MONTHYEARML20211Q4981999-09-10010 September 1999 Proposed Tech Specs Clarifying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits & Adding Ref to Caldon TR for LEFM ML20211G3221999-08-26026 August 1999 Proposed Tech Specs 4.0.6 Re SG Surveillance Requirements ML20212H0771999-08-20020 August 1999 Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820. Page 119 in Unit 1 ASME Section XI of Incoming Submittal Not Included ML20212G0821999-08-20020 August 1999 Rev 4 to Augmented Inservice Insp Plan for Cpses,Unit 1 ML20210R7091999-08-13013 August 1999 Revised Proposed Tech Specs for LAR 98-010,proposing Rev to TS Table 3.3.1-1, RT Sys Instrumentation & TS Table B 3.3.1-1, RT Sys Setpoints ML20211M0041999-08-0505 August 1999 Rev 31 to Technical Requirements Manual ML20211G7401999-07-27027 July 1999 Revs 29 & 30 to Technical Requirements Manual (TRM) for Cpses,Units 1 & 2 ML20209E1861999-07-0909 July 1999 Proposed Tech Specs,Adding Reactor Core Safety Limit Figures to Section 5.6.5 of Ts,Clarifying That Overpower N-16 Setpoint Remains in TS & Reflecting NRC Approval of TRs Used to Determine Core Operating Limits Presented in COLR ML20212J4251999-06-23023 June 1999 Proposed Tech Specs,Revising EDG Start Be Emergency Start Instead of Normal Start Following Loss of Offsite Power ML20195E5401999-06-0404 June 1999 Proposed Tech Specs Pages 3.2-6,3.4-24,3.4-25,3.7-23,3.7-30, 3.8-25,3.9-9,3.9-10 & 4.0-2,provided as Addl Aditorial Changes Supplementing LAR 99-001 ML20195B6461999-05-27027 May 1999 Marked-up TS Pages Re LAR 99-004,changing Plant Battery Surveillance ML20195B6771999-05-24024 May 1999 Proposed Tech Specs Relocating Parameter Limits Allows for Available Operating & Analytical Margins to Be Used in Most Efficient Manner ML20206G7111999-05-0404 May 1999 Proposed Tech Specs Revising Surveillances Associated with Plant Battery & EDGs & Miscellaneous Editorial Corrections ML20206Q0311999-04-16016 April 1999 Rev 28 to CPSES Technical Requirements Manual ML20205Q1681999-04-14014 April 1999 Rev 27 to CPSES Technical Requirements Manual ML20207F3511999-02-25025 February 1999 Fire Endurance Test to Qualify Protective Envelope for Class IE Electrical Circuits ML20203B0011999-01-25025 January 1999 Rev 10 to Security Training & Qualification Plan ML20211C1071999-01-15015 January 1999 Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval ML20198J3171998-12-21021 December 1998 Proposed Tech Specs,Proposing Changes Administratively for Unit 1 & Increasing Licensed Power for Operation of Unit 2 to 3445 Mwt ML20198J2541998-12-18018 December 1998 Proposed Tech Specs Sections 1.0,3.1,3.3,3.4,3.6,3.7,3.9 & 5.0,converting to ITS ML20198J5211998-12-17017 December 1998 Corrected Tech Specs Pages for Section 3.8 to 971211 Submittal Re TS Conversion Application ML20197K0491998-12-11011 December 1998 Proposed Tech Specs Section 3.8, Electrical Power Systems, Converting to ITS ML20196C5361998-11-20020 November 1998 Proposed TS Converting to ITS Sections 4.0,3.4 & 3.6 ML20195F1751998-11-13013 November 1998 Proposed Tech Specs,Revising Administrative Controls Section to Include Configuration Risk Mgt Program Into CPSES TS ML20195F5291998-11-11011 November 1998 Proposed Tech Specs Revising Core Safety Limit Curves & Overtemperature N-16 Reactor Trip Setpoints for Unit 2 Cycle 5 ML20196B8811998-10-30030 October 1998 Proposed Tech Specs Section 3.3 Re Instrumentation ML20154R7861998-10-21021 October 1998 Proposed Tech Specs Section 3.7, Plant Systems ML20154S2901998-10-14014 October 1998 Proposed Tech Specs Sections 3.1,3.2,3.4,3.5 & 5.0 Re Reactivity Control Sys,Power Distribution Sys,Rcs,Eccs & Administrative Control,Respectively ML20154C9101998-10-0202 October 1998 Proposed Tech Specs 4.0.6, SG SR, Adding Definitions Required for F* Alternate Plugging Criterion & Identifies Portion of Tube Subject to Criteria ML20153E2661998-09-24024 September 1998 Proposed Improved Tech Specs Sections 3.4, RCS & 5.0, Administrative Controls ML20237E8461998-08-28028 August 1998 Proposed Tech Specs Pages Re Sections 1.0,2.0 & 3.0 of Proposed TS Changes in 980707 & s,In Response to NRC RAI ML20154C4511998-07-20020 July 1998 Interim Change Request ISI-1R5-01, Unit 1 ISI Plan,Rev 5 ML20236T9931998-07-20020 July 1998 1RF06 ISI Summary Rept First Interval,Third Period,First Outage for CPSES Unit 1, Commerical Operating Date 900830 ML20236J3131998-07-0101 July 1998 Revised Proposed Tech Specs Pages Re Safety Injection Signal & Blackout Signal ML20249C6101998-06-22022 June 1998 Proposed Tech Specs Section 3.6 Re Conversion Application ML20216B2811998-04-24024 April 1998 Rev 13 to Cpses,Units 1 & 2,IST Plan for Pumps & Valves First Interval ML20216E6291998-04-0909 April 1998 Marked-up TS Pages,Reflecting Proposed Changes in Amends to Licenses NPF-87 & NPF-89 ML20216B1471998-04-0606 April 1998 Proposed Tech Specs,Allowing Plant to Continue to Operate W/O Having to Perform Portions of SRs ML20217A3901998-03-18018 March 1998 Proposed Tech Specs Surveillance Requirements 4.8.1.1.2f.4)a) & 4.8.1.1.2f.6)a) at Power Re Enforcement Discretion ML20216H1361998-03-13013 March 1998 Proposed Tech Specs Re Electrical Systems Surveillance Requirements ML20248L3191998-03-12012 March 1998 Proposed Tech Specs TS 4.8.1.1.2f.4)b) & TS 4.8.1.1.2f.6)b) Re Request for Enforcement Discretion ML20216D6021998-03-0909 March 1998 Proposed Tech Specs Temporarily Removing Requirement to Demonstrate Load Shedding Feature of MCC XEB4-3 as Part of SRs 4.8.1.1.2f.4)a) & 4.8.1.1.2f.6)a),for Unit 2 Only ML20203K8621998-02-27027 February 1998 Proposed Tech Specs,Increasing RWST low-low Level Setpoint ML20203J5211998-02-25025 February 1998 Proposed Tech Specs Page to Remove Requirement to Demonstrate Load Shedding Feature of MCC XEB4-3 as Part of Surveillance Requirements 4.8.1.1.2f.4(a) & 4.8.1.1.2f.7(a) Until Plant Startup Subsequent to Next Refueling Outage ML20203J6151998-02-24024 February 1998 Rev 26 to Technical Requirements Manual ML20217P1531998-02-12012 February 1998 Rev 2 to ISI-2R2-01, Unit 2 ISI Plan ML20202B1641998-02-0505 February 1998 Proposed Tech Specs Bases 3/4.7.1.5 Re Main Steam Line Isolation Valves ML20217P2961998-01-30030 January 1998 Rev 5 to Unit 1 ISI Program Plan ML20202E5981997-11-25025 November 1997 Rev 12 to CPSES Units 1 & 2 IST Testing Plan for Pumps & Valves,First Interval ML20212C3881997-10-24024 October 1997 Proposed Tech Specs Re Revised Core Safety Limit Curves & Revised Overtemperature N-16 Reactor Trip Setpoints 1999-09-10
[Table view] Category:TEST/INSPECTION/OPERATING PROCEDURES
MONTHYEARML20212G0821999-08-20020 August 1999 Rev 4 to Augmented Inservice Insp Plan for Cpses,Unit 1 ML20212H0771999-08-20020 August 1999 Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820. Page 119 in Unit 1 ASME Section XI of Incoming Submittal Not Included ML20211M0041999-08-0505 August 1999 Rev 31 to Technical Requirements Manual ML20211G7401999-07-27027 July 1999 Revs 29 & 30 to Technical Requirements Manual (TRM) for Cpses,Units 1 & 2 ML20206Q0311999-04-16016 April 1999 Rev 28 to CPSES Technical Requirements Manual ML20205Q1681999-04-14014 April 1999 Rev 27 to CPSES Technical Requirements Manual ML20203B0011999-01-25025 January 1999 Rev 10 to Security Training & Qualification Plan ML20211C1071999-01-15015 January 1999 Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval ML20154C4511998-07-20020 July 1998 Interim Change Request ISI-1R5-01, Unit 1 ISI Plan,Rev 5 ML20236T9931998-07-20020 July 1998 1RF06 ISI Summary Rept First Interval,Third Period,First Outage for CPSES Unit 1, Commerical Operating Date 900830 ML20216B2811998-04-24024 April 1998 Rev 13 to Cpses,Units 1 & 2,IST Plan for Pumps & Valves First Interval ML20203J6151998-02-24024 February 1998 Rev 26 to Technical Requirements Manual ML20217P1531998-02-12012 February 1998 Rev 2 to ISI-2R2-01, Unit 2 ISI Plan ML20217P2961998-01-30030 January 1998 Rev 5 to Unit 1 ISI Program Plan ML20202E5981997-11-25025 November 1997 Rev 12 to CPSES Units 1 & 2 IST Testing Plan for Pumps & Valves,First Interval ML20212E9811997-10-0606 October 1997 Rev 11 to CPSES Units 1 & 2 IST Plan for Pumps & Valves First Interval ML20210S3911997-09-0303 September 1997 Rev 10 to CPSES Units 1 & 2 Inservice Testing Plan for Pumps & Valves in First Interval ML20151L1391997-07-31031 July 1997 5 to Technical Requirements Manual, for Plant ML20141E6201997-06-26026 June 1997 Rev 24 of CPSES Units 1 & 2 Technical Requirements Manual ML20141F8471997-06-26026 June 1997 Rev 9 to IST Plan for Pumps & Valves First Interval ML20136G4361997-03-13013 March 1997 Rev 23 to CPSES Units 1 & 2 Technical Requirements Manual ML20135A8241997-02-24024 February 1997 Rev 22 to CPSES Units 1 & 2 Technical Requirements Manual ML20134C6831997-01-31031 January 1997 Rev 8 to Comanche Peak Steam Electric Station Units 1 & 2 Inservice Testing Plan for Pumps & Valves First Interval ML20134M4371996-11-13013 November 1996 Self Assessment Guide Program Guidelines ML20129A5991996-10-16016 October 1996 Rev 7 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First Interval ML20128G7661996-10-0202 October 1996 CPSES Unit 1 & 2 Inservice Testing Plan for Pumps & Valves First Interval ML20138B5181996-10-0101 October 1996 Rev 14 to ODCM for TU Electric CPSES Units 1 & 2 ML20117C8461996-07-19019 July 1996 Glen Rose,Tx ASME Section XI ISI Program Plan,Unit 1 - 1st Interval Rev 4 ML20217M1691996-05-24024 May 1996 Rev 3 to STA-750, Check Valve Reliability Program ML20117C6181996-05-0303 May 1996 Rev 1 to Unit 2 ISI Plan ML20117C6141996-04-14014 April 1996 Rev 1 to Unit 2 ISI Plan ML20107J0941996-04-0202 April 1996 Rev 1 to Interim Change Request ISI-2, CPSES Unit 2 ASME Section XI ISI Program Plan ML20107E4471996-02-0909 February 1996 Rev 1 of CPSES ASME XI ISI Program Plan Unit 2 ML20100B9471996-01-24024 January 1996 Rev 21 of CPSES Units 1 & 2 Technical Requirements Manual ML20086C5491995-06-30030 June 1995 Rev 20 to Technical Requirements Manual ML20091L1941995-03-29029 March 1995 Interim Change Request ISI-IR3-003, Unit 1 ISI Plan ML20081F1131995-03-12012 March 1995 Interim Change Request ISI-1R3-02 to Rev 3 to Unit 1 ISI Plan ML20080Q3351995-02-24024 February 1995 Rev 17 to CPSES Technical Requirements Manual ML20078R6371995-02-15015 February 1995 Rev 5 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First Interval ML20078H8501994-11-30030 November 1994 CPSES Odmc Rev Change Sheet ML20073L6591994-10-0606 October 1994 Rev 4 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First Interval ML20072C7081994-07-24024 July 1994 Rev 16 to Simulator Operations/Maint Instruction - 010, Simulator Certification Testing ML20069E5171994-05-17017 May 1994 Interim Change Request ISI-2RO-001, Comanche Peak Ses Unit 2 ISI Program Plan ML20029D0711994-05-11011 May 1994 Rev 16 to Technical Requirements Manual ML20065K1721994-04-15015 April 1994 Rev 15 to CPSES Units 1 & 2 Technical Requirements Manual ML20058E3841993-11-30030 November 1993 Rev 14 to Technical Requirements Manual, Page 2-27, Clarifying Discussion in Table 2.1.1 Notations for Local Test Connections,Vent & Drain Valves & Revising List of Effective Pages EPL-1 Through EPL-4 ML20058C4441993-11-23023 November 1993 IST Plan for Pumps & Valves First Interval, Rev 3 ML20058B5791993-11-19019 November 1993 Rev 14 to Comanche Peak Steam Electric Station Technical Requirements Manual ML20058J9711993-11-19019 November 1993 Interim Change Request ISI-1R2-005 to Rev 2 to Unit 1 ISI Plan ML20056D8161993-08-11011 August 1993 Salp,Directive 8.6 1999-08-05
[Table view] |
Text
_
1 L
COMANCHE PEAK RESPONSE TEAM ACTION PLAN ISAP I,b.3 i
Title:
Conduit to Cable Tray Separation I
l Revision No.
4 l
Reflects Comments Description On Plan j
Prepared and Recommended by:.
Review Team Leader EY Date
\\
l l
l Approved by:
Senior Review Team
[h t.1 b,f __
/f1-4lf Date hokOO O 861003
~
GARDE 86-272 PDR I
I
% W 43 f~ l e.
I Rsviciont 4
Pag 2 1 of 5 6
ISAP I.b.3 Conduit to Cable Tray Separation
1.0 DESCRIPTION
OF ISSUE IDENTIFIED BY NRC (NUREG-0797, Supplement No.
7, Page J-42)
"The TRT found no evidence that the existing G&H analysis for establishing the criteria for a 1-inch separation between rigid conduits and cable trays, as stated in G&H Electrical Erection Specification 2323-ES-100, had been evaluated by the NRC staff for Comanche Peak. This analysis should have been referenced in the FSAR."
2.0 ACTION IDENTIFIED BY NRC (NUREG 0797, Supplement No. 7, Item 6(e),
Page J-44)
"TUEC shall accomplish the following actions prior to fuel load:
Submit to the NRC the analysis substantiating the acceptability of the criteria stated in G6H electrical erection specification governing the separation between separate conduits and cable trays.
This analysis shall be supported with the necessary documentation in sufficient detail to perform an independent evaluation of how these criteria were established based on the analysis."
3.0 BACKGROUND
Raceway separation criteria utilized in Gibbs & Hill electrical drawings and specifications were based upon the requirements of IEEE 384-1974 and Regulatory Guide 1.75 (Revision 1, 1/75). Although very specific criteria are provided in the standard and regulatory guide for separation between cable trays, the interpretation and application of that criteria for separation between conduits and cable trays is not specified.
Documents internal to Gibbs & Hill were prepared to establish-the engineering interpretation of required separation between conduits and cable tray in accordance with established criteria in the standard and regulatory guide. These documents were not-submitted to the NRC staff for review because the interpretation was not considered a deviation to the standard or regulatory guide, but was considered documentation supporting the implementation of these requirements.
It is industry practice to not submit"such implementing documents to the NRC.
7 I
R;vicicn 4
Pegs 2 of 5 6
ISAP I.b.3 (Cont'd) l 4.0 CPRT ACTION PLAN 4.1 Scope and Methodology The objective of this actica plan is to substantiate the acceptability of the criteria governing the separation between conduits and cable trays, and submit the evaluation and supporting documentation to the NRC.
To achieve this objective, the following tasks' will be implemented:
Prepare Gibbs & Hill report compiling criteria Review report to substantiate separation criteria Submit report to NRC 4.1.1 Report Preparation Gibbs & Hill will prepare a report for TUGC0 presenting the methodology and criteria used in applying IEEE-384(1974) and Regulatory Guide 1.75 (Revision 1, January 1975) to conduits requiring separation from redundant cable trays. Included will be a copy of a l
Sandia Report (" Cable Tray Fire Tests" SAND 77-1125C) which is the primary reference used in establishing the separation criteria.
.4.1.2 Report Review The above report will be submitted to the Review Team Leader and his third-party adviser for review.
I w
R:vicion:
4 Paga 3 of 5 t
ISAP I.b.3 (Cont'd) 4.0 CPRT ACTION PLAN (Cont'd) 4.1.3 Report Submittal to NRC After the report has been reviewed and approved, it and any supporting documents will be submitted by TUGC0 to the NRC for review. An FSAR Change Request will be initiated to provide a description of the cable tray-to-conduit separation criteria in the FSAR.
4.2 Participants Roles'and Responsibilities The organizations and personnel that will participate in this effort are described below with their respective work scope.
4.2.1 TUGC0 Comanche Peak Project
- 4. 2.1.1' Assist the Review Team Leader in reviewing the report compiling the Gibbs & Hill criteria.
4.2.1.2 Submit, upon approval, the report to the NRC.
4.2.1.3 Personnel Mr. W. I. Vogelsang, TUGC0 Coordinator 4.2.2 Electrical Review Team 4.2.2.1 Review the report compiling the Gibbs & Hill criteria.
4.2.2.2 Review NCRs and inspection reports, if any.
I-4.2.2.3 Personnel (prior to October 18, 1985)
Mr. M. B. Jones, Jr., Review Team Leader Mr. E. P. Stroupe Issue Coordinator 4.2.2.4 Personnel (starting October 18, 1985)
Mr. J. J. Mallanda, Review Team Leader Mr. R. J. Bizzak, Issue Coordinator Mr. M. B. Jones, Jr., Third-Party Adviser Mr. E. P. Stroupe, Third-Party Adviser e
R;vicient 4
4 Paga 4 of 5 t
ISAP I.b.3 (Cont'd) 4.0 CPRT ACTION PLAN (Cont'd) 4.2.3 Gibbs & Hill 4.2.3.1 Prepara a report compiling the criteria used in confirming the adequacy of conduit-to-cable tray separation.
4.2.3.2 Personnel Mr. S. P. Martinovich, Senior Electrical Engineer l
4.2.4 Third-Party Adviser 4.2.4.1 Review the report compiling the Gibbs & Hill criteriar 4.2.4.2 Personnel Mr. L. D. Bates, Third-Party Adviser l
4.3 Qualification of Personnel Where tests or inspections require the use of certified inspectors, qualifications at the appropriate level will be to the requirements of ANSI N45.2.6,
" Qualification of Inspection, Examination, and Testing Personnel at Nuclear Power Plants." CPRT third-party inspectors will be certified to the requirements of the third-party employer's Quality Assurance Program, and specifically trained to the CPRT Program Plan.
Third-party participants in the implementation of this action plan will meet the personnel qualification and objectivity requirements of the CPRT Program Plan and its implementing procedures.
1 Other participants will be qualified to the requirements of the CPSES Quality Assurance Program or to the specific requirements of the CPRT Program Plan. Activities performed by other than third-party personnel will be governed by the
" Assurance of CPRT applicable principles of Section III.K, Program Quality", of the CPRT Program Plan.
4.4 Procedures Not applicable.
R;vicien:
4 4
Paga 5 of 5 ISAP I.b.3 (Cont'd) 4.0 CPRT ACTION PLAN (Cont'd) 4.5 Acceptance Criteria The acceptance criterion for the report is that it demonstrate that the cable tray-to-conduit separation criteria meet the intent of IEEE-384 (1974) and Regulatory Guide 1.75, Revision l
1, January 1975.
4.6 Decision Criteria If compliance with IEEE-384 (1974) and Regulatory Guide 1.75, Revision 1, January, 1975 cannot be adequately demonstrated, the conduits and cable trays will be modified, as appropriate, to achieve compliance.