP SUPE RV!5OR CiviU5TRUCTURAL ARCHITECTURAL P55G NUCLE AR ENGINE E R CONTROL S y E /Q MECHANICAL CONTROLS ELECTRICAL STP - QAPD
_, PARTB FIGURE 9
1 SOUTH TEXAS PROJECT CONSTRUCTION MANAGEMENT FIELD PROJECT QUALITY CONSTRUCTION ASSURANCE MANAGER MANAGER PROJECT ENGINEE RING ,,,,,,,,,,,,,,,,,,,,,,,,,
MANAGE R - SITE I
l - i i i PROJECT PROJECT PROJECT l COST SCHEDULING SERVICES FIELD
^^
"I
^
, SUPERVISOR SUPERINTENDENT ENGINEER l
i i i ,
i i i i i i MATERIAL PROJECT PROJECT INFORMATION TECHNICAL FINANCE AND EMPLOYEE CONTROL ADMINISTRATION SAFETY SERVICES SERVICES ACCOUNTING CONTRACTS RELATIONS MANAGER MANAGER SUPERVISOR SUPERVISOR SUPE RVISOR MANAGER SUPERVISOR MANAGER i..........
I LEGEND:
PPOJECT FIELD MATE RIAL - Administration & TeChanical MANAGER MANAGER """ *** == PrCject Coordination STP - QAPD i = * * * * = Project Direction PARTB
- = - Technical Direction FIGURE 10 oncs,
. . . . - . ~ . .
l SOUTH TEXAS PROJECT i
PROCUREMENT ORGANIZATION PROJECT COORDINATION PRWEG
==== PROJECT DIRECT 60N PROCUREMENT TECH NICAL t.ND MANAGER
- ADMINISTRATIVE DIRECTION L
FIELD PROCUREMENT = ---=
i MANAGER l I l A5515 TANT PROJECT PURCHASE ORDER PROCUREMENT PROCUREMENT CONTRACTS ADMINISTRATION ADMINISTRATOR SUPERVISOR MANAGER SUPERVISOR ga ea e e e e e e e e a e
- I SUPPLIER EQUIPMENT QUALITY QUAllFICATION DATA ENTRY SUPERVISOR COORDINATOR
~
! I STP - QAPD VETIP PARTB FIGURE 11 ORG40
)
l
SOUTH TEXAS PROJECT QUAUTY PROGRAM DOCUMENTS 10 CFR SO APPENDIX 8
. I ASME ' BQ-TOP-1 B&PV ' ^ ' ^ O^
CODE OLIO F NUCLEAR QA PROGRAM h ^ ^
9 P 1 r M&QS POUCY PROCUREMENT ASME AND PROCEOURE MANUALS QUALITY POLICITS PROCEDURES GUID5 DEPT. MANUAL 4
PROCFDURES QUALITY ASSURANCE ENGINE E RING QUAllTY CONTROL COf4STRUCTION PROCUREMENT e
1 P 1 r 1 P 1 P PROJECT PROJECT PROGRAM L REFERENCE, STP - QAPD REQUIREMENTS F AMEND AND PART B CLIE NT INPUT SUPPLEMENT ABOVE FIGURE 12
l BECHTEL QUAUTY PROGRAM DOCUMENTS REVIEW OF QA POLICY ORIGINATING AND PROGRAM AUTHORIZING DOCUME NT AUTHORITY RE OU:RE MENTS APPROVAL CONTE NTS
- BECHTEL QUALITY MANAGER C&S/R&E BWPC'* MANAGER OF PRESIDENT AND POLICIES AND PROCEDURES ASSURANCE MANUAL- QUAUTY ASURANCE APPROPIATE FOR OVERALL BECHTEL ASME NUCLEAR AUTHORIZED CODE PROGRAM APPLICABLE TO COMPONENTS (BQAM- INSPECTION AGENCY ASME WORK ASME 111)
QUALITY ASSURANCE PROJECT QUAUTY N/A CORPORATE QUALITY PROCEDURES FOR PROCEDURES ASSURANCE MANAGER ASSURANCE MANAGER CONDUCTING PROJECT QUAUTYASSURANCE ACTIVITIES ENGINEERING DESIGNATED BWPC MANAGER OF MANAGER DIVISION DEFINITON OF DEPARTMENT INDIVIDUALS QUALITY ASSURANCE E NGINEERING* *
- RESPONSIBILITIES AND PROCEDURES AND PROCEDURES FOR DESIGN, INSTRUCTONS DESIGN REVIEW, AND DOCUMENT CONTROL IN THE ENGINEERING DEPARTMENTS PROCURFMENT PROCUREMENT BWPC*
- COGNIZANT PROCEDURES FOROFFICE AND MANUALS (QUALITY PROCUREMENT FIELD PROCUREMENT PPOGRAM RELATED) MANAGER 5 NECESSARY TO FOLLOW QUALITY POLICY
' PROCUREMENT MANAGER BWPC*
- MANAGER PROCUREMENT SUPPLIER SUPPLIER QUAUTY PROCUREMENT PROCUREMENT QUALITY PROCEDURES MANUAL SUPPUER QUALITY SUPPUER QUAUTY M&QS PROCEDURE AND POUCY GUIDES MANAGER M&QS 9WPC*
- MANAGER M&QS POLICIES AND PROCEDURES (QUAUTY PROGRAM FOR PERFORMING M&QS RELATED) FUNCTONS TECHNICAL SUPPORT TECHNICAL SERVICES BWPC MANAGER OF MANAGER TECHNICAL RESPONSIBILITIES AND PROCEDURES MANUAL QUAUTY ASSURNACE SERVICES PROCEDURES FOR PROJECT SUPPORT GROUPS PROJECT MANUALS COGNIZANT PROJECT PQAE COGNIZANT NOTE 2 PROCEDURES (QUAUTY TE AM MEMBER MANAGERS PROGRAM RELATED)
STANDARD QUALTlY HL&P QUAUTY PQAC/QAS COGNIZANT QA NOTE 2 ASSURANCE ASSURANCE MANAGER PROCEDURES STANDARD SITE COGNIZANT PROJECT PQAE/QAS COGNIZANT PROCEDURES TO SUPPORT SITE PROCEDURE TEAM MEMBER ENGINEERING, ACTIVITIES INCLUDING CONSTRUCTION, AND CONSTRUCTION, ENGINEERING, QA MANAGEMENT INSPECTON AND ADMINISTRATION AVAILABLE ON REQUEST TO APPROPIATE REGULATORY NOTES: 1 REVISIONS TO THESE DOCUMENTS REQUIRE THE SAME AGENCIES REVIEW AND APPROVAL AS THE ORIGINAL
- 2 THESE ARE PROVISIONS FOR PROJECT UNIQUE INCLUDES REVIEW BY BWPCQUALTlY ASSURANCE MANAGERS MODIFICATIONS TO THE ABOVE DOCUMENTS TO
- DEUNEATE SPECIFIC PROJECT REQUIREMENTS BUT NOT HOUSTON OFFICE EDPS ARE REVIEWED AND APPROVED BY THE STPEGS PROJECT QUALTlY ASSURANCE MANAGER AND DEPART FROM THE OUALITY ASSURANCE PROGRAM l STPEGS PROJECT ENGINEERING MANAGER THESE EDP5 5 HALL DESCRIPTION (OAPD) REV!EW AND ADPROVAL SE SENT TO LOS ANGELES ENGINE ERING STAFF FOR POST AUTHORITY FOR SUCH MOD F CATIONS ARE DEFINED APPROVM PEVIEW WITHIN THE QAPD PART B TABLEl
4 PART C EBASCO QUALITY ASSURANCE PROGRAM DESCRIPTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION REVISION 15 September 26, 1986 Date t
, - . - - . _.- ... _ - _ --_ . - _ . - - - - . . . _ _ _ _ _ _ - ~ _ _ - - _ . _ _
_..._m -- _ . . . _ --. - - - - - - - - - -
EBASCO QUALITY ASSURANCE PROGRAM DESCRIPTION .
PART C too O'*:0 coa HOUSTON LIGHTING & POWER COMPANY ELECTRK: GENERATING STATION UNITS 1 & 2 50UfN
ESASCO SERVICES INCOMPORATED O '
Two World Trade Center. New York. N N.10048 FOREWORD This Quality Assurance Program Description - Part C reflects official Ebusco policy and has been prepared to also reflect the requirements of the United States Nuclear Regulatory Commission document 10 CFR 50, Appendix B (18 Quality Assurance Criteria), and American National Standards Institute document N45.2, entitled" Quality Assurance Program Requirements for Nuclear Power Plants".
Enclosure " Statement of Authority" dated July 1, 1986 confirms the authority for the establishment of a Quality Assurance Program and a Quality Assurance Program Manual. ,
The enclosure letter of R H Vollmer to L F C Reichle dated May 12, 1975 is the NRC's acceptance of Ebasco's Quality Assurance Program Manual (Ebasco Report ETR-1001, Revision 0, March 14, 1975).
The enclosure letter of U Potapovs to B E Tenzer dated May 4, 1984 is the NRC's latest acceptance of Ebasco's Quality Assurance Program Manual, Revision 12, dated June 1984 which is the basis of this Quality Assurance Program Description for the South Texas Project.
The primary responsibility for overall implementation and administration of the Ebasco Quality Program rests with the Vice President Corporate Quality Programs as delegated to him by the Senior Chairman, Chairman and President of Ebasco Services Inc. The Director Quality Assurance is assigned the responsibility and authority to enforce Ebasco Quality Program requirements and has the unqualified support of corporate management. His decisions may not be overriden by personnel in any division or department, except with the written consent of the Vice President Corporate Quality Programs.
The Director Quality Assurance shall staff this Project to the extent necessary to perform quality assurance tasks directly and audit departments other than his own in their performance of tacks related to quality assurance. The Director Quality Assurance has the authority to require immediate correction of any non-conforming activity or condition to comply with Ebasco Quality Program requirements, or if necessary, to stop work until S.ultable corrective action has been taken or a satisfactory resolution reached.
h/
B R Mazo g Vice PresidenrCorporate Quality Programs July 1, 1986
, --___-- a _ . _ - _ _ _ _ _ _ _ _ _ _ _ - _ . .__ --
EBASCO SERVICES INCORPORATED EB E O _
Two World Trace Centet New York.N Y 10048 STATEMENT OF AUTHORITY The Management of Ebasco Services Incorporated recognizes the necessity for a comprehensive Quality Program for Nuclear Power Plants. Ebasco Company Procedure No. N-21 establishes the basic organization, assigns authorities and responsibility for implementing the Quality Program, and establishes the requirement for a corporate Quality Assurance Manual. Accordingly, this Manual represents Ebasco Quality Program policy. In this respect, it is to be used as a standard by personnel in all Ebasco organizational units.
The primary responsibility for overall implementation and administration of the Ebasco Quality Assurance Program rests with the Vice President Corporate Quality Programs as delegated to him by the Senior Chairman, Chaiman and President. The Quality Program Comittee chaired by the Vice President Corporate Quality Programs will establish Corporate Quality Program policy. This permanent Comittee will be comprised of personnel from the various applicable operational divisions.
th kl$
l .' Scarola
'A. R.J. Christesen R.F. Albosta l' enior Chaiman Chaiman President l July 1, 1986
\
l l
UestTE3 STATES NUCLEAR REGULATORY COMMISSION wasWNGToN. D. c. 20555 NAY I 2 1975 Mr. Leonard F. C. Reichle Vice President Ebasco Services Incorporated Two Rector Street New York, New York 10006
Dear Mr. Reichle:
We have reviewed and evaluated the Dasco Services Incorporated (EBASCO)
Nuclear Quality Assurance Program Manual (Ebasco Report ETR-1001. Revision 0, March 14, 1975). We find that it describes an acceptable Quality Assurance Program for the design, procurement, and construction activities which are within the Ebasco scope of work for nuclear power plants.
For the Ebasco Quality Assurance Program, applicants need only reference this Topical Report in Section 17 of license applications. We do not intend to repeat our review of this Topical Report when it is referenced in an applica tio n.
Should regulatory criteria or regulations change such that our conclusions about this Topical Report are invalidated, we will notify you. You will be given the opportunity to revise and resubmit it should you so desire.
Please include a copy of this letter and our evaluation in each of the reports and resubmit 70 copies to the NRC.
Sincerely, Richard H. Vollmer, Chief Quality Assurance Branch Division of Reactor Licensing
Enclosure:
NRC Topical Report Evaluation of Ebasco Report LTR-1001,Rev. O, 3/14/75 fosuteo,*g,
, z
\ ,,,s .,,, /
TOPICAL REPORT EVALUATION Report Number: ETR-1001, Rev. O, Nonproprietary Report
Title:
Ebasco Nuclear Quality Assurance Program Report Date: March 14, 1975 0.iginating Organization: Ebasco Services Incorporated Reviewed By: Quality Assurance Branch
SUMMARY
OF TOPICAL REPORT Topical Report ETR-1001, Rev. O describes the Quality Assurance (QA)
Program which the Ebasco Services Incorporated (Ebasco) applies to those design, procurement, and construction activities involving safety related structures, systems, and components of nuclear power plants within the Ebasco scope of work. ETR-1001, Rev. O commits Ebasco to comply with the requirements of Appendix B to 10 CFR Part 50 and to follow the QA guidance provided by the NRC in:
- 1. " Guidance on Quality Assurance Requirements During Design and Procurement Phase of Nuclear Power Plants," WASH 1283, Rev.1 May 24,1974, and
, 2. " Guidance on Quality Assurance Requirements During the Construction
] Phase of Nuclear Power Plants," WASH 1309, May 10,1974.
Ebasco has provided for our evaluation a detailed organizational description of those individuals and groups involved in carrying out activities required by the QA Program and a delineation of duties, responsibilities, and authority of those organizational alaments involved in the QA Program. ETR-1001, Rev. O contains a description of the measures used to carry out the Ebasco QA Program activities and describes how applicable requirements of Appendix B will be satisfied by the administration and implementation of these measures.
SUWARY OF REGULATORY EVALUATION We have evaluated the QA Program and the organizations responsible for QA functions as described in ETR-1001, Rev. O. We find that QA policy and direction originate at an acceptably high management level and are effectively communicated to other parts of the organization.
Those performing QA functions have responsibility and authority commensurate
( with their duties in implementing the QA Program. We also find that measures have been establishec, to be implemented by written procedures and instructions, which address each of the criteria of Appendix B and demonstrate conformance with each criterion.
Based on our review and evaluation of ETR-1001, Rev. O we conclude that:
- 1. The organizations and persons performing QA functions within Ebasco have the required independence and authority to ef f ectively carry out the QA Program without reservation or undue influence from those directly
. , _ , . . _ . . - . . _ . _ . _ . - - _ . - - . _ . - , _ . _ . ~ , . , _ _ . . , , _ _ _ , . - - - _ , _ - - - - - , - - _ _ , , - _ _ _ _ . _ _ , , , - .-. . - _ _ . .
responsible for costs and schedules, and
- 2. The Dasco QA Program contains the necessary requirements, procedures, and controls to demonstrate that quality-related activities will be conducted in accordance with the requirements of Appendix 3 to 10 CFR Part 50.
REGULATORY POSITION It is the staff's position that the Ebasco Nuclear Quality Assurance Program Manual (Dasco Report ETR-1001, Revision 0, March 14,1975) is acceptable for use in the design, procurement, and construction of nuclear power plants. The Topical Report can be referenced by report number in Section 17 of future Safety Analysis Reports. ,
')
t
- I l
l e
e
- - - - . - - - - - - - . - , ~ , . . - _ - - . . - - - - - - - - - - - - - - - , . ..,,-...-,n-- _ . , _ - . . , - - . . , - , , , - - , , - _ _ _ - . - - - , - - - - - - . - - - - . . - - , - , - - - . . , - . - -,
s uNoTED status 7 ** "'%
p NUCLEAR CEOULATCRY COMMISSIEN
$ REGION IV sit RYAN PLAZA DRIVE. SulTE ISD ARLINGTON. TEXAS 1W11 EAY 04 BB4 i
Docket No. 99900505 i
l -
, Mr. B. E. Tenzer, Vice President Corporate Quality Programs ,
Ebasco Services Incorporated
- Two World Trade Center New York, NY 10048
Dear Mr. Tenzer:
Subject:
NRC Acceptance of Revised Ebasco Quality Assurance Topical Report We have completed our review of Revision 12 to Ebasco Topical Report i ETR-1001 submitted though your letters of May 27, July 13 August 5 September 23, October 7. October 31, and November 9,1983, and February 15, 1984. Revision 12 updates the topical report to reflect the current Ebasco Quality Assurance Program.
Based on our evaluation of the proposed changes described in Revision 12, i we find that the revised topic.a1 report continues to meet the criteria I of Appendix B to 10 CFR Part 50 and is, therefore, acceptable. Should regulatory criteria or regulations change such that our conclusions about i
this topical report are invalidated, we will notify you. You will be given the opportunity to revise and resubmit it should you so desire.
Progrannatic changes by Ebasco to this topical report are to be submitted to NRC for review prior to implementation. Organizational changes are to be submitted no later than 30 days after announcement.
l To use this topical report in future license applications, applicants need only reference this topical in Section 17 of the SAR. Should it be referwnced in a SAR for a new nuclear power project, the basis of our i evaluation will be the acceptance criteria in the latest revision to the l Standard Review Plan (SRP) Section 17.1 (currently Revision 2). Appropriate j changes may, therefore, be necessary.
! Please replace our letter of May 17, 1982, with a copy of this letter, renumber ETR-1001 as Revision 12 and forward eight copies to the Document l Control Desk and one copy to the Vendor Program Branch, Division of Quality Assurance, Safeguards, and Inspection Programs U.S. Nuclear Regulatory Comission Washington, D.C. 20555.
l 1
Mr. B. E. Tenzer ;
Your submittal should point out the changes by use of a black bar in the margin where a change is made, and the revision number shculd be adjacent to the bar.
Should you have any questions regarding our review, or if we can provide assistance please contact this office.
Sincerely, f
' & 'sh" 'o Uldis Potapovs. Chief i Vendor Program Branch Division of Quality Assurance, Safeguards, and Inspection Programs 4
f I
l l
i
enun e . a v e. , ,2,>... linuees.ve. ee asiew nu.a. r w 's t n Y
r . ,
s tot-a HsTpl448 I
PAGE1 of 2 HOU$ TON UGHTING AN'D POWER COMPANY SECTION
- 8- . . SOUTH TEXAS PROJECT El.ECTRIC GENERATING $TATION UNITS 1 & 2 teAsco SERvicts '
QUALITY AS$URANCE PROGRAM DESCRIPTION - PART C meopea A vro , Revision 15 TABLE OF CONTENTS Date 8-15-86 PART I_ - General Section Title Rev No. __Date QA-I-1 Quality Assurance Program 10 8/15/86 lR15 QA-I-2 Organization and Responsibilities 10 8/15/86 lR15 QA-I-3 Personnel Indoctrination and Training Program in Quality Assurance 5 9/24/84 QA-I-4 Deleted (not applicable)
QA-I-5 Deleted (not applicable)
QA-I-6 Quality Assurance Records 6 7/26/85 PART II - Engineering Offices Deleted (not applicable)
PART III - Cons.truction__S_ite_
Section ,
Title QA-III-I Instructions, Procedures, and Drawings 6 7/26/85 QA-liI-2 Docu=ent Control 9 3/28/86 I Q A-I II-3 Deleted (not applicable) l QA-III-4 Deleted (not applicable)
QA-III-5 Deleted (not applicable)
QA-III-6 Nonconformances 7 8/15/86 lR15 l
QA-III-7 Corrective Action 5 7/26/85 l
l l
I l
0598d Co right c 1986, 1985, 1984 Ebasco Services Incorporated
2 sios.2, ism:44s paog - 2 oF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO $ER ICES
, p QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Revision 15 TABLE OF CONTENTS Date 8-15-86 PART III - Construction Site (Cont'd)
Section Title Rev No. Date QA-III-8 Control of Special Processes 5 7/5/84 QA-III-9 Quality Assurance Audits 8 7/26/85 QA-III-10 Identification and Control of Items 3 7/5/84 QA-III-11 Inspection 5 7/5/84 QA-III-12 Test Control 5 7/26/85 QA-III-13 control of Measuring and Testing Equipment 5 11/13/84 QA-III-14 Control of Receiving, Handling, and Storage 6 7/26/85 QA-III-15 Inspection, Test, and Operating Status 4 7/26/85 Appendix I Terms and Definitions 3 7/5/84 Appendix II Ebasco Exceptions to US Nuclear Regulatory Guides and ANSI Standards Indicated in Section QA-I-1 6 7/26/85 l
i 0593d Copyright c 1986, 1985, 1984 Ebasco Services Incorporated i
i
- . _ _ _ . . . ~ , _ . . _ . , _ . . _ _ ,____. ..._. ._ _ _.-_.-_,...~ - - , - , _ . . . _ _ _ . - _ , _ . _ _ _ _ _ . _ , , , , _ _ . - _ - _ . . . , - -
s:0s 2tt57D14-e5 / pang 1 or N HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT
, ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsCo SEWICES
?,UALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-y_1 mcompoaarco QUALITY ASSURANCE PROGRAM 1.0 SCOPE The purpose of this Section is to describe the Quality Assurance Program of Ebasco Services Incorporated and its applicability to safety-related activities and services performed by Ebasco in the construction of the South Texas Project. This program has been designed to meet the applicable requirements of the United States Nuclear Regulatory Commission 18 Quality Assurance Criteria of 10 CFR 50, Appendix B. It has also been designed to meet the regulatory position of the following USNRC Regulatory Guides and ANSI 1 Standards, with exceptions and clarifications as stated in Appendix II of this Manual:
Standard Title ANSI N45.2-1971 Quality Assurance Program R.G. 1.28 (Rev. O, 6/72) Requirements for Nuclear Power Plants ANSI N45.2.1-1973 Cleaning of Fluid Systems and ,
R.G.1.37 (Rev. O, 3/73) Associated Components During (See Appendix'II Notes 3 through 5) Construction Phase of Nuclear Power Plants ANSI N45.2.2-1972 Packaging, Shipping, Receiving, R.G. 1.38 (Rev. O, 3/73) Storage, and Handling of Items (See Appendix II Notes 6 through 11) for Nuclear Power Plants (During the Construction Phase)
ANSI N45.2.3-1973 Housekeeping During the R.G. 1.39 (Rev. O, 3/73) Construction Phase of Nuclear l
(See Appendix II Noten 12 and 13) Power Plants ANSI N45.2.4-1972 Installation, Innipection, and l R.G. 1.30 (Rev. O, 8/72) Testing Requirements for (See Appendix II Notes 14 and 15) Instrumentation and Electric Equipment During the Construction of Nuclear Power Generating Stations ANSI N45.2.5-1974 Supplementary Quality Assursace (See Appendix II Notes 1 and 2) Requirements for Installation, Inspection, and Testing of Structural Concrete and Structural Steel During the Construction Phase of Nuclear Power Plants 0598d
2 ,, 20 sios austroc< , cog HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXA5 PROJECT ELECTRIC GENERATING STATION UNITS I & 2 raAsCO $ERVICES QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C OA-I-1
'~
lNCORPORATED QUALITY ASSURANCE PROGRAM Standard Title ANSI N45.2.6-1973 Qualifications of Inspection, R.G. 1.58 (Rev. O, 8/73) Examination, and Testing As Modified by Positions C.5, C.6, Personnel for the Construction C.7, C.8, and C.10 of Rev. 1 Phase of Nuclear Power Plants i (See Appendix II Note 24) l l ANSI N45.2.8-1975 Supplementary Quality Assurance R.G. 1.116 (6/76) Requirements for Installation, Inspection, and Testing of (See Appendix II Notes 16 through 18)
Mechanical Equipment and Systems i
for the Construction Phase of
[ Nuclear Power Plants
, ANSI N45.2.9-1974 Requirements for Collection, Storage, R.G. 1.88 (Rev. 2, 10/76) and Maintenance of Quality Assurance (See Appendix II Notes 19 through 21) Records for Nuclear Power Plants ANSI N45.2.10-1973 Quality Assurance Terms and R.G. 1.74 (Rev. O, 2/74) Definitions I
. ANSI N45.2.12-1977 Requirements for Auditing of Quality i R.G. 1.144 (Rev. 1, 9/80) Assurance Programs for Nuclear Power (See Appendix II Notes 12 and 23) Planta Qualification of Quality Assurance ANSI N45.2.23-1978 R.G. 1.146 (Rev. O, 8/80) Program Audit Personnel for Nuclear Power Plants l Table I-1.1 provides a matrix which shows the sections of the Ebasco Nuclear l Quality Assurance Program Manual that correspond to the requirements of 10 CFR 50, Appendix B and USNRC Regulatory Guide 1.28, Rev. O. The Ebasco l
( Quality Assurance Program is comprised of: The Ebasco Nuclear Quality j
Assurance Program Manual, written corporate policies, procedures, departmental l
instructions, and other site-specific documents related to quality.
Table I-1.2 piavides a matrix of the principal implementing procedures as they j relate to 10 CFR 50, Appendix B criteria. Table I-1.3 is a listing of these procedures by title. The principal implementing procedures are not necessarily limited to those indicated in the matrix. Implementing procedures will be issued for South Texas Project use as the need for specific procedures arises due to changes in scope of Ebasco safety-related activities.
L l
i j 0598d i
sios-austrus ecos 3 e, 20 1 HOUSTON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXA5 PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconeon Arso gg_y_y QUALITY ASSURANCE PROGRAM 2
- The Ebasco Nuclear Quality Assurance Program Manual has been designed to meet the requirements of 10 CFR 50.34(7) for a quality assurance program description. It will be incorporated into applicable portions of Houston
), Lighting & Power Company safety analysis reports in whole or by reference as
- provided by 10 CFR 50.32.
The Ebasco Quality Program for the South Texas Project is in force at the
{ Ebasco home office and Construction operations. The Ebasco home office is an l
organized unit where project-related support functions are performed.
Construction operations encompass those activities related to the construction of the nuclear power station. Ebasco's responsibility for 1 implementing the Ebasco Quality Program shall begin at the commencement of activities affecting quality and shall end with the turnover of completed systems to the Client or his designee.
i Definitions pertaining to the Ebasco Quality Program are listed in Appendix I
! of this Manual.
2.0 QUALITY ASSURANCE ORGANIZATION The Ebasco Quality Assurance organization is responsible for establishing new, and updating existing, quality assurance requirements. In addition, this organization is responsible to administer and enforce the implementation of the Ebasco Quality Assurance Manual.
3.0 QUALITY PROGRAM COMMITTEE
! 3.1 The Ebasco Quality Program Committee is responsible for and has
! authority to make and approve procedures for any changes to this Manual. #
! This committee is comprised of personnel from the various applicable lR15 I
operational divisions within Ebasco Services Inc. These people are I appointed by officers of Ebasco Services Inc. from the respective l organizational divisions.
The Vice President Corporate Quality Programs is designated by the Senior l Chairman, Chairman and President of Ebasco Services Inc. as the Chairman lR15 ,
of the Quality Program Committee. A member of the Quality Assurance organization shall be designated by the Chairman as Quality Program Coordinator, who shall function as the Quality Program Committee's secretary and be a member of the Committee.
The Director Quality Assurance is designated by the Vice President Corporate Quality Programs as a perasnent representative of Corporate Quality Programs on the Quality Program Committee.
0598d
1 pace 4 or .20 l .....a uswacs HOUSTON LIGHTING AND POWER COMPANY SECTION i SOUTH TEXAS PROJECT i ELECTRIC GENERATING STATION UNITS 1 & 2 EaASCO SENCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 mcon oa Atro 4
QUALITY ASSURANCE PROGRAM I
i
- The Committee shall be responsible for and shall have authority to make any changes to the policies and procedures of the Ebasco Quality Program. All changes or revisions to the Ebasco Nuclear Quality Arsurance Program Manual shall be processed through the Quality Program Committee by the Quality Program Coordinator.
! 3.2 Ebasco Quality Program Procedures document the various significant activities of the Quality Program that are the direct responsibility of the Quality Program Committee or the Quality Program Coordinator. These procedures include but are not limited to the following:
I 4
3.2.1 Quality Program Procedure No. 4 entitled, QUALITY PROGRAM COORDINATOR - DESCRIPTION OF POSITION, DUTIES, RESPONSIBILITIES.
3.2.2 Quality Program Procedure No. 5 entitled, DEVIATING FROM THE
- CORPORATE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL. This provides for control of such deviations by requiring execution of an
- authorization form involving approval of specified authorities to i assure, among other things, that safety and/or quality will not be j sacrificed.
I i 3.2.3 Quality Program Procedure No. 6 entitled, ASSIGNMENT, i DISTRIBUTION AND CONTROL OF THE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL.
l I
3.2.4 Quality Program Procedure No. 7 entitled REVISIONS TO THE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL.
4.0 GENERAL j 4.1 Section QA-I-2 describes the organizational structure, functional (R15 l
responsibilities, levels of authority, and lines of internal and external communication for management, direction, and execution of the Ebasco Quality Assurance Program. By the Statement of Authority at the front of this Manual, Ebasco's Senior Chairman, Chairman and President mandates lR15 l
the use of this Manual and its supporting documents which make up the
- Ebasco Quality Program for the South Texas Project.
! 4.2 It shall be the responsibility of each Ebasco department and the individual personnel of that department to adhere to the requirements of this Program. Section QA-III-1 requires these departments to develop and IR15 control Ebasco instructions, procedures, and/or drawings which describe the manner in which activities affecting quality are to be accomplished.
3 4
4 i
0598d 1
sios.rusrecas pace 5 or 20 HOU$ TON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QUALITY ASSURANCE PROGRAM When documented evidence is required for the satisfactory performance of these activities, checklists, forms, and/or other appropriate means shall provide this evidence. The documents which contain the procedures listed in Table I-1.3 and are used to implement the Ebasco QA Program are:
4.2.1 Quality Assurance Procedures Manual for South Texas Project 4.2.2 Standard Quality Assurance Procedures for the South Texas Project 4.2.3 Quality Program Procedures Manual 4.2.4 Company Procedures Manual - Nuclear 4.2.5 Quality Control Procedures Manual for South Texas Project 4.2.6 Site Quality Assurance Instructions Manual for South Texas Project 4.2.7 Construction Procedures Manual - Administrative Site Procedures for South Texas Project 4.2.8 Construction Procedures Manual - Construction Site Procedures for South Texas Project 4.2.9 Construction Procedures Manual - Construction Maintenance Instructions for South Texas Project 4.2.10 Standard Site Procedures for the South Texas Project The above-listed manuals may also contain departmental working procedures which do not describe activities affecting quality and therefore are not governed by the requirements of this Manual. Furthermore, certain implementing procedures may require changes in order to suit unique client requirements; such procedures for the South Texas Project will be included in a project manual of procedures and/or a site manual. In this case, the changed procedure shall be designated a Project Procedure.
These procedures will be subject to controls similar to those applicable to the original documents.
4.3 In addition to the requirements of Section QA-III-1 and Paragraph R15
- 4.2 above, Section QA-III-8 further assures control over quality-related j activities by requiring that special processes shall be performed in accordance with written qualified procedures, and that they shall be 1
l l
0598d t
}
l esos.rusip u s acce 6 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsCO $NCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C 1 mcomponarco QA-I-1 ;
QUALITY ASSURANCE PROGRAM l
1 performed only by qualified personnel. All qualifications shall be in accordance with applicable codes, standards, specifications, and other
- requirements as applicable. The Ebasco Quality Progran provides for the
, verification of quality requirements through written policies, procedures, and instructions for the performance of inspections and
! tests. These inspections and tests are performed on services provided by i Ebasco. All inspections shall be performed by individuals other than those who performed the activity.
- 5.0 INDOCTRINATION AND TRAINING Section QA-I-3 provides for the company-wide indoctrination and training of lR15 Ebasco personnel engaged in activities subject to the requirements of the Ebasco Quality Assurance Program. The objectives of the training program are to familiarize applicable Ebasco personnel with this Quality Assurance Program Manual and the implementing procedures identified in Table I-1.3. Overall responsibility for training as delineated in Section QA-I-3 rests with the
- Quality Assurance organization.
f 6.0 REVIEW OF QUALITY PROGRAM ADEQUACY l 6.1 The adequacy of the Ebasco Quality Program is reviewed on a regular l
basis. The determination of program adequacy is based on audit results
! and trend analyses. Section QA-III-9 provides for the performance and lR15
- follow-up of audits by Site Quality Assurance and home office Quality
, Assurance Engineering and of management audits of the Materials Applications and Quality Assurance functions.
l l 6.2 Audits performed by home office Quality Assurance Engineering and
- Site Quality Assurance are designed to evaluate the Quality Program effectiveness on a project basis. When corrective action is necessary, re-audits are scheduled to assure implementation of corrective action.
I Section Q*.-III-9 defines review activities and reports involved in the h15 suditing function.
{
I 6.3 Information on audits performed by home office Quality Assurance
{ Engineering and Site Quality Assurance shall be submitted to the Quality i
Assurance Engineering Supervisor of Auditing. He shall make an analysis
- of the available quality data with respect to quality trends and report l the result at least semi-annually to the appropriate executive level of
. management for review and assessment in accordance with Quality Assurance l Procedure QA-D.3. The Vice President Corporate Quality Programs shall be j responsible for initiating the implementation of any changes or
- corrective action deemed necessary to improve the effectiveness of the Ebasco Quality Assurance Program.
0598d I
sios. HSTSM45 PACE 7 OF 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA$CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED kk"I"1 QUALITY ASSURANCE PROGRAM TABLE I-1.1 MATRIX OF COMPLIANCE TO USNRC 10 CFR 50 APPENDIX B AND ANSI N45.2 10 CFR 50 ANSI N45.2 Ebasco Nuclear Quality Assurance Appendix B Criteria Paragraph Program Manual Section 1 3 QA-I-2 II 2 QA-I-1, QA-I-3 III 4 Not Applicable to Ebasco STP Work Scope IV 5 Not Applicable to Ebasco STP Work Scope V 6 QA-III-1 VI 7 QA-III-2 VII 8 Not Applicable to Ebasco STP Work Scope VIII 9 QA-III-10 IX 10 QA-III-8 X 11 QA-III-11 XI 12 QA-III-12 XII 13 QA-III-13 XIII 14 QA-III-14 XIV 15 QA-III-15 XV 16 QA-III-6 XVI 17 QA-III-7 XVII 18 QA-I-6 XVIII 19 QA-III-9 0598d
y TABLE l-1.2 e M o N MATRIE OF COMPLIANCE OF
- g MINCIPAL IIeLFJefJfTING MOCEDURES 7010 CFR 50 APPEN0tX B
}
fe m
$1te Standard Comet ruction Procedures ep 4 Nuclear Quality Centret Quality Assurance Queltt y Assu rance qualit y Assurance Ad a t eis t r e t t w Site Cometruction Cometruction
$tte Metatemence Quality Progree S teerte rd bg {g Crt- Precedures Precedones Isetructione Precedures Preceduree Procedures Procedures site O 3
o Procedures teatructismo Procedures
[0 v'
teries (N-) (QCP .NDE .QC-) (QAI-) (QA-) (SQAP-) (ASP-) ( G P- ) (Oti-) (QPP-) (SSP-) ..
2 m 1 -21 -1.1 -001 -2 > 2
-4 <
II -24 -2.1.-2.2,-6.3 -017.-018 -C.3 -34 -4 through -55
-022,-023
-1 en v -23 4.1.-4.3 -002,-005 -C.I.-C.2 -01 -1,-7.-10 -! through -I .-32.-49 l -017.-022 -12.-17 -96 (se apptteable) 01 4.2 -002,-022 -C. I .-C. 2 -6 vitt -9.3 through c
- - 189 , - 3 2 -38.-39 -13.-30,-48, >=
- 13. 3 ( s e applicable)*
-49 C i -17.2 Qh y
2 t II -9. 3 -10.1, -414 .-0 L5, -!!,-87,-93, -9.-10,-16 O hy y
) -002-1,-002-4,
-002-5,-005-1,
-020 -94,-95,-97 -17.-18.-22,
-29.-30,-31, h
H 2
$g g
-005-2 -005-3,
- h .-46 d o OC
-006-1 -007-n. M m
-009.-1,-0003 M ]Q>5g zg
-C.3.1 M o -42 3 -2.1.-9. 3 -04 -5,-10 -11, odmo through -13.3 -12.-14,-15 "2 (se applicable) 22 -23
~24,-26,-27, kh O -4%
]
. -a ,-34,- * ,
-38.-40,-41, g c> E
-45,-49 -52, g o@d"B3 3 o"
-H -Si 8 a C -e o $
at -11.1.-11.2 -C.3.1 -u -5.-32 -2,-37.-3s s=
ag ,
g Ett -12.1 -0 15 -23 - 34.-94 ,'," $
l E!II -10.22 -13.1,
-13.2,- 13.3
~4,-12
-82 11.-12
-37,43 -64,
-1 -13 $"
H
. -45 o IIT -024 -13 -40 - F .- 19,-3 3 en IT -15.1.-15.2, * -0u4,-007, -l% -3.-4,-8, m ,
-15.3 -Ott -H g svi -i5.2,-6.8 -OuF,-Os t -o.i -02 -is,-i. -e g "'
t 3988 -87.4.-17.2, -010,-019 -G.3 -C.4 -N -82,-28.-56 g) g 1
-17.3 >
l O Eyllt -24 -906.-023 -D.4 -03 H g 't l
-n.5.2 -C. 3 H 1
sios zitsrpe-as paos 9 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SER CES QUALITY ASSURANCE PROG TAM DESCRIPTION - PART C mco n pom Arco QA-I-1 QUALITY ASSURANCE PROGRAM TABLE I-1.3 PRINCIPAL IMPLEMENTING PROCEDURES Procedure No. Title NUCLEAR PROCEDURES (N)
N-21 Nuclear Quality Program Authorization and Implementation N-23 Reporting a Defect / Noncompliance to the NRC N-24 Ebasco Management Quality Assurance Audit Committee QUALITY CONTROL PROCEDURES (QCP, NDE, AND QC)
QCP-1.1 Qualit'y Control Organization and Responsibilities QCP-2.1 Indoctrination, Training and Qualification of Quality Control Personnel to ANSI N45.2.6 Requirements QCP-2.2 Inductrination, Training and Qualiff cation of Quality Control Personnel to ASME Section III, Division 2 Requirements QCP-6.1 Preparation, Review and Approval of Quality Control Procedures QCP-6.2 Document Control QCP-6.3 Quality Control Review of Incoming Revisions /
Changes to Bechtel Specifications and Procedures QCP-9.3 Inspection of Post-Weld Heat Treatment QCP-10.1 Cadweld Inspection QCP-10.2 Preplacement Concrete Inspection QCP-10.3 Concrete Placement Inspection 0598d
s us-a ustm.as pace 10 o, 20 HOU5 TON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT CG N A NG A ON UNR$ 1 & 2 ESASCO SERVICES
, QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C qg_
QUALITY ASSURANCE PROGRAM Procedure No. Title QUALITY CONTROL PROCEDURES (Cont'd)
QCP-10.4 Concrete and Grout Post-Placement Inspection QCP-10.8 Protective Coatings Inspection QCP-10.9 General Inspection QCP-10.10 Soils Inspection QCP-10.11 Mechanical Equipment Installation Inspection QCP-10.13 Mechanical Instrumentation Installation Inspection QCP-10.14 System / Subsystem Walkdown Inspection QCP-10.15 Electrical Equipment Installation Inspection QCP-10.20 Electrical Penetration Installation Inspection QCP-10.21 HVAC Duct / Hanger Installation Inspection QCP-10.22 Receipt Inspection QCP-10.25 Inspection of Bending and Fabricating of Reinforcing Steel QCP-10.27 Modification / Removal Control Procedure QCP-10.28 Control of Inspection Stamps QCP-11.1 Hydrostatic and Pneumatic Pressure Test Inspection QCP-11.2 Duct and Housing I4ak Test Inspection QCP-12.1 Control of Measuring and Test Equipment QCP-13.1 Storage and Maintenance Inspection / Verification QCP-13.2 Verification of Rigging and Handling Activities QCP-13.3 Housekeeping Inspections 0598d
sios.ausvous ecor 11 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsA5c0 SERWCES mcompoaarzo QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title QUALITY CONTROL PROCEDURES (Cont'd)
QCP-15.1 Identification and Control of Discrepancies and Nonconforming Conditions QCP-15.2 Stop Work Order QCP-15.3 Control and Processing of Transition Phase Deficiencies and Conditions QCP-16.1 Corrective Action QCP-17.1 Quality Assurance Records QCP-17.2 Preparation, Issuance, and Control of ASME Nameplates / Data Reports QCP-17.3 ASME On-Site Shop Fabrication NDE-002-1 Radiographic Standards for Welds and Components NDE-002-4 Radiographic Standardo for Welder's Qualification (ASME IX)
NDE-002-5 Radiographic Standards for Welder's Qualification (AWS D.1)
NDE-005-1 Ultrasonic Examination (Thickness Measurement)
NDE-005-2 Ultrasonic Examination of Pipe Welds and Components NDE-005-3 Ultrasonic Examination of Structural Welds NDE-006-1 Liquid Penetrant Examination NDE-007-1 Magnetic Particle Examination Procedure NDE-009-1 Visual Examination of NF Welds QC-0003 Preparation, Control and Distribution of NDE Procedures for the South Texas Project 0598d
sios-aiistems c>cce 12 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SEnlCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C inconponarco QA_I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title SITE QUALITY ASSURANCE INSTRUCTIONS (QAI)
QAI-001 Site QA Organization and Responsibilities QAI-002 Preparation, Review, Distribution and Control of Supplements to Quality Assurance Procedures QAI-004 Issuance and Processing of Nonconformance Reports QAI-005 Review and Approval of Quality Control and Construction Procedures QAI-006 Audit of Ebasco Site Organization by the Client, Bechtel, Ebasco Home Office, Code or Regulatory Agency QAI-007 Reportable Deficiencies QAI-010 Site Quality Assurance Records QAI-011 Corrective Action and Stop Work Authority QAI-014 Quality Assurance Review of Radiographs QAI-015 Procedure for the Operation and Calibration Verification of the Radiographic Densitometer
! QAI-017 QA Review of Incoming Revisions to Bechtel and l Houston Lighting & Power QA Program Documents QAI-018 Quality Assurance Indoctrination and Training Program QAI-019 Review, Processing and Turnover of Quality Records QAI-020 Training, Examination and Certification of NDE Personnel QAI-021 Allegation Investigation QAI-022 Quality Assurance Instructions 1 0598d l
sios-aitsroisas ocar 13 or 20 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsA5Co SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C inconponarec QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title SITE QUALITY iSSURANCE INSTRUCTIONS (Cont'd)
QAI-023 Planning of Site Quality Assurance Engineering Activities QAI-024 System Turnover QUALITY ASSURANCE PROCEDURES (QA)
QA-G.1 Preparation and Control of Quality Assurance Procedures QA-G.2 Control and Distribution of Project-Related Manuals QA-G.3 Qualification of QA Audit Personnel QA-G.3.1 Qualification of Inspection, Examination and Testing Personnel QA-G.4 Quality Assurance Records QA-D.3 Determination and Analysis of Quality Trends QA-D.4 Resolution of External Audit Findings QA-D.5.2 Site Audit Procedure I
STANDARD QUALITY ASSURANCE PROCEDURES (SQAP)
{
SQAP-01 Generation and Control of Standard Quality Assurance Procedures SOAP-02 Deficiency Reporting l SQAP-03 Project Audits l
i SQAP-04 Project Surveillances l
I l 0598d
sios. m st n u s poos 14 or 20
' HOUSTON LIGHTING AND POWER COMPANY SE CTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconpoaarzo QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. TJtle ADMINISTRATIVE SITE PROCEDURES (ASP)
ASP-1 Preparation of Site Procedures ASP-2 Organization and Responsibility ASP-4 Heavy Handling and Rigging ASP-6 Dccument Control ASP-7 Field Change Notice Procedure ASP-8 Preparation and Transmittsi of Quality Assurance and Nov-Safety Related Records ASP-10 Configuration Control ASP-12 Development of Construction Field Sketches ASP-13 Start-up Work Request Procedure ASP-15 Stop Work Procedure ASP-16 Corrective Action ASP-17 Configuration Control Package (CCP) -
l Design Change Package (DCP) l l ASP-16 Modification of Equipment / Component Tags ASP-20 ASME Section XI Repair Program ASP-22 Field Fabrication Modifications
! ASP-23 Measuring and Test Equipment Control l
l ASP-32 Maintenance of Construction Equipment l
ASP-34 Indoctrination and Training ASP-82 Fire Prevention and Fire Protection l
0598d i
en .atisten45 paar 15 o, 20 HOUSTON LIGHT'NG AND POWER COMPANf SECTION SOUTH TEXAS PROJECT ELECTRIC GENF. RATING ST ATION UNITS 1 & 2 ESA 0 SE N CE5 QUALITY ASSbRANCE PROGRAM DESCRIPTION - PART C IN CO R POfi A T E o QA-I-1 QUALITY ASSURANCE PROGRAM l
Procedure
_ No. Title CONSTRUCTION SITE PROCEDURES (CSP)
CSP-1 Excavation and Backfill CSP-2 Installation of Permanent Electrical and Mechanical Plant Equips.ent CSP-3 Control of Lifting Apperatus CSP-4 Concrete Placement CSP-5 Duct and Housing Leak Test CSP-6 Installation of HVAC Duct Hangers and Equipment Hangers CSP-9 Installation of Duct and Duct Accessories CSP-11 Storing, Installation, Cadwelding, Fabrication and Modification of Rebar CSP-12 General Instructions for Housekeeping During Construction CSP-17 Hydrostatic and Pneumatic Testing CSP-18 Soil Test Fill Procedure CSP-20 Construction Survey Activities CSP-21 Field Preparation and Coating of Surfaces Outside the Reactor Containment Building CSP-22 Valve / Pump Work CSP-24 Reactor Coolant Pump Volute Final Setting CSP-26 Reactor Vessel Final Setting CSP-27 Steam Generator Final Setting 0598d
s us.zus w i4.es pace 16 o, 20 HOU5 TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 EBA5CO SERWCE5 QUALITY ASSURAhCE PROGRAM DESCRIPTION - PART C mconpoa Arec QA-I-l QUALITY ASSURANCE PROGRAM Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd)
CSP-29 Reactor Vessel Internals Handling and Assembly CSP-30 Field Preparation and Coating of Surfaces Inside the Reactor Containment Building CSP-32 Insulation Resistance Testing CSP-33 High-Potential Testing CSP-34 Control and Verification of Survey Equipment CSF-35 Installation of Post-Tensioning Trumplate Assemblies and Sheathing CSP-30 Data Collection to Support Geotechnical Monitoring Program CSP-37 Crane and Hoist Load Testing CSP-38 Equipment or Component Interchange CSP-39 ASME Code Data Plate Modifications CSP-40 EE-580 Electrical Installations CSP-44 Installation of Electrical Penetration Assemblies CSP-47 Instrumentation Installation CSP-55 Field Fabrication of Reinforcing Steel CSP-56 Application and Repair of Waterproofing of Buildings CSP-63 Rigging for Setting the Reactor Head CSP-64 Rigging for Setting Urdt II Reactor Internalo 0598d
sios.rustpisco poor 17 og 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESASCO SENCEs QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C in co n cori A r c o QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd)
CSP-65 Reactor Coolant Pumps Rigging and Installation CSP-87 Welding Procedure Specification Qualification CSP-93 Control of Weld Filler Material For Non-Permanent Plant Maintenance CSP-94 Maintenance, Calibration and Repair Program for Dimetrics Automatic Welding Equipment CSP-95 General Welding Requirements for HVAC CSP-97 Cold Bending CONSTRUCTION MAINTENANCE INSTRUCTIONS (CMI)
CMI-1 Care and Maintenance of Permanent Plant Items QUALITY PROGRAM PROCEDURES (QPP)
QPP-4 Quality Program Coordinator - Description of Position, Duties, Responsibilities QPP-5 Deviating from the Corporate Ebasco Nuclear Quality Assurance Program Manual QPP-6 Assignment, Distribution and Control of the Ebasco Nuclear Quality Assurance Program Manual QPP-7 Revisions to the Ebasco Nuclear Quality Assurance Program Manual l
l 0598d 1
s ios.aiist r a.es pace 18 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO $EMICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcomponareo QA-I-1 QUALITY ASSURANCE PROGRAM l
Procedure '
No. Title STANDARD SITE PROCEDURES (SSP)
SSP-1 Preparation, Issue, and Control of Standard Site Procedures SSP-2 Project Generic Pressure Test Procedure SSP-3 Construction Turnover and Release for Test SSP-4 Jurisdictional Release SSP-5 Coring, Cutting or Drilling Concrete SSP-7 Work Package Statusing SSP-8 Nonconformance Reporting SSP-9 Pipe Support Installation SSP-10 Installation and Field Fabrication of Piping SSP-11 Fabrication, Erection and Bolt-up of Structural and Miscellaneous Steel SSP-12 On-Site Shop Fabrication SSP-13 Material Control SSP-14 Stud Anchor Installation and Inspection SSP-15 Non-Shrink Grout and Mortars SSP-16 General Structural Welding Requirements SSP-17 General ANSI B31.1 Welding Requirements SSP-18 General ASME III Welding Requirements SSP-19 STP QA/QC Responsibilities for System and Area Turnovers 0598d
siosoitsTPN 85 COGE.19__ or E__
HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoa^TEo QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title STANDARD SITE PROCEDURES (Cont'd)
SSP-20 control of ASME Code Nameplates and Permanent Plant Tags SSP-21 Preparation and Certification of ASME Code N-5 I Data Reports SSP-22 Piping System Cleanliness SSP-23 Release for Insulation SSP-24 Disassemby/ Reassembly of Safety and Non-Safety Related Valves SSP-26 Termination of Electrical Cable SSP-27 Installation of Electrical Cable SSP-28 Installation and Inspection of Electrical Raceway and Supports SSP-29 Post-Weld Heat Treatment SSP-30 Weld Filler Material Control SSP-31 Welder Qualifications SSP-32 Impact Review of Bechtel Documents SSP-33 Construction Safety Tagging l
SSP-34 Technical Requirements and Walkdown Procedure for As-Building of Piping Systems SSP-36 Construction Work Package - Work Package Control
- SSP-37 Configuration Control Package SSP-38 Installation and Inspection of HVAC Duct / Supports and Accessories l
0598d
.ios.ausrpa.es ocar 20 og 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsCo SERVICES QUALITY ASSURANCE FROGRAM DESCRIPTION - PART C mcom poa A T eo QA-I-l QUALITY ASSURANCE PROGRAM Procedure No. Title STANDARD SITE PROCEDURES (Cont'd)
SSP-40 Maxi-Bolt Installation and Inspection SSP-41 Rock Bolt Installation and Inspection SSP-45 Electrical Separation SSP-46 Field Material Requisition Preparation and Approval SSP-48 Equipment or Component Interchange SSP-49 Field Change Requests SSP-52 Installation, Assembly and Disassembly of Permanent Plant Mechanical Equipment SSP-53 Instrumentation Installation SSP-55 Indoctrination and Training of Site Personnel SSP-56 Project Record Review Activities SSP-57 Installation and Inspection of Electrical Equipment
{
I l
l l
0598d
- .- - -We - . - --- ---i ---m- -- ayr- r n -
sios.zitsvenes poor 1 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT '.
ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SEREES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcomponareo QA-I-2 ORGANIZATION AND RESPONSIBILITIES 1.0 SCOPE ThisSectiondescribestheorganizationalstructure,fuhetional lR15 responsibilities, levels of authority, and lines of internal and external communication for management, direction, and execution of the Ebasco Quality Program. It is recognized that quality assurance is an interdisciplinary function and not the sole domain of a single qualiry assurance group; for that reason, this Section of the Manual includes organizational and functional descriptions of several departments in addition to that organization whose sole function is quality assurance.
~
2.0 GENERAL 2.1 The Ebasco operations organization consists of various applicable l operational divisions within Ebasco Services Inc, each headed by an l officer of the company. The South Texas Project is an independently run l operation with support by other Ebasco organizational units as described l l herein. l lR15 2.2 Representatives from the various operational divisions including the Vice President Corporate Quality Programs comprise the Quality Program Committee which is responsible for Ebasco Quality Assurance policy.
2.3 The Ebasco organizational units on the South Texas Project most I directly involved in the implementation of the Quality Assurance Program for fabrication and installation are Corporate Quality Programs, and Ebasco Constructors Inc. The organizational structures of these are shown in Figures I-2,2 and I-2.4 at the end of this Section.
l The responsibilities of the individual Ebasco organizational units for l quality assurance requirements applied to nuclear power stations are described herein.
3.0 CORPORATE QUALITY PROGRAMS l Primary responsibility for quality assurance rests with the Vice President Corporate Quality Programs who reports directly to the Chairman of Ebasco l Services Inc. Qualification requirements for the position of Vice President lR15 Corporate Quality Programs are: Bachelor of Science Degree in Engineering; minimum of 10 years of experience in quality-related work or equivalent lR15 experience in the engineering or construction of a nuclear power plant, including at least 10 years experience in responsible managerial project positions; and a thorough knowledge of the Ebasco Quality Assurance Program.
I i
0598d
siosoitswo as pace 2 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 EBA5CO $ERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaaTeo QA-I-2 ORGANIZATION AND RESPONSIBILITIES The Corporate Quality Programs unit is comprised of the following organizations, each of which contributes directly to the implementation of the Quality Program (see Figure I-2.2):
a) Quality Assurance b) Materials Applications c) Vendor Quality Assurance d) Quality Assurance Consulting Engineer e) Materials Engineering Laboratory 3.1 Quality Assurance is administered by the Director Quality Assurance who reports to the Vice President Corporate Quality Programs.
Qualification requirements for the position of Director Quality Assurance are: Bachelor of Science Degree in Engineering; minimum of 10 lR15 years of experience in quality-related work or equivalent experience in the engineering or construction of a nuclear power plant, including at least 5 years experience in responsible managerial project positions; and a thorough knowledge of the Ebasco Quality Assurance Program. Quality Assurance is responsible to plan implementation of, evaluate, monitor, and enforce the Ebasco Quality Program. This responsibility is carried out by five functional subdivisions:
a) Quality Assurance Projects b) Quality Assurance Site Services i c) Quality Assurance Engineering i
d) Inservice Inspection / Nondestructive Examination Services e) Quality Assurance Consulting Managers in charge of the subdivisions report directly to the Director Quality Assurance. Engineers and Specialists cre then assigned to specific projects from these subdivisions. The Quality Assurance Organization is shown in Figures I-2.6 and I-2.7 at the end of this Section. The organization and responsibilities of the four Quality Assurence subdivisions associated with the South Texas Project ere described in the following paragraphs.
0598d l
.-. - . = ._
sios.zusvenes pace 3 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO $ERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoa-oa ATeo QA-I-2 ORGANIZATION AND RESPONSIBILITIES 3.1.1 Quality Assurance Site Services - The Quality Assurance Site Services subdivision is headed by the Manager Quality Assurance Site Services who is responsible for all site-related Quality Assurance /
Quality Control activities, including implementation of the site phase for all Ebasco project quality programs. A Manager Site Quality Assurance, who reports to the Manager Quality Assurance Site Services, and a Quality Program Site Manager, who reports to the Director Quality Assurance, are responsible for Quality Program implementation for the South Texas Project in accordance with the following:
I 3.1.1.1 Site Quality Assurance - The Manager Site Quality I Assurance, who reports to the Manager Quality Assurance Site
- Services in New York, is responsible for providing technical assistance and guidance to subordinate Quality Assurance Site Supervisors and staff, and for distribution and control of quality assurance manuals, as well as changes thereto, for the South Texas Project. (See Figures I-2.2 and I-2.6.)
The Manager Site Quality Assurance has delegated authority to
- the Quality Program Site Manager on the preparation, review, approval, and distribution control of Site Quality Control i Procedures and Site Quality Assurance Instructions; and to
! approve the Standard Quality Assurance Procedures, and the i Standard Site Procedures when applicable, developed by the Client-or his designee.
I 3.1.1.2 Site Quality Program - A Quality Program Site Manager is assigned to the construction site on a resident basis for the purpose of overall planning, direction, and implementation of the Ebasco Nuclear Quality Assurance Program Manual. The Quality Program Site Manager, who reports to the Director Quality Assurance, is subordinate to no individual on site and has the independent authority to identify site quality-related problems, to initiate or recommend solutions, to control existing nonconformances, to verify implementation of approved dispositions, to direct efforts to obtain ASME Certificates of Authorization for Ebasco as may be required for the South Texas Project, to represent the Ebasco Quality Assurance organization with regard to South Texas Project activities, such as Client or his designee and/or Ebasco meetings, Client or his designee audits, management audits, and, when necessary, to stop work. He is responsible to assure that all personnel working for him are qualified for their respective positions and properly trained. The Director Quality Assurance has 0598d
sios.zitsron-as pace 4 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C (NCORPORATEo QA-I-2 ORGANIZATION AND RESPONSIBILITIES delegated authority to the Quality Program Site Mana8er on the preparation, review, approval, and distribution control of project-related supplements to the applicable Quality '
Assurance Procedures. The Site Quality Program function is divided into three groups: Quality Assurance, Quality Control, and Quality Records, each reporting through a respective supervisor to the Quality Program Site Manager.
(See Figure I-2.6.)
3.1.1.2.1 Site Quality Assurance - A Quality Assurance Site Supervisor and staff of engineers and representatives are assigned the following functions:
a) Review and audit safety-related site construction and engineering activities and records on a continuing basis.
b) Perform audits and surveillances of construction forces for adherence to prescribed approved procedures.
c) Review and advise on quality control procedures, construction procedures, and nondestructive examination procedures for compliance with this Manual and code and regulatory l requirements. When necessary, the i
Quality Assurance Site Supervisor may request the Manager Site Quality I
Assurance to assist in the review of quality control procedures.
d) Generate records of all reviews and audits performed.
e) Review all radiographic film for site-related nondestructive examination.
f) Audit records and documentation prior to turnover to the Client.
0598d
sios ausepa4s pace 5 or 13 HOUSTON LIGHTING AND POWER CfXAPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsASCO SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoanoa ATEo QA-I-2 ORGANIZATION AND RESPONSIBILITIES g) Develop and implement Quality Assurance Instructions and review the Standard Quality Assurance Procedures
- prior to the Quality Program Site Manager's approval and their implementation. When applicable, review the Standard Site Procedures prior to the Quality Program Site Manager's approval and their implementation.
h) Perform on-site distribution of those Quality Assurance procedures which are issued and controlled by the Manager Site Quality Assurance or his designee, and distribute the Standard Quality Assurance Procedures.
- 1) The Quality Assurance Site Supervisor has stop work authority.
3.1.1.2.2 Site Quality Ccatrol - A Quality Control Site Supervisor and staff of engineers and inspectors are assigned the following functions consistent with the scope of work assigned to Ebasco:
a) Planning and performance of-inspection activities during the construction phase.
- b) Identifying and initiating correction
! of nonconforming conditions to requirements indicated by drawings, specifications, codes, or procedures, and performance of reinspection to verify corrective action taken.
I c) Establishing and enforcing quality l control documentation and inspection requiremsnts based upon l specifications,
, codes, standards, and drawings as established by the Client or his designee.
0598d
sioseusTr>44s pace 6 o, D HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PRCJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SmlCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C iwcomponareo QA-I-2 ORGANIZATION AND RESPONSIBILITIES d) Performance or monitoring of site NDE, soils, and concrete testing activities.
e) Assisting in organizing and administering training seminars as required to assure proper level of training, and engaging in the certification of Quality Control personnel to the required level of qualification.
f) Identification and control of the quality status of items.
g) Development and implementation of applicable Quality Control Procedures, implementation of applicable Standard Site Procedures, and generation of inspection reports covering sandatory inspection activities at the construction site, h) The Quality Control Site Supervisor
, has stop work authority.
The Site Quality Control Group will only be responsible for first-level Quality Control activities for safety-related items and services being performed by Ebasco's forces.
3.1.1.2.3 Site Quality Records - A Quality Records Supervisor and staff of specialists are assigned the following functions:
a) Develop, establish, and implement a system for the collection, storage, and maintenance of quality assurance i records at the project construction site.
b) Responsible for review for completeness, control, atorage, preservation, and safekeeping of Ebasco site generated quality assurance records until turnover to the Client or his designee.
0598d
.- - . _ ~ . -. -, .. -- _-
sios-a usroa4s paos 7 or 13 HOUSTON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA$CO SENCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATec QA-I-2 ORGANIZATION AND RESPONSIBILITIES i
c) Establishment and implementation of a records indexing system to permit proper traceability and retrieval.
d) Establishment of a procedure for access to the records storage area, and removal and retrieval of quality records.
3.1.1.2.4 At the site level, intermediate positions for all of the above categories may be required but functional reporting will remain as depicted in Figure I-2.6.
4 3.1.2 Quality Assurance Engineering - The Quality Assurance Engineering subdivision is headed by the Manager Quality Assurance Ingineering. He is responsible for the following activities which are under the direction of supervisors reporting to him and are performed in accordance with Quality Assurance procedures:
a) Administration of training and qualification programs for Quality Assurance audit and inspection personnel.
l b) Conducting Quality Assurance education, both internal and external to Quality Assurance. Quality Assurance Education Specialists from Quality Assurance Engineering are assigned to the construction site. These specialists report administrative 1y and functionally to the Quality l
Program Site Manager, but receive technical direction from Quality Assurance Engineering at the Ebasco home office.
c) Interdepartmental auditing of all individuals or groups l
responsible for activities covered by the Quality Program.
d) Development and implementation of Corporate Trend Analysis programs.
3.1.3 Inservice Inspection / Nondestructive Examination Services -
) The Inservice Inspection / Nondestructive Rummination Services subdivision is headed by the Manager of Inservice Inspection /
Nondestructive Examination. He is responsible for the following 0598d
sios.susreces once 8 Cr 13 HOUSTON LIGHTING AND POWER COMPANf SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C trecOR POR A TEc %-I-2 ORGANIZATION AND RESPONSIBILITIES activities which are under the direction of rupervisors reporting to him:
a) Establishment and/or interpretation of NDE requirements and acceptance criteria for fabricated and erected equipment as required.
b) Reviewing and commenting on NDE procedures and radiographic films submitted by site construction forces and/or clients.
c) Advising site construction forces as to proper NDE procedures, applications, techniques, equipment, and qualifications.
d) Qualification and certification of Ebasco NDE personnel.
3.1.4 Quality Assurance Consulting - The Quality Assurance Consulting subdivision is headed by the Senior Consulting Quality Assurance Engineer, who is responsible for the following activities:
a) Development of Quality Assurance standards and procedures.
b) Interpretation of quality assurance requirements as
- specified in national codes, standards, and regulatory I
documents, and incorporating these requirements in company documents.
3.1.5 Radiation Safety - Ebasco's Corporate Radiation Safety Officer reports to the Director Quality Assurance through the Manager ISI/NDE Services. He is responsible for the compilation of l occupational radiation exposure records received from Ebasco lR15 employees and Licensees. l 3.2 Materials Applications, under the supervision of the Chief Materials Engineer, includes two subdivisions: Materials Engineering and Welding Engineering. A Project Materials Engineer and Project Welding Engineer are assigned to the South Texas Project. These positions may be assigned to the same individual if properly qualified. A Site Welding Superintendent, who reports to the Chief Materials Engineer in New York, is assigned to the construction site and is responsible for the direction, supervision, and administration of a site welding operations 0598d l
stot atisTDie 45 pact 9 y 13 HOUSTON UGMTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 ESA5CO SENCE5 mconpoaarse QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 ORGANIZATION AND RESPONSIBILITIES s taff. Quality-related activities of Materials Applications personnel include the following:
a) Develop material and welding specifications.
b) Develop and qualify welding procedures and fabrication '
techniques for use by Ebasco site construction forces.
c) Prepare site welding operations implementation procedures for Ebasco site construction forces.
d) Advise Ebasco Ccastruction management as to the development and application of advanced welding techniques which would enhance quality.
e) Prepare Process Data Checkliets which provide comprehensive requirements for welding process and procedure selection, postweld thermal treatment, and inspection at the construction site.
f) Review specifications and drawings provided by the Client or his designee for compliance with applicable codes and regulatory requirements for proper selection of meterials, weld procedures, and joint details.
l
- g) Supervise the welder performance testing program at the l construction site to assure that all code and regulatory requirements have been met, h) Provide technical assistance as required to resolve problems at the construction site in the areas of welding, materials, heat treatment, and other related areas.
- 1) Provide technical assistance concerning material properties under service conditions involving stress, radiation, temperature, corrosive media, etc, to determine capability of specific materials to perform in such environments.
. j) Review, monitor, and provide recommendatiocs for upgreding of Ebasco welder training programs and welder assignment practices.
k) Prepare and monitor site filler material control procedures.
- 1) Supervise and direct testing and applied research programs required to resolve site construction materials and welding problems.
0598d
sm auste>44s pace 10 o, 13 HOUSTON UGHTING AND POWER COMPANY SECTioN SOUTH TEXAS PROJECT ELECTRtc GENERATING STATION UNITS 1 & 2 EuA5Co SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C l mcom poe A r ce QA-I-2 ORGANIZATION AND RESPONSIBILITIES l
l l
i 3.3 The Quality Assurance Consulting Engineer reports to the Vice President Corporate Quality Programe. He is responsible for conducting audits of the Ebasco Quality Assurance function to determine and report its compliacce with the Ebasco Quality Program requirements.
i 3.4 The Materials Engineering Laboratory performs field nondestructive l examination services. The Materials 2ngineering Laboratory is administered by a Manager who reports to the Vice President Corporate
, Quality Programs. The NDE Laboratory Supervisor reports administrative 1y
( to the Materials Engineering Laboratory Manager or his designee and is responsible for the technical direction of nondestructive examination activities performed by the Site NDE Laboratory at the construction l~
site. The NDE Laboratory Sepervisor reports functionally to the Quality j Control Site Supervisor or his designee.
! 4.0 EBASCO CONSTRUCTORS INC.
Primary responsibility for construction rests with the President Ebasco l Constructors Inc. The construction organization has the prime responsibility la15 for the performance of quality construction on the South Terms Project and is described in the following paragraphs. ,
i 4.1 The President Ebasco Constructors Inc reports to the President l Ebasco Services Inc. and is responsible for executive management of all lR15 construction activities and services. (See Figure I-2.4.)
4.1.1 The Ebasco Construction Manager reports to the President l
Ebasco Constructors Inc and is responsible for overall supervision i.
and coordination of all construction activities and services.
Additionally, the Ebasco Construction Manager shall approve the Standard Site Procedures. The Ebasco Construction Manager has stop work authority.
I
- 4.1.2 The Manager of Construction Quality reports to the President Ebasco Constructors Inc, and is responsible for development of Construction procedures, keeping abreast of NRC and code requiremento, and reporting to construction management of lR15 current Quality Program status. l 4.1.3 The Site Manager reports to the Ebasco Construction Manager.
The Site Manager has the responsibility for the direction and coordination of all on-site activities related to construction. The Site Manager has stop work authority.
0598d
sios.aissima-ss pace U oir D
HOUSTON LIGHTING AND POTER COMPANY SECTION SOUTH TEXAS PROJECT
' ELECTRIC GENERATING STATION UNITS 1 & 2 ESAACO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaaTro QA-I-2 ORGANIZATION AND RESPONSIBILITIES 4.1.4 The Discipline Managers report to the Site Manager. Each
! Discipline Manager is individually responsible for the Ebasco 4 construction operations and activities within his assigned discipline. He will manage all phases of construction within disciplines assigned, including field engineering and cost control, to assure that the work accomplished is completed within the budget
- and in accordance with the contract and all applicable installation plans, procedures, specifications, drawings, and the Quality Assurance Program. The Discipline Managers have stop work authority.
! 4.1.5 The Labor Relations Representative reports to the Site Manager.
- The Labor Relations Representative is conversant with the general provisions of the Project Stabilization Agreement. The Labor Relations Representative participates in settlement of local labor l disputes, assists in preparation for arbitration proceedings related to operations at the site, and advises the Site Manager on
- local labor relation matters.
4.1.6 The Senior Resident Engineer reports to the Site Manager and is responsible for administering, coordinating, and supervising all Site Construction Engineering and technical activities, for i interpretation of design documents and specifications, for l furnishing assistance to Ebasco site personnel as required, and for l establishing and providing training and development programs for construction. The Senior Resident Engineer has stop work authority.
l 4.1.7 The Construction Services Superintendent reports to the Site Manager and will be responsible for providing and establishing adequate and efficient accounting, timekeeping, and computer support programs as required to support the construction effort, i
4.1.8 The Manager of Safety / Security reports to the Site Manager.
l The Manager of Safety / Security is responsible for establishing and enforcing the site security, safety, and industrial hygiene programs in accordance with established policy and all federal and state regulations, as well as any other criteria necessary to ensure the safety of site personnel.
4.1.9 The Permanent Plant Maintenance (PPM) Superintendent reports to the Site Manager and is responsible for administering the maintenance program for permanent plant equipment upon receipt from the warehouse until turnover to the Client.
0598d
sio .ausrae.as occe 12 og 13 HOUSTON LIGHTING AND POWER COMPANV SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompomarco QA-I-2 ORGANIZATION AND RESPONSIBILITIES 4.1.10 The Start-up Support Superintendent interfaces with the Client's Start-up Manager and reports to the Site Manager for project coordination. He is responsible for systems testing, including ensuring construction progress in support of systems testing, and conducting construction test efforts.
4.1.11 The Site Fabrication Shop Coordinator reports directly to the Mechanical Discipline Manager and is responsible for coordinating work to be performed in the fabrication shop, ensuring housekeeping is maintained in the fabrication shop, and establishing laydown areas around the fabrication shop in support of the construction effort.
4.1.12 The Systems Completion Manager reports to the Site Manager and is responsible for the coordination of systems turnover to the Client.
lR15 4.1.13 The Shift Superintendents (2nd or 3rd shift) report to the Site Manager and are responsible for directing, coordinating, and providing general supervision of all construction activities associated with their shift. The Shift Superintendents have stop work authority.
5.0 INTERFACE Interface, as applicable, is so illustrated by Figure I-2.9 at the end of this Section and is explained by approprisi:e and applicable South Texas Project docu:aents.
0598d
6109 2115TPM45 pAog 3 or 4 HOUSTON LIGHTING AND POTER COMPANY SECTION SOUTH TEXAS PROJECT .
ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C mcom poa ATEo QA-III-2 DOCUMENT CONTROL I
3.3.2 The Senior Resident Engineer shall submit the proposed Field Change Request to the Client or his designee for evaluation, disposition, distribution, and control by the Client or his designee in accordance with the Client's or his designee's written procedures.
3.5.2.1 In order to expedite field change requests associated with in-process activities against design drawings, an "Interia Approval" shall be obtained by the Senior Resident Engineer from the Client or his designee in accordance with approved site procedures.
3.6 Field Change Notice 3.6.1 A " Field Change Notice" shall be generated by the Senior Resident Engineer as is allowed by the design specification and shall be approved, issued, and controlled by the Senior Resident Engineer in accordance with approved site procedures.
3.6.2 A Field Change Notice (FCN) is to provide construction with a method of documenting conditions (not tolerances) that are within criteria allowed by the applicable specifications. An FCN shall not be use.d in lieu of a Nonconformance Report (NCR) or a Field Change Request (FCR).
3.7 Field Sketches, 3.7.1 Field sketches shall be prepared, reviewed, and approved by the Senior Resident Engineer or his designee in accordance with approved site procedures. Only the following two types of field sketches shall be permitted to be utilized by field personnel as a basis for the fabrication, installation, and inspection of i safety-related items:
l
! a) Field sketches which have been approved by the Client or his designee.
l b) Field sketches which the Senior Resident Engineer has determined to be within standard detailing parameters
! established by specifications prepared by the Client or j his designee.
l l 3.7.2 Field sketches shall be transmitted by the Senior Resident
! Engineer to the Client or his designee for approval and/or distribution to the established document control stations by the Client or his designee.
. 0599d l
siosoustre4s pace 4 or 4 HOUSTON LIGHTING AND POOEQ COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C incoapoaArec QA-III-2 DOCUMENT CONTROL 4.0 CHANGES TO DOCUMENTS Changes to Ebasco documents shall be distributed in the same manner as the original document. Revised documents shall be controlled in accordance with the requirements of this Section and/or written procedures in order to avoid inadvertent use of outdated documents.
5.0 QUALITY ASSURANCE RECORDS Quality Assurance records shall be maintained by Site Quality Records which shall be audited by Site Quality Assurance to assure that they are maintained properly.
5.1 The system for control and retrieval of Quality Assurance records at the site shall be in accordance with Section QA-I-6 of this Manual.
6.0 AUDITS Ebasco Site Quality Assurance shall audit the Client's or his designee's control and distribution of Ebasco generated construction, special process, and quality control procedures and instructions in accordance with the requirements of Section QA-III-9 of this Manual.
l i
0599d i
sios.austaus pace 1 or 5 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C incompoa4Tec QA-III-6 NONCONFORMANCES 1.0 SCOPE This Section establishes the requirements for the identification, control, and disposition of items or services found to be in nonconformance with the applicable requirements at the construction site. All activities described in this Section shall be performed in accordance with written instructions and/or procedures.
2.0 CONSTRUCTION SITE NONCONFORMANCES 2.1 Nonconformances at the construction site may be detected by Ebasco Site Quality Control, Site Quality Assurance, or Construction. The person identifying a nonconforming condition shall document the condition by initiating a South Texas Project Site Nonconformance Report.
2.2 All nonconformances detected shall be reported to the Quality Assurance Site Supervisor and/or the Quality Control Site Supervisor or their designees. A preliminary assessment of the severity of the nonconformance shall be made in accordance with Company Procedure N-23 or i
approved site procedures. The final responsibility for evaluation of all nonconformances for possible reportability rests with the Client or his designee.
l 2.3 Quality Control procedures shall require that all nonconforming items shall be clearly marked or tagged as nonconforming and shall be segregated when possible.
2.4 The Nonconformance Report shall then be reviewed and processed in accordance with Paragraph 4.0 of this Section of the Manual.
2.5 After processing of the Nonconformance Report, the Quality Assurance Site Supervisor or his designee shall distribute copies of the reviewed and evaluated report in accordance with internal Site Quality Assurance Instructions.
2.6 The Quality Assurance Site Supervisor and the Quality Control Site Supervisor or their designees from the Site Quality Assurance organization shall verify by audits, reinspections, or other appropriate means that the necessary corrective actions are taken.
0599d
sior.stistra-os paos 2 er 5 4
HCUSTON LIGHTING AND POWER COMPANY SEcTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconeoa4Tro QA-III-6 NONCONFORMANCES 3.0 REINSPECTION 3.1 For nonconformances detected at the construction site, the Quality Control Site Supervisor or his designee shall assure that reinspection is performed on all items and services reported as nonconforming.
Reinspection shall be performed in accordance with the requirements of the governing code (s) and in accordance with requirements at least as stringent as those by which the nonconformance was detected. He shall document the satisfactory correction or resolution of all nonconformances on the dispositioned Nonconformance Report. This documentation shall i provide sufficient detailed information for as-built records.
3.1.1 Nonconformances not corrected in accordance with the requirements of the approved disposition to the Nonconformance Report shall not be accepted by Site Quality Control. Items or services shall not be accepted by Site Quality Control until such time as the appropriate corrective action has been accomplished.
4.0 REVIEW OF NONCONFORMANCE REPORTS 4.1 Upon receipt or initiation of a Nonconformance Report, the Quality l Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall perform the following functions in accordance with QA procedures and/or instructions:
4.1.1 Log-in the report and record a unique identifying number on the report.
4.1.2 Route the report to the Client or his designee who shall disposition and approve the report.
4.1.3 Receive the report from the Client or his designee following approval of the dispositioned report.
4.1.4 Upon receipt of the approved Nonconformance Report from the Client or his designee, the Quality Assurance Site Supervisor or his designee shall log-in the results of the review and distribute copies of the report for implementation of the approved disposition as necessary in accordance with approved procedures.
0599d
s tosaustpo4s pact 3 or 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS FROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 1 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcom poa A r co QA-III-6 NONCONFORMANCES 4.2 Dispositions for all nonconformances to the design specifications or other documents originally requiring review and approval of the Client or his designee, must have the review and approval of the Client or his designee prior to implementation unless otherwise permitted by approved procedures.
4.3 The Quality Assurance Site Supervisor or his designee shall perform a final review for closure of Nonconformance Reports generated in accordance with the requirements of this Section.
4.4 The Quality Assurance Site Supervisor or his designee shall maintain on file, copies of all open Nonconformance Reports generated in accordance with the requirements of this Section.
5.0 DEFICIENCY NOTICES 5.1 Deficiencies in the quality of items and services which either violate the restrictions of Paragraphs 5.2 and 5.3 of this Section of the Manual or are detected during final inspection at the construction site, and which can be corrected by reworking or by standard repair procedures
- (approved by the Client or his designee) during the normal course of construction, shall be documented on a Deficiency Notice. Copies of all Deficiency Notices shall be transmitted to the Quality Control Site Supervisor or his designee who will initiate Nonconformance Reports based
- on information given in the Deficiency Notices when he determines that l this action is necessary. In this case, the Deficiency Notice becomes a I part of the Nonconformance Report and only the Nonconformance Report is required to be resolved.
5.2 Items discovered to be out-of-tolerance or not to specification at in process inspection checkpoints of an inspection process shall be documented on a Deficiency Notice, provided all conditions listed below are met: .
a) The condition is corrected prior to final inspection / acceptance of the work.
b) The work does not proceed beyond the checkpoint until the correction is made.
c) The out-of-tolerance condition does not reflect on work previously accepted.
d) No violation of code is evident.
0599d
. .. ~. .
PAGE oF 4109 21(STP14 85 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 JNCORPORATco NONCONFORMANCES Deficiencies meeting the above requirements, which can be easily reworked l immediately by Construction, or are easily controlled by and documented on lR15 the Construction work package inspection documentation, require no docu- l mentation, other than on the aforementioned inspection documentation. l Examples include, but are not limited to:
a) Loose bolts, b) Undersized welds, c) Coating thickness too low.
d) Surface profile too low.
Damage which would affect the integrity of an item shall be classified as' a nonconformance and processed accordingly.
5.3 An unacceptable ASME Code weld found during the normal welding / inspection process shall be processed and reported on a
" Process Data Checklist" form in accordance with approved Site Quality Control procedures. Any unacceptable weld found after the normal welding / inspection process is completed shall be documented as nonconforming in accordance with this Section of the Manual.
5.4 The processing of Deficiency Notices shall be detailed in approved Site Quality Control procedures.
6.0 TREND ANALYSIS OF NONCONFORMANCE REPORTS AND DEFICIENCY NOTICES 6.1 Ebasco's Corporate Trending Copies of Nonconformance Reports from the sources mentioned above shall be submitted to the Quality Assurance Engineering Supervisor l of Auditing. The Quality Assurance Engineering Supervisor of i
l Auditing subsequently receives the Nonconformance Report and makes an analysis of the available data with respect to quality trends.
The trend analysis and distribution of subsequent reports shall be made in accordance with the requirements of Quality Assurance i Procedure QA-D.3.
l I
l ._,
sios.ausrea4s pace 5 or 5 HOUSTON LIGHTING AND PO"ER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C incompoaATee QA-III-6 NONCONFORMANCES 6.2 Client's Trending Copies of Nonconformance Reports (NCR's) and Deficiency Notices (DN's) from the sources mentioned above shall be transmitted to the Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Project Trend Program activity in accordance with their procedure (s).
7.0 RECORDS Nonconformance Reports shall be maintained in accordance with Section QA-I-6 of this Manual and/or approved Site Quality Assurance Instructions.
8.0 AUDITS Ebasco Site Quality Assurance shall be responsible for the performance of audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.
0599d t
sios.ausroods oaos 1 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTR!C GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcom aca A Teo QA-III-7 CORRECTIVE ACTION 1.0 SCOPE This Section establishes the requirements for the identification, analysis, and implementation of corrective action for safety-related items and services. The Section applies to activities performed at the construction site.
2.0 GENERAL 2.1 Corrective action shall be required for identified and documented nonconformance(s) associated with safety-related items and services.
2.2 The need for corrective action may be identified from the following sources:
a) Inspection activities performed by Site Quality Control.
b) Site Quality Records document reviews.
c) Quality Assurance audits performed by the Quality Assurance organization in accordance with Section QA-III-9 of this Manual.
l l d) Audits of Ebasco performed by the Client or his designee or regulatory bodies.
e) Nonconformances detected at the construction site as described in Section QA-III-6 of this Manual.
f) Audits of the Quality Assurance and Materials Applications organizations performed by the Management Audit Committee.
g) Surveillances performed by Site Quality Assurance.
2.3 Determination and review of corrective action items shall be made as early as possible in order to preclude the possible repetition of deficiencies.
2.4 During the review of all corrective action items, consideration shall be given to the training of personnel if it is determined that this was a cause of the deficiency.
2.5 Dissemination of corrective action information to responsible individuals shall be performed in a minimum length of time.
0599d
s tos-a t t sTDH45 poac 2 er 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESASCO SERWCES QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C mcomponArec QA-III-7 CORRECTIVE ACTION 2.6 At the discretion of the Quality Assurance Site Supervisor or his l
designee from the Site Quality Assurance organisation, for corrective action items identified per Paragraph 2.2 of this Stetion, a
, corrective action document may be issued. ThIs document shall be used '
when deficiencies detected are not isolated cases and when they are of sufficient magnitude to warrant a documented supervisory review in accordance with approved Quality Assurance procedures or instructions.
This document goes beyond the standard audit action response required by audit reports.
2.7 For programmatic deficiencies detected by Site Quality Assurance, the maximum length of time for corrective action response shall be 20 working days from the receipt of notice of deficiency. The maximum implementation time shr.11 be 20 working days from the acceptance of i corrective action response, unless otherwise approved by the Director
{ Quality Assurance or his designee from the Quality Assurance organization. Nonconformance reports shall be initiated and processed in accordance with Sectica QA-III-6 of this Manual. i 2.8 It shall be the responsibility of the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization to assure that all required corrective action is implemented in a timely manner.
2.9 A preliminary assessment of the severity of deficiencies and conconformances detected shall be made in accordance with Company Procedure N-23 or approved site procedures. The final responsibility for evaluation of all deficiencies and nonconformances for possible j reportability rests with the Client or his designee. Reporting of i
deficiencies and nonconformances in accordance with 10 CFR 50.55e and its subsequent evsluation will be the responsibility of the Client or his designes.
3.0 DETERMINATION AND IMPLEMENTATION METHODS
! 3.1 Nonconformance Reports Generated at the Construction Site 3.1.1 Site Quality Control shall perfora direct inspection of activities at the construction site as required by Section QA-III-11 of this Manual.
i 1
0599d
s to s.2 ?lsT Pl445 PAGE 3 or 4 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXA3 PROJECT ELECTRIC GENERATIN3 STATION UNITS 1 & 2 E8ASCO $ERVICES ggg. lTY ASSURANCE PROGRAM DESCRIPTION - PART C iscoareaArce QA-III-7 CORRECTIVE ACTION 3.1.2 Nonconformances acted during these inspection activities shall be documented on a Nonconformance Report in accordance with Section QA-IIl-5 of this Manual. Site Quality Control shall verify that the corrective action which has been stipulated on the conplated form is implemented. Site Quality Control shall maintain a log of all required corrective action and shall review this periodically to assure the resolution of deficiencies and impicaentation of required corrective action.
3.2 Site Quality Assurance Audits Site Quality Assurance shall perform audits of activities performed at the construction site as required by Section QA-III-Q of this Manual. Site Quality Assurance shall also perform follow-up action as described in Section QA-III-9 to assure that corrective action, if required, has been accomplished. If disagreement about the type or effectiveness of corrective action exists, the problem shall be reviewed by appropriate levels of management until satisfactory resolution ir obtained.
3.3 Client or His Designee, or Regulatory Agency Audits Audits of construction site activities may be performed by the Client or his designee and/or appropriate regulatory agencies. If l
corrective action is required as a rescit of one of these audits, the Quality Assurance Site Supervisor or his designee from the Quality Assurance organization shall be responsible for obtaining a l
response from the cognizant individual (s) for submittal to the auditing body.
l l
4.0 FINAL VERIFICATION OF CORRECTIVE ACTION IMPLEMENTATION In addition to his other duties, overall responsibility for verification of the implementation of required corrective action rests with the Quality Assurance Site Supervisor or his designee from the Quality Assurance organization. He shall be responsible for performing this verification for all items indicated in Paragraph 3.0 of this Section, and shall assure that the corrective action is implemented and in a timely manner. In the event that there is a disagreement between those individuals who detect a deficiency and those responsible for the function found to be deficient, the Quality Assurance Site Supervisor shall contact appropriate higher levels of management as necessary until resolution is obtained.
0599d J
sios. *tstria os occe 4 or 4 l HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO 5mlCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoapoaaTeo QA-III-7 CORRECTIVE ACTION 5.0 DETERMINATION AND ANALYSIS OF QUALITY TRENDS 5.1 Ebasco's Corporate Trending In order to prevent the recurrence of quality problems, Ebasco has developed a method for the determination and analysis of quality trends. Copies of audit reports and Nonconformance Reports (or other appropriate documentation) mentioned above shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. The Quality Assurance Engineering Supervisor of Auditing subsequently receives all reports and makes an analysis of the available data with respect to quality trends. The trend analysis and distribution of subsequent reports shall be made in accordance with Quality Ascurance Procedure QA-D.3.
5.2 Client's Trending Copies of Nonconformance Reports (NCR's), Standard Deficiency Reports (SDR's), and Management Corrective Action Requests (MCAR's) shall be transmitted by the Site Quality Assurance organization to the Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Project Trend Program activity in accordance with their procedure (s).
l l
l I
l l
0599d
stos 2ttsTD10.e5 DQGE 1_ CF 3 HOUSTON LIGHTING AND POCER COMPANV SECTION SOUTH TEXAS PROJECT ESA5CO SERylCES ELECTRIC GENERATING STATION UNITS 1 & 2 i QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-III-8 CONTROL OF SPECIAL PROCESSES 1.0 SCOPE This Section of the Quality Assurance Manual establishes the requirements for the control of special processes at the construction site. Included herein are provisions for the establishment of critical process parameters, qualification of the processes, and training and qualification of personnel who perform the functions covered by this Section.
2.0 RESPONSIBILITIES 2.1 The Quality Assurance organization shall be responsible for the following:
2.1.1 Developing and implementing Site Quality Control procedures and for qualifying personnel to perform inspection of special processes.
2.1.2 Providing technical assistance for procedure review and development as required.
2.1.3 Qualifying personnel performing nondestructive examination.
2.1.4 Performance of audits in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.
, 2.2 The Materials Applications organization shall be responsible for the following:
a) Development and qualification of welding procedures.
b) Providing technical assistance for procedure review and development as required by Site Quality Assurance and Site Quality Control.
c) Qualification of welders and welding operators.
d) Development of heat treating procadures.
1 2.3 The Construction organization shall be responsible for the following:
2.3.1 Implementing welding and heat treating procedures.
0599d
s t os.2 HsTRO45 eact 2 or 3 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT i ELECTRIC GENERATING STATION UNITS 1 & 2 I"*5CO 5"""CIS QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaaTro QA-III-8 CONTROL OF SPECIAL PROCESSES 2.3.2 Developing and implementing procedures for other activities classified as special processes (eg, cadwelding, chemical cleaning, flushing) and for qualifying personnel to perform those functions.
2.4 The Ebasco Site NDE Laboratory, an extension of the Materials Engineering Laboratory, is responsible for developing and implementing nondestructive examination procedures.
3.0 METHODS FOR CONTROL OF SPECIAL PROCESSES 3.1 Site Special Process Procedures I
3.1.1 Nondestructive examination procedures used at the construction site shall be developed by the Site NDE Laboratory and shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee, to assure compliance to the requirements of all applicable codes and standards, as a minimum. Conformance to i
these procedures and qualification requirements shall be verified through audits and surveillances performed by Site Quality Assurance.
3.1.2 All welding procedures used at the construction site shall be l
prepared by the New York Materials Applications organization. The weld procedures test material shall be prepared either at the home office or the construction site according to instructions for qualification provided by the New York Materials Applications I
organization.
3.1.3 Construction procedures for site implementation of welding and heat treating requirements shall be developed by the Site Welding Superintendent or his designee.
3.1.4 All welders installing safety-related components shall be qualified according to appropriate codes and standards. Walder qualification shall be performed by the Site Welding Superintendent or his designee. Verification of conformance to procedure and operator qualification requirements shall be performed in accordance with site procedures by Site Welding Superintendent (or his designee) surveillance, Site Quality Control inspection, and/or Site Quality Assurance audit and surveillance functions.
0599d
esos.zus mio-as once 3 or 3
~'
HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EB ASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoanomatto QA-III-8 CONTROL OF SPECIAL PROCESSES 3.1.5 All Construction procedures for site implementation of requirements for welding, heat treating, and other special processes shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee. All comments resulting from such reviews shall be resolved prior to procedure implementation.
4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
l 0599d
sios. nsrocas ocar 1 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaatec QA-III-9 QUALITY ASSURANCE AUDITS 1.0 Sc0PE Quality-related activities at the construction site and Ebasco home office are independently audited by the Quality Assurance organization. This Section establishes the requirements and guidelines for the preparation, performance, reporting, and follow-up of quality assurance audits as performed by Site Quality Assurance, home office Quality Assurance Engineering, and the Ebasco Management Audit Committee.
2.0 RESPONSIBILITIES 2.1 The Ebasco Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall assign qualified Site Quality Assurance personnel to perform audits of construction site i
activities.
2.2 The Quality Assurance Engineering Supervisor of Auditing shall assign qualified Quality Assurance personnel to perform home office audits of Ebasco site activities.
2.3 A committee chaired by the Quality Assurance Consulting Engineer shall conduct audits of the Ebasco Materials Applications and Quality Assurance organizations at the home office.
3.0 GENERAL REQUIREMENTS FOR AUDITS PERFORMED BY THE QUALITY ASSURANCE ORGANIZATION 3.1 Audit Personnel 3.1.1 Audit personnel shall be independent of direct responsibility for performance of the activity being audited.
3.1.2 Audit personnel shall be qualified to perfora quality assurance audits based on experience and training as described in Quality Assurance Procedure QA-G.3.
3.2 Training and Orientation 3.2.1 Audit personnel shall have experience and training or orientation to assure their competence for performing audits. The competence of personnel to perform audits shall be developed by one or more of the following. methods:
a) Providing personnel with working knowledge of appropriate regulatory documents, practices, codes, and standards.
0599d
sios.ausreads pace 2 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT L G NERADNG STADON UNWS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaarro QA-III-9
- QUALITY ASSURANCE AUDITS b) Training or orientation in general and specialized methods of planning and performing audits.
c) On-the-job training under direct supervision of a Lead
- Auditor.
3.2.2 The requirements for training and orientation of auditors shall be in accordance with Quality Assurance procedures.
I 3.3 Proficiency of Lead Auditors 3.3.1 Lead Auditors performing audits shall maintain their proficiency through one or more of the following methods:
a) Regular, active participation in the audit process.
b) Review and study of codes, standards, and procedures related to Quality Assurance Programs and program auditing.
c) Participation in orientation or training programs.
3.3.2 The Director Quality Assurance or his designee shall evaluate Lead Auditors in accordance with Quality Assurance Procedure QA-G.3 to assure that the Lead Auditors are maintaining their proficiency.
l 3.4 Scheduling of Audits 3.4.1 Audits shall be initiated as early in the life of the project or activity as practicable in order to assure timely implementation i
of the applicable Quality Assurance Program requirements, and to assure effective quality assurance during construction activities.
3.4.2 Audits shall be regularly scheduled on the basis of the status and safety importance of the activities to assure conformance to the Ebasco Nuclear Quality Assurance Program. Applicable elements of the Quality Assurance Program shall be audited by the home office Quality Assurance Engineering and the Ebasco Management Audit Committee at least annually or once within the life of the activity, whichever is shorter.
3.4.3 Audits performed by Ebasco Site Quality Assurance at the construction site shall be scheduled in accordance with the Standard Quality Assurance Procedures requirements.
1 0599d r-.,----- c-m._,--w - . _ . - , -m-_----_.r- .r_,___-_._ _ _ _ _ . - , _ _ - - _ _ - - _ _ , . ,.,.y ,. ,.- , - _ , - .,. . _ _ _ _ . . _ , , _ . - . , _ _ _ . _ _
4109 2f(STDk3.45 occe 3 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SENCE5 4
QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCoRPOR ATEc QA-III-9 QUALITY ASSURANCE AUDITS l
3.4.4 Supplemental audits shall be conducted when:
i a) Significant changes in the Quality Assurance Program are ande.
- b) There is evidence of significant noncompliance to the Quality Assurance Program.
c) An assessment of the effectiveness of the Quality Assurance Program is requested.
d) It is necessary to verify implementation of corrective
- action.
e) It is considered necessary by the Quality Program Site Manager.
3.5 Planning of Audits Preparation for audits shall include the development of a written 1
' audit plan of standard format which shall include or identify the following:
I a) Audit scope.
b) Requirements and applicable docuacnts.
c) Activities to be audited.
4 d) Organization to be audited.
e) Tentative audit schedule.
f) Approved written procedures and/or checklists which assure that
, the organisation will be audited to the extent necessary. These 1 procedures and/or checklists shall provide for verifying corrective action of deficiencies identified in previous audits.
Audit procedures and/or checklists may be developed as part of a general audit program and need not be unique for each audit.
i 0599d
sios.a usr o o cs ocos 4 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaareo QA-III-9 QUALITY ASSURANCE AUDITS 3.6 The Audit Team 3.6.1 The audit shall be performed by one or more individuals. A qualified Lead Auditor shall be established as the team leader for audits when teams are comprised of two or more auditors. When audits are performed by only one individual, that individual shall be a qualified Lead Auditor and considered to be the team leader.
The team leader shall be responsible for:
a) Orientation of the team.
b) Assuring communication between the team and the organization being audited.
c) Coordinating the preparation and issuance of audit reports.
d) Establishing the pace of the cudit.
3.6.2 The team leader shall assure that the team is prepared prior '
to performing the audit. Information such as appropriate procedures, manuals and prior audit reports shall be made available to the team members. Each auditor shall be provided with any appropriate audit plans, procedures, or checklists necessary to performing the audit.
3.7 Audit Notification The organization to be audited shall be notified of a scheduled audit and the scope of the audit. Such notification shall be given a reasonable time before the audit is to be performed.
j 3.8 Audit Performance 3.8.1 Checklists and/or written procedures prepared during audit planning shall be used to conduct the audit.
l 3.8.2 An informal pre-audit conference shall be arranged at the audit site in order to confirm audit scope and discuss the audit plan.
0599d
s ios.2nstpo4s pace 5 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcomaamarec QA-III-9 QUALITY ASSURANCE AUDITS 3.8.3 A post-audit conference shall be conducted to:
a) Inform those audited of the audit results.
b) Assure understanding of audit results.
3.9 Reporting of Audit Results 3.9.1 An audit report shall be compiled and shall be signed by the audit team leader. The audit report shall provide:
a) Description of the audit scope.
b) Identification of the auditors.
c) Persons contacted.
d) A summary of the audit results, including an evaluation statement regarding the effectiveness of the Quality Assurance Program elements which were audited.
I e) Detailed description of Quality Assurance Program deficiencies and causes thereof where possible.
f) Recommendations for correcting program deficiencies or improving the Quality Assurance Program, if possible.
3.9.2 The audit report shall be issued in a timely manner as defined in the applicable Quality Assurance procedure, but shall not exceed 30 days from the post-audit conference.
3.10 Audit Follow-up 3.10.1 A response to the audit report shall be prepared by the responsible individual and submitted within the required time period as established in the audit report, but shall not exceed 30 days. The response shall state the corrective action taken or to be taken, and the date of completion. The audit team leader, or another qualified Lead Auditor or the management of the auditing group shall review the response for acceptance. As necessary, subsequent responses may be required to verify completion of corrective action.
l 0599d l
l
[
coseusvoo4s poor 6 or 8 HOUSTON UGHTING AND POWER COMPANY SECTION
' SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EB ASCO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaa rec QA-III-9 QUALITY ASSURANCE AUDITS 4
4 3.10.2 Follow-up action shall be performed by a qualified Lead Auditor to:
a) Assure that the written reply to the audit report is received.
b) Assure that corrective action is identified and scheduled for each program deficiency.
c) Confirm that deficiencies are resolved and corrective action, when necessary, is accomplished.
3.10.3 Follow-up action may be accomplished through written communication, re-audit, or other appropriate means.
j 3.10.4 Follow-up action taken shall be documented.
3.11 Trend Analysis of Audit Reports The Quality Assurance Engineering Supervisor of Auditing shall make an analysis of the available data (such as the audit reports mentioned above) with respect to quality trends, and report the result of the analysis. Distribution of the trend analysis reports shall be made in accordance with the requirements of Quality Assurance Procedure QA-D.3.
4.0 SPECIFIC AUDIT REQUIREMENTS l 4.1 Management Audits 4.1.1 A committee chaired by the Quality Assurance Consulting l Engineer is responsible for conducting audits of Ebasco Materials Applications and Quality Assurance functions to determine compliance with the Ebasco Quality Assurance Program requirements.
This committee is made up of personnel not in the Quality Assurance organization and who are qualified in accordance with criteria
! denoted in Ebasco Nuclear Procedure N-24. These audits will also include evaluating quality assurance policy effectiveness and assuring that appropriate implementing procedures are available and are being complied with.
i a
0599d 9
..ew, .-....n. - , e..,_,,-n. , .---.-,-.....,,m.,,..,,,-- - - - - , - . - . . . . , . --- - , _ _ - , - - . , , . , , , - . . , - , , , _ _ - - , , - , , , _ _ _ , . . .
s ios.m sins-as pace 7 or 8 HOUSTON UGHTING AND POWER COMPANY $ E CTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SEMICES QUALITY ASSURANCE PROGRAM DESCRIPTION - t' ART C mcom poa A T eo QA-III-9 QUALITY ASSURANCE AUDITS ,
4.1.2 This auditing shall be accomplished on an annual basis in accordance with the requirements of Ebasco Nuclear Procedure N-24.
The management audit committee shall be comprised of at least two qualified representatives from either Ebasco Constructors Inc or Engineering, and the QA Consulting Engineer. Each committee representative shall be appointed by the respective group Vice President; however, no committee member can be directly engaged in any policy-making or administrative phase of the Ebasco Quality Assurance Program, but shall be knowledgeable in the general area of l quality assurance. The committee shall be directly responsible to l the Vice President Corporate Quality Programs.
4.1.3 The committee shall prepare an audit report for each audit performed. This report shall be submitted directly to the Vice ,
j President Corporate Quality Programs, with copies to other
'I appropriate parties.
i 4.1.4 The Vice President Corporate Quality Programs shall be j responsible for informing the concerned Ebasco management of the I
results of the audits performed by the committee. He shall also be responsible for initiating the implementation of any changes or corrective action deemed necessary to improve the effectiveness of the Ebasco Nuclear Quality Assurance Program.
4.2 Audits by the Quality Assurance Organization 4.2.1 Site Quality Assurance shall audit the various quality-related activities performed by Ebasco organizations on the construction site in accordance with the requirements of this Section, the applicable Site Quality Assurance Instructions, and the Standard Quality Assurance Procedures.
4.2.2 Training and qualification records for Site Quality Control personnel shall be audited in accordance with Section QA-I-3, Paragraph 8.0, of this Manual.
4.2.3 Quality Assurance auditors shall have the authority to reject items, services, or work for nonconformance to the specification, drawing, or quality control requirements.
4.2.4 Home office Quality Assurance Engineering will conduct periodic audits and evaluations of the construction site annually in accordance with this Manual and Quality Assurance Procedure QA-D.5.2.
0599d l__ , _ .._ ___. _ .. . _ _ _ _ . _ _ _ . _ . . _ . ~ . _ . . _ _ _ _ _ . . - . - _ _ - - . _ - , _ _ .
s to s.21(ST PO-45 POGE.__O,_ QF 0 HOUSTON UGdTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTPIC GENERATING STATION UNI T5 i & 2 EBASCO SERVICE 5 QUALITY ASSURANCE PROGRAM DESCR:PTION - PART C mcoRPORATEo QA-III-9 l QUALITY ASSURANCE AUDITS 5.0 AUDIT RECORDS 5.1 Records generated during audit preparation, performance, or follow-up shall be retained for all audits in accordance with the applicable requirements of Section QA-I-6 of this Manual and/or approved Quality Assurance procedures. Such records shall include:
a) Audit plans and checklists.
b) Audit reports.
c) Written replies to audit reports.
d) Status of required corrective action.
e) Other documents which support audit findings and corrective action as appropriate.
5.2 Records of training and experience of auditors shall be maintained for c11 personnt.1 who are performing audits or who have previously performed audits. These shall be retained for the same period of time as required for the audit reports with which the auditors are associated.
Maintensuce and retention shall be in accordance with Quality Assurance Procedure QA-G.3.
i l
l 0599d
u os.aits w i4.es pace 1 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E5ASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoa.om a t e c QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS 1.0 SCOPE 1.1 This Section establishes the requirements for the identification and control of safety-related items at the construction site.
1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.
2.0 RESPONSIBILITIES i
2.1 Site Quality Control shall be responsible to perform the following l functfons in accordance with written procedures:
a) Assure that items received from the Client or his designee at the construction site are properly identified and are accompanied by appropriate documentation traceable to the items.
b) Assure that all items shall be physically identified in accordance with Paragraph 3.0 of this Section of the Manual, and appropriate written procedures.
j c) Assure that identification of items shall be transferred to j inspection and test records and as-built documents in a manner
! sufficient to provide the required traceability.
d) Assure that items are handled and stored in accordance with the requirements of Section QA-III-14 of this Manual so as to maintain identification.
2.2 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to assure compliance to the requirements of this Section.
3.0 CENERAL 3.1 Documented Quality Control procedures require that items shall be physically identified by the following means, as applicable:
a) Stenciled or etched markings b) Strip markings 0599d
sios-austrocs pace 2 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoaatco QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS c) Imprinted tape d) Tagging e) Stamping f) Color-coding g) Records traceable to the items h) Procedural control
- 1) Other appropriate means in accordance with approved Site Quality Control procedures
{ 3.2 When it is impractical to physically identify individual small items, these may be identified as to heat numbers, batch, lot, or specification by applying markings to bags, bins, tanks, or other suitable containers.
3.3 Identification of items shall provide the required degree of traceability to pertinent documents.
3.4 All markings shall.be clear, unambiguous, and indelible and shall not affect the function of the ites when applied.
l 3.5 When an ites is subdivided, markings shall be transferred to each part of the ites.
3.6 Markings shall not be obliterated or hidden by surface treatment or coatings unless other means cf identification is substituted.
3.7 All safety related items r. a materials shall be controlled by one or more of the followings a) Uniquely identifiable and traceable.
b) Physically marked items are not traceable but readily retrievable.
c) Physically identified as to type and users tested.
d) Identifiable as to type, by some physical characteristic or other administrative control.
0599d
/
sios.stistoi44s paos 3 o.r 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C inconpomarzo QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS l
4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
I e
0599d
oos4cstaa4s pace 1 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICE 5 QUALITY ASSURANCE FROGRAM DESCRIPTION - PART C mcom poR ATE e QA-III-11 INSPECTION 1.0 SCOPE This Section establishes the requirements for the inspection of safety-related items and services at the construction site as necessary to assure compliance with dcrumented instructions, procedures, specifications, drawings, codes, and regulatory requirements.
2.0 _ RESPONSIBILITIES 2.1 Site Quality Control shall be responsible for the following:
a) Development bf written procedures for the inspection of safety-related items and services which list the required inspection activities when existing inspection documents such as standard specifications and drawings do not provide an adequate basis for inspection.
b) Submittal of insphetion procedures to Ebasco Site Quality Assurance for revi'aw and acceptance in accordance with Section QA-III-1 of this Manual.
c) Preparation of reports for all inspections made.
d) Approval processing of inspection procedures and revisions thereto.
2.2 Site Quality Control shall be responsible for performing inspection activities in accordance with appropriate inspection documents.
2.3 Qualification of inspection personnel shall be in accordance with applicable Quality Assurance procedures and Paragraph 4.0 of this Section of the Manual.
2.4 The Quality Assurance Site Supervisor or his dasignee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance with the requirements of this Section.
l 3.0 GENERAL l
3.1 Inspection documents shall be prepared based upon the quality requirements contained in specifications, quality control documents and
- procedures, and applicable codes and standards.
0599d
l stosainTDeas poo2 2 or 3 i HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 EsAsco sERwcEs QUALITY ASSURANCE PROGRAM CESCRIPTION - PART C mcompoa A TEo QA-III-11 INSPECTION 3.2 If mandatory inspection hold points are required, the specific hold points shall be indicated os the inspection documents.
3.3 Inspection documents shall specify or reference as a minimum the activities to be performed, acceptance criteria, by whom activities are performed, and the sequence in which the activities are to be performed.
3.4 Where mandatory inspection hold points are indicated on inspection documents or procedures, work may continue beyond a hold point only with j ths written approval of the Quality Centrol Site Supervisor or his qualified designee.
3.5 Inspection reports shall indicate the acceptability status of the items or services inspected with respect to meet.ing the applicable j quality requirements.
] 3.6 When inspections are to be performed by use of a sampling progras
- (ie, to determine the acceptability of a group of like-items based upon the results of an inspection of a representative number of items from the group), the sample size shall be identified on the inspection documents.
Justification for this sampling shall be based upon recognized standard construction practices and successful past experience, as well as the complexity and function of the activity, ites, or service to be inspected.
4.0 TRAINING AND QUAI.IFICATION OF INSPECTION PERSONNEL 4.1 Inspection personnel shall have experience and training to assure their competence for performing inspection. The competence of personnel to perfora inspections shall be developed by one or more of the following i methods:
a) Providing personnel with working knowledge of appropriate regulatory documents, practices, codes, and standards.
4 l b) Training or orientation in general and specialized methods of planning and performing inspections.
c) On-the-job training under direct supervision of an experienced, i qualified inspector.
i
)
4 j 0599d 3
cosaustones pace 3 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoa Arco QA-III-11 INSPECTION 4
1 4.2 The requirements for training and qualification of inspectors shall be in accordance with applicable Quality Assurance procedures, and qualification of inspectors shall be based upon consideration of the following:
a) Records of education and experience.
b) Test results, where applicable.
c) Results of capability determination.
4.3 Site Quality Control shall be respcasible for scheduling and coordinating training for quality control personnel in advance of implementation of the applicable inspection documents. This training shall be conducted in sufficient detail and with sufficient frequency to assure that the personnel responsible for the inspection fully undersrand j the requirements contained in the applicable inspection documents.
t 4.4 Inspectors performing inspections shall maintain their proficiency 4
through cne or more of the following methods:
a) Regular, active participation in the inspection process.
a b) Review and study of codes, standards, and procedures ralated to
- Quality Assurance Programs and program insplt:ction.
4.5 TheDirectorQualityAssuranceorhisdesigner[shallperiodically I
evaluate inspectors in accordance with applicable hur.lity Assurance procedures to assure that the inspectors are maigfatning their preficiency.
5.0 RECORDS 5.1 All inspection documents shall be maintained in accordance with Section QA-I-6 of this Manual.
5.2 Records of training, experience, and certification of inspectors shall be maintained for all personnel who are performing inspection or I who have previously performed inspections. These records shall be retained for the same period of time as required for the inspection reports with which the inspectors are associated.
0599d
I sios rusrp>s4s pace 1 or 2 HOUSTON LIGHTING AND POIER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsCo SERWCES
, QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompomarzo QA-III-12 TEST CONTROL I
1.0 SCOPE 1.1 This Section describes the system employed at the construction site which assures that tests required to demonstrate that items will perform satisfactorily in service are identified and documented. The requirements of this Section apply to all phases of the testing program at the construction site, including, but not limited to: functional 2
testing, proof testing, acceptance testing, and operational testing.
1.2 These tests shall be performed in accordance with written test i procedures which include or reference the requirements and acceptance limits contained in applicable design documents.
2.0 RESPONSIBILITIES 2.1 Site Quality Control procedures shall provide for the following:
a) Assuring that all prerequisites for the given test have been met.
b) Use of trained personnel to witness tests.
c) Identification of test equipment and the ites to be tested.
)
d) Checking the condition of test equipment and the item to be tested.
e) Use of devices calibrated in accordance with Section QA-III-13 of this Manual for the performance of tests.
f) Verification that tests are performed under proper environmental conditions; eg, claan11 ness.
I g) Documentation of test results.
j b) Acceptance criteria for test requirements.
, 2.2 Site Quality Assurance shall review and comment on the written i
procedures for tests covered by this Section. All comments shall be resolved prior to implementation of the procedures. These test procedures shall be reviewed in accordance with Site Quality j Assurance procedures and/or instructions for the inclusion of:
l a) Provisions for assuring that all test prerequisites have been set.
a 0599d i
e sos.2ttsTDO as pace 2 or 2 HOUSTON UGHT'NG AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESASCO SENCE5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcon aoa ATeo QA-III-12 TEST CONTROL b) Identification of items to be tested.
c) Identification of calibrated devices or equipment to be used during testing.
d) Provisions for checking condition of test equipment and item to be tested.
e) Proper environmental conditions under which test is to be
, performed.
f) Test methods.
g) Operations to be performed.
h) Inclusion of, or reference to, acceptance criteria.
i
- 1) Data to be recorded. ;
1 j) Requirements for qualified and/or certified personnel.
2.3 Test reports shall be reviewed and signed-off by Ebasco Quality Control in accordance with written procedure f.equirements to assure that test requirements have been satisfied.
(
I 2.4 The Quality Assurance Site Supervisor or his designee from the Site l Quality Assurance organization shall be reappasible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure complianct4 to the requirements of this Section. !
3.0 RECORDS All records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
l i
0599d
sios-mstwoos paos 1 or 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA$CO SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoa ATeo QA-III-13 CONTROL OF MEASURING AND TESTING EQUIPMENT 1.0 SCOPE 1.1 This Section describes the interface activities between the Client and Ebasco for the purpose of providing Neasuring and Test Equipment (M&TE) and calibration services. This Section also describes the requirements of Ebasco's M&TE control for the equipment used at the construction site when performing tests and inspections of safety-related items.
1.2 Ebasco's activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.
2.0 RESPONSIBILITIES 2.1 The Client shall be responsible for the issuance and subsequent calibration of all measuring and testing devices.
2.2 The Ebasco Quality Control Site Supervisor or his designee shall be responsible to assure compliance with site implementing procedures for the control of user M&TE apparatus used by the Site Quality Control.
2.3 The Ebasco Site Manager or his designee shall be responsible to assure compliance with site implementing procedures for the control of user M&TE apparatus used by Ebasco Construction.
/ 2.4 The users shall assure that the seasuring and testing devices used are marked with the proper identification number and identified to their L calibration due date, and are of the proper range, type, and accuracy to
- verify conformance to established requirements.
.i
) 3.0 GENERAL 3.1 Measuring and Test Equipment issued from the Client to Ebasco shall be controlled in accordance with approved site procedures.
3.2 Methods shall be employed to assure proper handling, storage, and care of the M&TE in order to maintain its required accuracy.
l l
l l
0599d i
i
sios.ausrpa4s pace 2 or 2 HOUSTON LIGHTING AND POIER COMPANY SECTION
$0UTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICE 5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCOR,ORATre QA-III-13 CONTROL OF MEASURING AND TESTING EQUIPMENT 3.3 Any M&TE found to be out-of-calibration shall be returned to the Client. When M&TE is found to be out-of-calibration, damaged, lost, or stolen, an evaluation shall be made to ascertain the validity of previous inspection or test results and the acceptability of suspect items, the original required inspections and/or tests shall be repeated using properly calibrated equipment. Suspect items on which a questionable device was used shall be listed on the Nonconformance Report (NCR) or Deficiency Notice (DN), as applicable.
3.4 Inspection and test reports shall include identification of M&TE used to perform the inspections and/or tests.
3.5 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance
- of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance with the requirements of the
, Client's measuring and test equipment calibration program and the
) requirements of this Section.
4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
i e
i 0599d
sios.rustem es pace 1 or 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA$CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcom poa A T eo QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 1.0 SCOPE 1.1 This Section describes the methods employed during receiving, handling, storage, and installation to assure that all safety-related items received by Ebasco at the construction site will be usable when needed. These requirements apply to both items received by Ebasco from the Client or his designee and Ebasco site-fabricated subassemblies which require temporary storage before assembly or installation. They also apply to both on-site and off-site facilities which are used for the storage of items under control of the construction forces.
1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.
1.3 The storage of safety-related items maintained in facilities under the direct control of the Client or his designee is excluded from the scope of this Manual.
2.0 RESPONSIBILITIES 2.1 The Ebasco Construction organization shall be responsible for the following:
a) Performance of receiving, handling, storage, maintenance, and cleaning activities in accordance with specifications provided by the Client or his designee and/or code requirements.
b) Development of methods for special handling (off-loading) in accordance with manufacturer's recommendations and/or
~
specifications provided by the Client or his designee.
c) Establishing storage areas to meet levels as briefly described below:
- 1) Level A - Indoor, controlled environment.
- 2) Level B - Indoor, heated and ventilation controlled.
- 3) Level C - Indoor or equivalent, ventilation controlled.
- 4) Level D - Outdoor.
0599d
e sos.aitsma.es pace 2 Cr 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO 5mlCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE d) Development of general storage plans which list types of items and their intended storage locations and levels. Such plans shall be prepared prior to receipt of items from the Client or
, his designee.
2.2 Ebasco Site Quality Control shall be responsible for the following:
1
, a) Qualification of personnel performing inspection functions applicable to receiving, handling, and storage, b) Assigning qualified quality control personnel for performance of inspection and/or surveillance of receiving, handling, storage, maintenance, and cleaning activities.
! c) Performing and documenting inspection and/or surveillance activities in accordance with approved checklists to verify that
, receiving, handling, storage, maintenance, and cleaning
- activities, as described in Paragraph 2.1 of this Section, are i
performed in accordance with project requirements.
d) Establishing and implementing methods for rejection of nonconforming items which provide adequate means of identifying the item as nonconforming and physically segregating the item j where practical. When segregation is not practical, a status type indicator shall be used. Application and removal of status type indicators shall be by quality control personnel i only.
! 2.3 Ebasco Site Quality Assurance shall be responsible for the performance of audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.
l 2.4 The Client or his designee is responsible for procurement and
, initial receiving inspection of all safety-related items. However, if requested in writing by the Client or his designee to perform initial l receiving inspection of safety-related items upon their arrival at the l job site, Ebasco will conduct a complete program that covers the full parameters of this Section. Otherwise, Ebasco shall conduct a receiving inspection program as is applicable and in accordance with approved site i
procedures.
l t
i 0599d l
i
sios.austou os ocar 3 or 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXA5 PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERWCE5 QUALITY A$$URANCE PROGRAM 0ESCRIPTION - PART C mcoanomarzo QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 3.0 RECEIVING INSPECTION 3.1 Safety-related items utilised for fabrication, erection, 4.
installation, or modification shall be subjected to receiving inspection to assure conformance to the requirements of the applicable drawings, specifications, and other documents as required. Where source inspection is not performed, receiving inspection at site for acceptability will be performed.
3.2 Inspection Requirements Receiving inspection procedures shall be prepared by the Quality Control Site Supervisor or his designee in accordance with the requirements of this Manual. These procedures shall provide instructions and checklists for performing receiving inspection and shall include at least the following activities:
a) Documentation review to assure that the documentation package has been received and that a signed " Release for Shipment" form accompanies the items received, when applicable.
b) Visual examination.
c) Marking and tagging for traceability.
d) Testing when specified.
e) Preparation for storage.
4.0 HANDLING 4.1 Handling practices applied to safety-related items shall assure miniaun possibility for damage or loss of environmental protection.
4.2 Inspection Requirements Site Quality Control procedures shall provide for at least the following3 a) Review of handling requirements for safety-related items.
b) Performance of appropriate inspections to assure that handling operations have not jeopardized ites integrity.
0599d
' - - ---- ~"
6 --
sios.ausmus pace 4 or 5 HOU$ TON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICE 5 QUALITY AS$URANCE PROGRAN DESCRIPTION - PART C incompoarteo QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 5.0 STORAGE AND IN-PLACE PROTECTION 5.1 All safety-related items shall be stored in locations and storage levels as outlined below except for those items released from storage and placed in their permanent or staged locations which shall be cared for, maintained, and inspected in accordance trith design specifications and the applicable approved procedures. In place protection in permanent location is permitted for large items such as equipment, provided that the permanent location is ready for the ites installation. If the permanent location or the area in which the ites is staged does not afford the required level of protection, additional protection shall be provided to prevent degradation of the ites. For in place protection purposes, a permanent location shall be considered to be within the room and/or immediate vicinity in which the iten is to be permanently installed.
l 5.2 Inspection Requirements Site Quality Control procedures shall provide for at least the following:
a) Monitoring of the storage levels listed below:
- 1) Level A - Indoor, controlled environment.
- 2) Level B - Indoor, heated and ventilation controlled.
- 3) Level C - Indoor or equivalent, ventilation controlled.
- 4) Level D - Outdoor.
b) Monitoring maintenance of storage areas to control such items as
, the followings l
- 1) Physical condition of storage area.
- 2) Access to storage area.
- 3) Fire protection.
- 4) Prohibited materials.
I 0599d
e sos austrisos pace 5 or 5 HOUSTON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA$CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoa ATeo QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE c) Inspection of stored items and items protected in place to assure their integrity.
!~
d) Verification of general storage plans which list types of items and their intended storage locations and levels.
e) Monitoring of storage areas to maintain proper segregation of materials. Items shall retain an appropriate identification for retrievability and inventory control, as applicable to the nature and use of the material.
f) Monitoring of provisions for preservation of items, as required by special conditions.
g) Verification that the withdrawal of any component, assembly, system, or materials from the Client's or his designee's warehouse or storage areas shall be by the Requisition for Stored Items completed by the responsible supervisor or his designated representative. The request shall identify the
- asterial and applicable references to a drawing or specification.
5.3 The Client or his designee shall be responsible for the establishment.of storage levels, maintenance, and any other applicable handling and storage requirements.- The Ebasco Construction organization i
~
is responsible for developing and implementing procedures addressing these requirements.
l 6.0 RECORDS Records pertainfng to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
l 0599d
sico-m ustoi44s pact 1 or 2 I
HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsc0 SERVICE 5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C incoaaoaavro QA-III-15 INSPECTION, TEST, AND OPERATING STATUS 1.0 SCOPE 1.1 This Section establishes requirements for identifying and documenting the status of inspections and tests perforneo on safety-related items at the construction site and the status of the readiness of these items for turnover to the Client or his designee.
The Client or his designee is responsible for preoperational testing.
1.2 The activities described herein shall be performed in sccordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual. Procedures and instructions shall include identification and authority of the individuals or groups responsible for application and removal of status indicators.
2.0 RESPONSIBILITIE_S 2.1 Site Quality Control shall be responsible for the following:
2.1.1 Develop and implement a system for maintaining the status of safety-related items throegh the use of status indicators such as physical location and tags, mariings, work travelers, stamps, or inspection records. This system shall provide for the identification and maintenance of the status of inspections and tests performed on these items throughout fabrication, installation, and erection. This system shall provide methods which assure that only items that have passed the required inspections and tests are used or installed. Where physical tagging is either impractical or insufficient, procedural control or other appropriate means for maintaining item status shall be employed.
2.1.2 Control and maintain a log of the issuance and removal of l
status indicators such as tags.
2.1.3 Develop and implement plans for the witnessing and i
documenting the results of inspections and tests.
2.1.4 Provide methods for assuring that all required inspections and tests are performed (checklists, travelers, etc).
2.2 Construction shall be responsible for the following:
2.2.1 Develop and implement a system for marking and tagging to indicate those safety-related items which are in test, so as to prevent inadvertent operation.
l i
0599d
siosausten.as pace 2 or 2 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcom poa Ar ec QA-III-15 INSPECTION, TEST, AND OPERATING STATUS 2.2.2 Develop and implement a system for maintaining the status of all systems turned over to the Client or his designee for preoperational testing.
3.0 GENERAL 3.1 Quality Control procedures shall require that inspection and test status be maintained by the use of status indicators such as tags, markings, travelers, stamps, inspection records, work sequence plans, or other appropriate means.
3.2 The progress of fabrication, installation, erection, inspection, and test shall be entered on appropriate .iocuments. Provisions shall be made for updating these documents to reflect current conditions.
3.3 Nonconforming safety-related items shall be clearly identified and marked and shall be processed in accordance with Section QA-III-6 of this Manual.
3.4 Records of tests and inspection results shall be prepared and maintained in an orderly and systematic manner.
3.5 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.
4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.
l l
0599d
sios.a usrea.es pace 1 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA$CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORpQRATee Appendix I TERMS AND DEFINITIONS This Appendix contains certain teras and their definitions used in this Manual that are important to the uniform understanding of the Manual and its application. Where a term is used to convey a different intent than that related herein, clarification must be provided at the point of application:
ACTIVITIES AFFECTING QUALITY (Quality-related activities) - Activities affecting the quality of safety-related items, including designing, purchasing, fabricating, handling, shipping, storing, cleaning, erecting, installing, inspecting, and testing.
AUDIT - A planned and documented activity performed in accordance with written i procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of a quality assurance program have been developed, documented, and effectively implemented in accordance with applicable regulatory documents, guidelines, or requirements. An audit does not include surveillance or inspection for the purpose of process control or product acceptance.
AUDITS (INTERNAL) - Audits performed by Ebasco personnel on those Ebasco organizations that are governed by the Ebasco Quality Assurance Program.
CLIENT OR HIS DESIGNEE " Client" is defined as Houston Lighting and Power Company and "his designee" as Bechtel Energy Corporation.
I CONSTRUCTION OPERATION - Activities related to construction of a nuclear power station.
ERASCO HOME OFFICE - Office where project support and related functions are performed at Ebasco, New York.
INSPECTION - A phase of quality control which by means of examination, observation, or measurement determines the conformance of items or services to predetermined quality requirements.
INSTRUCTIONS - Written descriptions of activities to be performed, including job specificetions, work instructions, shop construction drawings, job tickets, planning sheets, operating or procedure manuals, test procedures, or other written forms, to assure that the activity is adequately described.
ITEM - Any level of unit assembly, including structure, system, subsystem, component, part, or material.
0599d
sios-a usre>s4s pace 2 or 3 HOU$ TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconcomarzo Appendix I TERMS AND DEFINITIONS NONCONFORMANCE - A deficiency in characteristic, documentation, or procedure which renders the quality of an item or service unacceptable. Items discovered to be out-of-tolerance of specification at routine checkpoints of an inspection process shall not be considered as a nonconformance, provided:
a) The conditions are corrected prior to acceptance of the work.
b) The work does not proceed beyond the checkpoint until the correction is made.
c) The condition does not affect work previously accepted.
d) No violation of procedure or Code is evident.
QUALITY ASSURANCE (QA) RECORDS - are those records which furnish documentary evidence of the quality of items and of activities affecting quality. A document is considered a quality assurance record when the document has been completed. QA records may be either the original or a reproduced copy.
QA RECORDS (LIFETIME) - are those records which meet one or more of the following criteria:
a) Those which would be a significant value in demonstrating capability for proper functioning of safety-related items.
b) Those which would be of significant value in maintaining, reworking, repairing, replacing, or modifying the ites.
c) Those which would be of significant value in determining the cause of an accident or malfunction of an ites.
d) Those which provide required baseline data for in-service inspection.
QA RECORDS (NONPERMANENT) - are those records which meet all of the following criteria:
a) Those of no significant value in demonstrating capability for safe operation.
b) Those of no significant value in maintaining, reworking, repairing, replacing, or modifying the ites.
0599d a
sios.austan4s pace 3 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC CENERATING STATION UNITS 1 & 2 E8ASCO $EWICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCoRPORATEo Appendix I TERMS AND DEFINITIONS c) Those of no significant value in determining the cause of malfunction of an ites.
d) Those which do not provide baseline data for in-service inspection.
QUALITY TREND - A consistent reporting of conformance or nonconformance with applicable criteria attributed to a specific organizational unit.
SAFETY-RETATED ITEM - Any iten designated by the Client or his designee, in accordance with the guidelines established by the Licensing Department of the Client or his designee, to be Safety Class 1, 2, 3, Seismic Category I, or electrical Class IE and any other items as desig2ated by the Licensing Department and indicated as safety-related in the PSAR or FSAR.
SERVICE - Performance of nuclear safety-related activities such as fabrication, inspection, nondestructive examination, installation, and test.
SPECIAL PROCESS - A special process is a fabrication, testing, or inspection operation whose correct performance is governed by parameters established during qualification testing for the operation, eg, welding and nondestructive testing.
t I
1 0599d
siosaitsim44s paoc 1 or 6
)
HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO SERVICES
'"C0""0"^7E QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGUIATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1 i
EXCEPTIONS TO ANSI N45.2.5-1974:
- 1. ANSI N45.2.5-1974, Section 4.8, states " Pumped concrete must be sampled from the pump line discharge." In lieu of this statement, in process strength samples of pumped concrete are taken at the delivery point.
Correlation tests of air content, slump, and temperature are performed to verify these plastic properties of the concrete at the placement point in accordance with the following frequency requirements:
A. A minimum of two correlation tests are performed for each pumped placement exceeding 200 cu. yds.
B. OtherC se, a minimum of two correlation tests per week are performed when any individual pumped placement during a week requires delivery of more than one truckload of concrete.
1 C. During a week when a pumped placement exceeding 200 cu. yds. is made, the correlation tests performed on that placement will satisfy the weekly requirement for performing two correlation tests as specified in Item B above.
If the correlation test result shows a concrete property not meeting the specification limits and/or tolerances at the point of placement, the frequency of correlation testing shall be increased to 100 cubic yards.
If two consecutive correlation tests exceed the specified limit for i slump, air content, or temperature, the Constructor shall document the condition, notify Bechtel Site Engineering within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of completion of the placement and shall return to control of the concrete by in process testing at the point of placement per ANSI N45.2.5-1974.
" Correlation Testing," " Delivery Point," and " Placement Point" are as defined in ANSI N45.2.5-1978, Section 1.4.
- 2. Samples and frequency for cadweld testing is in accordance with ACI-359-ASME Section III, Division 2, issued for trial use and comment in 1973, including Addenda 1 through 6 (see Sections 3.8.1.6.3 and 3.8.3.6.3 of the South Texas Project Final Safety Analysis Report).
1 0599d
stos.81tsTP)4 85 pace 2 o, 6 HOUSTON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXAS PROJECT ELECTRIC CENERATING STATION UNITS 1 & 2 EBASCO SENCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mecanoaare Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1 EXCEPTIONS TO ANSI N45.2.1-1973:
- 3. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality. This is consistent with Section 2, Paragraphs 2 and 3, of ANSI N45.2-1971 which
- provides for examination, measurement, or testing to assure quality or j indirect control by monitoring of processing methods. However, final cleaning or flushing activities will be performed in accordance with procedures specific to the system.
- 4. Section 4, Pre-Installation Cleanness. This section states, " Items should not be delivered to the point of installation site sooner than necessary unless the installation location is considered a better storage l area." As an alternate to this requirement items may be delivered to the l installation site sooner then absolutely necessary when determined to be advantageous for other considerations, for example, reduced handling or easier access, thereby reducing susceptibility to handling damage. In
! all such cases, equipment stored in place will be protected in accordance with Section 5 of ANSI N45.2.1-1973.
- 5. Section 3.1.2, cleanness Classifications - Class B. Ebasco interprets the lighting level of 100 footcandles to be guidance. It is Ebasco's normal practice that the lighting level for determining " metal clean" of accessible surfaces of piping and components is determined by the inspector. Typically he uses a standard two-cell flashlight supplemented by other lighting as he deems necessary.
EXCEPTIONS TO ANSI N45.2.2-1972:
- 6. Section 2.7, Classification of Items. The four-level classification system may not be used explicitly. However, the specific requirements for each classification as specified in the standard will be applied to l
the items suggested in each classificatior and for similar items.
Classification differing fron Section 2.7 will be considered acceptable provided no degradation is assured; for example, electric motors designed for outside service may be stored in Level C area rather than a Level B.
0599d
6109 21fSTP!4C5 DQGE or 6 HOU$ TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C
- C """"" Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1
- 7. Section 6.2, Storage Areas. Paragraph 6.2.1 requires control and limited access to storage areas. In lieu of and to amplify this paragraph, the following will be applied:
" Access to storage areas for Levels A, B, and C will be controlled by the individual (s) responsible for storage. While the above areas will be posted to limit access, other positive controls (other than that for the overall site area) or guards may not be provided. Level D areas will be posted with the storage level designation only."
- 8. Section 5.5, Correction of Nonconformances. This section provides for
" rework" and "use-as-is" dispositions for nonconforming items. As an alternate, the " repair" disposition (as defined in ANSI N45.2.10-1973) will also be used.
- 9. Section 6.2.4, Storage of Food and Associated Items. Controlled areas, within storage areas, will be established for the storage of food, drink, and salt tablets. These areas will be controlled through normal supervision and inspection.
- 10. In Section 8, the control of documentation and records shall be in accordance with Section QA-I-6 of the Ebasco Nuclear Quality Assurance Program Manual for the South Texas Project.
l
- 11. Appendix A3.4.2, Inert Gas Blankets. There may be cases involving large or complex shapes for which an inert or dry air purge flow is provided rather than a static gas blanket in order to provide adequate protection due to difficulty of providing a leakproof barrier. In these cases a positive pressure purge flow may be utilized as an alternative to the leakproof barrier.
EXCEPTIONS TO ANSI N45.2.3-1973:
- 12. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans
+
will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achiave required quality.
0599d
T sios ausrow.es ococ 4 or 6 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoanteo Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGUIATORY GUIDES AND ANSI STANDARDS TNDTPATRD TM RRETTOM OA-T-1
- 13. Alternative equivalent zone designations and requirements may be utilized to cover those situations not included in the subject standard; for example, situations in which shoe covers and/or coveralls are required but material accountability is not. In addition, zones might be combined into the next more restrictive category in order to reduce total number of zones.
EXCEPTIONS TO ANSI N45.2.4-1972:
- 14. Section 1.2, Applicability. The standard is applied to the items and systems identified in Paragraph 1.1.1 and to additional systems depending on the nature and scope of the work to be performed and the importance of the item or service involved.
i
- 15. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspections and testing which meet the requirements of the standard.
Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
EXCEPTIONS TO ANSI N45.2.8-1975:
- 16. Section 1.1, Scope. The term "important items" will be interpreted to apply to those activities or quality attributes of an item or service that could affect a nuclear safety-related characteristic. For example, if a barrier is required for leakage control, but serves no structural function, the leaktight characteristic would be considered "important,"
but appearance, dimensional requirements, and structural features would not necessarily be considered important; or if a pump casing is required for coolant boundary integrity, but the pump does not have to operate to provide for nuclear safety, those attributes which affect its operation would not be considered important from the standpoint of nuclear safety.
Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.
Individual plans for each ites or system are not normally prepared unless the work operations are unique. However, standard procedures or plans 0599d
sios.atisTeus pace 5 or 6 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICE 5 QUALITY AS$URANCE PROGRAM DESCRIPTION - PART C
- "" "^ Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1 e
will be reviewed for applicability in each case. Installation plann or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.
- 17. Section 3.3, Processes and Procedures. The terms " installation site,"
" installation area," and " site" used in this standard shall be interpreted as follows:
a) " Installation site" or " site" will be interpreted the same as
" construction site." When applied to documents, these may be at the central office or work area document control station.
b) Installation area - Immediate proximity of location where work is to be performed.
I
- 18. Section 3.5(e), Site Conditions. This requirement will be applied only if subsequent correction of adjacent nonconformances could damage the item being installed.
Section 4.6, Care of Items. HL&P retains the authority and is the
" Responsible Organization" for temporary usage of equipment or facilities unless specific (ie, on a case-by-case basis) or general authority is granted in writing to the Construction Manager's organization.
( EXCEPTIONS TO ANSI N45.2.9-1974:
i
- 19. Section 1.4, Definitions. Quality Assurance Records - A document is considered complete when it has finished full processing and has been issued for use in design, procurement, construction, or manufacturing.
- 20. Section 1.4, Definitions. Authenticated Records - Those records which are clearly identified as a statement by the individual or organization holding responsibility. Handwritten signatures are not required if the document or printout is clearly identified as a statement by the reporting individual or organization.
- 21. For Appendix A, an installation shall be considered to be in an "as constructed" condition if it is installed within the tolerances established by Project Engineering indicated in the design output documents.
0599d
sios-a usmo os pace 6 or 6 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 ESA5CO SERVICES QUALITY A$$URANCE PROGRAM DESCRIPTION - PART C n.compoaATE Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1 EXCEPTIONS TO ANSI N45.2.12-1977:
- 22. ANSI N45.2.12-1977, Section 4.5.1, states, "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed." This implies that the audited organization must provide the auditing organization with written notification detailing what corrective action was taken sud when the corrective action was completed.
In actual practice, the audited organization will provide the auditing organization with documented corrective action including the date when the corrective action will be completed. The auditing organization will evaluate the corrective action response to determine if corrective action verification is necessary. If verification is necessary, the corrective action verification will be performed after the scheduled completion date and the result of the verification will be documented.
- 23. ANSI N45.2.12-1977, Section 1.3 states, "In no way shall the performance of audits by an organization diminish the responsiblity of the audited organziation or contractor for audit of his designated portion of the quality assurance program or the quality of his product or services."
For the South Texas Project all quality-related activities implemented for the South Texas Project are audited annually at a minimum, or at least once within the life of the activity, whichever is shorter. These audits are performed by either Houston Lighting & Power Company (HL&P), Bechtel Energy Corporation (BEC), or Ebasco Services Incorporated (ESI) Quality Assurance personnel.
EXCEPTIONS TO ANSI N45.2.6-1973:
- 24. As an alternate, compliance with ANSI N45.2.6-1978 and R.G. 1.58 (Rev 1, 9/80) in its entirety is acceptable.
0599d
sios.ausroa4s pace 13 ,,13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO 5ERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C inconpoa*Tro QA-I_2 ORGANIZATION AND RESPONSIBILITIES 6.0 ORGANIZATION CHARTS The following figures apply to this Section:
Figure No. Title Revision I-2.1 Deleted -
lR15 I-2.2 Corporate Quality Programs Organization 8-STP lR15 I-2.3 Deleted -
I-2. 4 Organization for Construction 7-STP lR15 I-2.5 Deleted -
I-2.6 Quality Assurance Organization 7-STP lR15 I-2.7 Quality Assurance Engineering Quality Assurance Specialists 6-STP I-2.8 Deleted -
I-2.9 Interface Between Houston Lighting &
Power Company, Bechtel Energy Corporation, and Ebasco Services Incorporated 5-STP lR15 0598d
Ebasco Services incorporated CORPORATE QUALITY PROGRAMSORGANIZATlON CHAIRMAN I
VICE PRESIDENT CORPORATE QUALIT Y PROGRAMS I
I I I I CH AE F DIRECTOR CHIEF VE400R MATER ALS MATE RI ALS OUALITY OUALITY ASSURANCE ENGINEERING ENGINEER ASSURANCE REPRESENTATIVE LABORATORY I l MANAGER MANAGER VENDOR NOE LASOMATORY
" MAT ERI ALS QUALITY ASSURANCE = OUALITY ASSURANCE SUPERVISOR OUALITY ASSURANCE ANO STAF F ENGINE E R S PROJECTS ENGINEERING SUPERVISORS l I I
- OUALITY ASSURANCE PROJECT VENDOR QUALITY ASSUR ANCE l
- WE LOING OUALITY ASSURANCE ENGINE ERING OUALITY ASSURANCE COhSULTING -
l ENGINEERS SUPERVISOR 5 SUPERVISORS & REPRESENT ATIVES ENGINEER j SPECIALISTS ENGINEERS & STAFFS MANAGER
- QUALITY $$URANCE "m#0E =
SERVICES SE R VICE S I I MANAGER SITE ISl/NOE QUALITY ASSUR ANCE SUPERVISORS SITE SUPERVISORS g
& STAFFS STAFFS A ER SENIOR CONSULTING
- SIT OUALITY ASSURANCE =
SITE SUPERVISORS ENGINEER & STAFF AND STAF F S
. NOT APPLICABLE TO THE5TP OU ALITY PROGR AMS ORGANi2ATION
.* REPORTS FUNCTIONALLY TO THE OUALITY CONTROL SITE SUPERVISOR FIGURE I-2.2 REV 8-STP
( ' - - - -. ._ _ __ _ _ _
Ebasco Services incorporated ORGANIZATION FOR CONSTRUCTION ADAPTED FOR HOUSTON LIGHTING & POWER COMPANY SOUTHTEXAS PROJECT ELECTRIC GENERATweG STATION UNITS 1 & 2 PRE SIDE NT E 8ASCO SE RvlCE S INC.
I PRE SIDE NT E S ASCO CONST RuC TOR $
INC DIRECTOR MAN AGE R O' OUALIT Y CueE F CONST RUC TION MATERsALS ASSURANCE OUALIT Y E NGiNE E R NEW YORK Nga yong e _ _seeeeeeeeeeeeeeeemes se eeeemeseemeeseemesseememeesmesem wmeesse. esseenmmeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee* maneumesee mmusem
$1TE gey g e
CONSYRUCiION MANAGER
-e-.-.-e- e I I I I I _,_,_,_
- e o OUALITV PROGRAM DISCIPLINE NA E R 07 gwery SENIOR sv5TEMS STARTup
' ' , Se T E SITE MANAGER $ $UPE RINT E NDE N TS RE 5sDE NT COM*L E IION SUPPOR T WE LDING MANAGER SECURl V E NGINE E R MAN AGE R CUPE RIN T E NDE NT SUPE RINT E NDf NT I
mn fTI M
- C C)
C N SITE PE RuANg NT I M F ABRIC ATBON l" 251RUC1 SON LINE SUPE RvelaON PLAN 3 N 8V' --.-. p%mm COORD TORS REPRES N Tevt , ,",TuTf kD v Wt ,$T 8 ,N'
. Stur Wore Au .,R .,
e
. 4
EBASCO SERVICES INCORPORATED QUALITY ASSURANCE ORGANIZATION i
D684f CIDR fR f At 11 v AMI)ft ANf.f l ,
.I _
1 l l MANAGIR MANAGfR MANAGER 5t NeOR MANAGfR ggypd%Ut IWG OUAL 4IV OtJAL STY OUAt IIV AS4t sft Apot.f AR%URAff0f II3 00I II' A$$URA9sCE PROJG f. I t 8 0eGefuli RING 5t RVSCI $ A A l Sill 50 AvaCES y g, gg q
_ . _ _ _ ..I . .- I -- ..
I, .,
I MANAGEtof NI & MAadAGE het N T 4 SUPtRVessNG SUPf RV15aNG MANAUIRS HOAt eI v MANAGIR CON 5U4 IING esa NOF
$ NGINE E R$ (88Gl88f f R$ ONif RNATIONAt """"^" MANAGEMENI& MANAGfMfNT4 OUAt ti v satt Ossately OUAt t T V OUALIT Y AREA Sif t MANAGf R St8PE R VISORS SUPfRVf9)R$ A$5URAmeCf A55URApsCf A%$UR ANC E AS$URANCF E NCetteti RS
- PROff C15 t $dGINF f RING --- - - - - - - ---- . ~ . - --- -- U
,_. . - - - ~
esse n=at aucem A158$f ANI PROJf CT OUAt LIV OUAtlTV $8 8(
' veescon evasuarseas e ASSURANCE OtaAt tiv F '
CONIROL RfCORDS A$$URANCE Ouataf,y.8 As,inumCES E & $4IE ilIE ""'"'"'
f.4GINE E RS SUPI R VISOR $tsPt RVISOR manece'a" wet $UPl R VISOR SUPT RVISORS f NGING f R5 nPenatenes sa e -* ~ ~ ~ '- ~~ ~ ~ '
OuateIv atconOS anamaceasent o
-- faseso assas vses e
OuAttiv 415URAmeCf INGIref f R$ ~ --- ---- - - - - -- .
OUAtlTV OtJALIT Y OUAttiv $11f Ot#ALIIV RfCutATORy i
A55U8tafsCE A%SUR ANCE C(WI ROL E ORDS AS$41RA W / M AWf N 5T RUCIM R5 WIRE MW $
! f RfGt8ef f R$/ INGINt f RS/ f PsGINf ER$/ f NGlastiRS/ QUALIf Y COnsTROt INSPt C TION f N AMINAItON INDUSTRV CODI% g SPECIALISTS SPf CI Atl515 SPfCsatts15 SPfCIALISYS f eeGsNf f R$/ $PE CI ALISYS 5Pf C0 At t$15 &$fANDARD% g SPEC 44 TESTS ADMINe%f Ra tsON ,
O ees0T APPLGCAAlf TO tesE Sir N OUAL0TV ASSUIsassCE ORGas sfAfgose H
C) #
. C N,
(/) N N6 N f4 -
e
EBASCO SERVICES INCORPORATED QUALITY ASSURANCE ENGINEERING QUALITY ASSURANCE SPECIALISTS on.ECIO.
(.m ,
assu.t asect e ty I _1 _ _l
,= -.
-. c ma ==
== a s,a.tt.i,y a
,y,,',,8,,
. os cs c=.
i . _ I __ _
1__, ..__ i i
1 . .
cuaanry assu asecs
. mat.svy....G =sou. css = co= orgou.a.ri.oseas y
,=,, es avets soo,n,os,s,,r.u,c,,s,e,va an ,a EsaA,sa.G oe.st N.9 . amu.fla,d.s[G.
M .c .v6,o,, M avr5Dft 88 ha( E oA.AE k.l su V o I I I I I I __ _ _. _. . . _ _ _ _
1 I o,. .a e.o m,= o cs IDElou tgg
,y I =Co aNc0 gg g,g,
= = .va ==.v== .
agot
=c.s.oE...
O G
= c.e.of.m o.ca,a,,.o ==aaa"I aa'"O au=.sv --- - -am.oS.e (B,at.e.f.v a.m.u a,,,,
=,,, = ==*=ai = == - '= aa c. . . v s. . no .
=c. .m = ==iar~ :
-. -6 m .. o.
o.
AuoelessG i
._l I
_.._1____. __. . _ . .
oo. * = ie ==
ou..,vam.u.a Simpson og c.
, , . . , , , , , tv=Uaf sose .AUostessG El
- I G.ou,oGaade L8 aos .
I I3 G.esto, Games .
ou t4act gatVELo ygb(Kl,au.gg astlef 8
_ . _ _, __3
.l _ _I _I -_I __I__ _ ._ l .__ I
_1_ _ .l._. I 1 ._ ._
anos .s e av s.e nu asass a a possas asuca t a. "'I of rece amat es.s mac , g,s,se,s,,, eEf t g,n,s, p acet s tas t Of fics gog,
'~
--m-._
H $ Is0T APPLICASLE TO THE STP O ' OuAL4TV AamuRAsete cet0A8042ATIOse
}@ ,
f,/) H H 1 N .N N
INTERFACE BETWEEN HOUSTON LIGHTING & POWER COMPANY, BECHTEL ENERGY CORPORATION, AND EBASCO SERVICES INCORPORATED
= " t" ",',
A"..
HOUSTON LIGHilNG ab POWpf H ( O
.- mm. .......................................... .............................................m......n......
88 Chit L l NI HG t CintP a, A . ,
. .A . o. ..c. . . .
as == a oA __________ _ <,,,,s,',',,'l',,o.,
RAAAgAG8 H ggggggg,g g l
l l
j Ph0M CT j L eeGeset E RIIeG 3'
un.nu..nm.mmu..u...mmu.nm...une munun.m.mu m u.m m..mm.m. SECHIE L E.N..(.HG.V
.n .n . ronP E SASCO SE RVICE S INC f)tHf t'IGH8 PRE litet fet
- LN84t ef f - ( RAStil A11tMI A8sCE COas$1RUCf tNe$ ImeC C010%1H480 f N3 0 (MSAtilV PRIMiH A40 04AfeAG6 H E $8tE ABAN4talH = == === - - e e ese a== =
%8 56 esApsAGt R l
ni e-e
. 8 -i j
W.
e 5801f Rf Aff MM =========n spesCert enst $l ash)R Rf itog egl CoesastfWlf 4 8 Hl.e I ii CH0004 At sAIMl00NetlR A Igyg MA8s AE.8 H$ 1 Nt.68 0 g H
,g
. G eeni C 5 H We
l sios aturpa-ag pace 1 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 31 & 2 EB UC0 SEWICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPQRATEc QA-I-3 PERSONNEL INDOCTRINATION AND TRAINING PROGRAM IN QUALITY ASSURANCE i
! l 1.0 SCOPE This Section describes the program for indoctrination and training of Ebasco personnel engaged in activities affecting quality with respect to the requirements of this Manual and its supporting principal implementing procedures. Ebasco personnel shall be indoctrinated and trained, as necessary, to assure that proficiency is achieved and maintained in those parts of the Quality Assurance Program as it applies to the individual's responsibility.
2.0 GENERAL The Indoctrination and Training Program is a combined effort of the Ebasco organizations implementing any portion of this Manual and its principal implementing procedures, and the Quality Assurance organization. The Construction, Materials Applicaticas, and Quality Assurance organizations are responsible to schedule, indoctrinate, and train their personnel, and to record this indoctrination and training, unless otherwise denoted by project commitments.
! 3.0- PROGRAM REQUIREMENTS 3.1 Preplanned written lessons shall contain the substance of the indoctrination and training program. These lessons shall address one or more quality-related topics, to achieve one or more stated educational objectives. The training will be conducted by trained supervisors or their designees within the Construction and Materials Applications organizations, and by a Quality Assurance Education Specialist or designee when the need arises. A Quality Assurance ?ducation Specialist will be responsible for training the selected instructors within the other Ebasco organizations in methods of conducting required quality assurance training.
3.2 For Construction, Quality Assurance, and Materials Applications, preplanned training lessons are maintained by each organization respectively. The preplanned training lessons relate to activities the perscanel shall be performing. For Construction and Materials Applications, a responsible person within the respective organization shall determine the training requirements for each individual based on -
that individual's assigned responsibilities and past experience. Within the Quality Assurance org aization, a Quality Assurance Education Specialist shall be responsible for determination of an individual's 0598d
s ic s-29 t ST PMC PAGE 2 or 3 l
HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ,
ELECTRIC GENERATING STATION UNITS 1 & 2 EsAsco SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconpoaarec QA-I-3 PERSONNEL INDOCTRINATION AND TRAINING {
FROGRAM IN QUALITY ASSURANCE training requirements based upon that individual's assigned responsibilities and past experience, as applicable. Prep 3saned training Jessons are updated, when reqcired, and reflect any changen in the program. Copies of these preplanned training lessons shall be kept on 1 file by the respective organization. Quality-affected training will )
reflect project requirements.
4.0 RECORDS Individual training files for personnel in the Construction, Quality Assurance, and Materials Applications organizations receiving ladoctrination and training fa accordance with this program's requirements shall be maintained by each affected organization. These records will indicate, as applicable, the subject matt.er, the trainir.s received, attendance date, time duration, instructor, and special qualifications or restrictions, if any.
5.0 SCHEDULING Scheduling training of applicable organization personnel will be coordinated with a Quality Assurance Education Specialist where necessary. As new personnel are added to the South Texas Project within en org nization, appropriate indoctrination and training sessions will be scheduled based ca
> the requirements of this Manaal.
6.0 PROGRAM UPDATING i This indoctrination and training program is subject to continuous dcVelopment to broaden and improve its effectiveness. A Quality Assurance Education Specialist will hold periodic discussions with those groups involved with the training program to coordinate recommendations for updating. A Quality Assurance Education Specialist is responsible for updating the program for the Quality Assurance organization.
7.0 ADMINISTRATION 7.1 The Quality Assurance Engineering Quality Resources and Training Management Group shall have overall responsibility for administrating the quality assurance training program. It shall provide technical expertise for developing necessary programs and review existing programs for currency.
7.2 Management of each Ebasco organization is responsible to assure that the appropriate personnel attend the training program (s) for which they are scheduled.
0598d
sios.r u sr ens-es pace 3 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C iscoanoaArec QA-I-3 PERSONNEL INDOCTRINATION AND TRAINING PROGRAM IN QUALITY ASSURANCE 8.0 TRAINING, QUALIFICATION, AND CERTIFICATION OF QUALITY CONTROL PERSONNEL Training, qualification, and certification of Site Quality Control inspection personnel shall be in accordance with written procedures. The Quality Control Site Supervisor or his designee shall coordinate with a Quality Assurance Education Specialist regarding the training, qualification, and certification of Quality Control personnel. Qualification records for all Quality Control personnel assigned to the South Texas Project site shall be maintained by a Quality Assurance Education Specialist at the site. These records will be reviewed initially by the Manager Quality Assurance Engineering, or his designee, for compliance with the qualification requirements, and thereafter on an annual basis by auditors from the Site Quality Assurance organization.
Any deficiencies detected shall be reported in writing by the Quality Assurance Site Supervisor, or his designee, to the Quality Control Site Supervisor for resolution. Pending resolution of the deficiency, the individual shall be restrained from performing any Quality Control activities.
9.0 AUDITS Audits of indoctrination and training activities shall be performed to assure compliance with this Program. Such audits shall be performed in accordance with the requirements of Section QA-III-9 of this Manual.
l 0598d
sioscustmado ocoe 1 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERWCES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcoapoaATec QA-I-6 QUALITY ASSURANCE RECORDS 1.0 SCOPE This Section covers the requirements and guidelines for the collection, filing, storage, disposition, and maintenance of lifetime and nonpermanent quality assurance records associated with the construction and maintenance of nuclear power plants.
2.0 RESPONSIBILITY It shall be the responsibility of Ebasco to maintain quality assurance (QA) records in accordance with the requirements of this Section until such time as those records are turned over to the Client or his designee for permanent storage. The HL&P STP - RMS Site Records Center is the principal and final records repository. All QA records shall be accessible to the Client or his designee until such time as they are turned over to the Client or his designee.
3.0 QUALITY ASSURANCE RECORDS SYSTEM Each organization within Ebasco (including but not limited to the Construction and Quality Assurance organizations) that participates in the generation, collection, filing, storage, disposition, or maintenance of quality assurance records shall establish a written quality assurance record system applicable to the function (s) performed by that organization. These written procedures shall provide that each completed quality assurance record shall be transmitted by the organization generating the records to the Ebasco Site Quality Records group for final review and transmittal to the Client or his designee. This system shall be implemented and enforced in accordance with the requirements of the following paragraphs that apply to the function (s) of l that organization.
4.0 GENERATION OF QUALITY ASSURANCE RECORDS 4.1 The QA records to be generated shall be specified in the applicable design specifications, construction, maintenance, test, or inspection procedures, and other documents as necessary.
l l 4.2 All QA records shall be dated and signed or otherwise authenticated.
i 4.3 QA records shall be indexed. The indexing system shall include as a minimum:
4.3.1 QA records retention times (retention period begins on date of satisfactory operation of items).
0598d
sios.rustre4s c>cce 2 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO SERVICE 5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompoa ATEc QA-I-6 QUALITY ASSURANCE RECORDS 4.3.2 Location of storage area.
4.3.3 Location of QA records within storage area.
4.4 All QA records shall be distributed and handled in accordance with written instructions.
4.5 There shall be sufficient information in the QA records to permit identification between the records and the item (s) or activity to which it applies. Identification of QA records may be by purchase order number, system, or any means that permits accurate traceability.
4.6 All QA records shall be classified as " lifetime" or " nonpermanent."
4.7 When QA records are corrected or supplemented they shall be reviewed or approved by the organization that originated the records. All corrections and supplements shall bear dates and authorized signatures or initials traceable to the authorized individual.
4.8 Inspection and test records shall contain the following, as e applicable:
a) The type of observation.
b) Evidence of completing and verifying an inspection or test operation.
c) The date and results of the inspection or test.
d) Information related to nonconformances.
e) Inspector or data recorder identification.
f) Evidence of the acceptability of the results.
5.0 RECEIPT OF QUALITY ASSURANCE RECORDS 5.1 A system shall be established for receipt of QA records at the Site which shall include:
5.1.1 A checklist designating the required QA records.
0598d l
l l _ . . _ _ . . _ . _ _ _ . _ _ - . . _ _ . . _ _ _ . _ . _ . _ _ . _ _ _ _ _ _ _ . . _ _ _ .
sios.austpo4s oco2 3 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGP.AM DESCRIPTION - PART C INCORPORATED Qk=l=6 QUALIT FASSURANCE RECORDS l
5.1.2 A record of QA records received.
5.1.3 Written procedures for receipt and inspection of incoming Site QA records.
These quality assurance records shall be maintained by Site Quality Records and audited by Site Quality Assurance to assure that they are maintained properly until turned over to the Client or his designee.
, 5.2 The system described in Paragraph 5.1 of this Section shall permit l an accurate assessment of the status of the QA records during the receiving process.
6.0 TEMPORARY STORAGE, PRESERVATION, AND SAFEKEEPING 6.1 QA records shall be stored in accordance with a written procedure which shall require or include the following:
6.1.1 Description of storage facility, if other than a dual facility.
6.1.2 Description of filing system to be used.
6.1.3 Method for verifying that QA records received are in agreement with transmittal documents and pre-established records checklist and that the QA records are legible.
6.1.4 Rules governing access to files.
6.1.4.1 A list shall be generated designating those i personnel who shall have access to the files.
6.1.5 Method for maintaining control of QA records removed from storage. Such method shall provide for signing out of QA records
, removed from storage or other appropriate means of maintaining
- control of the records removed.
6.1.6 Method of filing supplemental information and superseding obsolete QA records. Supplemental information shall be filed with i the original documents whenever practical.
l l 6.2 A custodian (or custodians) shall be designated to implement the l
requirements of Paragraph 6.1 of this Section.
0598d
sios-austocas occe 4 er 4 )
HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 EBASCO SENCE5 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATEo QA-I-6 QUALITY ASSURANCE RECORDS 6.3 QA records may be stored within a temporary storage facility if they are protected from damage and loss. This shall include:
6.3.1 Storage within fire-resistant cabinets with a four-hour Underwriters' rating or a satisfactory alternative.
6.3.2 Protection from condensation.
6.3.3 Disallowance of loose documents. Records shall be attached to binders, placed in folders, or similarly maintained.
6.3.4 Specially processed QA records such as radiographs, microfilm, etc, shall be stored and protected in accordance with the manufacturer's recommendations.
6.4 A satisfactory alternative to the requirements of Paragraph 6.3 of this Section is maintenance of duplicate QA records stored in a separate remote location.
6.5 Audits shall be performed to assure the effectiveness of the storage system, and shall include:
l l 6.5.1 Verification that QA records which have been processed into the records facility are available in their proper location and in good condition, including those records that have been logged-out and removed away from the storage system.
6.5.2 Audit results shall be documented and its resulted discrepancies shall be verified to assure their correction.
6.6 The storage systems shall provide for accurate retrieval of QA records without undue delay.
7.0 DISPOSITION OF QA RECORDS Upon transfer of QA records, the Client or his designee shall acknowledge in writing the receipt of the particular QA records.
8.0 AUDITS Audits shall be performed in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.
0598d
e sos.a nst ra4s pace 1 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompon ATse QA-III-1 INSTRUCTIONS, PROCEDURES, AND DRAWINGS i
1.0 SCOPE Activities affecting quality performed at the construction site shall be described in written instructions, procedures, or drawings that have been developed in accordance with the requirements of this Section. Departmental procedures which describe the manner in which activities affecting quality are to be accomplished are part of the Ebasco Quality Program.
2.0 RESPONSIBILITIES 2.1 Where the Ebasco Nuclear Quality Assurance Manual designates an individual or organization with the responsibility of performing quality-related functions at the construction site, such functions shall be performed in accordance with written instructions, procedures, or drawings that have been developed by the organization performing the function. These instructions, procedures, and drawings shall establish the manner of performing the activity in accordance with the requirements of the Ebasco Nuclear Quality Assurance Program Manual and of the organization performing the activity.
i 2.2 When documented evidence is required for the satisfactory performance of particular activities, checklists, forms, and/or other
- appropriate means shall be utilized to provide this evidence. Such documents shall be signed and dated by the party performing the activity.
l l 2.3 Ebasco procedures, instructions, or drawings describing activities I affecting quality which are qualitative or quantitative in nature (ie, inspections or tests) shall contain or reference criteria for determining that such activities have been satisfactorily accomplished.
2.4 Standard Quality Assurance Procedures, and Standard Site Procedures when applicable, shall be reviewed and approved by the Quality Program Site Manager prior to implementation.
3.0 DEVELOPMENT OF INSTRUCTIONS, PROCEDURES, AND DRAWINGS 3.1 Instructions, procedures, or drawings for activities affecting quality at the construction site shall be developed by the Construction and Site Quality Assurance organizations for their respective quality-related functions. The Ebasco Nuclear Quality Assurance Program Manual shall be used as a guideline for their development. In addition, all Site Quality Control Procedures shall include or reference at least the following:
l 0599d
6109 2H47D1449 PAGE 2 CF 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8ASCO SERVICES ggggg.Y ASSURANCE PROGRAM 0ESCRIPTION - PART C mcoaaoaateo QA-III-l INSTRUCTIONS, PROCEDURES, MD DRAWINGS a) Identificatioa cf characteristics to be inspected.
b) Identification of the individuals or groups responsible for performing the inspection operation.
c) Acceptance and rejection criteria.
d) A description of the method of inspection.
e) Verification of completion and certification of inspection.
f) A record of the results of the inspection operation.
3.2 The Ebasco Engineering Development and Standards Department shall develop company instructions and procedures of categories, such as Nuclear (N), pertaining to quality-related functions.
3.3 Individual departments / disciplines shall be responsible for the development of their own intradepartmental/ discipline instructions, procedures, or drawings that establish the methods for performing quality-related functions. The Ebasco Engineering Development and Standards Department will provide, upon request, guidance and assistance in developing the documents.
3.4 If so requested by a department, Quality Assurance Engineering shall act in an advisory capacity during the preparation of internal Ebasco procedures.
3.5 All procedures, instructions, and drawings for activities affecting quality shall be identified, dated, and shall provide authorized signature (s) of approval.
3.6 To assure that all Ebasco Qualiry Conteol and Construction procedures and instructions comply w'Li c.4 i Manual, site-specific requirements, and applicable code 6 c ,A vg,tlatory requirements, they shall be submitted for review and acceptance to Ebasco Site Quality Assurance prior to implementation. When required by the Contract, quality assurance, quality control, special process, and construction l procedures and instructions shall also be submitted to the Client or his designee for acceptance prior to implementation.
{
l 0599d i
stos.2ttsTDe e5 ocos3 er4 I
HOU3 TON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 EBA5CO SERVICESI QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconacaarse '
QA-III-1 INSTRUCTIONS, PROCEDURES, AND DRAWINGS 3.7 The Standard Quality Assurance Procedures are procedures which are developed by the Client, Bechtel, and Ebasco and are common to each organization. Standard Quality Assurance Procedures shall be approved by the Quality Program Site Manager prior to implementation.
3.8 The Standard Site Procedures are developed by Bechtel, Ebasco, and the Client, as applicable, for project activities. The Standard Site j
Procedures shall be approved by the Ebasco Construction Manager and, where required, by the Quality Program Site Manager prior to implementation.
4.0 DISTRIBUTION AND CONTROL 4.1 Each Ebasco department shall be responsible for maintaining and enforcing a written system for the distribution and control of that organization's instructions, procedures, and drawings (other than design; ie, rigging drawings) for activities affecting quality. This system shall provide for at least the following:
4.1.1 Copies of these documents and revisions thereto shall be distributed to all appropriate department personnel in a timely manner.
4.1.2 Outdated and/or superseded documents shall either be destroyed or shall be clearly marked as " Superseded" or " Void" to avoid inadvertent use.
I 4.1.3 A file of the latest revision of these documents shall be maintained. Such a file shall be readily available to all affected personnel. -
4.1.4 A log of the documents shall be maintained. The log shall indicate as a minimum:
a) Title of document.
b) Document identification number.
c) Latest revision number and date of document presently in use, d) Distribution.of document (Manual Holder No.).
0599d
s eos.mstrus acce 4 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION llNITS 1 & 2 EBASCo SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-III-1 INSTRUCTIONS, PROCEDURES, AND DRAWINGS 4.2 A historical file of all revisions and changes to instructions, procedures, and drawings shall be maintained by the applicable organization responsible for such documents or as may be described in the applicable organization's procedures.
4.3 All approved Ebasco site generated field sketches, construction procedures, quality control procedures, and special process procedures shall be transmitted to the Client or his designee for distribution and control in accordance with Section QA-III-2 of this Manual.
5.0 CHANGES TO DOCUMENTS Changes to Ebasco documents, the Standard Quality Assurance Procedures, and the Standard Site Procedures shall be reviewed and approved by the same organization responsible for the original document when those changes affect the original reviewer, unless delegated in writing by the originating i organization to another responsible organization. The reviewing organization shall have access to pertinent background information upon which to base their approval and shall have adequate understanding of the requirements and intent of the original document.
6.0 AUDITS l
l Audits shall be performed in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.
0599d
.s ._.
sios,sust ro4s acce 1 or 4 HOUSTON LIGHTING AND POWER COMPANY S E CTION SOUTH TEXA$ PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 E8A5CO SERVICE 5 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcom pon A rco QA-III-2 DOCUMENT CONTROL 1.0 SCOPE This Section of the Manual establishes the requirements for the control of all project documents used by Ebasco which have an effect on quality-related activities. These requirements apply to those documents such as specifications and drawings, as well as site instructions and site procedures, which control or direct activities affecting quality.
2.0 RESPONSIBILITIES 2.1 The corresponding Department Heads or their designees shall be responsible for furnishing the Client or his designee with the latest of all Ebasco site generated field sketches, construction procedures, quality control procedures, and special process procedures.
2.2 The client or his designee shall be responsible for the distribution and control of all construction site design documents, drawings, specifications, construction procedures, quality control procedures, special process procedures, and Standard Site Procedures.
l 2.3 Ebasco shall assure satisfactory implementation of the Client or his
- designee's distribution and control of Ebasco generated documents as per j the requirements of Paragraph 6.0 of this Section of the Manual.
L
- 2.4 The Quality Assurance Site Supervisor 01
- his' designee shall be responsible for the distribution and control of site-generated Quality l
Assurance Instructions and the distribution of Standard Quality Assurance Procedures.
3.0 ISSUANCE OF CONTROLLED DOCUMENTS 3.1 Establishment of Document Control Stations 3.1.1 Document control stations shall be established and maintained by the Client or his designee.
3.1.2 Requests by Ebasco for the establishment of new or deletion of existing document control stations for the distribution of controlled documents shall be submitted by the corresponding Department Head or Discipline Manager to the Client or his designee.
3.1.3 Requests by Ebasco for additions or deletions of documents issued to an established document control station shall be submitted
- to the Client or his designee.
l l
i 0599d t
I
sios zitsvoo4s ocos 2 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUDi TEXAS PROJECT ELECTRIC GENERATING $TATION UNITS I & 2 ESASCO SERVICES QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mcompon ATeo QA-III-2 DOCUMENT CONTROL 3.2 Design Documents, Drawings, and Specifications 3.2.1 The Client or his designee shall furnish, distribute, and l control all design documents, drawings, and specifications to the l established document control stations in accordance with the Client's or his designee's written procedures.
3.2.2 Ebasco personnel shall use during their work activities the latest design documents, drawings, and specifications as provided by the Client or his designee at the appropriate document control stations, except that field change requests in an " Interim Approval" stage shall be controlled by the Senior Resident Engineer in accordance with approved site procedures.
3.3 Ebasco Intradepartmental/ Discipline Instructions and Procedures l 3.3.1 Intradepartmental/ Discipline instructions and procedures shall be issued and controlled in accordance with Section QA-III-1 of this Manual.
3.3.2 Quality Assurance Instructions and Standard Quality Assurance Procedures describing responsibilities of Site Quality Assurance shall be distributed and controlled at the construction site in
" book" form by the Quality Assurance Site Supervisor. A master file shall be maintained of all procedures and revisions. A master list shall be maintained indicating each person or organization to whom a book of procedures has been issued. New or revised procedures will be issued to each holder of a procedure
" book." A receipt system shall be used which requires written acknowledgement of distributed procedures. Receipt acknowledgements
- shall be maintained for the latest revision.
3.4 Ebasco Site-Generated Procedures and Instructions Ebasco site generated construction, special process, and quality
, control procedures and instructions shall be transmitted to the Client or his designee for distribution to the established document control stations.
3.5 Field Change Requests 3.5.1 A Field Change Request shall be submitted to the Senior Resident Engineer from applicable site personnel whenever conditions arise which may warrant consideration by the Client or his designee of a change in the specified design.
0599d
_ - - _ _ . _ - . _ - _ - - _ - _ - _ - _ - _ _ _