Extends Invitation to Attend Early Emergency Responders Workshop on 870204-05 in Chicago,Il to Discuss Lessons Learned & Current Problems in Coordination & Integration of Emergency Response Efforts.Proposed Agenda Encl
ML20215B643
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 12/05/1986
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
References
NUDOCS 8612120264
Download: ML20215B643 (4)


Text

I DEC 051986 Docket No. 50-440 Docket No. 50-441 The Cleveland Electric Illuminating Company ATTN: Mr. Murray R. Edelman Vice President Nuclear Group Post Office Box 5000 Cleveland, OH 44101 Gentlemen:

SUBJECT:

EARLY EMERGENCY RESPONDERS WORKSHOP The Region III Office of the U.S. Nuclear Regulatory Commission is sponsoring an Early Emergency Responders Workshop on February 4-5, 1987, in Chicago, Illinois. Preceding the Workshop, from 1:00 p.m. to 5:00 p.m. on February.3, 1987, a FEMA Region V REP Conference will be held. Forther information regarding the REP Conference will be provided to you by FEMA in separate correspondence.

The Early Emergency Responders Workshop, described in Enclosure 1, will bring together representatives of the States, the Department of Energy (DOE), the Environmental Protection Agency (EPA), the Federal Emergency Management Agency (FEMA), and the Nuclear Regulatory Commission (NRC) with representatives of nuclear power plants and other major licensees in NRC Region III. The purpose of the Workshop is to discuss lessons learned and current problems in the coordination and integration of emergency response efforts. Through the Workshop, we hope to promote a better understanding of our respective roles and coordination between responding organizations.

We invite you and your senior emergency response personnel to attend. We request that you limit the number of attendees at the Workshop to five. To aid us in estimating the number of attendees and making other necessary j arrangements, please complete the Pre-registration Form (Enclosure 2) and return it by December 29, 1986.

A major part of the workshop will be devoted to emergency response from

! the licensee perspective. We ask that you identify on the attached

' Pre-registration Form any specific issues you believe should be covered during the Workshop.

' The Workshop will be held at the Chicago Marriott O' Hare, 8535 West Higgins Road, Chicago, Illinois. It is tentatively scheduled to begin at 8:30 a.m. on February 4 and end at 4:00 p.m. on February 5. A block of rooms has been reserved and you should call (312) 693-4444 or (800) 228-9290 to make your reservations. A special room rate of $65.00 per night has been arranged for Workshop attendees. Other area hotels are also available.

8612120264 861205

\\

i PDR ADOCK 05000440 j p PDR \\

C1 e and Electric Illuminating 2 DEC 05 E86 We will provide you with a detailed agenda of the program as soon as possible. We look forward to seeing you in February and believe the Workshop will present an excellent opportunity to exchange information and enhance the coordination and integration of emergency response activities.

If you need any additional information, please contact Linda L. Kers (312/790-5711) or William G. Snell (312/790-5513) of this office.

Sincerely,

  1. 4I4e1 sfgoed g h G. kepoter James G. Keppler Regional Administrator

Enclosures:

1. Proposed Agenda of Early Emergency Responders Workshop
2. Pre-registration Form cc w/ enclosures:

F. R. Stead, Manager, Perry Plant Technical Department M. D. Lyster, Manager, Perry Plant Operations Department DCS/RSB (RIDS)

Resident Inspector, RIII D. Hulbert, EPC, Perry NI RIII I 1 II RIII RI Kers/nma v0C.,S Snell r

b Davis K iahju , w., njr ,,

h Enclosure 1 NRC REGION III EARLY EMERGENCY RESPONDERS WORKSHOP SESSION I, FEBRUARY 4, 1987 8:00-8:30 Registration 8:30-8:45 Welcome and Conference Overview 8:45-9:45 Federal Radiological Emergency Response Plan Overview 9:45-10:30 Region III Implementation of the NRC Emergency Plan 10:30-10:45 Break 10:45-11:30 Functions and Tasks of the NRC Operations Center 11:30-1:00 Lunch 1:00-2:30 Panel Discussion: Federal Response Capabilities 2:30-2:45 Break 2:45-3:15 Legislative Issues in Nuclear Emergency Planning 3:15-5:00 Panel Discussion: Emergency Response From a Licensee Perspective - Lessons Learned SESSION II, FEBRUARY 5, 1987 8:00-8:45 Implementation of the Price-Anderson Act 8:45-9:30 Perspectives on Protective Action Decisionmaking 9:30-10:00 Beaver Valley Recovery Table Top Exercise - Lessons Learned 10:00-10:15 Break 10:15-10:45 Status of Planning for the Zion FFE2 10:45-11:30 Aerial Measurements System 11:30-12:30 Lunch 12:30-2:00 Panel Discussion: Emergency Response from a State Perspective 2:00-3:30, Open Discussion - Topic (s) to be determined 3:30-4:00 Workshop Summary and Closing Remarks 4:00 Adjourn

h Enclosure 2 EARLY EMERGENCY RESPONDERS WORKSHOP FEBRUARY 4-5, 1987 ATTENDEE QUESTIONNAIRE l Name(s) of Attendees (s):

(Please Print)

Organization Represented:

! Mailing Address:

Telephone Number: ( )

PLEASE RETURN BY DECEMBER 29, 1986 T0: LINDA L. KERS U.S. NUCLEAR REGULATORY COMMISSION REGION III 799 ROOSEVELT ROAD GLEN ELLYN, ILLIN0IS 60137

_ - _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ -