ML20214V930

From kanterella
Jump to navigation Jump to search
Insp Repts 50-454/86-31 & 50-455/86-17 on 860527-1022. Violations Noted:Failure to Impose 10CFR21 Requirements on Contractors,Failure to Indoctrinate or Train Qa/Qc Personnel & Failure to Follow Procedures
ML20214V930
Person / Time
Site: Byron  Constellation icon.png
Issue date: 12/05/1986
From: Love R, Phillips M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20214V927 List:
References
50-454-86-31, 50-455-86-17, NUDOCS 8612100011
Download: ML20214V930 (83)


See also: IR 05000454/1986031

Text

. _ - _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-454/86031(DRS); 50-455/86017(DRS)

Docket Nos. 50-454; 50-455

Licenses No. NPF-23; CPPR-131

l

Licensee: Commonwealth Edison Company

Post Office Box 767

Chicago, IL.60690

Facility Name: Byron Station, Units 1 and 2

'

Inspection At: Byron Site, Byron, Illinois

!

Inspection Conducted: May 27 through October 22, 1986

N f4

Ray S. Tove

M

Ah//C

,

Inspector:

i

!

Date ' /

bb

l

Approved By: Monte P. Phillips, Chief

/A/S//t

l

Operational Programs Section

Date/ '

Inspection Summary

Inspection on May 27 through October 22, 1986 (Report No. 50-454/86031(DRS);

50-455/86017(DRS)

Areas Inspected:

Unannounced special inspection of licensee's action

on previous inspection findings, IE Bulletins, and 10 CFR 50.55(e) reports.

Also, an NRC review was initiated following receipt of allegations and

concerns from numerous sources relating to safety-related electrical work.

The inspection consisted of an examination of pertinent procedures, records,

and specifications, observations, and interviews of personnel. During this

inspection, Inspection Procedures 92701, 92703, 099014 and 099020 were used.

Results:

In the area of allegations reviewed, one example of a violation

of 10 CFR Part 21 and 21 examples of violations of ten of the eighteen criteria

of 10 CFR Part 50, Appendix B, were identified. See the Attachment for a cross

reference between the violations and report details.

.

8612100011 861205

i;

PDR

ADOCK 05000454

G

PDR

L

.

- _ _ - - - _ . _ _ _ _ _ _ - _ - _ _ . _ _ _ _

_ _ - - . - _ . - . _ _

DETAILS

1.

Persons Contacted

Commonwealth Edison Company (CECO)

  1. +T. J. Maiman, Vice President, Projects
    1. +E. L. Martin, QA Superintendent
  • +K. J. Hansing, Director of QA
  1. W. J. Shewski, Manager of QA
  1. G. E. Peterson, Section Engineer
  1. J. O. Binder, Project Electrical Supervisor
  1. G. E. Groth, Assistant Construction Superintendent
  1. B. R. Shelton, Project Engineering Manager
  1. K. A. Ainger, Nuclear Licensing Administrator
  1. D. Farrar, Nuclear Licensing

+R. B. Klingler, Project QC Supervisor

E. Briette, QA Engineer

  • L. E. Bihlman, QA Engineer
  • V. Schlosser, Project Manager
  • G. Sorensen, Project Construction Manager
  • J. L. Woldridge, QA Supervisor
  • T. L. Lamb, PCD Electrical Field Engineer
  • E. M. Zittle, Regulatory Assurance Staff

Sargent and Lundy (S&L)

T. E. Thorsell, Senior Electrical Project Engineer

  1. J. D. Regan, Electrical Project Engineer
  1. R. J. Netzel, Senior Structural Project Engineer

Hatfield Electric Company (HEco)

G. Vanderhet, Project Manager

R. P. Larkin, QA/QC Manager (Present)

A. Smith, QA/QC Manager (Past)

J. T. Hill, QC Superivsor (Present)

R. Farra11, QC Supervisor (Past)

D. Griggs, QA Supervisor (Past)

D. McCarty, Assistant QC Supervisor

S. Bindenagel, Electrical QC Group Leader

,

K. Higgins, Assistant Office Supervisor

E. Tovo, Project Engineer

U.S. Nuclear Regulatory Commission, Region III (NRC)

  1. A. B. Davis, Deputy Regional Administrator
  1. C. W. Hehl, Branch Chief, DRS
    1. +J. J. Harrison, Branch Chief, DRS
  1. R. F. Warnick, Branch Chief, DRP
  1. B. Berson, Regional Counsel

2

.

..~.-_,,,,y

_ ---

.

- __ _ _ _ __. _

.

_ _.

_

_

.

_

. _

,

  1. D. H. Danielson, Section Chief, DRS

'

  1. W. -L. Forney, Section Chief, DRP
    1. +R. S. Love, Reactor Inspector, DRS

'

  1. J. M. Jacobson, Reactor Inspector, DRS
    1. J. M. Hinds, Jr. , Senior Resident Inspector, Byron
  1. K. D. Ward, Reactor Inspector, DRS
  1. T. Vandel, Reactor Inspector, DRS

'

  1. R..M. Lerch, Project Inspector, DRP
  1. C. H. Weil, Investigation and Compliance Specialist

i

The' inspector also contacted and. interviewed other Itcensee and contractor

j

. personnel during this inspection.

  1. Denotes those present at the meeting in Region III Office on July 2,1986.

+ Denotes those present at the meeting in Region III Office on

October 1, 1986.

  • Denotes those present at the exit interview on October 22, 1986.

2.

Licensee Action on Previous Inspection Findings

(Closed) Open Item (455/83000-15; 455/85047-02): As part of the Safety

Evaluation Report (SER), Paragraph 8.2.4, the licensee committed to perform

verification testing to determine the adequacy of station electric

.

distribution system voltages in accordance with guidelines in Part 4 of

!

Branch Technical Position (BTP) PSB-1. To perform this test, the licensee

prepared and implemented Procedure AP-61. The Region III inspector reviewed

'

1

Procedure AP-61; witnessed the test; reviewed the test data collected; and

determined that the voltages were within the guidelines established in the

'

BTP.

Based on the inspector's observations as noted above, this item is

'

closed,

f

3.

Licensee Action on IE Bulletin 85-02

(Closed) IE Bulletin (454/85002-BB; 455/85002-BB):

IE Bulletin 85-02

,

was issued to inform all power reactor licensees and applicants of

,

'

reliability problems with Westinghouse 08-50 type ci cuit breakers

utilized in the reactor trip system.

Byron Station uses DS-416 type

circuit breakers rather than DB-50 breakers in the reactor trip system

i

!

(RTS). However, to prevent the same type of problems with the 05-416

!

circuit breakers, Westinghouse issued Field Change Notices (FCN)

(CAEM 10749, CAEM 10807, and CAEM 10808 for Unit 1 and CBEM 10685,

CBEM 10707, and CBEM 10709 for Unit 2) to replace the under voltage (UV)

trip assemblies and to modify the RTS to add an automatic shunt trip feature

P

!

4

i

$

3

<

.

. . . ~ . . -

. .

.. m

..r.-rm,.--,.-..~-..--.,,,..,,.,-.--.-..,.,m_,_---w

-. - ,

w3

eeym..,m

er~,-

--w-,

,-

1

1

l

on the Main and Bypass Circuit Breakers. The inspector reviewed the

Westinghouse FCNs, the Material Receiving Reports, vendor documentation,

Work Releases to incorporate the various FCNs, QC inspection reports, and

the OAD test reports for the Unit I and 2 RTS main and bypass circuit

breakers.

Based on the inspector's observations as noted above, this

item is closed.

4.

Licensee Action on 50.55(e) Report

(Closed) 50.55(e) Inspection Report (454/83009-EE; 455/83009-EE): On

July 6,1983, the licensee notified Region III of a deficiency reportable

pursuant to 10 CFR 50.55(e) regarding the Westinghouse 7300 process

protection. system at Byron station. The first deficiency involved the

adhesive bond in the heat sink assembly on loop power supply (NLP) cards

was subject to failure.

Failure of the bond could cause the separation

of the metal heat sink plate from the thermal links such that it falls

off of the printed circuit board. Under certain conditions, this plate

could cause shorting of the low-level signal if it became wedged between

cards in the card frame.

For corrective action, the heat sinks on the

NLP cards were replaced. The second deficiency involved contact bounce

as experienced in seismic testing of the temperature channel test (NTC)

card. This would result in signal saturation of the RTD Amplifier (NRA)

card in the T

U ) and T

N ) circuits. This deficiency could

hot

h

cold

c

delay initiation of the over temperature - delta temperature (OT-AT) and

overpower - delta temperature (OP-AT) trips. Westinghouse issued FCN

No. CAEM-10756 to provide a temporary bypass of the input test relays

pending a final resolution of the contact bounce deficiency.

For final

corrective action, Westinghouse issued FCN No. CAEM-10832A for Unit 1 and

FCN No. CBEM-10730 for Unit 2.

These FCNs installed modified NTC printed

circuit cards (8 per unit) to resolve the mercury wetted relay contact

bounce problem during a seismic event. These modified daughter boards

have reed relay contacts wired in parallel with the mercury wetted relay

contacts on the printed circuit boards. The inspector verified corrective

action by reviewing the following: the above referenced Westinghouse FCNs; the

revised drawings that ir corporated these FCNs; S&L Post Fuel Load ECN

l

No. P-374 that incorporated the Westinghouse FCNs; the Work Requests that

installed the modified circuit cards; the Westinghouse safety evaluation;

and the test data that verified the proper operation of the modified NTC

printed circuit cards.

l

5.

Followup on Allegation RIII-86-A-0090

a.

Background: On May 7,1986, the NRC Senior Resident Inspector (SRI)

at Byron Station received an allegation involving alleged harassment

and intimidation of HECo Quality Control (QC) inspectors at the

Byron Station. On May 9, 1986, the SRI and Chief, Projects Section

t

1A (Region III) met with 16 Level II HECo QC inspectors onsite at

Byron Station. On May 28, 1986, the NRC's Division of Reactor Safety

(Region III) was assigned the responsibility for followup on the HECo

QC inspector's concerns.

In most cases, these concerns were so general

i

in nature that it would be impossible for the NRC to perform a

meaningful followup inspection on the expressed concerns.

!

!

4

l

.

___

_

. _ _

. _ - , - . -

-

Due to the large number of concerned QC inspectors, the NRC inspector

elected to contact all QA/QC personnel employed by HECo from

February 1, 1986, through the start of this inspection, May 27, 1986.

The purpose of this contact was to provide each individual an

opportunity to identify and discuss their concerns, if any, with an

NRC inspector one-on-one off-site. A review of organizational charts

indicated that 94 persons had been/were employed during the time

frame selected. The NRC inspector telephonically interviewed 75 of

the 94 HECo QA/QC personnel. At the discretion of the interviewee,

the NRC inspector took the individuals concern over the phone or

met with the individual to receive their concerns.

For the 19

individuals the inspector was unable to contact, they were sent

registered letters, inviting them to contact the NRC inspector if

they had concerns with the safety-related equipment and/or applicable

documentation at Byron Station. The registered letter receipts were

returned from all 19 individuals, however, no additional concerns

were identified.

Summary: As a result of the special NRC inspection conducted at the

Byron Station, multiple examples of apparent violations of 10 CFR Part 21

and 10 CFR Part 50, Appendix B, were identified. These proposed

violations demonstrate Commonwealth Edison Company's failure to exercise

adequate oversight and control of their principal electric contractor,

Hatfield Electric Company, to whom they had delegated the establishment

and execution of a quality assurance program in the electrical area.

During the inspection _it was revealed that (1) Commonwealth Edison

Company (CECO) failed to incorporate the requirements of 10 CFR Part 21

into their contract with Hatfield Electric Company; (2) Ceco failed to

resolve (repair / rework / reject /use-as-is) identified hardware deficiencies

in Unit 18 emergency diesel generator system.

Some of these deficiencies

had been identified as early as 1983; (3) CECO and HEC 0 had dispositioned

NCRs, DRs, and inspection reports "use-as-is" without the design

organization's approval or without a clear basis for the inspection

elements acceptability; (4) CECO did not have a procedure for CECO

construction to notify CECO operations of deficiencies that could affect

the safe operation of Unit 1 or a procedure to ensure that items are

reassembled after fireproofing activities had been completed; (5) CECO

was deleting inspection attributes by memorandum and HECo was deleting

inspection attributes by verbal directions; (6) by verbal directions from

a CECO field engineer, the modification of 11 items of Unit I safety-

related equipment were not QC inspected; (7) HECo failed to accurately

status Unit 1 inspection reports which resulted in 57 required inspections

not being performed; (8) two HECo QA Lead ' Auditors and 16 HECo QC inspectors

were improperly certified; (9) HECo failed to include all NCRs and DRs in

their trend analysis (i.e., 98 of 104 NCRs and 199 of 236 DRs prepared

during the trending period were not included in the trending analysis),

and (10) HECo had closed NCRs (approximately 38 identified) before the

corrective action to prevent recurrence had been implemented.

,

5

(1) Concern: Temporary hangers were installed by using an unsigned

Field Change Request (FCR). These hangers are welded to

Category 1 steel and are located inside the secondary shield

wall next to each steam generator (S/G) in Unit 2.

They have

weld travelers but the welds have never been inspected.

NRC Review: The NRC inspector performed a physical inspection

of the area identified by the alleger. The inspector identified

12 temporary hangers (three per S/G) that were welded to

Category 1 (safety-related) box beams. During personnel

interviews, the inspector was informed that these hangers were

installed per the verbal direction of CECO Project Construction

Department (PCD) to protect the electrical wiring associated with

the " Loose Parts Monitor" for each S/G. Through the review of

the applicable weld travelers, the inspector determined that

these hangers were installed during the February 24-28, 1986,

time frame. The inspector was also informed that these temporary

hangers are scheduled for removal prior Unit 2 fuel load. The

HECo Level III welding inspector was maintaining the applicable

weld travelers in his " work pending" file.

In accordance with

HECo procedures and site instructions on temporary attachments,

an inspection of the attachment weld is not required. However,

when these temporary attachments are removed, an inspection of

the base metal will be required per CECO direction.

In this

instance, the box beams are scheduled for a visual and magnetic

particle (MT) inspection when the 12 temporary hangers are

removed.

Conclusions:

It was substantiated that 12 temporary hangers

were installed in the area of Unit 2 S/Gs and that these hangers

were attached to Category 1 steel (box beams). Additionally, it

was established that these hanger attachment welds were not QC

inspected.

However, there is no requirement for the inspection

of temporary attachment welds. The base metal is scheduled for

visual and MT inspections when the temporary hangers are removed.

No violations or deviations were identified.

(2) Concern: HECo QA/QC management instructs QC inspectors to stay

out of Unit 1 areas. If an inspector identifies a deficiency in

Unit I area, he " catches hell".

Examples of defective wd ds in

Unit 1 are hangers WCP1-1 and WCP1-5.

NRC Review:

During personnel interviews, (CECO PCD, Ceco QA

and HECo QA/QC), the NRC inspector was informed that when Unit 1

was declared operational, CECO informed all contractors to keep

their personnel out of Unit I areas unless they had a specific

job to perform in those areas.

In addition, as part of CECO's

Nuclear General Employee Training (NGET) personnel are informed

that the security program required controlled access for certain

areas. Due to their job requirements, most HECo QC inspectors

have a photo badge and a key card that allows them access to

,

6

'both Unit 1 and Unit 2' areas.

If an' inspector was inspecting

Unit 2 work operations, he/she would have free access to Unit 1

equipment. Therefore, the only way to control access to Unit 1

items is through verbal or written direction.

If an inspector

was'in the Unit 1 area without a specific job assignment, that

meant they were not performing their required job functions in

Unit 2.

However, if the inspector observed a deficiency while

passing through the Unit 1 area, the inspector is expected to

notify CECO of the deficiency by the use of a meno. With:

respect to hangers WCP1-1 and WCP1-5, the inspector was unable

to' locate those hangers with defective welds. Without a speci-

fic drawing number, it is impossible to identify the hangers

that the alleger was alluding to in that most all drawings

reviewed had these hanger numbers assigned, i.e., each building,

and each elevation of the building, and if different drawings,

each area of a given elevation could have hangers WCP1-1 and

WCP1-5. When queried, the alleger could not remember the

building, elevation, area, or drawing. As stated above, the

inspector could not identify any WCP1-1 or WCP1-5 hangers with

defective welds.

Conclusions: . It was substantiated that HECo QC inspectors were

directed to stay out of Unit I areas. However, this direction

,

was given so as to limit the personnel in the vital areas of an

operating plant (Unit 1) and was at the direction of the

licensee.

If an inspector identified deficiencies in Unit I

while his job assignment was for Unit 2 work activities, he/she

may " catch hell" for being in Unit 1, but not for reporting a

discrepancy. With respect to hangers WCP1-1 and WCP1-5, the

inspector could not identify any WCP1-1 or WCP1-5 hangers with

defective welds. No violations or deviations were identified.

(3) Concern: Weld traveler cards are missing on approximately 20%

of the Unit 2 J-Box' attachment welds.

NRC Review: During interviews of HEco QC and engineering

personnel and the review of Discrepancy Reports (DR) and

Nonconformance Reports (NCR) it was apparent that HECo had an

extensive problem with missing weld travelers (lost or never

prepared). DR 8512 identified 37 Category 1 J-Boxes that were

missing weld traveler (WT) cards. After research, it was found

that 11 J-Boxes did not require WT cards in that the J-Boxes

were installed with concrete expansion anchors (CEA) or by bolts

to tube steel.

For the remaining 26 J-Boxes, new WT cards were

generated and the welds inspected and repaired as necessary.

If

some of the data required on the WT was not recreatable from

other records, the DR number was entered in that space.

For

example if the actual date of installation could not be

determined from the foreman's construction reports, DR 8512

would be entered as the installation date.

In addition, Ceco QA

Surveillance Reports 6941, dated February 11, 1985; 3780, dated

July 25, 1985; and 7948, dated March 5, 1986, also addressed the

fact that HEco was missing WT cards.

Concern (4) below also

7

1

addresses alleged missing WT cards.

The NRC inspector verified

l

that DR8512 and CECO QA Surveillance Reports 6941, 7380, and 7948

were properly closed.

In addition, the inspector randomly selected

- 24 Category I and II J-Boxes from the 6E-2-3600 series drawing

for review of WT cards. One or more WT cards were reviewed for

each J-Box selected and were found acceptable.

Conclusions: HECo had problems with missing WT cards for Unit 2

J-Boxes, however, the missing WTs had been documented and

resolved by HECo on DR8512 and on Ceco QA Surveillance Reports

No. 6941, 7380, and 7948.

In addition, the NRC inspector

selected 24 J-Boxes at random and did not identify any missing

WT cards. No violations or deviations were identified.

(4) Concern: There are no WT cards for Category II welds.

Example

provided was cabinet / panel attachment welds.

NRC Review: The NRC inspector reviewed approximately 125

non-safety related (Category II) Equipment Installation Reports

where attachment welds were required.

In all cases, WT cards

had been prepared for these attachment welds. Also, see

Concern (1) above for additional examples of WT cards being

prepared for the installation of non-safety related items.

Conclusions:

In that weld travelers were prepared for the

approximately 125 non-safety-relatea items reviewed, this

concern could not be substantiated.

No violations or

deviations were identified.

(5) Concern:

If a hot item (item required to support testing and/or

turnover) was rejected by one inspector, another inspector was

directed to reinspect the item and accept it.

For example,

approximately four months ago (February 1986) an inspector

rejected some welds on Category I cabinet attachments in Area 7

and HECo QC inspector (by name) accepted the welds.

NRC Review: All WT cards are entered into the HEco computer

system by WT number, drawing number, area number,

hanger / equipment number, welder, and QC inspector that accepted

the weld (s) associated with that WT. The NRC inspector requested

and was provided a printout of all WT cards inspected by the

named individual in Area 7 between November 1985 and June 1986.

A review of the WT cards indicated that the named individual

had not inspected any weld in Area 7 (between November 1985 and

June 1986) that had been previously inspected by another

inspector.

It should be noted that the QC inspector documents

his/her inspections on the original WT card.

This included

rejections and reinspections. As part of CECO's ongoing

overinspection program, Pittsburgh Testing Laboratory (PTL)

selects, at random, 10% of each inspectors work for reinspection.

PTL's 10% sample of the named individual's work resulted in a

50% reinspection of his work in Area 7 between November 1985

and June 1986, with no rejections.

8

Conclusions:

Based on the NRC-inspector's review of the named

individuals work in the area specified this concern could not

be substantiated.

This concern was also refuted based on PTL's

overinspection of his work. No violations or deviations were

identified.

(6) Concern: The HECo QA supervisor restricted access to vaulted

records. The following examples were provided: (a) QC inspectors

were not allowed to look at old (vaulted) WT cards and could

only use the WANG to verify acceptability; (b) if a QA inspector

wanted to look at any vaulted records, the inspector must have

the QA supervisors written approval, i.e., the supervisor

initials the records sign-out card;-(c) the QA supervisor would

look at the records requested and inform the inspector that "You

don't need to see the record, it was inspected and accepted -

Trust me."

NRC Review: To establish the need for QC inspectors to review

vaulted records, the NRC inspector reviewed several of HECo

procedures. The following are typical examples where the

inspector needs to verify vaulted records (completed QC records

stored in a records vault):

(a) Procedure 20

" Class I Exposed Conduit System

Installation." When the QC inspector is performing

a conduit inspection per Form HP-201, Item 3 on the

checklist requires verification that the supports

(hangers) were installed per drawing. This task is

performed by verifying support inspection checklist,

Form HP-203, was complete and acceptable.

Form HP-203

is completed by a welding inspector.

(b) Procedure 20 - When the QC inspector is completing a J-Box

installation report, Form HP-206, the inspector has to verify

that a complete and acceptable WT or CEA traveler is on

file.

(c) Procedure 19

" Equipment Turnover Reporting" and

Procedure 19A

" Electrical Panel Turnover Reporting."

These procedures require QC to verify that numerous

inspection reports are complete, acceptable, and on file.

If there are any exceptions, these exceptions must be

noted on the turnover report.

Based on the NRC inspector's review of HECo procedures, it was

determined that the QC inspector must have free access to the

vaulted records to perform his/her job related functions.

During personnel interviews, the inspector was informed by the

vault clerk that the QA Supervisor must initial the " Records

Checkout Card" before she could provide the QC inspector with

the requested records. The inspector also observed various QC

inspectors obtaining the QA Supervisors initials on checkout

cards. Also during interviews of computer operators and QC

9

.

'

personnel, the NRC inspector was informed that the general

guidance provided was to utilize the computer to determine

item acceptance. This was enforced more if the records were

in Vault No. 2.

Vault No. 2 is under the control of CECO and

contains HECo Unit I records, some Unit 2 records, and

' certification records for former HECo QA/QC personnel. With

respect to the third example provided (Concern c. above), this

appeared to be a statement taken out of context.

In order to

resolve this problem, meetings were held with Ceco and HEco

personnel and HECo was directed to "open the vault" to all

QA/QC personnel; i.e., allow personnel to checkout documents

without the QA supervisors approval. The subject QA supervisor

was terminated July 2, 1986.

Conclusions: Based on the inspector's observations and personnel

interviews, examples (a) and (b) of this concern were substantiated

and it was also determined that the QC inspector needed free

access to the vaulted records in order to perform his/her job

related functions as described in the HECo procedures.

The licensee was informed that failure to assure that QC

inspectors had the authority and organizational freedom to

verify inspections of safety-related _ functions is an example of

failure to implement 10 CFR 50, Appendix B, Criterion I

(454/86031-01; 455/86017-01).

(7) Concern: Temporary Ticket Holders are afraid to reject anything

for fear of being fired.

HEco QC inspector (by name) is a good

example. Temporary Ticket Holder was defined as a craft

i

journeyman that was working as a QC inspector (Red Hat) and -

,

took a pay cut under the new union agreement to work as a QC

^

inspector (White Hat).

CECO Project Electrical Supervisor (by

name) directed HECo to get rid of Red Hat QC inspectors.

Red

'

Hat QC inspectors that went "back to the tools" (working as

craft journeymen) were better' qualified than many present QC

inspectors.

NRC Review: To fill a void in the HECo QC Department,

journeymen electricians and welders were transferred on.a

'

temporary basis to the QC department. These personnel were

trained, tested, and certified as QC inspectors. At a point

in time, the HEco QC department was made up with non-union QC

inspectors and union journeymen QC inspectors (Red Hats). Due

to the large difference in pay, the non-union inspectors

organized and a union contract was negotiated for HECo QC

inspectors. At that time, " Red Hats" were afforded the

t

opportunity to change over to " White Hat" QC inspectors at a

reduced pay.

In accordance with the QC union contract,-the Red

Hats were the "first to go" on a reduction in force (RIF). At

the present time, there are no Red Hats in the HEco QA/QC

department.

10

y

,

-

,

,

,

l

~

'

1

g

.

With respect to qualification of QC inspectors, the NRC

.f'

established the minitrum requirement that would be acceptable ~

for certification with the issuance of Regulatory Guide 1.58

h; '

previously employed HEco QC inspector's qualification records.

and Generic Letter 81-01. A sample review of present and

,

.'

indicated that all 0C inspectors met.the minimum requirements'

s

for certification.

In fact, some'of these Red Hat and White Hat

inspectors exceeded the minimum requiremeKts for certificattorJ

"

The inspector reviewed the last eight .nonths 'of welding

'

-inspections (area certified) performed by the named QC

.s

inspector and the inspections of eigat additional 16spectors.

The reject rate on initial inspections wis higher for the named

inspector than for the.other eight inspectors.

,

,

4

Conclusions: Basedon'theNRCinspector'srevkewofinspection

reports, certification records, and union contra:ts, the

s

allegers conc ^rns could not be substantiated. All QC

e

inspectortwere qualified and properly certified.- There wts no

evidence thaii the " Red Hats" were treated it, a discriminatory

-

manner. Na VI'olations or deviations were identified.

(8) Concern: .The Assistant QC Supervisor (by 1narne) was fired. 'He

was the one lha.t lied about his education. 011y Leads and

a

fanagement .oro allowed to reips,%ct his work after he was

,

terminated.

,

s

g

NRC Review: 7 Threugh the review of records relate'd to this

.

concern, it war donfirmed that the named individe,41 had falsiYied

g

a Diplo.n of Graduation from North Cee. tral Collega, School of

Technology. The individual resigned from HEco on tierch 21,

1986. A reinspection of the indisicual's hori wa3 nerformed

.under the guidance of CECc. At the time of tin reiaspec'. ion of

,

stud welding, thesonly 19dividual certified inithis ares \\was the

Level JII inspector., Thu, required " Management" to. p'nspect

the in:lividuals stud weldirq inspections. The rainsphtton of

,

-

the individual's visual weld lnspections were perforr.ed by a

HEco QC Lead Ir.spector. .Further,research by the NRC inspector

,~

indicated that'the indivicarl's Neld ingections had been ;

'

previously reinspected under the Byron Reinspection Prcgram.

It

i

should also"ce noted that the NRC SRI at Byron Station had been

'

previously informed of the falsified education, reinspection

program, and resbits of the reinspection.

'

,

1

-

-

!

Conclusion:' This concern v a .substantikted in that Management

(

D.evel DT) uid reinspect the individuals stud weld inspections,

.however, tha Level III was the only inspector certified in<this

- area at,the.tiie of reinspection. Also, a certified dead

inspectur rcinspected the individuals visual,welo inspections.

h/

Additionally, the individual's visual weld inspections had been

previously reinspected under the Byron Reinwetion Program.

No violations or deviations were identified

.,

11

,

-L

-.-

-____.__--.-,...,-__.___-_---.--.,,.,_,----,m

-_

_ ._. . _ . . .

._.

, _ _ _ __

. _ _ _ . _ _

._

. _ _ _

'

(9) Concern: A QC inspector questioned an engineering design on

a Detail J-(type of conduit hanger attachment). At.a special-

meeting, the Level III Welding Inspector (by name) informed the

QC inspectors that they do not perform engineering design

j

reviews. The. Level III also stated that if an engineer said to

put bubble gum on a hanger, QC's job was to inspect the bubble

gum.

l

~

-

..

NRC Review: During an interview of the named Level III, the

i

Level III confirmed his meeting with the inspectors.

In that a

,

small faction of the welding QC inspect' ors wanted to " redesign

the plant", the Level III deemed the meeting to be justified.

-

3

With respect to the bubble gum, the Level III stated that the

allegers statement was not correct. The Level III informed the

3 -

NRC inspector that what he actually said was, "If engineering

,

said to put bubble gum on a hanger, it was QC's job to inspect

!

.i

the bubble gum and to make damn sure it was the brand specified."

Conclusion:

The Level III welding. inspector made a valid point,

in that QC inspectors are to verify compliance with instructions,

procedures, and drawings, not to conduct engineering reviews,

The Level III's analogy was taken out of context. No violations

,

or deviations were identified.

4

(10) Concern: HEco QC Department has gone to hell since Energy

Incorporated (EI) came in.

i

+

,

i

NRC Review:

EI is a company that supplies QA/QC personnel

.

l

'

under a contract with HECo. These personnel were assigned

positions as QA engineers and cs QA/QC Management /Supervisers.

During personnel interviews, it was perceived by the Region III

'

inspector that an anomic condition exists within the HEco QA/QC

,

Department. This appeared to stem from the fact that outside

'

personnel (EI) were brought in and placed in management and

I

supervisory positions and the lack of communications between

Managment/ Supervisors and the QA/QC staff. However, this anomic

i _

condition did not affect the inspection effort and integrity of

j.

the QC inspectors. As part of . Ceco's QA program, PTL does a 10%

overinspection of the HECo work.

From September 27, 1985

'

l

through July 10, 1986 (inspector's sample period), PTL performed

approximately 800 overinspections and identified only two (2)

rejectable attributes that had been previously accepted by

,r

.

HEco QC inspectors.

'

'

Conclusions: Although it was evident that some high level'of

4

animosity had developed between HECo QC staff ara the EI staff.

.

and significant communication probelms existed, a high level of

'

l

quality inspections was maintained. This is based on the fact

that PTL performed approximately 800 overinspections and found

two rejectable attributes. Therefore, thfs concern was not

substaptiated. No violations or deviations were identified.

l

'

i

!

i

l

12

'

-

-n

il

s

)

.

(11) Concern: ' QC identified deficiencies on inspection reports

are being dispositioned "use-as-is" by CECO and HECo. HEco

engineering prepares a separate report (OIR) to accept the

items as installed.

Some of their engineering reports were

not numbered, or after the QC inspection report is closed,

'

the engineering backup documentation (0IR) was destroyed.

i

NRC Review:

Based on a review of Paragraph 5.1 of HECo

Procedure 6, " Reporting of Damage or Nonconforming Material or

-

Equipment," and personnel interviews, the following is a summary

of how the Open Inspection Report (OIR) system should work:

(a) Deficiencies identified during routine surveillance or

inspection activities are identified on the appropriate

inspection checklist (IR) by the QC inspector.

'

(b) OIRs (reports that indicate deficient checklist items found

during QC inspections) are filed in a " work pending" file.

(c) Copies of OIRs,'along with the associated installation

report, are provided to the Assistant Project Manager

for resolution of the deficiencies,

i.e., construction

corrects the deficiencies.

(d) Corrected installation reports are returned to QC

for verification of the corrected deficiencies.

(e) QC verifies the resolution and documents their acceptance

on the OIR from the work pending file.

The NRC inspector identified the following examples of

deficiencies within the HEco OIR program:

(a) Conduit inspection checklist, (Form HP-201) No. 4902,

identified that conduit C2A7429 contained 370 of bends

(maximum is 270 per specification). This nonconforming

condition was dispositioned "use-as-is" by HECo

engineering without licensee and S&L approval on an

,

uncontrolled HECo engineering document (No form number)

identified as 0IR No. 4902-19?.

(b) Equipment modification inspection checklist (Form

HP-12A-1) No. 5101, identified exposed copper at a

termination lug on Terminal 13. This nonconforming

condition was found acceptable as installed per a " Speed

Letter" from T. Lamb, CECO PCD, to S. Bindernagel

(Bindenagel), HEco' QC.

'.

(c) Conduit inspection checklist (Form HP-201), No. 4788,

identified that the "0" ring was missing on conduit

C2A1209.

"0" rin'gs are required per S&L specifications,

13

,

.

- ,-

-

__

Standard EB-146. This nonconforming condition was found

acceptable as installed per a " Speed L:.cter" from S.

Vovos, CECO PCD, to E. Tovo, HECo engineering.

(d) Conduit inspection checklist (Form HP-201), No. 4736,

identified that conduit C0A62F9 was installed outside the

elevation tolerance. The inspection report indicated that

during a reinspection, the Detail J connections had been

cut off of a previously accepted hanger (SCC-1) and

reinstalled without any documentation, i.e., Discrepancy

Report (DR), Nonconformance Report (NCR), or Form 7A, Rework

Request. During a review of this inspection checklist, the

NRC inspector was informed that HECo engineering had prepared

an 0IR to rework the hanger to correct the conduit

elevation, however, no OIR could be found.

(e) Equipment modification checklist (Form HP-12A-1), No.14217,

required a 100% inspection of panel 2PA11J prior to turnover

to CECO. The inspector identified two potential problems:

(1) "Cannot determine if wire size is per print"

(2) "Cannot inspect lugs landed up-side down"

Both of these items were marked " acceptable" on the HEco

inspection report by a CECO PCD engineer.

As a result of a management meeting in NRC's Region III office

on July 2,1986, CECO QA initiated Audit 6-86-201 to address

NRC concerns expressed during the management meeting. The lack

of control of OIRs, as noted above, was one of these NRC concerns.

The CECO QA audit was performed by seven CECO auditors with

assistance from PTL certified QC inspectors. This audit was

initiated on July 7,1986, and concluded on August 4,1986. As

a result of Ceco QA review of the HECo 0IR program, Ceco QA

issued two findings against HECo and one finding against the

CECO PCD electrical group.

Conclusions:

Based on the five examples of violations identified

by the NRC inspector and the three findings identified by the

licensee in Audit 6-86-201, this concern was substantiated.

The licensee was informed that failure to assure that design

changes were approved by the organization (S&L and/or

Westinghouse) that performed the original design was an example

of failure to implement Criterion III of 10 CFR 50, Appendix B

-

(Reference: Paragraph 5.a.(11)(a), (b), (c), and (e) above)

(50-455/86017-02).

The licensee was further informed that failure to assure that

nonconforming conduit C0A62F9 (Reference: Paragraph 5.a.(11).(d)

above) was reworked or repaired in accordance with documented

instructions (NCR or DR) or procedures is an example of a

failure to implement Criterion XV of 10 CFR 50, Appendix B

(50-455/86017-03).

14

(12) Concern: HECo material is not traceable. There are no heat

numbers on any of the material.

If CECO accepted the material,

HECo QC is not to question its acceptability.

NRC Review: Criterion VIII of 10 CFR 50, Appendix B, requires

that the identification of an item be maintained in some manner

throughout fabrication, erection, and use of the item. This

identification and control is designed to prevent the use of

incorrect or defective material, parts, and components. Based

on an interpretation by the NRC, it is not necessary to provide

unique traceability for items such as hanger material (A36),

unistrut, conduit, cable tray, etc. that are used in the

electrical area (non-coded applications) provided:

The material is ordered safety-related,

'

During receipt inspection, it is verified that the material

meets the applicable specification requirements, including

documentation,

Safety-related material is not comingled with

non-safety-related material, and

The issue of the material for use or installation is

controlled.

At the Byron Station, Ceco procures all material for all site

contractors. With respect to electrical raceway material,

these items are procured and received as safety-related.

In

accordance with HECo Procedure 5, " Class I Material and

Equipment Receiving and Inspection", HECo QC performs receipt

inspection of CECO procured material, upon request, to Ceco

requirements as stated on the Material and Equipment Receiving and

Inspection Report (MRR).

In addition, for CECO Station Nuclear

Engineering Department (SNED) procured items (permanent plant

material items), CECO PCD and Ceco QA also performs a receipt

inspection and/or documentation review. The release of the

items or material for installation or use is performed by CECO

QA after the material and documentation has been inspected / reviewed

and accepted.

In general, when CECO issues items / material to

HEco for installation or use, an additional receipt inspection

by HECO QC is not required to determine its acceptability.

In

that the vendor documentation is controlled by S&L or Ceco,

'

HECo QC can not determine the acceptability of an item. However,

t

if a damaged or defective item is observed by the HECo QC inspector,

this deficiency must be documented and reported in accordance

I

with HEco Procedure 6, " Reporting of Damaged or Nonconforming

Material or Equipment."

'

Conclusions: This concern was substantiated, however, the

tracking of an item by part or heat number is not required for

non-coded applications in the electrical area. HECo and/or

CECO performs the required receipt inspections. HECo can

however identify nonconforming hardware problems.

In that HEco

QC does not have access to the vendor documentation, they cannot

determine an items software acceptability. No violations or

l

deviations were identified.

l

l

15

.

.

.

-

-

.

-_ .

-_.

.

.

. .

_ _ _

_

.

-

_

__

.

_ _.

_

,

4

(13) Concern: HECo QC was instructed not to look at vendor welds.

HECo QC rejected better welds than most of the vendor welds,

however, CECO bought-off all of the vendor welds. Think the

i

vendor was Systems Control.

NRC Review: A review of the history on Systems Control

revealed that welding problems had been identified and documented

by HECo, CECO, and the NRC. As documented by CECO and the NRC,

there were instances where undersized welds and missing welds

were evaluated by S&L and found acceptable as installed.

The following are examples of NCRs and reports that address

'

problems, corrective actions, and acceptance of welding by

Systems Control: HECo NCRs 461,1062, 1065, 1066 and 1067; CECO

NCR 885; Ceco 50.55(e) Reports No. 454/82008 and No. 455/82008;

CECO QA Audit Report No. 6-84-309; and NRC Inspection Reports

'

454/83039, 455/83029, 454/84C31, 455/84024, and 454/84050,

455/84034.

.

Conclusions:

It was substantiated that Ceco experienced

problems with Systems Control welding and based on an analysis

by S&L, many of these welds were accepted in the as-found

l

' condition.

However, these welding problems had been documented

and resolved by the licensee with followup inspections and

acceptance by the NRC.

No violations or deviations were

identified.

(14) Concern: The HECo QC Supervisor (by name) does not have any

certifications to any of the procedures at Byron Station.

HECo

5

wanted to make the named individual a Level III inspector but the

present Level III (by name) would not sign his name to any

>

certifications for the named QC Supervisor.

It was also stated

that this same QC Supervisor misplaces / destroys NCRs and DRs.

A QC inspector (by name) told the alleger that the Supervisor

destroyed three of his NCRs/DRs. The named QC Supervisor managed

by intimidation and was interested in quantity, not quality.

NRC Review: The NRC inspector reviewed the training,

!

qualification and certification file for the named QC Supervisor.

Except for a resume, this individual's file folder was blank.

,

,

HECo Procedure 17, " Qualification and Training of Inspection and

i

Audit Personnel", Paragraph 5.3, requires that all QA/QC personnel

!

complete the "QA/QC Personnel Indoctrination Checklist",

Form 172. This indoctrination includes but is not limited to:

4

reading electrical specifications; knowing Byron alarm signals,

i

<

emergency phone location and procedure; reading the HECo QA

Manual and QC procedures; and becoming familiar with the S&L

i

drawings and standards.

This named QC Supervisor started his

employment with HEco at the Byron Station on October 7,1985,

and as of June 13, 1986, he had not started his basic

!

indoctrination as indicated by his file.

In addition, the HECo

QA/QC Manager (Employment date of August 6,1984) and the QA

.

Supervisor (employment date of February 25,1985) had not

1

l

completed their basic indoctrination as of June 13, 1986. The

i

16

- - ,

. .

.

- - - .

,..- - -.-

,

- .

. .

- - - - . - - , , - . - . -

QA Supervisor inform d the NRC inspector that none of his QA

engineers had completed this training. During an interview

of the named Level III inspector, the NRC inspector was informed

that the Level III had no confidence in the named QC Supervisor

and that he would not certify him to any procedures.

On August 6, 1986, a physical search was made of the named QC

Supervisors office and no open NCRs, DRs or 0 irs were found.

During an interview of the named OC inspector, he did not

identify any concerns pertaining to any specific documents that

the named QC Supervisor may have destroyed. As stated in

Paragraph 5.a.(10) above, there was a lack of communications

between Supervision and the QC inspectors, however, based on the

small rejection rate (0.25%) of HECo QC inspection activities by

PTL's overinspection, this lack of communication did not affect

quality.

Conclusions:

It was verified that the named QC Supervisor was

not certified and the named Level III would not certify him,

however, there is no requirement for a supervisor to be certified

if he/she does not perform QC acceptance inspections.

It could

not be verified that this supervisor destroyed or misplaced any

quality related documentation. Based on the results of PTL's

overinspection program, this supervisor's management techniques

did not affect the quality of the project. However, the licensee

was informed that failure to assure that indoctrination and

training was provided to QA/QC personnel in accordance with

approved procedures is and example of failure to implement

Criterion II of 10 CFR 50, Appendix B (454/86031-14A;

455/86017-14A).

(15) Concern: The QA/QC Manager told a QC Group Leader (by name)

to hold a stack of Unit 1 inspection reports. These reports

identified deficiencies that were never corrected and items

that were never reinspected. The Unit 1 turnover logs are not

accurate.

NRC Review: On July 18, 1986, while conducting personnel

interviews related to this concern, the NRC inspector was

provided a printout that listed 44 Unit 1 and 11 Unit 2 open

inspection reports. The NRC inspector provided a copy of this

printout to the CECO QA Site Superintendent for information and

corrective action.

In that Unit I was shutdown for other

maintenarce activities, immediate action was taken to resolve

the 44 Unit 1 open inspection reports. The reinspection

identified some deficiencies which resulted in 15 nuclear work

requests (NWR) being issued to rework and reinspect the

identified deficiencies. Upon returning to Byron Station on

Monday, July 21, 1986, the NRC inspector was informed that all

corrective actions had been completed to resolve the deficiencies.

The inspector reviewed all the NWRs and selected 12 for physical

inspection of the reworked items. All corrective actions

reviewed were found to be adequate.

Following are examples

of the deficiencies identified:

17

l

l

l

. .

.

-._.

-

.-

t

NWR 6DG049 - Class IE Equipment Modification Inspection

Report No. 4377, dated August 15, 1983, identified that all

the bolts.on a buss bar insulator support were loose (i.e.,

less than finger tight). This deficiency was located in

Unit 1 4160V diesel generator panel IDG01KB.

NWRs 6DG046 and 6DG047 identified improperly installed

,

4

heat shrink tubing.

Six NWRs identified conductor insulation damage.

In

several cases, the copper. conductor was also damaged.

In these cases, damaged conductors were cut off and new

conductors butt spliced onto the cable.

Five NWRs required the replacement of termination lugs

due to improper installation or damage.

To determine the root cause for Unit 1 inspection reports still

being open approximately 17 months after the unit went into

operation, additional interviews were conducted. During these

interviews, the NRC inspector was informed that a HECo QC Group

Leader was made aware of the existence of an unknown quantity of

Unit 1 inspection reports in HECo's possession that had not

been processed. With HEco management approval, a physical

search of the HEco premises was conducted on April 12, 1986.

This search uncovered 360 Unit I and 13 Unit 2 inspection

reports in a tool box controlled by the QC Group Leader named

in the concern. This named Group Leader was permitted to

resign, effective April 22, 1986, indicating that he was not

holding these reports at the direction of the QA/QC Manager.

HECo QA took possession of these 373 reports and-initiated a

review to determine acceptability. In that Unit I had been

turned-over to CECO, the HECo Quality Program had no means to

'

'

formally transmit a Unit 1 deficiency to CECO except when they

are performing work activities under the licensee's nuclear

work request (NWR) program. A review of the HECo QA Manual and

Specifications F-2790 indicated that the requirements of

10 CFR 21 had not been imposed on HECo.

In addition, a

Commonwealth Edison Company Vice President stated during a meeting

i.

in the NRC's Region III Office on July 2, 1986, that Commonwealth

Edison Company does not impose the requirements of 10 CFR Part 21

on any of their onsite contractors. On approximately June 10,

1986, a HEC 0 QC Group Leader informally informed the CECO PCD

Project Electrical Supervisor and a PCD Electrical Engineer of

the 44 Unit 1 open inspection reports that had been identified by

'

HECo QA.

In that the HECo QA/QC Manager and QA Supervisor had

'

baen terminated approximately July 2,1986, the NRC inspector

could not determine why CECO was not notified sooner. When

cuestioned as to why he (QC Group Leader) decided to inform CECO

of the open inspection reports, he responded, "I knew that sooner

,t

,

,,

18

t

,, - - - . . - - - - . - _

,

-- - , . - . .

,.-...c

-

--,,#.,r.-

-

m.,.,-e.,.xm,.

,m

m-

r--.-

4

e---..,

---.-s..

.,--~r.-,m7_.u

- , - , , , . , . , +

r

,-y

-

-

or later you would ask the right question and I thought they

(CECO) should know about it before I had to tell you."

Although

CECO PCD became aware of the Unit 1 open inspection reports on

approximately June 10, 1986, this fact was not documented in

any CECO corrective action system as of July 18, 1986.

Based on this latest information, the inspector queried several

QA engineers to determine the location and status of the 360

Unit 1 inspection reports. Upon request, the NRC inspector was

provided a stack of Unit 1 inspection reports. Again, this

information was shared with the CECO QA Site Superintendent.

During a review of these reports, it was observed that there

were 28 unnumbered inspection reports r.nd an additional 13

reports where the status of the item was indetcrminate.

An

immediate reinspection of these items was initiated by the

licensee. This reinspection verified that five of the inspection

reports were acceptable and eight reports required rework and

reinspection. The rework and reinspection was completed in

approximately 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />.

The NRC inspector performed in process

inspections of these work activities and found them to be adequate.

In addition to the 360 Unit 1 inspection reports discussed above,

HECo QA had an additional 81 closed Unit 1 inspection reports for

work activities directed by the licensee. On approximately

July 24, 1986, these 441 (360 plus 81) Unit 1 inspection reports

were transmitted to the licensee on transmittals 293, 294, 323,

and 314.

With respect to the concern regarding Unit 1 turnover logs, the

concern was substantiated by the fact that neither the turnover

reports or turnover log identified the 360 inspection reports

discussed above.

In addition, HECo failed to establish a

system to accurately status inspection reports (i.e., open,

closed) to preclude inadvertent bypassing required inspections

and tests and assurance of final acceptance.

The NRC inspector also established during the review of this

concern that CECO does not have a proceduralized system for

Byron Construction to notify Byron Operations of construction

deficiencies which could potentially impact the safe operation

of Unit 1.

Also, it was apparent that CECO does not have an

effective system to determine if the site contractors have

turned-over all required documentation prior to accepting an

item / system from the contractors (HECo).

Also, as of July 17, 1986, the deficiencies identified with

Unit 1 items, as identified above, were not evaluated for

reportability per the requirements of 10 CFR 21. An evaluation

for reportability would have been initiated per procedure if

CECO PCD had prepared an NCR when they learned of the open

Unit 1 inspection reports.

,

19

Conclusions:

It was established that HECo was holding 360

Unit 1 inspection reports (with an indeterminate status) and

that CECO was not aware of this problem until approximately

June 10, 1986. Of these 360 reports, 28 were not numbered and

57 required reinspection or rework and reinspection.

It was

also verified that the HECo turnover log / reports were not accurate

in that these 360 Unit I reports were not listed.

The licensee was informed that:

(a) Failure to incorporate the provisions of 10 CFR 21 intc

the HECo contract is an example of a failure to implement

Paragraph 21.31, " Procurement Documents", of 10 CFR 21.

This violation is generic for all CECO site contractors

(454/86031-02; 455/86017-04).

(b)

Failure to assure that conditions adverse to quality were

promptly identified and corrected is an example of a

failure to implement Criterion XVI of 10 CFR 50, Appendix B

(454/86031-04).

(c) Failure of the electrical contractor (HECo) to ensure that

all required documentation (inspection reports) were

contained in the Unit I turnover packages in accordance

with HECo Procedure 22A is an example of a failure to

implement Criterion V of 10 CFR 50, Appendix B (454/86031-05).

(d) Failure of the electrical contractor (HECo) to establish a

system to accurately status inspection reports to preclude

inadvertent bypassing required inspections and tests is an

example of a failure to implement Criterion XIV of 10 CFR 50,

Appendix B (454/86031-06; 455/86017-05).

(e) Failure of CECO to have a proceduralized system for Byron

Construction to notify Byron Operations of deficiencies

which could potentially impact the safe operation of Unit 1

is an example of a failure to implement Criterion V of

10 CFR 50, Appendix B (454/86031-07).

(16) Concern: HECo received an FCR for a TYK connection, (this.is a

tube steel to tube steel weld). HECo was to qualify this joint

but they never prepared a WPS or anything. AWS does not have a

pre qualified procedure for a flared V weld.

NRC Review: During interviews of QC personnel regarding this

concern, the NRC inspector was provided a copy of Discrepancy

Report (DR) 8311.

The DR stated, " Weld detail DV-315 and DV-316

on drawing 1-3366F, Revision E, requires a flare V groove weld.

Hatfield has no welding procedure for this joint configuration."

The resolution to this problem was to revise the joint

configuration so that a flare V groove weld was no longer

required. This was accomplished by S&L's approval of Field

Change Request (FCR) No. F-26801 and FCR No. F-26803.

20

_ _-

.,

__

_ _.

_

. - . _ _ . . - -

_

_ _

. __

..

Conclusion: Based on the NRC inspector's review, it'was

established that HECo did not have a qualified weld procedure

for flared V groove welds. However, the requirements for this

type weld was deleted by issuing FCRs F-26801 and F-26803. No

violations or deviations were identified.

(17) Concern: Welding QC inspectors were denied overtime (OT)

because their number of inspections were not up to par. Also,

'

the Level III Welding Inspector (by name) stated at a safety

meeting on May 7,1986, that there was a planned lay-off in

August and the inspectors with the most acceptable inspections

would stay. Quantity not Quality.

NRC Review: With respect to the concern that welding QC

,

l

inspectors were denied 0T because their number of inspections

were not up to par, this concern was refuted. During personnel

'

interviews, the NRC inspector was informed of OT problems in

January 1986 and was provided copies of letters on this

subject.

Overtime had been scheduled for numerous welding and

conduit inspectors on Saturday, January 25, 1986, however, 11

,

inspectors (including the alleger) failed to show up for the

scheduled overtime. The following week, when the OT schedule

i'

-was being prepared, these 11 inspectors were not asked to work

due-to their refusal to work the previous week. The QC

Supervisor had a change of. heart after some of the inspectors

apologized for their actions the previous week at about 4:00

p.m. January 31, 1986.

In that the alleger had left the site

at approximately 2:30 p.m. that day, he could not be contacted

i.

to work on Saturday, February 1,1986.

With respect to the scheduled lay-off, as a result of personnel

interviews and observing the reduction in force (RIF) schedule,

.

this concern could not be substantiated. As part of this

I

inspection, the NRC inspector obtained the HECo RIF schedule from

l

CECO. This schedule was prepared by HECo and submitted to CECO

for information. This RIF schedule has been generally adhered

'

'

to.

The exceptions to this schedule are as follows:

four

inspectors were terminated due to positive tests for drugs

,

(Reference Paragraph 5.b of this report); termination of the

QA/QC Manager, QA Supervisor, and QC Supervisor; and the

extension of employment of several inspectors. The named

Level III welding inspector stated that he had informed his

inspectors of the pending RIF, and that the RIF schedule was

'

determined by their Lead Inspector's evaluation of their

performance and attendance. This statement was confirmed during

.1

interviews of other QC personnel. The safety meeting was not

limited to welding inspectors in that the named Level III is

also the Assistant QC Supervisor. See Paragraph 5.a.(10) on

quality of inspections.

21

i

_ _.

.

-

.

. - -

_ _ . _ _ _ _ . . . . , . _

Conclusion: Based on personnel interviews, review of HECo

letters, and the comparison of the RIF schedule with

termination dates, these concerns could not be substantiated.

See Paragraph 5.a.(10) on quality of inspections. No violations

or deviations were identified.

(18) Concern: HEco engineering sent out a clarification letter on

Detail J installations. An inspector rejected an installation

based on this letter and a discussion with an S&L engineer.

Engineering reversed their decision after thousands of

Detail Js were installed and the inspector got hell for going

to S&L.

NRC Review: During personnel interviews, the NRC inspector was

provided a copy of the subject letters and Discrepancy Report

(DR) 8320. The first letter, dated March 8, 1985, provided two

examples of acceptable Detail J (type of raceway support)

configurations and one example that wcs unacceptable. A QC

inspector contacted an S&L engineer for an interpretation on a

hanger being inspected.

In accordance with the S&L engineer,

the QC inspector described the unacceptable Detail J

configuration. The S&L engineer informed the QC inspector

that the configuration described was unacceptable. Based on his

discussion with the S&L engineer and HECo engineering letter of

March 8,1985, the QC inspector prepared DR 8320 on February 20,

1986. The DR was dispositioned "No Discrepancy as Written" with

justification.

It appears that the QC inspector confused a CS

type connection (actually installed) with an unacceptable

Detail J type connection. These two types of connections are

similar in appearance except, the CS connection is welded at

the four coraers only and the unacceptable Detail J is welded

on two sides of the plate.

DR 8320 was closed on March 3, 1986.

The second HECo letter on Detail J connections, dated April 22,

1986, states, in part, "The acceptable configurations for a

Detail J are shown on the attached sketch. Notice that the

configuration that was disallowed in the March 8, 1985, letter

has been re-analyzed by S&L structural as being acceptable."

From a safety stand point, the 1986 letter did not disallow any

configurations that were allowed in the 1985 letter. Also, the

design change was made by S&L, not HECo engineering, and is

shown on S&L drawing 6E-0-3393F.

In accordance with HECo

policy, HECo engineering interfaces with S&L engineering.

If a

HECo QC inspector has an engineering type problem, they are to

take their problem, through their Lead, to HECo engineering for

re:,ol u tion. This policy meets the intent of Criterion III of

10 CFR 50, Appendix B, which states, in part, " Measures shall

be established for the identification and control of design

interfaces. . . ."

Conclusions: HECo engineering did in fact issue two

clarification letters on Detail J configurations. The second

letter, based on an S&L analysis, allows the installation of a

previously disallowed configuration. The use of these two HECo

22

_ _ _

__

_

_ . _

engineering letters would not permit the installation of an

unacceptable Detail J configuration. DR 8320 was properly

closed. HECo interface policy with S&L is acceptable. No

violations or deviations were identified.

(19) Concern: A QC inspector (by name) prepared an NCR approximately

one year ago for cross-flange welds, blow hole (burn thru) in

the J-Box, no welding pre-heat, and welded with 6010 rod. This

J-Box is located in the cable spread room, 451' elevation, and

the cables entering this J-Box came from the screenhouse. The

NCR was dispositioned use-as-is and it shouldn't have been.

NRC Review: During a review of NCRs issued in the timeframe

specified above and interviews of QC personnel, NCR 1537, dated

June 10, 1985, was identified as the NCR of concern. This NCR

documented four cross-flange welds, use of 6010 rod and lack of

pre-heat during the installation of J-Box 704A. The J-Box was

located in the cable spread room at columns 21 and P at the

473' elevation. The S&L approved disposition stated, " Abandon

the four cross-flange welds and add new welds per FCR 70050."

'

NCR 1537 was properly closed on July 29, 1985, by the alleger.

Conclusions: This concern was not substantiated in that NCR

1537 was reworked in accordance with an S&L approved disposition

and the NCR was properly closed by the alleger.

(20) Concern: The HECo QA/QC Manager (by name) is " bird-dogging" a

QC inspector (by name). Every time the named QC inspector came

to the office to review drawings or documentation, the named

QA/QC manager would call the inspector's Lead and/or the

Assistant QC Supervisor or the QC Supervisor and inquire as

to why the named inspector was in the office again.

NRC Review: As part of the followup on this concern, the NRC

inspector reviewed the Byron SRI's notes of his interviews of

the named QC inspector and named QA/QC Manager on the

" bird-dogging" issue. The NRC inspector was unable to interview

the named QA/QC Manager, the involved QC Supervisor, and one of

the involved Lead Inspectors because they were no longer employed

by HECo. The NRC inspector interviewed co-workers and previous

supervisors of the named QC inspector and also reviewed

performance evaluations of this QC inspector. The named QC

inspector was assigned to work out of a field office some

distance from the HECo main office. All the QC inspectors and

supervisors working out of the field office had a need to go to

the main office to review " vaulted" documents. During personnel

interviews, the NRC inspector was informed that the named QC

inspector was noted for his socializing when he had to go to

the main office.

During an interview with the NRC SRI, the named

QA/QC Manager stated that he did in fact call the inspector's

superv,isor one time to verify that the inspector had a need to

be in the main office.

The QA/QC Manager also stated that he

made the call to the supervisor only after cbserving the named

P

23

se,

w-

-

w

,

I

/

!

QC inspector in the main office every day for a week. During

an interview of the involved supervisor, he stated that the

QA/QC Manager called him several times about the named QC

inspector being in the main office.

The supervisor also stated

that in general, the inspector had a need to be in the main

office and the inspector's Lead knew the task being worked on.

The supervisor said that at times he felt that the QC inspector

would invent reasons to go to the main office just to antagonize

the QA/QC Manager. However, from a review of performance

evaluations and additional interviews, it would appear that

undue restrictions were placed on the named inspector in that

he was the only inspector that required specific approval from

his Lead Inspector to go to the main office.

Following is part

of a written statement (one of four) made by one of the named

inspector's Leads, "During the period from January 6 to April 28,

1986 (named inspector) was assigned to the Welding QC Department

under my supervision.

During this period I was directed by

(name) (QC Supervisor) and (name) (Asst. QC Supervisor) to

insure that (name) did not make unnecessary visits to the

Hatfield Main Office.

(Name) was to inform me of his reasons

for such visits to the main office.

I understand the reason

for this policy being implemented was that (name) had previously

been observed spending unnecessary time in the main office."

This written statement is typical of the four statements provided

to the inspector.

Conclusions: Based on interviews of QA/QC personnel and the

review of written statements, it appears that undue restrictions

(bird-dogging) were placed on the named inspector in that he

was the only inspector that required specific approval to go to

the HECo Main Office. However, a contributing factor appears

to be his (named inspector) excessive socializing while in the

main office and attitude toward QA/QC management.

No violations

or deviations were identified.

(21) Concern: Construction worked through a Hold Tag (NCR 1860).

The inspector could not write an NCR, instead QA wrote

Corrective Action Reports (CAR) 002 and 003.

NRC Review: During an interview with the alleger, the NRC

inspector was provided a copy of a draft NCR (NCR without a

report number assigned) and CARS 002 and 003. The draft NCR

stated that Hold Tag 1860 was attached to J-Box 2JB683A and

that construction installed conduit and cable in the J-Box in

violation of the Hold Tag. The inspector reviewed the NCRs

prepared in the same timeframe (February 1986) to verify that

the draft NCR had not been placed in the system without the

alleger's knowledge. No NCR was observed for working through

Hold Tag 1860. CAR 002 was prepared on February 17, 1986 to

document the violation of Hold Tags, with a sequence of events

attached. On February 21, 1986, CAR 002 was voided due to an

incorrect description of the concern and CAR 003 was prepared.

24

i

--

_

CAR 003 not only described the violation of Hold Tag 1860

(NCR 1860), it also describes the violation of Hold Tag 1825

(NCR 1825).

CAR 003 was properly closed on March 11, 1986.

For this type of nonconformance, working through Hold Tags, the

CAR would be the most effective document in that it receives a

higher level of management review.

Conclusions:

This concern was substantiated, however, for

this type of nonconformance the CAR would be the most effective

document to identfy and resolve these violation. No violations

or deviations were identified.

(22) Concern: HECo was working through Hold Tags per direction from

CECO PCD.

NRC Review: The NRC inspector was provided a copy of a memo to

the HECo QA/QC Manager, dated January 16, 1985.

Following is a

sequence of events as described in the above referenced memo:

(a) Roughneck (Ceco's core holing contractor) was coring a 3"

hole for HEco when a rebar was hit. The HECo QC inspector

verbally stopped work and prepared NCR 1281 to document

the rebar hit.

(b) A HECo QC supervisor informed the PCD engineer that work

could not continue on the coring until HECo received a

disposition on the NCR.

(c) A Ceco PCD engineer (by name) instructed Roughneck to

continue coring the hole and that an FCR would be prepared

to allow the rebar hit.

(d) When the inspector went back to the area to attach the

Hold Tag, he observed that the core hole had been

completed.

(e) S&L issued FCR F-25836 after NCR 1281 was prepared _ without

referencing the NCR, indicating that the FCR was being

used to document a nonconforming condition.

Based on the above memo, the NRC inspector performed an indepth

i

review of HECo core drilling activities.

Even though the

'

actual core drilling is performed by a different contractor,

HECo is responsible for the inspection and documentation of the

cering when tbc hele is being used for electrical installations.

'

HECo Procedure 21, " Cored Hole Installation and Inspections,"

states, in part, " Paragraph 5.1.13 - No items may be installed

in a cored hole until Hatfield Electric Company receives a

completed CHR (Cored Hole Report) signed off by CECO PCD.

Paragraph 5.3.3.3 - Only cored holes in Category I structures

.

where rebar has been cut and/or hit and which are in areas

!

'

where rebar cuts are not allowed, shall have the cut / hit

documented on a HECo NCR. The NCR number shall be referenced on

f

.. - . - , -

, -

- - -

_ _ ~ . . _ _ _ , - ,

.

. - -

- _ _ -

,


.-.-.3-4_,.

-,

e...-.-

, --

l

the CHR." Paragraph 5.3.5.3 of HECo Procedure 6, " Reporting of

,

Damaged or Nonconforming Material or Equipment," states, " Items

'

identified as nonconforming, if not yet installed, may not be

i

used or if installed, may not have additional work performed on

them unless it is authorized by the owner."

A review of HECo's NCR form indicates that the owner's

authorization to work on a nonconforming item prior to corrective

action being completed (work may proceed) requires approval by

CECO PCD with concurrence by CECO QA. During an interview with

the CECO QA Superintendent, he stated that the NRC inspector's

understanding of the HECo NCR form was correct in that " Work May

Proceed" must be approved by CECO PCD and receive concurrence

from Ceco QA. During a review of HECo NCRs, the NRC inspector

observed that when HECo prepares an NCR to document the fact

that HECo construction installed conduit in a cored hole in

violation of a " Hold Tag", the NCR would be forwarded to CECO

PCD for disposition. A typical disposition by CECO's Project

Electrical Supervisor for this type NCR is "This is not an NCR,

therefore, no C/A (Corrective Action) is required." With the

explanation that "The completed CHR, signed off by CECO PCD is

the owner's authorization to proceed with installation work."

NCRs 2056 and 1627 are two examples with the above disposition.

In addition, the inspector was provided several " draft" NCRs

(i.e., no number assigned) that were voided by the HECo QA/QC

Manager with the disposition for UCR 1627 attached.

During an

interview of the CECO PCD structural engineer (engineer that

reviews and approves CHRs), the NRC inspector received the

impression that this Engineer did not realize that his signature

was the Owner's authorization (per NCR dispositions) for HECo

to proceed with installation work when there was an open NCR on

the subject cored hole.

During a review of NCRs on cored holes versus conduit

installation reports, approximately ten instances were identified

where " Hold Tags" were violated. However these violations were

not documented based on PCD's interpretation of Owner's

authorization.

Conclusions:

Based on the NRC inspector's review as noted above,

it was established that CECO PCD (Project Electrical

Supervisor) directed HECo to violate their Procedure 6 with

respect to Owner's authorization for continued work on a

nonconforming item.

This violation appeared to be for cored

holes only.

The licensee was informed that failure to control

nonconforming item to prevent their inadvertent use is an

example of failure to implement Criterion XV of 10 CFR 50,

Appendix B (455/86017-06).

(23) Concern: HECo Project Engineer (by name) threatened to void NCR

on procedure violation.

The alleger told the Project Engineer

that he would take the NCR to the NRC if it was voided.

The

Project Engineer signed the NCR.

Example was not provided.

26

__.

-

- -.

.

-.

___

NRC Review: The NRC inspector reviewed HECo Procedure 6,

" Reporting of Damaged or Nonconforming Material or Equipment,"

to determine the duties and responsibilities of the Project

Engineer with respect to NCRs.

Paragraph 5.3.3 assigns the

responsibility for preparing NCRs to HECo QA and Engineering.

During the review of NCRs, it was noted that both QA and

Engineering did, in fact, prepare NCRs.

Paragraph 5.3.4

assigns the responsibility for the completion of the deficiency

description on the Construction Deficiency Evaluation (CDE) form

and attaching this form to the NCR. Utilizing this form, the

licensee evaluates the deficiency for reportability per the

requirements of 10 CFR 50.55(e). A completed CDE form was

attached to all NCRs reviewed during this inspection.

Paragraph 5.3.6.1 assigns HECo engineer the responsibility for

completion of Part II (Corrective Action and Action to Prevent

Recurrence) of the NCR, when appropriate, prior to review by the

HECo QA/QC Manager. This is a recommended disposition only.

The final disposition is made by the licensee and/or S&L. When

the NCR comes back from the licensee, HECo engineering is

responsible for notifying the appropriate personnel of the

required " corrective action" and " action to prevent recurrence"

to be implemented. The only time the Project Engineer signs an

NCR is when he is the preparer of the NCR. During the NRC

inspector's review of hundreds of NCRs, it was observed that all

voided NCRs had been voided by the HECo QA/QC Manager.

'

Conclusions: Based on the NRC inspector's review of Procedure 6

and hundreds of NCRs, this concern could not be substantiated.

No violations or deviations were identified.

(24) Concern:

Procedure 20, " Class I Exposed Conduit System

Installation," Paragraph 5.6.5, states that final inspection

of conduit terminations would be made during cable termination

inspections. This is not addressed in Procedure 11, " Class I

Cable Termination and Splicing."

NRC Review:

Paragraph 5.6.5 of Procedure 20 states, in effect,

that final inspection of conduit terminations to equipment,

except J-Boxes and Pull-Boxes, would be made during cable

termination inspections when the equipment was not installed at

'

time of the conduit inspection, per Procedure 11.

Paragraph

5.1.24.1 of HECo Procedure 11 states, in part, "If a short run

of Sealtite or conduit is required to bring the cable into a

gear, Hatfield QC must be notified so that any required

,

inspections can be picked up."

This attribute is inspected

and documented on Form HP-118, " Cable Termination Inspection

Report," item 14. The NRC inspector reviewed HP118 Reports

21601 through 21850 and verified that item 14 was being

inspected by the QC inspector.

No deficiencies were

'

identified.

o

l

27

l

.

.

..

.

.__

__ .

- -

.

-_.

- .-

Conclusions: Based on the NRC inspector's review of HECo

Procedures 11 and 20, and the review of 250 Cable Termination

Inspection Reports, this concern was not substantiated.

No

violations or deviations were identified.

(25) Concern:

For Battery Rack 2DC01EA and 2EC02EA, the minimum

embed depth for CEAs (concrete expansion anchors) is four

inches.

PTL (Pittsburgh Testing Laboratory) Reports 23821 and

23820 indicated embed depths of 3 1/2" and 3 1/8". A HECo QC

inspector (by name) could not write an NCR on these two

nonconforming conditions.

NRC Review: During interviews of HECo QC and engineering

personnel and CECO QA and engineering personnel, the NRC inspector

was informed that Blount Brothers Corporation (BBC) installed

the CEAs for Battery Racks 2DC01EA and 20C02EA.

During the CAT

Inspection on August 19 through September 20, 1985 (Reference:

IE Report No. 50-455/85027), an inspector identified one CEA on

each of the subject battery racks that did not appear to meet

the minimum embed depth. As a result of this observation, PTL

was directed to inspect the CEAs for these two racks. Using

the ultrasonic test (UT) method, PTL identified one of ten CEAs

on battery rack 2DC01EA with an embed depth of 31/2". The

other nine CEAs exceeded the minimum 4" embed depth (Reference:

PTL Report 23821, dated September 10,1985). Based on this PTL

report, BBC prepared Deviation Report (DR) Q3-955 to document

the deficiency. This deficient CEA was evaluated by S&L and DR

Q3-955 was dispositioned "use-as-is" and FCR F44367 was issued

to document the as-built conditions.

PTL also identified one of

ten CEAs on battery rack 2DC02EA with an embed depth of 31/8".

The other nine CEAs exceeded the minimum 4" embed depth

(Reference: PTL Report 23820, dated September 10,1985). This

deficiency had been previously identified on September 15, 1983,

as documented on BBC's OR Q3-725.

S&L issued FCR F-43535, dated

May 29, 1984, to accept the CEA (DR Q3-725) in the as-found

condition. Based on the licensee's actions, this item was

closed in the CAT Report 455/85027, Paragraph II.B.3.b.(5).

Based on the CAT report and the NRC inspector's review of the

PTL reports, BBC DRs, and S&L FCRs discussed above, the NRC

inspector determined that there was no need for HECo to prepare

an NCR to identify the same nonconforming issues.

Conciustoas: Based on the NRC CAT inspection report and the

NRC inspector's review of the applicable documents referenced

above, it was concluded that there was no need for HECo to

prepare an NCR or tne two CEAs that did not meet the minimum

embed depth. No violations or deviations were identified.

l

l

'

28

!

l

l

.

.-.

-

,-

-

__

(26) Concern: There are no weld travelers listed for conduit hanger

WP2-1 on hanger inspection report (Form HP-203) number 1021.

Two Detail J's are not welded to the hanger and the AP

attachment is no good.

NRC Review: Utilizing the WANG (computerized tracking system),

it was determined that no weld travelers were listed for hanger

WP2-1.

During a review of inspection report 1021, the NRC

inspector observed that hangers TS-1, WP2-1, SWCP3-3, and

SWCP3-4 had been inspected to drawing 0-3302A and were found

acceptable on May 4, 1982. A review of the applicable drawing

indicated that these hangers were located in the Auxiliary

Building, Columns 15 and L, 346' elevation. During a physical

inspection of conduit hanger WP2-1, the NRC inspector observed

that the two Detail J's (steel plates) were not attached (welded)

to the hanger and tbc AP connection was not installed per the

design drawing and that hanger WP2-1 supports conduits C0A0203

and C0A0204.

In that hangers / supports are also verified during

conduit inspections, the inspector reviewed Conduit (C0A0203)

Inspection Checklist 928, dated May 5,1982 and Conduit (C0A0204)

Inspection Checklist 929, dated May 5,1982. During the review,

both of these checklists (928 and 929), the supports were checked

as acceptable and hanger inspection Report 1021 was referenced,

and both reports were signed off as being acceptable.

During

electrical cable installation, a pre pull inspection is performed

on the applicable raceway and this inspection is documented in

Part 1 of the Cable Installation Inspection Checklist

(Form HP-105) (Reference: HECo Procedure 10).

From applicable

records, the NRC inspector determined that cable 2SX031-P1E was

installed in conduit C0A0204 and cable 2SX032-CIE was installed

in conduit C0A0203. A review of Cable Installation Inspection

Checklist for cable 2SX032 indicated that the raceway was

acceptable, and the cable was released for pull on October 13,

1982. Cable 2SX032 was installed on November 8, 1982. A

review of Cable Installation Checklist for cable 2SX031 has

conduit (Part 1, Item B) marked as "N/A", however, Page 3 of 3

'

of this checklist listed conduits C0A09E5 and C0A0204 for cable

routing points. The checklist for cable 2SX031 indicated that

the cable was released for installation and installed on April 27,

1984. On July 30, 1986, the licensee prepared NCR 2059 on hanger

WP2-1 to document the as-found condition. The issuance of this

NCR should result in the correction of the problems found with

hanger WP2-1.

Corclusions: This concern was substantiated in that a physical

inspection of hanger WP2-1 revealed two detail J connections were

not welded and the AP attachment was not in its designed location.

Also, using the WANG, it was determined that a weld traveler had

not been prepared for hanger WP2-1, listed on drawing 0-3302A.

The licensee was informed that failure to assure that measures

,

were established to promptly identify and correct conditicns

adverse to quality is an example of a failure to implement

Criterion XVI of 10 CFR 50, Appendix B (455/86017-07A).

<

29

._

_

_

(27) Concern: There are no conduit inspection reports (Form HP-201)

for conduits C0A32K8-C2E, C0A2265-K2E, C0A0282-P2E and

C0A0283-C2E.

NRC Review:

During interviews of HECo QC and engineering

personnel and review of applicable records, the NRC inspector

established that the conduits noted above were installed in

Byron Unit 1.

Utilizing the WANG system, it was also established

that conduit inspection reports (Form HP-201) for the subject

conduits did not exist. The licensee determined that the subject

conduits did not need to be reinspected to HECo's routine

inspection program (Procedure 20) in that they had been inspected

and accepted under the licensee's as-built inspection program.

Conclusions: The HP201 forms had not been prepared to document

the inspection and acceptance of conduit C0A32K8, C0A2265,

C0A0282 and C0A0283, however, these conduits had been

subsequently inspected and accepted under the licensee's as-built

inspection program. No violations or deviations were identified.

(28) Concern: Nonconformance reports (NCR) are typically

dispositioned "use-as-is."

Think there should be more rework

or repeir dispositions.

Corrective action to prevent recurrence

is not effective or not adequate (Reference: HEco memo 1866)).

Poor disposition on NCR 1581.

NRC Review: The NRC inspector reviewed all HECo NCRs prepared

between June 1,1985 and June 8,1986. The NRC inspector also

reviewed HECo Procedure 6, " Reporting of Damaged or Nonconforming

Material or Equipment." In that most of the items requiring

rework / repair are documented on Inspection Reports (IR) or

Discrepancy Reports (DR), the NCR is generally reserved for

deficiencies that HECo is requesting an analysis for a "use-as-is"

disposition. The NRC inspector reviewed the NCRs for proper

closure with respect to corrective action and action to prevent

recurrence. During the review, the NRC inspector selected

approximately 30 NCRs for review of analyses at the S&L onsite

facilities. All analyses reviewed at S&L were found to be

adequate.

During the review of NCR 1990, it was observed that Pin Connector

Termination Tool W-002 had been sent to Burndy for repair and

calibration. Tool W-002 was received back onsite in calibration,

however, Burndy failed to record the as-found condition, thus

making the quality of the termination crimps made since the

previous acceptable calibration indeterminate. During the review

of the tool checkout log and inspection reports, HECo determined

that Tool W-002 had been utilized on 16 plug connectors since

the previous calibration. The NCR (1990) was dispositioned

" Accept crimps as is. The last 16 inspections were done in

proces; and the crim;. tool's calibration date had not been

reached when the tool was in use."

This disposition was approved

by a CECO PCD engineer without considering that all documentation

from Burndy indicated that the tool had been repaired. After

l

30

E

-

. -

the NRC inspector expressed a concern with the disposition of

NCR 1990, the licensee obtained the tool acceptance criteria

from Burndy.

From the HECo inspection reports, the last usage

of the tool was identified. Using the information from Burndy,

the licensee measured the termination crimp indents and found

them acceptable. This reinspection resolved the inspector's

concern with the acceptability of the crimps made with

Tool W-002.

HECo NCR 1581 and CECO NCR F-997 documented the improper use

of Kellem type cable grips (Detail G) that was specified for

use in the Auxiliary Electrical Equipment Room only and was

used in other areas of the plant.

S&L issued FCR F-6665 to

allow the use of Detail G cable grips in all areas of the

plant. S&L drawing 6E-0-3393P was revised to incorporate this

FCR.

CECO NCR F-997 was properly closed on November 22, 1985,

based on the issucce of FCR F-6665 and the training of HECo

crt.f t personnel . 3ECo NCR 1581 was properly closed on

December 3, 1985, based on the closure of CECO NCR F-997.

On May 23, 1985, a training session with craft personnel was

conducted due to the number of nonconformances being identified

by HECo QC inspectors. Topics covered included installation

requirements; drawings; S&L standards; HECo procedures; and the

requirement to obtain prior written approval before making any

deviations. HECo QA/QC Memorandum 1866 was prepared to

document this training and states, in part, "This training

session covers training required per ' Action to Prevent

<

Recurrence' for any NCR's written on work completed prior to

May 23, 1985." During the review of NCRs, Memorandum 1866 was

referenced on numerous NCRs, however, no misuse of the memorandum

was observed.

With respect to " Action to Prevent Recurrence," during the

review of NCRs, the inspector observed 12 instances where NCRs

were improperly closed before action to prevent recurrence had

been completed.

(Reference: NCRs 1772, 1758, 1754, 1798, 1787,

'

1783, 1825, 1822, 1818, 1816, 1815, and 1802) Based on the

NRC inspector's concern, HECo QA performed a review of NCRs and

identified 38 NCRs that were improperly closed before action to

prevent recurrence had been completed.

In addition, CECO QA

Audit 6-86-201 identified that the instruction / retraining required

as part of the action to prevent recurrence had not taken place

until, in some cases, nine months after the NCR was prepared.

This resulted in additional NCRs being prepared on the same type

problems involving the same personnel.

Conclusions: A review of NCR 1581 indicated that the disposition

'

was adequate based on S&L analysis and the issuance of FCR F-6665.

,

For the NCRs reviewed, with one exception, the NRC inspector

found the "use-as-is" disposition acceptable.

For NCR 1990, it

was identified that there was inadequate justification for the

31

.

_

_ _

_

_

- .

.

_

__.

"use-as-is" disposition until additional tests were performed.

During the review of Action to Prevent Recurrence, the NRC

inspector identified 12 NCRs that were closed before action to

prevent recurrence was completed. The licensee also identified

that in many cases the action to prevent recurrence was not

effective due to the time interval between the preparation of

the NCR and the implementation of the required retraining.

The licensee was informed that failure to assure that corrective

action to prevent recurrence was completed prior to closing the

NCR was an example of a failure to implement Criterion XVI of

10 CFR 50, Appendix B (455/86017-078).

(29) Concern: The trend analysis as performed by HECo QA does not

prove anything.

NRC Review: During a review of NCRs discussed in. Paragraph

5.a(28) above, the NRC inspector performed a " bean count" of the

NCRs prepared during the fourth quarter 1985 for comparison to

the trend analysis performed by HECo QA. The NRC inspector

determined that 104 NCRs were prepared and 12 of these NCRs were

written on concrete expansion anchor (CEA) installation problems.

A review of the HECo trend analysis indicated that none of the

12 NCRs on CEAs were trended and only 6 of 104 total NCRs

prepared during the fourth quarter were trended.

A review of DRs for the fourth quarter 1985 revealed that '!36

DRs had been prepared. When compared to the HECo trend analysis,

only 37 of the 236 total DRs prepared during the fourth quarter

were trended.

During interviews of the HECo QA personnel responsible for the

trend analysis, the NRC inspector was informed that if the physical

work activity was not performed during the subject quarter, the

NCR/DR was not counted for trending purposes in that quarter.

The NRC inspector was also informed that HECo does not perform

a running (complete) trend analysis;

i.e., include two or more

i

l

quarters in the trend analysis performed each quarter.

During

!

interviews with the HECo QA/QC Manager, the NRC inspector was

l

informed that during the fourth quarter of 1985, HECo QC had a

1

60-90 day backlog of inspections and presently (June 1986), the

backlog was down to 30 days and for practical purposes this is

considered current with work activities. When the QA personnel

were asked if the previous quarter trend analysis was revised to

reflect the additional NCRs/DRs identified, their reply was no.

In summary, when HECo QA performed the fourth quarter trend

analysis, 94% of the NCRs and 84% of the DRs were discarded from

the trending population. Under ideal conditions (30 day backlog),

approximately 33% of the pertinent data would not be included

in the trend analysis.

/

32

1

t

Conclusions: This concern was substantiated in that prior to

performing the trend analysis, HECo QA discarded up to 95% of

the pertinent data needed to perform the analysis.

(30) Concern: We had problems with the welds on DV88 and DV89 type

connections. There are 456 in Unit I and 542 in Unit 2.

CECO

QA Audit 6-84-309 caused the reinspection of 58 DV88 and DV89

connectors that had been reworked by HECo. Why wasn't a larger

sample taken? Also, Page 2 of 2 of HECo's response to Audit

6-84-309 is missing from Ceco's file copy of this audit. A

copy of HEco QA/QC Memorandum 1405 was provided.

NRC Review:

HECo QC inspectors identified undersized welds

on electrical raceway hangers as supplied by Systems Control.

These undersized welds were documented on HECo NCR 461. The

NCR disposition directed HEco to add additional welds to 58

DV88 and DV89 connectors with undersized welds. During CECO

QA Audit 6-84-309, a cracked weld was identified on one of the

hangers repaired by HECo. HECo was directed to visually

reinspect the 58 hangers and identify any welds that had crack

indications. The reinspection identified ten potentially

cracked welds, six were accepted by PTL using the magnetic

particle (MT) method of nondestructive examination (NDE). The

remaining four welds were repaired by HECo per NCRs 1062, 1065,

1066, and 1067 and subsequently accepted by PTL, using the MT

method. CECO NCR F885 was prepared to document potential

undersized welds on DV88 and DV89 type connectors supplied by

Systems Control.

Based on statistical guidelines, an additional

60 hangers were inspected and weld maps prepared. Based on worst

case analysis, S&L was able to accept these hangers with

undersized welds. The weld deficiencies identified by CECO on

items supplied by Systems Control were closely monitored by the

NRC (see NRC Inspection Reports 454/84031, 455/84024, 454/84032,

455/84025, 454/84050, 455/84034, 454/84071, and 455/84049).

The NRC inspector's review of QA Audit 6-84-309 revealed that

the corrective actions and corrective action to prevent

recurrence were agreed to during the audit and were documented in

the audit report.

Therefore, no HEco response to the audit was

required. Memorandum 1405, dated July 18, 1984, is from a HECo

Level II welding inspector to the HEco QA/QC Manager. This

memorandum documents, in summary form, the results of HECo's

and PTL's reinspection of the DV-88 and DV-89 hanger connections.

The inspector could not find any evidence that the HECo QA/QC

Manager had ever transmitted this memcrandum to CECO. Hcwever,

,

Memorandum 1405 was found in the HECo vaulted records file.

In

that the applicable QA/QC Manager was no longer employed by HECo,

he was not interviewed in reference to this memo.

.

33

_ _ _ _ _ . -

- . -

. -

.

._ __.

Conclusions: This concern could not be substantiated in that

-additional hangers were reinspected per CECO'NCR F885~and an

analysis was performed by S&L. -In addition, the welding

problems. identified on items supplied by Systems Control were

closely monitored by NRC inspectors. No HECo response to

Ceco QA Audit 6-84-309 was required and the inspector could

find no' evidence that HEco QA/QC Memorandum 1405 was ever

transmitted to CECO. Therefore, there was no requirement for

HEco QA/QC Memorandum 1405 to be placed in the CECO audit file.

No violations or deviations were identified.

(31) Concern:

In Unit 1 on the west face of Q wall, 426'

elevation, Area 5, a DR was prepared for a cover being left

off of a J-Box. Was the cover replaced and the DR closed?

NRC Review: Using the applicable Unit 1 drawing, it was

determined that the concern could apply to.any one of three

J-Boxes that are installed in the area described. .Using the

WANG system, it was identified that DR3282 had been written

against J-Box IJB1737A. A review of DR3282 indicated that it

had been prepared on October 5, 1983, for a missing J-Box

cover.~ The cover was replaced and DR 3282 was closed on

October 18, 1983.

Conclusions: DR 3282 documented the missing cover on J-Box

1JB1737A. The J-Box cover was replaced and the DR closed. No

violations or deviations were identified.

.(32) Concern:

Rebars were cut in a non-safety-related man-hole-(MH)

during the cutting of a cored hole.

The FCR stated that no

rebar.was to be cut. HECo could not write an NCR on these cut

rebars.

For non-safety-related walls, HECo has no way to report

cut. rebar. This happened in approximately January 1986.

NRC Review: The NRC inspector reviewed all Cored Hole Reports

[

prepared between January 1 and March 31, 1986. No reports were

identified for a non-safety-related MH. The inspector reviewed

'

Cored Hole Reports prepared between October 1 and December 31,

1985. This review found that Report 85-10-26, dated October 24,

1985, documented rebar cuts in MH 2B. This report also referenced

HECo NCR 1738. A review of the NCR revealed that two vertical

'

!

rebars vere cut on the south face of MH 2B and FCR 26571 only

t

permitted one rebcr to be cut.

The information contained in

(

the NCR was analyzed by S&L and the NCR was dispositioned

"use-as-is."

During interviews with CECO and S&L personnel, the

!

NRC inspector was informed that ali Cored Hole Reports are

,

routed to S&L. "Rebar cuts" or "no rebar cuts" are documented

L

on the cored hole reports, so that even though a rebar is cut

in a non-safety-related wall / floor and e.n NCR is not prepared

'

(which is typical) S&L would be aware of any/no rebar cuts.

'

.

Except upon request, QC does not inspect non-safety-related

!

!

34

1

- . _ . _ . _ . . _ _ . _ _ _ _ . _ ~ _ _ . _ _ _ - . _ . _ _ _ - _ . _ , - _ _ . _ -

_ . . _ , _ . - -

_

_

_

_

installations, therefore, NCRs are not normally prepared on

non-safety-related items. During the review of Cored Hole

Reports, non-safety-related MH 28 Report 85-10-26 was the only

report identified that fits the description of the concern.

Conclusions: This concern was refuted in that NCR 1738 had

been prepared to document cut rebars, in MH 28, even though

an NCR was not required. No violations or deviations were

identified.

(33) Concern:

PTL rejected concrete expansion anchor (CEA)

installations for Category II (non-safety-related) equipment

inside Containment 2 for spacing and edge distance. NCR 2017

was preparea to document the rejected CEAs however, it was

cancelled.

NRC Review: A review of HECo NCR 2017, dated May 9, 1986,

indicated that this NCR had been cancelled. The description of

the nonconforming condition indicated a CEA edge distance

violation only. A review of PTL CEA Inspection Report 24673,

<

on the same installation, found that the violation was for edge

distance only and S&L had dispositioned the PTL report "use-as-is"

on March 28, 1986 (Approximately 42 days before NCR 2017 had been

prepared).

In that the edge distance violations had been

previously addressed by S&L, the NRC inspector concurs with the

4

cancelling of NCR 2017.

Conclusions: The CEA edge distance violation identified on

PTL Report 24673 had been satisfactorily addressed by S&L,

therefore, a HECo NCR was not required. No violations or

deviations were identified.

(34) Concern: The ceiling is leaking in the feedwater tunnel,

causing pitting of the conduits. Conduit segregation code is

K2R (safety-related instrumentation conduit).

See conduit

inspection reports (Form 201) 5780 and 5978.

In accordance

with the HECo Project Engineer, this deficiency is not within

HECo's scope of work.

NRC Review: The NRC inspector performed a physical inspection

of the feedwater tunnel.

During this insoection it was observed

that at some point in time, the ceiling had, in fact, been

leaking. However, the licensee had taken appropriate action to

seal the leaking ceiling. An inspection of the conduit in the

,

area of the leaks snowed a deposit that appeared to be calcite.

'

'

Upon removal of the deposit, no pitting of ti e conduit was

observed.

In that the ceiling had been repaired (sealed), it

was apparent that CECO was aware of the leak, therefore, no

HECo NCR/DR was required.

Conclusions: A physical inspection of the feedwater tunnel

indicated that the ceiling leak had been repaired and the

leakage caused no detrimertal effects on the conduit. No

violations or deviations were identified.

35

-

_

-

_.-

.-.

-

. _ _ _ _ _

_ - - - . -. -

-.

(35) Concern: White out was used on NCR 1759. also changes were made

on NCRs 1759, 1766, 1775, 1802, and 1825 that were initialed

but not dated.

NRC Review: HEco NCRs are typed by the clerks and during the

preparation of NCR 1759, it appears that the letter "S" on one

word was retyped. A correction fluid had not been used. When

reviewing a copy of this NCR, it appears that a correction fluid

(white out) may have been used, which, in the NRC inspector's

opinion, resulted in this concern. With respect to the changes

on NCRs 1759, 1766, 1776, 1802, and 1825, they were made by an

individual with the intitials "R.A.B." and was not dated.

These NCRs were corrected during this inspection and from the

number of NCRs reviewed during this inspection, it appeared

that these were isolated instances.

Conclusions: Correction fluid had not been used on NCR 1759,

however, it appears that the clerk typed over/ retyped the

letter "S" in one word. Changes had been made, initialed but

not dated on NCRs 1759, 1766, 1775, 1802 and 1825. These NCRs

were corrected during the inspection. Based on the number of

NCRs reviewed during this inspection, these errors are considered

isolated instances and no further action is required.

(36) Concern: Wrong FCR numbers are referenced on core hole inspection

reports 26884, 26887, 26890 and 26891.

NRC Review: During the review of core hole reports, the NCR

inspector could not identify any reports with the numbers

provided by the alleger. The NRC inspector was informed that the

series of numbers provided appeared to be FCR numbers.

Using

the FCR log, it was confirmed that the numbers provided were, in

fact, FCRs issued for cored holes.

The log also provided a

cross-index to the Core Hole Inspection Report (CHIR) number.

During a review of the FCRs and the inspection reports, the

following observations were made:

CHIR 86-04-02 referenced FCR F26984 and on June 15, 1986,

this FCR number was corrected to read F26884.

CHIR 86-04-03 referenced FCR F26897 and on June 15, 1986,

this FCR number was corrected to read F26887.

'

FCR F26884 was superseded by FCR F26890 (after the hold

was cored) which abandoned the hole because it was not

needed.

FCR F26884 was identified as being superseded.

FCR F26891 deleted one 3" hole and added two 3" holes.

This FCR was correctly listed on CDRs 2052 and 2054.

,

i

36

' Conclusions: CHIRs 86-04-02 and 86-04-03 referenced an

incorrect FCR number, however, they had been corrected prior to

the NRC inspector's review.

FCRs F26890 and F26891 were listed

correctly on the applicable reports. No violations or

deviations were identified.

(37) Concern:

Cable installation Report 9877 incorporated an FCR

before it was issued.

NRC Review: A review of cable installation report 9877, revealed

that the cables were released for pull on February 17, 1986, and

that FCR F26763 was referenced on the report. This FCR was

issued on February 14, 1986, to change the cable from type 01599

to type 01646. This cable type change affected cables 2AR189,

191, 193, 195, 252, 253, 258, 259, 266, and 267. A comparison

of the cables listed on the FCR and on Report 9877 indicated

that there were one or more additional cable installation

reports affected by the FCR. Additional research revealed that

Report 9878 was the other report within the scope of the FCR.

A review of cable installation report 9878 indicated that the

cables were also released for pull on February 17, 1986.

Conclusions:

FCR F26763 was issued three days before the

affected cables were released for pull as indicated on cable

installation reports 9877 and 9878. This concern was therefore

not substantiated.

No violations or deviations were identified.

(38) Concern: We only inspect for minimum torque valves (Note 5,

,

Drawing 0-3000L, Sheet 1, Revision L). During operations the

vibration could pop the boltheads off if they were overtorqued.

NRC Review:

Bolt torque valves are specified in order to

preload the bolts for high cycle fatigue, shear connection or

locking considerations. Of these three reasons, only high cycle

fatigue has critical requirements for minimum and maximum bolt

preload values. The other two considerations, which are

basically static load cases, really only have a minimum preload

requirement.

For most static bolting applications, if the bolt

does not break during the initial torque-down, then it should

not break during service. This is because during installation

the bolt must withstand the induced tensile force as well as

the applied torque. The tensile and shear stresses resulting

from these two forces are approximately the same under normal

conditions.

Since the ultimate shear stresses are about half of

the ultimate stresses, the biaxial state of stress will be

overall one of the most highly stressed conditions for the

bolt. Once the bolt is installed, the residual torsional

stresses disappear due to slight frictional slippages after the

torque is removed. Once this torsional stress component is

,

37

removed, the available tensile capacity above the preload value

increases significantly. As long as the applied load is less

than the bolt preload, the increased tensile stress should be

less than the bolt capacity and therefore, never fail.

(Reference: Mechanical Engineering Design, Shigley, J. E. c

1977, Third Edition.)

Conclusions: Although dynamic loads are considered for this

bolting application, there are no high cyclic fatigue

+

concerns. On this basic, maximum torque valves need not be

considered during installation.

The concern in therefore

unsubstantiated.

(39) Concern: There are no weld traveler cards for Units 1 and 2

riser collars.

c

NRC Review: A riser collar is a type of raceway support used to

support vertically mounted cable tray (risers) and is shaped like

a collar. Riser collars are installed at floor penetrations.

Weld travelers (WT) had been prepared for riser collar welds,

however, due to the lack of unique identification, WTs could not

be traced to a given weld or series of weld on a given riser

collar.

On January 26, 1986, HECo QC prepared DR 8314 to document that

WTs for 17 safety-related and non-safety-related Unit 2 welded

riser collars could not be found.

New WTs were prepared, the

welds were inspected, and the DR was closed on March 17, 1986.

On February 28, 1986, DR 8444 was prepared to document additional

i

missing WTs for Unit 2 riser collars having welded connections.

As a result of this DR, 136 WTs were prepared and the welds were

inspected. As a result 96 were rejected for various deficiencies.

These deficiencies were transferred to NCR 2073, dated September 9,

1986, and DR 8444 was closed on September 15, 1986, based on the

preparation of the NCR. With respect to Unit 2, HECo identified

the problem of missing WTs and corrective action was in process

before the allegers concern was received.

With respect to the missing Unit I riser collar WTs, it appears

that the licensee was aware of the problem in the same time

frame that HECo DR 8314 was prepared, on January 29, 1986. On

February 14, 1986, CECO QA performed Surveillance No. 7898 on

missing WTs for Unit 2 riser collar welds which resulted in

l

HECo DR 8444 being issed on February 28, 1986.

From interviews

'

of CECO QA and engineering personnel and review of records, the

NRC inspector could not identify any actions taken by HECo or

the licensee to identify and document (NCR, DR, etc.) the

missing WTs for Unit I riser collar welds. On June 9, 1986,

while investigating this concern on the missing WTs, the NRC

inspector expressed a concern regarding the lack of licensee

action to document the missing WTs on Unit I riser collar welds.

On June 20, 1986, Project Instruction (PI)-BB-106 was issued for

38

.--

.

_ - __.

_

_-

- - - .

. .

-Tt

<

q,

i

I.

l\\

!

'

L ' 'l

'

s<

1

L

}

'

,

,

the inspection of Unit I riser collar welds.

Gom June 23 to

,

.

June 25,' 1986, a S&L Level III weld inspector inspect.ed 50 of

,

-

the! approximate'ly 150 Unit 1 and common riser collar welds. Per

.

' -

an S&L (R. J. Netzel) to CECO (R. E. Querio) letter dated

'

July 29, 1986, an engineering evaluation was performe.1 o, Unit i

s

riser collar walds based on results from the S&L inspecb!cn.

S&L's evaluation of the discrepancies based onja worse mase

,

i

analysis, determined that the riser collar welds are within

'

o

s

the allowable stress limits., However, one case was identified

4

<

s

where the as-found yeld condition was less than the detign

V

drawing requirements.4 This riser collar is located on~ elevation

439, l'5" south of column line 10 and 10'9" west of column line

.

L, as shown on drawing.6E-1-3061. These riser collar welds were

repaired and accepted by HECo on September 16, 1986, as documented

,

on Nuclear Work Request (NWR) 6EG018.

-

Conclusions: This concern was substantiated. However, for-

Unit 2, HECo had identified the problem of missing WTs for

'

riser collar welds on DR 8314 and DR 8444 and corrective action

was in-process before this coacern was identified to the NRC.

With respect to missiag WTs for Unit I riser collar welds, it

i

.appears that the licensee became sware of the missing Unit 1

WTs in the January to February 1986. However, th? licensee

.

failed to take any corrective actioris until the NRC inspector

expressed his concern on June 9, 1986.

'

The licensee was inforced that:

.(

r

(a) Failure to assure'~that conditions adverse to quality were

'

'

promptly identified and corrected is an exanple of a

failure :to implement Criterion XVI of 10 CFR 50, Appendix B

(454/86031-04B).

,

,

i

s

(40) Concern: .The disposition on DR 8350 is not correct. An HP-7A

(Rewat Requast) should have been inithted.

v

NRC Review: A review of DR 8350 identifled the discrepancy as

" cable 2FW216 was determinated to terminate cable 2FW230 on the

same terminals without an HP7A form being prepared. This is in

s

.

violation to Procedures 7 and 7A."

The disposition on the OR

stated, in effect, "that procedures were not violated and the DR

was written in error." The DR referenced various paragraphs

s.

\\

from HEco Procedures 7, " Electrical Design Changes" and 7A,

y

" Rework Control."' The NRC inspector reviewed HECo Procedures 7

and 7A.

Procedure 7' describes the actions to be taken by HECo

1'

when a desiqn change is received.

In that the discrepancy noted

'

'

j

was not a design change, crocedure 7 was listed in error on the

l

DR.

Procedure 7A, Paragraph 2 d , states, in part, "The scope

of this procedure includes the revisions to installed work

>

required by design change or removal and reinstallatica of-

previously installed work . . . ." Paragraph 2.4 of

j

Procedure 7A states, in part, "The scope does not include

i

the remaval of wire or cable conductor terminations in order

,

k

,

'

39

s

s

y

i-

. -

~

.-

.

>

to terminate additional wires or cable conductors on the same

point ...." During the review of Cable Termination Inspection

Report 21586 fcr cable 2FW230, it was noted.that the termination

inspection was performed "in process", indicating that a QC

inspector had observed the determination an'd re-termination of

cable 2FW216. Based on the NRC inspector's review of

Procedures 7 and 7A, DR 8350, and inspection report 22586, the

NRC inspector concurs with the HECo engineer that the DR did

not describe any violation of procedures.

"

Conclusions: DR 8350, as writtenp did not describe a procedure

violation.

In addition, a certified HECo QC inspector did in

fact perform an in process _ inspection of cable terminations. .No

violations or deviations were fdentified.

(41) Concern: There are bad resolutions on DRs 8339 and 8426.

In

addition, "use-as-is" DRs should have been documented on NCRs.

NRC Review: The NRC inspector reviewed approximately 300 prs,

including DRs 8339 and 8426, for proper closure.

Following

are the results of this review:

'

DR 8339 - Documented screws and terminal points have

corrosion on them and 3" sealtite outer jacket is pulled

out of the connector in panel 2VA-04J. A CECO PCD engineer

dispositioned this DR "use-as-is" with an explanation,

however, "use-as-is" dispositions require design engineer's

approval;

i.e., S&L or Westinahouse.

During a physical

inspection of Panel 2VA-04J, the NRC inspector determined

that the observed corrosion was not detrimental to the

operation of the equipment. No discrepancies were

observed with the sealtite jacket.

DR 8426 - Documented 2 1/2 pages of discrepancies or

potential discrepancies that were identified during a 100%

inspection of Panel 2PS47J prior to turnover to the

licensee. All discrepancies identified on this DR were

" accepted-as-is" by a Ceco PCD engineer. A typical

disposition was "ok" or "all ok."

Several of the potential

discrepancies were " terminal lugs landed backwards - Can't

check." To verify the acceptance of these lugs, the lugs

'

would have to be determinated for inspection. When

questioned by the NRC inspector, the PCD engineer stated

that the lugs were not determinated for inspection but were

accepted ("use-as-is") based on his knowledge of like

terminations.

From the interview, the inspector

determined that no physical corrective actions were taken

before the discrepancies were' accepted; 1.e., dispostioned

"use-as-is".

i

40

i

.

/

+.

DR 8501 - Documented that Class I (safety-related) cables

2RC437, 2RC422, 2RC419, and 2RC440 were pulled without QC

<

being present. NCR 1992, dated April 17, 1986, was

prepared to document this procedure violation. This NCR

was dispositioned "use-as-is" by a CECO PCD engineer

without design engineer's approval. DR 8501 was closed

based on " Resolution Implementation Documented on: (HECo

QA) Special Surveillance #13-86 and NCR 1992." During a.

review of HECo QA vaulted Surveillance Reports, the NRC

irspector could not locate Special Surveillance #13-86.

During personnel interviews, the NRC inspector was informed

by a HECo QA engineer that Special Surveillance #13-86 had

not been issued.

DR 8504 - Documented that cable installation inspection

report 8790 was issued for the removal and reinsta11ation

of safety-related cable 2MS518.

Report 8790 only documented

the removal of the cable.

There is no documentation for the

reinstalls. tion of the cable. This DR was dispositioned

"use-as-is" by.the HECo QA Supervisor and final reviewed

and accepted by the same Supervisor on May 20, 1986. This

disposition was not approved by the design engineer.

DR 8534 - Documents miscellaneous discrepancies, (including

lack of cable tension data during the pull), with two cable

cable installatior, inspection reports (9991 and 9992). The

inspector who originally witnessed the cable pull was no

longer employed in HECo QC. The inspection reports could

not be closed because no one knowns the circumstances of

each cable installation. This DR was dispositioned

"use-as-is" by HEco engineering.

The "use-as-is" disposition

i

was not approved by the design engineer.

'

DR 8049 - Documented that conouit fittings are loose at

2PSL-DG0878 and 2PS-DG094B. These conduits were acceptable

as installed, based on a memorandum from a CECO PCD engineer.

This memorandum stated, "Above installations are acceptable

as installed. HECo should close their DR. Conduit cannot

become looser. Byron Station can tighten connector during

a future calibration." This disposition was not approved

by a design engineer.

CECO QA Audit 6-86-201, that was conducted as a result of NRC

concerns, also reviewed the HECo DR program.

This audit states,

in part, "A review of 356 DR's which were closed during the

aforementioned period verified that HECo Engineering / Production

had properly dispositioned the identified concerns in 205

'

instances. An additional 50 DR's were elevated to NCR's for

resolution by the Owner. However, 101 DR's were either dispo-

sitioned by PCD as acceptable per an attached speed memo or

were d,ispositioned as acceptable per PCD without a clear basis

for the inspection Llements acceptability.

'

>

's

1

41

.

.

-

.

- - - -

..

-

During the course of the audit, minor concerns were identified

which related to the processing and/or closecut of DR's.

However, the instances were unrelated and were submitted to

HECo QA for resolution.

In general, the HECo DR program was

found to be acceptably implemented with the exception of its

trending process."

Conclusions: The NRC inspector's review of HECo's DR program

revealed that DRs were being dispositioned "use-as-is" by HECo

QA, HECo Engineering, and CECO PCD Engineers without the con-

currence of the design engineer and/or without a clearly

documented basis for the closure of the DR.

The licensee was informed that:

(a) Failure to assure that design changes were subject to

design control measures commensurate with those applied to

the original design is an example of a failure to

implement Criterion III of 10 CFR 50, Appendix B

(455/86017-028).

(b) Failure to assure that conditions adverse to quality are

identified and corrected and the cause of the condition is

determined and corrective action taken to preclude repetition

is an example of a failure to implement Criterion XVI of

10 CFR 50, Appendix B (455/86017-07C).

(42) Concern: Cables were pulled with a " mares tail" (non-metallic

basket weave cable pulling device) in the steam tunnel at twice

the maximum allowable cable pulling tension. This happened

9-12 months ago and no NCR was prepared.

NRC Review: A review of cable pull records and interviews of

HECo QC and engineering personnel revealed that the concern

related to a bulk cable pull involving 16 cables. These

cables were being pulled from J-Box 2JB101A through conduits

C2A-4115, C2A-0141, C2A-0104, C2A-0501 and C2A-0595 to J-Box

2JB031A. These 16 cables were being pulled with a " mares tail"

and a pulling tension of 1600 pounds was recorded.

S&L

Standard EA-121 limits the maxinum pulling tension to 1000

pounds when using a basket weave cable pulling device. This

violation was documented on DR 7884 which was subsequently

up graded to HECo NCR 1682 on September 5, 1985. To transmit

this information to S&L for analysis, CECO prepared NCR F-1011,

dated September 13, 1985.

In an S&L letter dated September 18,

1985, S&L transmitted Ceco NCR F-1011 to the Okonite Company

(cable manufacture) for their review and analysis. On October 7,

1985, S&L transmitted additional information to Okonite per their

request. The Okonite Company responded in a letter to S&L on

October 9, stating that, " based on their evaluation of the

information provided, the cables in question are acceptable for

,

42

-_

__.

..

-

-.

-

.

use in their intended application."

In an S&L to CECO letter on

November 5, 1985, S&L provided their concurrence with an " accept

as-is" disposition on CECO NCR F-1011.

Personnel involved were

re-trained in the 1000 pound pulling tension limitation when

using a basket weave cable pulling device.

CECO NCR F-1011 was

closed on November 26, 1985 and HECo NCR 1682 was closed on

December 3, 1985.

Conclusions: This concern was not substantiated in that both

HECo and CECO prepared NCRs on the over tensioning of cables

being pulled with a " mares tail". These NCRs were properly

analyzed, dispositioned, and closed. No violations or

deviations were identified.

(43) Concern: The cable pull training requirements for QC inspector

(by name) were lowered so he could be certified. He never

observed a Class IE (safety-related) cable pull before he was

certified.

NRC Review: ANSI N45.2.6-1978, " Qualification of Inspection,

Examination, and Testing Personnel for Nuclear Power Plants,"

Subsection 2.2 states, "The capabilities of a candidate for

certification shall be initially determined by a suitable

evaluation of the candidate's education, experience, training,

test results, or capability demonstration."

In accordance with

Table 1 of N45.2.6, the discipline Level III inspector is

responsible for evaluating each candidate for certification and

determining the minimum training, if any, required prior to

certification. This training may consist of formal training

(classroom) or on-the-job training (0JT) or a combination of

both. HECo Procedure 17, " Qualification and Training of

Inspection and Audit Personnel," basically reiterated N45.2.6

for evaluation and training of QC inspectors. The NRC inspector

reviewed the training and certification records package for the

named individual.

For cable pull and terminations, the Level

III evaluation indicated that the individual required nine hours

of formal training and 40 hc9rs of OJT. A review of the documented

training (cable pull and tenninations) indicated that the named

individual had received 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> of formal training and 45 hours5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br />

of OJT.

In that HECo utilized the same procedures for safety-

related and non-safety-related work activities (for QC inspections

are not performed on non-safety-related work), therefore it is

acceptable to train and test QC personnel on non-safety-related

work activities.

In the case of the named individual, his 0JT

was on four safety-related and two non-safety-related cable pulls.

Due to the lack of safety-related cable pulls, the named

individual's practical test was given on a non-safety-related

cable pull. The NRC inspector reviewed the written test (closed

book) taken by the named individual for Level II certification.

A minimum of 80% is required on the written tests and the named

individual had a passing grade of 84.5%.

43

l

l

t

,

&

Conclusions:

In that the named QC inspector had been evaluated

by HECo's Level III inspector, and minimum training requirements

established, the individual met the qualification and certifica-

tion requirements of ANSI N45.2.6 and HEco's Procedure 17, this

concern was not substantiated. No violations or deviations were

identified.

(44) Concern:

In electrical panels 2PA09 and 2PA10, there is bare

vendor wire showing and this has been accepted.

NRC Review: The NRC inspector and a CECO QA electrical engineer

performed independent inspections of panels 2PA09 and 2PA10

located in the Auxiliary Electrical Equipment Room. No discre-

pancies were identified with vendor or HECo installations.

Conclusions: Based on a physical inspection of panels 2PA09

and 2PA10, this concern was not substantiated. No violations

or deviations were identified.

(45) Concern:

The CECO PCD Project Electrical Supervisor directed

HECo on how to perform QC inspections. This occurred during a

training session prior to the butt splice reinspection. QC was

directed to accept exposed copeer beyond the lug insulation.

NRC Review: As a result of a 1984 NRC concern (see IE

Inspection Reports 454/84027; 455/84019), the licensee performed

a reinspection of accessible butt splices in Units 1 ar.d 2.

This reinspection program, including the training session

4

alluded to by the alleger, was closely monitored by two NRC

inspectors (See NRC Inspection Reports 455/84029; 455/84021).

The subject training session was conducted by the Project

Electrical Supervisor on May 24, 1984 and was attended by NRC

inspectors.

For butt splices that were to be covered with

'

Raychem heat-shrink tubing or tape, it was permissible to have

,

exposed copper beyond the lug insulation in that the exposed

copper would be covered in the final product. This action was

acceptable to the NRC.

In addition, the licensee had notified

the NRC of this problem via a 10 CFR 50.55(e) report

(455/84003-EE; 455/84003-EE). This 50.55(e) report was

addressed in IE Inspection Reports 454/84055; 455/84038. An

open item pertaining to the butt splice reinspection program

is also addressed in IE Inspection Report 454/84072; 455/84050.

Conclusions: This concern was substantiated, however, the

exposed copper that extended beyond the lug insulation was

being appropriately covered with heat-shrink tubing or tape.

The entire butt splice reinspection program was monitored and

accepted by NRC inspectors. No violations or deviations were

identified.

(46) Concern: The HEco QA/QC Manager (by name) pre-dated and

back-dated inspection reports, also, QC inspector (by name)

back-dated equipment modification reports (Form 12A).

44

_ . -

-

.-- .

_ _ _ - _ - _ - - - - _ _

-

. - _ - _ __

_

--

-

-

-

_

-

.

-.

.

.

.

-

-

- -_

h

9

~

NRC Review: -The NRC inspector reviewed several hundred

[

~

inspection report and did not observe the named QA/QC Manager's

'

name on any reports. -A review of personnel qualification files

revealed that this individual was not certified in any area by

HECo. During interviews'of HECo QA/QC personnel, the NRC

inspector was informed that. they (the interviewees) were not

aware of .the named QA/QC Manager pre-dating or back-dating any

documents and were not aware of him approving / signing any

inspection reports. The inspector was unable to interview this

individual in that his employment with HECo was terminated

July 2, 1986.

With respect to the named QC inspector, it was established

through personnel interviews and review of records that this

QC inspector back-dated his " review" of Class 1 Equipment

Modification Inspection Requests (Form HP-12A-1).

In accordance

with HECo procedures and inspection report forms, the QC

inspector that performed the inspection, signs, dates and enters

his/her certification level (Level I,'II or III) at the bottom

of the report. This report is then " reviewed" by an additional

QC inspector certified Level II or III. When inspection reports

reach the QC office from the field, they are given to the QC

4

clerks. The QC clerks then formally transmit these reports to

,

the appropriate Lead QC inspector for their review. After the

reports have been reviewed, they are returned to the clerks for

filing. At the time of filing, the clerk enters the inspection

!

date and the date filed in a permanent log.

1

Modification inspection reports 6132 through 6137 were received

by the QC clerk from the field on August 10 or 11, 1984, and

transmitted to the Lead Inspector on August 13, 1984. When

these reports were received for filing, all had a " review" date

of March 21, 1984. All the QC inspectors and the lead inspector

_

involved with these inspection reports have not been employed by

I~

HEco for some time.

In that the involved personnel are no

longer employed by HECo and the " review" function did not change

or modify the inspection results, no additional followup is

planned.

>

j

Conclusions: The named QA/QC Manager had not signed any

.

inspection reports and none of the QA/QC personnel interviewed

!

were aware of any documents that he pre-dated or back-dated.

!

Records indicated that the named QC inspector back-dated his

review of modification reports 6132 through 6137. The review

function did not change or modify the inspection results and

l

does not have any impact on quality of the item inspected.

!

(47) Concern: Certification and records packages were missing from

the vault. Craft personnel need to be recertified every six

'.

months on cable terminations.

Some of the craft were

i

recert,1fied without any backup data,

i

t

,

45

i

.

. .. .

- - -- - -. . . . -

. - . . .

. - - - . .

- - .

- . . . - . -

. - - - . -

NRC Review: A review of HECo Procedure 11, " Class 1 Cable

Termination and Splicing," revealed that Paragraph 5.9.2

" requires an in process QC inspection of each terminator's

work at least once every six months for the terminator to

maintain his/her qualifications." A log is maintained for each

terminator and lists the QC inspector's name that performed

the in process inspection, termination report number and date.

The NRC inspector selected five terminators for a review of their

maintenance of qualifications.

During this review, the

,

following observations were made:

Terminator 4069 (individual's Brass Number) - Two reports

were listed as in process inspections when in fact they

were not.

If an inspection was performed in process, it

is so noted on the inspection report. During a review of

termination inspection report 14610, it was noted that the

termination was made on December 3, 1984, and the inspection

was conducted on December 19, 1984. Also, termination

inspection report 22757, dated March 7, 1986, was not

identified as being an in process inspection. These errors

did not affect the terminator's qualifications in that valid

in process inspections were on file for the applicable six

month periods.

Terminator 4193 - Termination inspection report 2165 was

also listed in error in the log for this terminator in that

the termination was made on December 10, 1985 and inspected

December 11, 1985; not in process inspected.

Valid

in process inspections for November 1985 and January 1986

were also on file and this error did not affect the termi-

nator's qualifications.

Terminator 3320 - Termination Report 15278 was listed in

the log for this terminator, however, the report was

missing from the HEC 0 Records Vault. A review of the

Termintaion Report Log reve led that reports 15270 through

15275 and 15277 through 15285 had been " thrown away by DG

5/16/86."

During interviews of HECo QA/QC personnel, the NRC inspector was

informed that for terminators to maintain their qualifications,

they were permitted to make " test booth" terminations with a QC

inspector present.

These " test booth" termination inspections

were documented on termination reports 15270 through 15275 and

15277 through 15285. Under current HECo procedures, all documents

are reviewed by HEco QA prior to being vaulted. When these

reports were transmitted to QA for their review, a QA engineer

showed the reports to a QA/QC clerk and informed her that the QA

Supervisor said that these reports were not needed and threw

them in the clerk's trash can. After the QA engineer left

the area, the clerk retrieved the reports from the trash can

and stored them in her desk. The clerk could not " vault" these

records because they had not been reviewed by HECo QA. To

46

--

-

--

-

- _ .

._

_

.

.

_.

l

'

account for the termination report numbers, the clerk noted in

the Termination Report Log that these reports had been " thrown

away by DG."

After the NRC inspector expressed his concern with

the discarded reports they were retrieved by the clerk and were

again transmitted to HECo QA for review. After QA completed

their review, termination inspection reports 15270 through 15275

and 15277 through 15285 were returned to the QA/QC clerks and

properly filed in the HEco Records Vault.

During interviews of QA/QC personnel, the NRC inspector was

informed that during the 1982-1983 time frame, a named QA

Supervisor removed certain QC inspector's (by name) certification

records from the inspector's vaulted files. These missing

certifications were discovered after this QA Supervisor terminated

his employment with HECo on November 14, 1983. The named

individual's records were subsequently corrected by using the

master list of personnel certifications and copies of records

retained by the individual QC inspectors. On August 5, 1986,

the NRC inspector reviewed approximately ten inspector's files

and compared the certifications with the master list.

In

addition, the NRC inspector queried the named inspectors still

employed by HECo as to their area of certifications and compared

their responses with the master list of their certifications.

No discrepancies were identified.

Conclusians: Through personnel interviews, the NRC inspector

determined that certification records had been removed from

personnel files by a QA Supervisor during the 1982-1983 time

frame.

However, the inspectors' certification record files had

been corrected prior to the NRC involvement in this concern.

The review of termination inspection records that support the

recertification of craft terminators revealed that several

inspection reports were missing from the HECo records vault.

The termination inspection report log indicated that reports

15270 through 15275 and 15277 through 15285 had been " thrown

away" by the HECo QA Supervisor on May 16, 1986. This was

verified by a QA/QC clerk and a QA engineer. However, the

clerk had removed the termination reports from the trash can

and stored them in her desk. After the NRC expressed concerns

in this matter, the termination reports were retrieved from the

clerks desk, reviewed by HECo QA and subsequently filed in the

HECo records vault.

The licensee was informed that failure to assure that sufficient

records are maintained to furnish evidence of qualification of

personnel (craft terminators) is an example of a failure to

implement Criterion XVII of 10 CFR 50, Appendix B (454/86031-08;

455/86017-08).

(48) Concern: When HECo craft personnel perform work activities

under the direction of CECO OAD, this work was not always

inspected by HECo QC.

47

NRC Review: A review of Unit 1 Cable Termination Inspection

Reports (Paragraph 5.a. (47) above) revealed that several

inspection reports associated with NWR 6EG006 were marked N/A

(not applicable) for all inspection attributes. A note on

these reports stated, " Work performed under 0AD direction. No

inspection required per XXXXX (named CECO PCD electrical

engineer). The following are examples identified during this

review:

Report 21105, dated November 25, 1985, Class 1E equipment

1FWO6JB. All inspection attributes were marked N/A with

the above listed note.

Rework Request (Form HP-7A-1) 7963

was referenced on termination report 21105. The work

description on this Rework Request stated, "F1d, to

replace existing SIS wire W/Rockbestos SIS wire as

required in 1FWO6JA, JB and JC per PCD."

SIS wire is a

type of single conductor wire used in switchgear, motor

control centers, panels, and valve operators. The NRC

inspector was informed that the existing SIS wire was not

qualified and it was being replaced with qualified

Rockbestos SIS wire.

Reports 21106, 21113, 21114, 21119, 21120, 21115, 21116,

21102, 21103 and 21117 were all similar to termination

inspection report 21105, except they applied to different

items of equipment and rework request numbers. The work

description on the rework request were similar to Rework

Request 7963, except they applied to different items of

equipment.

During interviews of QA/QC personnel, the NRC inspector was

provided a copy of open HEco Cable Termination Inspection Report

19980, dated July 3, 1986. This report documented that the red

conductor on cable 2RH033-P2E was butt spliced and the splice

covered with heat-shrink tubing. This butt splice work activity

was inspected in process by a CECO 0AD engineer and was

documented on HECo termination report 19980. However, this OAD

engineer was not certified to HECo's termination and splicing

procedure. This discrepancy had been previously identified by

HECo QC and is being corrected under HECo's open inspection

report (0IR) program.

In that the butt splice is covered with

heat-shrink tubing and cannot be inspected, the butt splice must

be replaced with HECo QC performing an in process inspection of

the work activity.

,

48

1

,

Conclusions: During a review of cable termination inspection

reports, the NRC inspector identified 11 reports where no

inspections were conducted during the replacement of unqualified

SIS type wire. This wire was replaced in various Unit 1 items

of Class 1E (safety-related) equipment. The required QC

inspections were not conducted per the directions of a CECO PCD

electrical engineer.

00e instance was identified where an in process termination / splice

inapection was performed by an un-certified CECO OAD engineer.

However, this discrepancy had been previously identified by

I!ECo QC and corrective action was being implemented.

The licensee was informed that failure to assure that

inspection activities are executed to verify conformance to

documented instructions (NWR 6EG006) is an example of a failure

to implement Criterion X of 10 CFR 50, Appendix B (454/86031-09).

(49) Concern: DR 8160 was prepared for a Procedure 7A violation.

The DR was rejected about two months ago. The same type of

situation arose with an NWR and the HECo Project Engineer stated

at that time that a Rework Request (Form 7A-1) was required.

Both these situations involved 8' flex conduit. NWR log in the

conduit trailer (remote office) should indicate the 7A number.

NRC Review: DR 8160, dated January 7, 1986, identified the

following, discrepancy " Conduit C2A4201 has 7' 8 1/2" of flex

installed per FCR 26570.

This work was accomplished after the

^

original 6' 0" flex was installed per CIR (conduit inspection

report) 8534. The above mentioned work was accomplished without

initiating a 7A-1 (Form 7A-1, Rework Request) and in violation

of Procedure 7A, Revision 1."

The resolution on this DR states,

in part, "This item is not in the scope of 7A per section 2.3.

The CIR 8534 stated the sealtite was not connected to the

equipment at the time it was turned in."

The NRC inspector verified that the flex conduit had not been

inspected and accepted on Conduit Installation Report 8534,

dated February 21, 1985. After instrument 2PT-0937 was installed

(termination point for conduit C2A4201 flex), S&L authorized the

,

installation of a 8' maximum flex conduit by issuing FCR 26579

on September 11, 1985. A 7' 81/2" flex was installed, terminated,

inspected and accepted on September 17, 1985, as documented on

Inspection Report 19604.

OR 8160 was properly closed on March 11,

1986.

In addition, Paragraph 2.3 of Procedure 7A, " Rework Control,"

states, "The scope does not include reinspection of reworked

appurtenances. This shall be construed as installation work

and shall be inspected in accordance with the appropriate

installation procedure."

A review of the NWR log indicated that the alleger was alluding

to NWR-6VC092, dated February 17, 1985, and Rework Request

i

(Form 7A-1) 5412, dated March 18, 1985. A review of these

documents indicated that PECN P-40 was issued on January 21,

49

- - . -

-

, _ _ _ .

- .-

- - . - ---

._ -

-W

1985 to install HVAC " Bubble Tight" dampers. This required a

conduit modification. An NWR (6VC092) was issued in February to

repair the flex conduit.

In that a Rework Request was required

to complete the conduit modification per the PECN, the flex

repair was included on Rework Request 5412.

Conclusions: DR 8160 and Rework Request 5412 described two

different situations. DR 8160 discussed the replacement of

flex conduit per an FCR prior to the inspection and acceptance

of the originally installed flex conduit.

Rework Request 5412

discussed the modification of a previously accepted conduit

system per an PECN and the repair of the attached flex conduit

per an NWR.

In both instances, the work activity was properly

performed, inspected and accepted.

No violations or deviations

were identified.

(50) Concern: A Detail J connection was installed and accepted on

WT (weld traveler) 79929. Conduit Inspection Checklist 4736

rejected the detail. The Detail J was cut down and reinstalled

without a rework request. DR 8485 was prepared, however, this

DR was rejected.

NRC Review: A review of HECo Procedure 6, " Reporting of

Damaged or Nonconforming Material or Equipment" and Procedure

7A, " Rework Control" revealed the following:

Procedure 7A states, in part, "The scope (of this

procedure) does not include any rework required as a result

of initial quality control inspections. The scope

includes the revisions to installed work required by

design change or removal and reinstallation of previously

installed work when directed by HECo engineering and/or

the owner."

Procedure 6 states, in part, " Items discovered to be

deficient during routine surveillance or inspection

activities shall not be considered a nonconformance.

These deficiencies shall be tracked thru the use of open

inspection reports provided, the deficiency does not

affect any work previously accepted. Deficient items

which are not identified for correction and tracked thru

the use of open inspection reports, will be brought to the

attention of the appropriate supervisor for evaluation.

Supervisors shall write DRs (Discrepancy Reports) as

appropriate. based upon their evaluation."

A review of WT 79929 revealed that the welding on hanger SCC-1

had been inspected and accepted. Also, Conduit Inspection

Checklist 4736, dated October 21, 1985, rejected the Detail J

connection on initial inspection because of incorrect location.

DR 8485, dated April 28, 1986, was prepared to document the

removal and reinsta11ation of the Detail J without a Rework

Request. The resolution on DR 8485 states, "that the

discrepancy is not within the scope of Procedure 7A and can be

50

_ _ _

l

repaired / reworked under HECo's 0IR program". A stated in the

various procedure paragraphs above, the discrepancy was not

within the scope of Procedure 7A in that the-location violation

'

was identified during initial conduit inspection. Also, the

Detail J could not be reworked / repaired under the OIR program in

that the welding had been accepted on a weld traveler.

In-

accordance with-HEco procedures, the appropriate document to

rework / repair the Detail J connections on. hanger SCC-1 would be

a DR or an NCR (DRs can be upgraded to an NCR). During the

rework of hanger SCC-1, a new WT (81221) was generated for the-

new welds which were inspected and accepted, and attributes

including configuration and location were reinspected and

accepted on Conduit Inspection Checklist 4736.

In summary, it

would appear that there was an in adequate understanding of

procedure requirements prior to preparing the DR and the

engineer provided a partially correct resolution. As documented

throughout this report, the inspector reviewed numerous DRs

and inspection reports and this was the only violation of this

type identified.

Conclusions: A-hanger was reworked under the OIR program when

a DR/NCR should have been prepared. DR 8485 was written

without an adequate understanding of the nonconformance/ rework

process. The resolution on DR 8485 was partially correct in

that the rework was not in the scope of Procedure 7A. However,

the resolution incorrectly implies that the hanger could be

reworked under the OIR program.

This is considered an isolated

programmatic deficiency with no hardware impact.

(51) Concern: Rework requests, at times, lack clarity of work to be

performed and work performed.

Rework Request 07510'is a good

example. Cables and flex conduit were determinated, what

authorized their reinstallation? Also, why wasn't a 201 form

(conduit inspection checklist) issued to inspect the

re-terminated conduit?

NRC Review: The rework description on Rework Request 07510

states, "Determ cables and seal tites (flex conduit) a valve

10G-057A." This rework was completed on November 1, 1985. There

were no work instructions on this rework request to indicate

that the cables and flex conduit were to be re-terminated.

However, Rework Request 07510 documents the re-termination of

cables 10G093, 10G092 and 10G123, and their associated flex

conduits on November 5, 1985. The re-termination of the flex

conduits is documented on Cable Termination Inspection Reports

20766, 20767, and 20768 (Attribute 14), therefore, a separate

Form 201 would not be required for the flex conduit termination.

Rework Request 8854, dated February 18, 1986,- is another example

of an inadequate work description.

In this case, the rework-

was to determinate cable 2FW870 and pull the cable back to a

defined point.

Rework Request 8854 also indicated that cable

2FW870 was re pulled, re-terminated, and re-inspected, which

was outside the scope of the rework description. The NRC

51

inspector selected one file folder of rework requests from 1985

and one from 1986 for review. As a result of this review,

Rework Requests 6957, 6967, 9006, 9017, 9018 and 9055 were also

identified as having an inadequate work description which

resulted in work being performed that was outside the scope of

the work request. -All HECo rework requests are approved by

CECO PCD engineers and in some cases, the request is initiated

by a CECO PCD engineer. The NRC inspector's concerns with these

rework requests were discussed with HEco and CECO PCD engineers.

Following the NRC inspector's meeting with these engineers,

they have made a concentrated effort to ensure that the work

description adequately defines the work activities that need to

be performed. The NRC inspector reviewed the September 1986

rework requests and did not identify any additional violations,

indicating that corrective action was adequate.

Conclusions: The NRC inspector confirmed that there were

inadequate work descriptions on rework requests (eight examples

were identified) which resulted in work being performed without

adequate instructions. A review of cable termination inspection

report associated with rework request 97510 revealed that

attribute 14 documents the inspection of the reterminated

flex conduits and a separate conduit inspection was not

-

required.

The licensee was informed that failure to assure that activities

affecting quality are prescribed by documented instructions and

accomplished in accordance with these instructions is an

example of a failure to implement of Criterion V of 10 CFR 50,

Appendix B (455/86017-09A).

(52) Concern: Do not think CECO's audit of HECo on cored holes was

properly closed.

This audit was performed mid-1985 by a (named)

CECO QA engineer.

NRC Review: The NRC inspector reviewed all audits of HECo

performed by this CECO QA engineer and determined that this

concern related to CECO QA Audit 6-85-150 or Audit 6-85-152.

CECO QA Audit Report 6-85-150, dated May 26, 1986, documented

that Concrete Core Drilling Requests were reviewed to verify

.

that the cored holes were inspected by HECo QC prior to conduit

installation. HECo QC had indicated that there had been a

'

problem in the field with conduit being installed prior to the

QC inspection of the cored hole. The audit also revealed that

HECo had identified this deficiency on Special Surveillance 85-15,

an additional review was deferred to allow HECo time to implement

corrective action. A review of CECO QA Audit Report 6-85-152,

dated October 11, 1985, indicated that CECO QA verified that HEco

52

____

-

-

-

_

. _ .

.

.

-

had implemented corrective action and action to prevent recurrence

for the deficiencies identified in HECo's Special Surveillance

85-15.

This verification was made by CECO QA's review of NCRs,

cored hole reports, training records and procedure implementation

dates. The NRC inspector's review of Audit Report 6-85-152,

including audit backup data, indicated that the audit was

adequate to close the concern on cored holes.

Conclusions: The NRC inspector reviewed CECO QA Audit Reports

No. 6-85-150 and 6-85-152 and determined that these audit reports

were properly closed.

No violations or deviations were identified.

(53) Concern: No one is preparing a rework request for fire proofing

when items such as pull sleeves, tray covers, and J-Box covers

are removed or disassembled so Transco can install fireproofing

material. Without a rework request, HECo QC does not know when

to reverify reinsta11ation of pull sleeves, covers, etc.

NRC Review: A review of rework requests (Form HP-7A-1),

'

determined that 7A-1 forms were prepared if the fireproofing

was identified on a Nuclear Work Request (NWR); required the

removal of cable tray siderails; and required the removal of

a raceway hanger.

Rework requests were not being prepared for removal / replacement

.

of items such as J-Box and cable tray covers, and pull sleeves.

During interviews with HECo and Transco QC personnel, the NRC

inspector was informed that neither ccmpany was verifying the

reinstallation of these items after fireproofing. During the

inspection, the licensee initiated an interface agreement

'

between HECo and Transco to assure that all items were returned

to their designed conditions upon completion of fireproofing

work activities.

To verify past work activities, CECO QA

initiated a surveillance program. As of October 2, 1986, CECO

QA identified several discrepancies with the installation of

flex conduit.

However, it could not be deternined if these

discrepancies were the result of fireproofing or construction

activities.

Conclusions: The NRC inspector verified that when a rework

request was not prepared for fireproofing activities (For

.

examples; removal of J-Box and cable tray covers, disassembly

of pull sleeves and flex conduit), these items were not

reinspected by HECo or Transco after the fireproofing was

completed. During the inspection, the licensee initiated an

interface agreement between HECo and Transco to ensure that

all future items would be reinspected after fireproofing work

activities had been completed. CECO QA has initiated a

surveillance program on past work activities to ensure that

affected items were returned to their designed condition after

fireproofing was completed.

53

. - .

.- -

. -

. - .

-_

_-_

.

-

-.

---.

.-

The licensee was informed that failure to assure that activities

affecting quality are prescribed by documented instructions and

. accomplished in accordance with these instructions is an

example of a failure to implement Criterion V of 10 CFR 50,

Appendix B (455/86017-098).

(54) Concern: HECo does~not have a Level III Electrical QC

Inspector. Who certifies QC inspectors?

NRC Review: The NRC inspector reviewed HECo's list of QA/QC

personnel _ certifications and observed that a qualified individual

(by name) had been properly certified Level III in all HECo QC

procedures on August 3, 1984.

In order to verify that HECo

QA/QC personnel were qualified and properly certified, the NRC

inspector selected 16 individuals for review.

Following are the

results of this review:

The QA/QC Manager and QC Supervisor not certified to any

HECo procedures.

In that these two individuals were not

performing any inspections, there is no requirement that

they be certified.

The QA Supervisor was certified as a Lead Auditor on March 4,

1985.

In reviewing this individuals certification (Form

HP-177), the NRC inspector noted that the audit participation

(five audits within last three years prior to

certification) did not meet the requirements of HEco

Procedure 17, " Qualification and Training of Inspection

and Audit Personnel," Paragraph 5.5.8.3.

A review of the remaining individuals records revealed

that in several cases, the individual was certified

without or before the Level III inspector's approval.

As a result of the inspector's concern, HEco QA performed

several Special Surveillances in this area.

Following are the results of the Special Surveillances

performed by HECo QA:

Special Surveillance Report (SSR) 16-86 identified a QA

engineer that was certified as a Lead Auditor that did not

meet the requirements of Paragraph 5.5.8.3 of Procedure 17.

This was in addition to the QA Supervisor identified by

the NRC. Corrective action was to withdraw the individuals

lead auditor certification.

As a result of SSRs 21-86 and 22-86, NCR 2057, dated July

25, 1986, was prepared to document that 16 individuals

were certified without prior approval of the Level III

inspector as required by Paragraph 4.2 of Procedure 17.

54

-_ .

-

. .

_ _ _ _ . .

_ _ _ __ _ _ _._ . _ ._ _ _ _- _

_

.

1

c

A review of HECo Procedure 17 determined that this procedure

'

met ANSI N45.2.6-1978, " Qualification of Inspection, Examination,

and Testing Personnel for Nuclear Power Plants," for qualifica-

,

tion and certification of QC inspectors and ANSI N454.2.23-1978,

'

" Qualification of Quality Assurance Program Audit Personnel for

Nuclear Power Plants," for qualification and certification of

Auditor and Lead Auditor personnel.

!

Conclusions: The NRC inspector verified that HECo has a

qualified and certified Level III Electrical QC Inspector on

staff. This individual was certified Level III in all HECo

2-

- procedures on August 3, 1984. However, a review of QA/QC

certifications by the NRC inspector and HECo QA identified that

L

18 individuals (16 QC and 2 QA) were not qualified and/or

l

certified in accordance with HECo Procedure 17.

!

The licensee was informed that failure to assure that QA/QC

i:

personnel were properly qualified and certified is an example

j-

of failure to-implement of Criterion II of 10 CFR 50, Appendix B

(454/86031-14B; 455/86017-14B).

.

l

(55) Concern:

Cable pulling and rework was done on the back shift.

Least experienced QC inspectors were assigned to the back shift

j

with no supervision.

l

.NRC Review:

From interviews of QC personnel and review of records,

it was established that the increase in second shift (back-shift)

3

i

QC personnel occurred in approximately February 1985. The

second shift nucleus consisted of a foreman (QC Lead Inspector)

c

j

and four QC inspectors. This QC nucleus was supplemented by

-

additional inspectors on an as-needed basis. A review of the

experience level of the four QC inspectors assigned to second

i

shift indicates that inspector "A" was initially certified on

i

October 15, 1982; inspector "B" on December 18, 1981; inspector

I

"C" on June 24, 1982; and inspector "D" on December 18, 1981.

!

All four inspectors were qualified and certified in four or more

i

areas, and in addition,~they were all journeymen electricians.

The foreman was certified in six areas of inspection. The

.

i

foreman was not certified in cable pulling, cable termination,

i

Class 1 equipment installation, and cable pan and pan hanger

!

installation although the personnel he was supervising were

certified in these areas of inspection. However, ther is no

l

requirement that a supervisor be certified'in all areas of

?

inspection. Also see Paragraph 5.a(14) above for another

!

example where a supervisor was not certified in the areas he was

i

supervising.

i

l"

Conclusions: The experience of the QC inspectors on second

shift exceeded two years per inspector, in addition, all the

i

inspectors were journeymen electricians. The QC foreman on

-

second, shift was not certified in all areas of inspection,

l

however, there are no requirements for a supervisor to be

!

certified in all areas that he is supervising.

No violations

or' deviations were ioentified.

55

i

t

mm,-<--<,mo,,,,o--

,-m-.,v-nw-,-mw --

w.~+

--.-.--.---+we.-.

-..e+

,.e.--+-<.e.---e.-,.---,--.

  • - - - - -

(56) Concern:

During the spring of 1983, Energy Incorporated

audited HEco on Procedures 9A, 99, and 9C. This has been

referred to as the " Black Book Audit." During this audit,

approximately 70 of approximately 1200 hangers were hand picked

for review. The sample was too small and 80-90 QC identified

discrepancies went away as a result of this audit.

NRC Review: A review of HEco procedures indicated that

Procedure 9A is for " Class 1 Cable Pan Hanger Installation";

Procedure 98 is for " Class 1 Cable Pan Installation"; and

Procedure 9C is for " Class 1 Cable Pan Cover Installation."

Energy Incorporated (EI) is under contract to HECo to perform

periodic management audits of HECo at the Byron Station and to

supply a limited number of QA/QC personnel to supplement the

HECo QA/QC Department. The NRC inspector reviewed EI audits of

HEco.

The NRC inspector was unable to identify an audit that

fits the description of this concern. The only audit, that the

inspector could identify, that approached the alleger's concern

was CECO QA 6-84-309. This CECO QA Audit is discussed in

Paragraph 5.a(30) above. The alleger stated that 80-90 deficiencies

went away as a result of the alleged audit. With this concern

in mind, the NRC inspector reviewed the NCR and DR logs and

selected NCRs and DRs (HECo DR system was implemented May 1982).

The NRC inspector was unable to identify any group of NCRs and

DRs relating to pan hangers that were closed in a relatively

short time frame. There were several major HEco and CECO NCRs

prepared that caused a large reinspection effort of cable pan

hangers (HECo NCRs 407, 407R, 540, and 1235 and CECO NCRs F-786

and F-961). These reinspection efforts were monitored by NRC

inspectors, (Inspection Report numbers are listed below). As

a result of an NRC team inspection at the Byron Station (See

NRC Inspection Report 454/82005; 455/82004) a major reinspection

was initiated.

In the case of HECo, the NRC SRI selected 20%

of HECo's QC inspectors (by name) for a reinspection of their

inspections performed during the first 90 days after their

certification.

Due to the construction effort in that time

frame, a large percentage of the reinspection activity was

concentrated on cable tray hangers.

The following is a partial

listing of NRC Inspection Reports that documents NRC's review

of the CECO reinspection program (This list is not complete in

that the inspector did not perform a 100% review of all 1982,

1983, 1984, and 1985 reports for Byron Station):

Unit 1

Unit 2

454/82017

455/82012

454/83037

455/83029

454/83048

455/83037

454/84013

455/83048

454/84027

455/84009

454/84047

455/84019

454/85,069

455/84041

455/84047

56

The above listed NRC Inspection Reports provide a status and a

final acceptance of the CECO Reinspection Program, which included

cable tray hangers and appeared to be the allegers prime concern.

Conclusions: This concern could not be substantiated in that

the NRC inspector could not identify any audits that came close

to the allegers description that were preformed by Energy

Incorporated. A major reinspection program had been conducted

at Byron Station by the licensee. This reinspection program

included cable pan hangers. This reinspection program was

inspected and accepted by the NRC. No violations or deviations

were identified.

(57) Concern: The alleger questioned the quality of the welds in

Unit 1.

Review HECo NCRs 540 and 1235.

NRC Review: HECo NCR 540 was initiated due to defective welds

in Units 1 and 2.

To facilitate the timely closure of the NCR

for Unit 1, the Unit 2 deficiencies were removed from NCR 540

and documented in HECo NCR 1235.

Both of thee HECo's NCRs were

transferred to CECO's NCRs F-786 and F-961 respectively. The CECO

NCRs were necessary to facilitate a review and dispositioned of

the NCRs by S&L. These NCRs were a part of CECO's reinspection

program which was monitored and accepted by the NRC.

See

Paragraph 5.a(56) above for additional details. In addition, a

NRC Welding /NDE inspector stated in the Byron ASLB Hearings that

he had personally inspected thousands of HECo welds and had found

them acceptable.

Conclusions: The CECO reinspection effort resolved the

deficiencies documented in HEco NCRs 540 and 1235. The NRC

monitored and accepted this reinspection program. The NRC also

performed additional inspection of HECo welds and found them

acceptable.

No violations or deviations were identified.

(58) Concern: Under Procedure 7A, if a hanger is relocated, the

welds may not be reinspected.

NRC Review:

The NRC inspector reviewed Procedure 7A, " Rework

Control." This procedure defines rework as "the removal and

reinstallation of previously installed work." Paragraph 5.4

states, "All work shall be performed to the current revision of

,

the installa.:on documents";

i.e.,

if cable pulling is involved,

use Procedure 10 or if welding is involved, use Procedure 13

series. Paragraph 5.8.2 requires that "an advance copy of all

safety-related rework requests be provided to HEco QA/QC."

Paragraph 5.13 requires " notification of HECo QA/QC when the

work is complete." All inspection reports are listed on the

rework request. An independent review for acceptability is made

by HECo QC with a quarterly surveillance by HEco QA.

In addition,

HECo engineering reviews the rework request and provides a copy

a

to CECO PCD for their review.

Procedure 13AA, " Class 1 Shielded

Metal Arc Welding," Paragraph 5.15 requires "a weld traveler

)

57

card (WTC) to be prepared for all welds." If the weld is

safety-related, a QC weld inspector must inspect and complete

Section III of the WTC in accordance with Paragraph 5.15 of

-

Procedure 13AA, and Procedure 13AE, " Class 1 Visual Weld

Examination Procedure." The WTC number is listed on the rework

'

request.

In addition, the WTC number is also listed on the

conduit support checklist or cable pan hanger checklist, as

applicable.

The NRC inspector selected 100 rework requests for

review.

In all cases where welding was required, a WTC number

was listed.

Using the WTC number and the WANG, the inspector

was able to identify the welder's ID, date welded, weld inspector,

date inspected, item number, drawing number, and the rework

request number was listed in the comment column.

Conclusions:

Based on the NRC inspector's review of procedures,

rework requests, inspection reports, and WANG printout of WTC

numbers requested, this concern is refuted in that no missed

inspections were identified. No violations or deviations were

identified.

(59) Concern: Hanger 15HV-1 has a " slugged-up" welds and no NCR or

DR was prepared. This hanger is located at 364' elevation, at

columns L and 15.

NRC Review:

From the column lines and elevation provided,

the NRC inspector determined that hanger 15HV-1 was shown

on S&L drawing 0-3099H01, Revision AA.

From this drawing, it

was determined that the exact location of hanger 15HV-1 was

l'9" south of 16 line and 2' west of L line. Using the WANG,

it was determined that HECo NCR 1220, dated November 27, 1984,

was prepared by the alleger to document a " slugged weld" on

hanger 15HV-1. A slugged weld is a weld with excessive fit-up

gap and the welder will place pieces of weld rod in the gap and

weld over top of the rod. This type of welded joint does not

develop the required strength and is therefore unacceptable.

.

The slugged weld was removed and the joint was rewelded and

i

inspected as documented on WTC 75377 and on NCR 1220.

In

addition, the welder was retrained, and the NCR was properly

closed on June 24, 1985.

Conclusions: This concern was not substantiated in that

NCR 1220 had been prepared on hanger 15HV-1 for a slugged

weld. The weld was repaired and the NCR properly closed.

No violations or deviations were identified.

(60) Concern: There are 8-10 discrepancies on the Unit 1 AF system

l.

battery racks.

Do not think they will meet seismic

l

i

s

l

l

\\

58

l

l

_ - ,

..

- -

. _ _

_

. . .

-

-

.

- -

. . - - . . -

- - - . .

_ , - _ _ _ .

requirements and no NCR or DR was prepared on these racks. The

battery racks are located at 383' elevation, at columns L and

19.

NRC Review:

From the equipment list, it was determined that

the AF (Auxiliary Feedwater) system batteries, including racks,

were assigned equipment numbers IAF01EA and 2AF01EB. A review

of the records for this equipment revealed that DR 8094 was

prepared by the alleger to document the fact that battery racks

2AF01EA and 2AE01EB were not installed per detail 801 on S&L

drawing 0-3391H. This DR was subsequently upgraded to NCR 1734,

dated October 24, 1985, which was forwarded to Ceco /S&L for

disposition. After performing an analysis, S&L issued ECN

(Engineering Change Notice) 30487 to document the as-built

condition of the subject battery racks and NCR 1734 was

dispositioned "use-as-is."

NCR 1734 was properly closed on

May 23, 1986. Based on the NRC inspector's review, the S&L

analysis was found acceptable.

Conclusions: The discrepancies identified on AF system battery

racks 2AF01EA and 2AF01EB were documented on DR 8094 which was

subsequently upgraded to NCR 1734.

The as-found condition was

analyzed by S&L and found acceptable. ECN 30487 was issued to

document the as-built condition of battery racks 2AF01EA and

2AF01EB. No violations or deviations were identified.

(61) Concern: HECo engineering or QA writes all NCRs per

Procedure 6 and at times, they do not address the problem. The

applicable QC inspector should have input in preparing the NCR

or at least, let the QC inspector review the NCR before it is

issued.

Inspectors can only write " practice" (un-numbered) DRs

and NCRs.

NRC Review: A review of HECo Procedure 6, " Reporting of

Damaged or Nonconforming Material or Equipment," Revision 15,

dated September 23, 1985, revealed that QC inspectors

were not permitted to prepare DRs or NCRs.

Paragraph 5.2.1 of

this procedure states, " Deficient items which are not identified

for correction and tracking thru the use of open inspection

reports, will be brought to the attention of the appropriate

supervisor for evaluation.

Supervisors shall write DR's as

appropriate based upon their evaluation." DRs are then forwarded

to HECo Project Engineer and/or QA/QC Manager for resolution.

DRs may be upgraded to NCRs. The NRC inspector expressed a

concern with QC inspectors not being permitted to prepare, at a

minimum, DRs. As a result of this NRC conern, HECo issued

procedure change notice (PCN) 67 to revise Procedure 6.

This PCN

allows the QC inspector / supervisor to prepare DRs. .In that the

QC inspector can now prepare DRs and DRs are typically attached

to the NCR (when they are upgraded), this should alleviate the

QC inspector's concern with the wording on NCRs. Also, the

present QA/QC Manager has stopped the practice of preparing

" Practice" deficiency reports. During the inspection, the NRC

inspector did not identify any hardware problems resulting from

the use of " practice" DRs.

59

-_ --

. . _ - .

-_

1

A review of NCRs, DRs, and inspection reports (IR) revealed that

in some cases _the description of the deficiency was not clear

and/or pertinent data was missing.

This resulted in some poor

and/or incomplete resolutions.

In order to prevent recurrence

of similar deficiencies in the description of the deficiency,

the HECo QA/QC Manager issued QA/QC Memorandum 2365, dated

September 5, 1986. This memorandum states, in part, "The Lead

Inspector, Group Leader and Assistant QC Supervisor is responsible

for reviewing the reports (DRs, open and closed inspection

reports) to assure completeness and inclusion of sufficient data

to substantiate the inspection results. Any reports which lack

sufficient data will be returned to the inspector for correction."

Conclusions: PCN 67 to Procedure 6 was issued to permit QC

inspectors to prepare DRs. Most NCRs are upgraded DRs with

the DR attached. This now allows QC inspector input to DRs

and NCRs. A review of NCRs, DRs, and irs revealed that in some

cases, the description of the deficiency was not clear and/or

pertinent data was missing.

irs (open and closed) and DRs

now go through several levels of QC review prior to issue.

In

addition, the preparation of " practice" deficiency reports has

been stopped by.the direction of the present HECo QA/QC

Manager. .The use of " practice" DRs did not impact the quality

of the inspections.

(62) Concern:

The HECo QC inspectors cannot get QA/QC management to

listen.

NRC Review:

From personnel interviews and observations during

this inspection, the NRC inspector determined that there was a

severe communication problem within the HECo QA/QC organization.

During this inspection, (a) the QA/QC Manager resigned and was

replaced with an individual that has an "open-door" policy; (b)

the QC Supervisor resigned and was replaced with an individual

that is known and respected by the QC inspectors; and (c) the

QA Supervisor resigned. The QA Supervisor's position is being

filled by the present QA/QC Manager.

In addition, the QC-field

office was closed and all QA/QC personnel are now in the HEco

main office. Since the above changes were implemented, there

appears to be a harmonious atmosphere within the QA/QC office.

Based on the PTL overinspection program (See Paragraph 5.a(10)

above), the lack of communications did not affect the quality

of inspections.

s

Conclusions: There was a severe communications problems within

the HEco QA/QC organization. However, the quality of

inspections were not affected. This appears to have been

resolved with the replacement of the " top-three" in the QA/QC

organization and the closing of the QC field office. No

violations or deviations were identified.

(63) Concern: The QC Supervisor (by name) harassed and attempted to

intimidate a QC inspector (by name). The NRC inspector

was provided a copy of HECo NCR 2021, dated May 12, 1986.

60

_-

.

-

._- - -

-

-

-._

-

. - - - - - - - - - . . -

. -

t

.

NRC Review: The NRC inspector interviewed the named QC inspector

and the inspector's immediate supervisor (Lead Inspector). The

Region.III inspector was unable to interview the named QC

Supervisor in that he had terminated his employment with HECo.

<

_ The named QC inspector stated that on May 9, 1986, he was

i

assigned to core drilling. This work operation is performed by

another contractor (Litgen) but HEco is responsible for the QC

,!

inspection of cored holes in accordance with HEco Procedure 21,

" Cored Hole Requests and Inspections." On May 9, 1986, the

,

named QC inspector attended a meeting with two NRC inspectors

i

(Reference: Paragraph 5.a above). Prior to attending this

!

meeting, he informed his lead inspector he would not be available

to inspect cored holes while the meeting was in progress. After

'

i

the meeting was over, the inspector stated he went into the

i

plant and observed that Litgen had cored holes 2059 and 2060

j

without QC being present.

In that this was a violation of

procedures, the named QC inspector prepared two draft NCRs, one

on each cored hole, and submitted them to his lead inspector for

i

review and processing.

The named QC inspector stated that the

next time he saw the NCR (2021) was when the named QC Supervisor

2

called him into his office and " chewed him out" for missing two

j

inspections. The QC inspector also stated that the supervisor

threatened to place a letter (letter of reprimand) in his

personnel file. The QC inspector stated that he informed the QC

.

j

Supervisor that he told his lead inspector he was meeting with

,

the NRC and that his lead attended the same meeting. The QC

i

inspector stated that "the QC Supervisor told me that I was

lying because XXXXX (lead inspector) said that I never told him

I would be attending the meeting." The named QC inspector

-

provided the NRC inspector copies of the two draft NCRs he had

-

i

prepared on cored holes 2059 and 2060. When the draft NCRs were

compared with NCR 2021, it was observed that the two draft

NCRs were combined into NCR 2021 with additional words added.

NCR 2021 now reads in part, " Core Hole #2059 was drilled without

.

'

QC (inspector's name) present. This is a violation of Procedure

l'

  1. 21, paragraph 5.3.3 and 5.3.3.1.

(Hatfield QC was notified

prior to core drill, but choose not to attend to their

l

responsibilities)." There was a single line drawn through the

inspector's name with initials and a date.

It was determined

I

that the initials were placed there by the HEco QA/QC Manager,

j

The NRC inspector was informed that the information within

j

parentheses on NCR 2021 was added by the named QC Supervisor.

This was also confirmed by the lead inspector.

1

i

During an interview of the subject lead inspector, the NRC

{'

inspector was informed that the named QC inspector had informed

,

him (lead inspector) that he would be attending the meeting with

'

the NRC and that he was aware that the named QC inspector was

assigned to core drilling on that day (May 6, 1986). The lead

<

1

inspector stated that he had informed the named QC Supervisor

l

j

that hp (lead inspector) was at fault for not assigning another

'

I

inspector to the core drilling effort. This lead inspector

confirmed that he had attended the meeting with the NRC on May 9,

1986 and that he had discussed his attending with the named QC

i

4

61

i

-~v-,-,-

,

--

.__---,-__,--,---~w-.

.

.v..--~....

.

. -

Supervisor before and after the meeting (Also see Paragraph

5.a(64) below).

The NRC inspector verified that a letter of reprimana had not

been placed in the named QC inspector's personnel file. Also,

NCR 2021 was properly closed on June 2,1986.

Conclusions:

From personnel interviews and review of records,

it was determined that an unnecessary and uncalled for

statement was placed on NCR 2021 by the named QC Supervisor.

However, since NCR 2021 was properly closed, no letter of

reprimand was placed in the inspector's file, and the named

QC Supervisor is no longer employed by HECo.

No additional

NRC follow-up action is planned on dis concern.

(64) Concern: The QC Supervisor (by name) called a lead inspector

(by name) into his office and questioned him about the May 9,

1986, meeting with the NRC. This meeting lasted approximately 1

1/2 hours and the lead told all.

NRC Review: The NRC inspector interviewed the named lead

inspector about this concern.

The NRC inspector was informed

that he (the lead inspector) discussed his attending the May 9,

1986 meeting with the NRC with his supervisor (named QC

supervisor) and he initiated the interview with his supervisor

following the meeting with the NRC. The lead inspector stated

that he and his supervisor discussed the concerns expressed to

the NRC.

Conclusions: This concern was not substantiated in that the

named lead inspector initiated the interview with the named

QC supervisor. No violations or deviations were identified.

(65) Concern: Safety-related drawings are not checked for

inspections.

There are no termination cards for internal

wiring and QC has to depend upon constructions to issue an

inspection request.

NRC Review: The NRC inspector reviewed Procedure 11, " Class 1

Cable Termination and Splicing," and noted the folloving

related requirements:

Paragraph 5.1.5 states, "The S&L Wiring Diagrams shall

identify the terminal point of each conductor."

Paragraph 5.1.7 states, "The cable will be terminated as

shown on the wiring diagram."

Paragraph 5.9.1 states, " Inspections for cable

terminations, splices and repairs shall be performed using

Fprm HP-118."

62

_

-

Form HP-118, Cable Termination Inspection Report,

inspection attribute 15, states, " Terminated per Wiring

Diagram." The wiring diagram number and revision must be

entered on this form.

Exhibit N provides an example of a " Cable Pull Card,"

also, the back of the pull card provides the cable

"From End" and "To End" termination data.

Paragraph 5.1.28 states, "Upon completion of the splice,

the termination, or the repair, the field personnel will

fill in the required information on the cable pull card

and on the Form HP-118. These documents will then be

returned to the QA/QC Department for acceptance and

retention."

This is constructions method of notifying QC

that an item has been installed and is ready for

inspection.

For Unit 2, HECo QC is now in the process of listing all items

requiring inspection (For examples, hangers, cables, cable pans,

and conduit) and verifying that the applicable inspection

reports are on file. To assure that revised drawings are being

reviewed for additional work (revisions to installed items cr

new work), the NRC inspector selected six drawings for review.

All six drawings had been reviewed by production, engineering,

and QA/QC. This review resulted in four rework requests being

prepared to rework items that had been previously installed and

accepted. The NRC found the controls to be adequate and the

controls acceptable.

'

Conclusions:

Procedures are in place to preclude missing of

required inspections for Unit 2.

Paragraph 5.a(39) above is

an example where HECo identified missing WTCs for Unit 2 riser

collar welds.

Procedures also require construction to notify

QC when an item has been installed and is ready for

inspection. No violations or deviations were identified.

(66) Concern:

Sargent and Lundy (S&L) added conduits to a J-Box

without considering load effects. Think XXXXX (named QC

inspector) wrote up one box and additional anchors (CEAs) had

to be added.

NRC Review: The NRC inspector reviewed NCRs 540 through 1992

and could not identify any NCR that fits the description of this

concern.

During this review, the NRC inspector noted that

some NCRs had been issued on undersized concrete expansion

anchors (CEA) being installed, or CEAs not being installed to

the minimum embedded depth.

In all cases noted, the CEAs

were found to be acceptable as installed based on analyses by

S&L. During this review of NCRs on CEAs, the NRC inspector

selected the NCRs dispositioned "use-as-is" and reviewed the

S&L analysis to verify justification for the disposition.

l

No discrepancies were identified with the analysis.

63

Conclusions: Based on the NRC inspector's review of approximately

1450 NCRs, without being able to identify an NCR that fit the

allegers concern, this allegation was not substantiated.

In

addition, the NRC inspector reviewed the S&L analyses on ten

NCRs where the CEAs were accepted as installed. The S&L analyses

was found to be adequate. No violations or deviations were

identified.

(67) Concern:

HECo QC was directed to limit their inspections to the

scope of the applicable 7A (Rework Request).

NRC Re,iew: During interviews of HECo QC inspectors and lead

inspectors, the NRC inspector was informed that certain

QC inspectors wanted to reinspect everything in the area when

they were assigned to inspect an item on a rework request.

Two examples were provided (a) As a result of a drawing revision,

a new conduit hanger is being installed on previously accepted

tube steel by a rework request. At least one QC inspector would

have the fireproofing removed so he could reinspect all the

tube steel welds as well as the welds on the new conduit

hanger and (b) As a result of a drawing revision, a new cable is

being added to a cabinet by a rework request. Again, at least

one inspector would reinspect all the terminations in the

cabinet in addition to the termination of the new cable.

For

the examples provided, it is not necessary to reinspect the

surrounding items. Only the actual rework requires inspection.

If however, an item was being reworked, and the nature of the

rework caused damage to the surrounding equipment, then an

expanded reinspection would be justified.

In all examples

discussed above, if a discrepancy was identified outside the

scope of the rework request, it should be documented in

accordance with HECo procedures. During a review of rework

requests, the NRC inspector did not identify any rework that

would justify a reinspection of any item (s) outside the scope

of the rework request.

Conclusions: Based on personnel interviews and review of

rework requests, the NRC inspector did not identify any rework that

would justify a reinspection of any item (s) outside the scope

of the rework request.

However, if any discrepancy is

identified, it should be documented in accordance with HECo

procedures. No violations or deviations were identified.

(68) Concern: When using a standard 45' or 90* conduit fitting, the

minimum cable pulling and training radius is exceeded.

NRC Review:

Conduit fitting are designed to have cable pulled

through the fitting without causing damage to the cable. When

pulling cable, the cable does not follow the inside radius of a

conduit bend (fitting or formed conduit).

The cable contact

points, during a pull, would be the outside of the fitting

radius on both ends and the inside of the fitting radius in the

middle of the fitting.

Electrical cables (except for special

64

cables) can be pulled through a specified conduit fitting without

exceeding the minimum cable bend radius. . Cables under tension

have a more restrictive bend radius than cables not under

tension. Therefore, the cable train radius would also be

acceptable for a cable installed in a conduit with specified 45'

<

or 90' fittings.

S&L Standard EB-146, paragraph 7.2.6, does

not permit " standard" radius elbows (bends) unless specifically

indicated on the Electrical Drawings.

.

Conclusions:

Electrical cables (except for special cables) can

be pulled through a specified conduit fitting without exceeding

the minimum cable pulling or training radius.

S&L Standard

EB-146 does not permit a " standard" radius elbow unless

specifically indicated on the Electrical Drawings. No violations

or deviations were identified.

(69) Concern: There is a memorandum from the Assistant Project

Manager, dated April 18, 1986, on NCRs and DRs.

If this

memorandum.is implemented, it would give the craft a chance to

correct the deficiency before the DR/NCR is written and

dispositioned.

NRC Review: The NRC inspector obtained a copy of the Assistant

Project Manager's subject memorandum for review. This memorandum

indicates that when a violation is identified, all the applicable

HEco personnel should be notified immediately so the violation

could be reccnstructed for the owner while the facts were fresh

in people's minds. This memorandum states, in part, "The above

subject (NCR and DR violations) has been discussed many times,

where as QA/QC would identify violations such as pull over tensions,

preheat and any other violations that we, HECo, knows will result

in a NCR that we will have to reconstruct for the owner.

...

the QC inspectors can be instructed to let QC Supervisor know when

there is a violation.

This will enable us to get it resolved

and down on paper by the time the NCR appears, which in most

cases has been weeks later." As can be seen from the memorandum,

the Assisthnt Project Manager recognized the fact that an NCR

would be prepared for certain violations and that the facts of

the violation must be presented to the licensee on the NCR.

Conclusions: Based on a review of the Assistant Project

Manager's memorandum of April 18, 1986, it was concluded that

the purpose of the memorandum was to request early notification

of violations. This early notification would permit HECo to

gatter the facts of the violation for' presentation to the

licensee and not to correct the violations before a DR/NCR was

prepared. No violations or deviations were identified.

(70) Concern:

Field Change Request (FCR) F-26448 relocated a

terminal box on panel 2PL85JA.

This panel was installed by

Powers-Azco-Pope (PAP) and the subject terminal box appeared on

a PAP drawing. HECo relocated the terminal box. Was FCR

F-26447 ever incorporated on the applicable PAP drawing?

65

.

NRC Review: The NRC inspector reviewed FCR F-26447. This

review revealed that'the subject FCR had been incorporated on

Systems Control (panel vendor) drawing 6577-M-2PL85JA on

September 19, 1985. The systems control drawing was provided

to PAP for their use in the installation of instrument panel

-

2PL85JA.

Conclusions:

FCR F-26447 was incorporated on Systems Control

Drawing 6577-M-2PL85JA.

This drawing was provided to PAP for

their use in the installation of panel 2PL85JA. No violations

or deviations were identified.

(71) Concern: Review HECo NCRs 937 through 942 for proper closure.

Also review S&L's walkdown for separation violations.

NRC Review: The NRC inspector reviewed HEco NCRs 937 through

942 and found that all these NCRs pertained to electrical

separation violations and were prepared after the CECO, HEco,

and S&L separation walkdowns.

These NCRs identified previously

identified separation violations. The NRC reviewed the separation

walkdown effort; S&L analysis of the violations identified;

applicable drawings to verify that tray covers were specified

<

as part of the corrective action; and performed a tour of the

power block and identified separation violations and verified

1

that these violations had been identified during the joint

separation walkdown. (See NRC Inspection Report 454/84027;

455/84019). These walkdowns and corrective actions were found to

be acceptable, however, the licensee was issued a violation, by

the NRC, for failure to inspect for separation violations on

i

items installed after the joint walkdowns were completed.

The

'

NRC issued violations were subsequently closed in NRC Inspection

Reports 454/84047; 455/84041 and 454/84069; 455/84047.

Conclusions: The electrical separation violations identified

on NCRs 937 through 942 had been previously identified during a

joint (CECO, HEco and S&L) separation walkdown. The NRC's

actions on separation issues are documented in the NRC

Inspection Report referenced in the above paragraph. No

violations or deviations were identified.

(72) Concern:

Review HECo QA/QC Manager's (by name) interoffice

memorandum. QC inspectors need approval to go to Ceco for any

'

reason.

NRC Review:

The NRC inspector reviewed the QA/QC memorandum

file and memorandum log. A review of the file revealed that

QA/QC Memorandum 1669 was missing. A review of the log indicated

that the subject of this memorandum was " Department Policy," and

was prepared on January 10, 1985. During interviews with

numerous QA/QC personnel it was revealed that during a staff

meeting, conducted by the named QA/QC Manager, they were informed

that they could not go to the CECO office without their Supervisors

66

. - .

._

.

_ _ _ .

_ _ - _ _ _ _ _ . _ - -

__

_

_ - - _ _ - - -

_ - . - - _ _ .

.

g..

- - ,

-.

.. ~ - -

- -

.__r

]%;

Q* .-

,

_

c

+~

'i

-

n;

,j

.-

q-

(

^-

4

j ' [

,

.

3

_

.,

'

,f .

pm

y

a

y,

'

g

huthorization. At the NRC'ii'spector's request, various inspectors,

~

i

p. lead inspectors, and clerks searched their personal files for a

hopy of Memorandum.1669 with negative results. , Based on the NRC

.

m

"

j

inspector's observations during the inspectin, neither quality

nor communications nith the'11censee was affected by the HECo

'

j.

t

QA/QC Manager's vernal directions and/or the subject memorandum.

f

1

The named QA/Q? Manager was not interviewed in that he had

.g

terminated his'empicyment with HECo.

'

-

A.

. Conclusions: 1This concern could not be refuted nor

p

substantiated in!that a copy of HECo QA/QC Memorandum 1669

~L

could not be found. The named QA/QC manager was not interviewed

's

in that he had terminated his employment with HEco. There was

}.

l.,

no effect on the quality of the plant and communications iwth-

the licensee. Mo violations or deviations were identified.

V

,

,

?

  • W

(73) Concern: LFor hurtain Unit 1 equipment, the weld downs inside

"

the cabinets were not welded per detail. These weld downs were

$

q

never repaired.

!

'

-

NRC Review: The NRC inspector was able to identify HECo DR

.

, .

4181, dated February 9,'1984, HEco NCR 855, dated Fe.bruary 13,

1

'

!

e1984, and Ceco NCR F-916, dated June 1, 1984, that addressed

  • this concern. JAs can be seen from the dates of the various

'

., (

.,

!

documents, the deficiencies were first identified on DR 4181.

4

i

'p

'This DR identiflad defective welds or welds that were not welded

Q

'per.the drawing detail for the following items of. equipment;i

44'

+

1AP05E

1AP06E

1AP106E

1AP26E

^

F

\\

1AP99E

1AP98E

1PLO4J

j ':

y'

(

'

,,

j ",

DR 4181 was subsequently upgraded to HECo NCR 855. The largest

"

t

number of defects pertained to slot welds not being welded per

.

'

the drawing detail. Detail 47 requires slot welds to be welded

[ p

c.

onall?Jpursidesanditwasidentifiedthattheywereonlywelded

Nh

on the two long sides of the slot. 'Several instances of problems

L['

with weld overlap, u'ndercut, slag inclusion, and weld spacing

were'also identified. At the licensee's direction,-weld maps

~

n-

-

were prepared for the above listed equipe nt.

This information

!

O

was ccmpiled and incorporated in CECO NCR C-916 whl:h was

(

forwarded to S&L for their evaluation. Based on the S&L analyses

,,

v

.r. "of the as-welded condition, it was determined that no additional

'

welding (repair or rework) was required fob these items to meet

'

l

Ahe seismic requirements for Class IE equipment. These NCRs

j

'were properly closed on July 9,1984. The same type of weld

i

deficiencies were identified on similar Unit 2 equipment. The

i

Unit 2 deficieacies were documented on HECo NCR 1669 and Ceco

'

'

i

NCR F-1005. These Unit 2 NCRs were properly closed on

i

December 14, 1965.

For additional details, see NRC Inspection

l

Report 454/86019, 455/86014.

,

'\\

i

4

'

i

I

.'

7

67

<

ic

-

tj

3

, , . , . , -

- '

n,.,.s

.. .

-,,,m.m

mw%

__

>

Conclusions: As documented on HECo DR 4181, HEco NCR 855, and

CECO NCR F-916, some Unit 1 and Unit 2 equipment weld downs were

identified as not being welded to detail and/or had defective

welds.

The S&L analyses of the as-welded condition determined

that no weld repair / rework was required for these items to meet

the seismic requirements. No violations or deviations were

identified.

(74) Concern: Cable tray span is never verified.

NRC Review:

Cable tray span is defined as the span / distance

between adjacent cable tray hangers. The maximum cable tray

span is determined by the design analysis.

From this analysis,

the design engineer determines the hanger location and the

hanger installation tolerance.

If the cable tray hangers are

installed per the design drawings (design location + the

installation tolerance), then the cable tray span criteria

would be met. During a review of HECo Procedure 9A, " Class 1

Cable Pan Hanger Installation," the NRC inspector verified that

cable tray (pan) hanger location was inspected by QC. Attribute

6 on Form HP-9A-1, " Class 1 Cable Pan Hanger Inspections

Checklist," states, " Hanger Location per Drawings." The criteria

for this attribute states, "The hanger must be located within

the tolerances specified on the Cable Pan Hanger Drawing 0-3272."

'

The NRC inspector reviewed approximately 100 HP-9A-1 forms to

1

verify that QC was inspecting this attribute. No discrepancies

'

were identified.

Conclusions: Cable tray span was in fact being verified by

~~

confirming that the cable tray hangers are installed per the

design drawings.

Inspections for cable tray hanger location

were properly documented on Form HP-9A-1. No violations or

!

deviations were identified.

(75) Concern: A HEco QC inspector (by name) and his wife were

'

threatened and HECo management did nothing about it.

The

named QC inspector would not allow the craft to pull cable '

until they installed a dynamometer.

'

NRC Review: Toprotecttheelectricalcablefrombeingdver

stressed during cable pulling, a maximum cable. pulling tension

is established. To prevent exceeding the msximum cable pulling

tension, a dynomometer is installed to measure the actual pulling

tension. The requirements for using a dynomometer are established

in HECo Procedure 10, " Class 1 Cable Installation." The NRC

inspector interviewed the named QC inspector with respect to

this concern. The NRC inspector was informed that neither the

named QC inspector nor anyone in his' family had even been

threatened.

The named QC inspector stated that an incident had

~

taken place in approximately November 1985 where he had stopped

a cable pull due to a lack of the required dynomometer being

installed for the cable pull.

During this incident, one of the

68

__

i

i

craftsmen addressed this QC inspector using abusive and foul

language, but the inspector was never threatened.

This QC

inspector reported the incident to his supervisor.

The NRC

inspector was informed that an immediate investigation was

performed by HECo management. This investigation culminated in

the termination of the craftsman.

Conclusions: The named QC inspector stated that neither he nor

his family had ever been threatened. However, there was an

incident where a craftsman addressed the named inspector using

/

.busive and foul language. HECo management conducted an

immediate investigation which culminated in the termination of

the craftsman. No violations or deviations were identified.

)

(76) Concern: The signature of a QC inspector (by name) was forged

on Class 1 Exposed Conduit System Inspection Checklist Report

Numbers 576 and 577. These forged signatures were reported to

the deco QC/QC Manager (by name) but nothing was ever done to

get the issue resolved.

NRC Review: The NRC inspector discussed the alleged forged

reports-(576 and 577) with the CECO QA Superintendent and

present HECo QA/QC Manager. The named QA/QC Manager is no

longer employed by HECo.

The licensee retrieved the original conduit inspection reports

(576 and 577) with the purported signatures of the named QC

inspector and 12 original documents containing the known

signatures of the named inspector. These original documents

were provided to a Foresic Document Examiner for examination

to determine if all of the signatures were written by the named

QC inspector.

.

During this inspection, the NRC inspector reviewed a

letter, dated October 27, 1986, from the Forensic Document

Examiner to the law firm of Isham, Lincoln and Beale that

described the documents reviewed and the results of his review.

The Document Examiner's letter stated, " Based upon the

examinations and comparisons of the exhibits submitted, the

examiner is of the opinion that the writer of the known

exemplars authored the three (3) questined signatures on

Exhibits Q-1 and Q-1" (Inspection Report 576 and 577).

Conclusions: After examination by a Forensic Document

Examiner, it was concluded that the signatures on conduit

inspection reports 576 and 577 were not forged, therefore, this

concern was not substantiated.

No violations or deviations were

identified,

i

69

1

,

!

--

(77) Concern: Category II (non-safety-related) to Category I

(safety-related) welds are not being inspected by HECo QC.

Also, there are many Category II to Category I cross-flange

welds.

NRC Review: The NRC inspector reviewed Electrical Specification

F-2790 for welding requirements in the areas of this concern.

Section 30.12 states that S&L Standard Form 1701, Revision G,

forms a part of the specifications. The title of Form 1701 is

" Standard Specification for Welding in Steel Construction."

Section 401.19.1 of the specifications states, " Welds,

includirg full and partial penetration groove welds, shall be

subject to visual inspection as specified in BY/BR/VWAC."

~

Section 3.2.2 of Form 1701 states, " Fillet welds across flanges

of any steel member will not be permitted unless specifically

indicated on the design drawings; any under cutting or damage

that will reduce the flange area will not be permitted."

Section 4.1.1 of Form 1701 states, "All welding shall be

inspected and examined by contractor . . . unless otherwise

indicated in the Project Specifications or the design drawings."

With respect to this concern, the inspector requested and

received assistance from NRC Welding /NDE inspectors. The

results of their findings will be documented in a subsequent

NRC Inspection Report (454/86042; 455/86038).

Conclusions: With respect to this concern, NRC welding /NDE

inspectors are investigating this concern ,and the results of

their findings will be documented in a subsequent NRC

Inspection Report.

Pending the completion of this inspection,

this item is open (454/86031-10, 455/86017-10).

(78) Concern: Procedure 20 is not compatible with S&L Standard

EB-146.

NRC Review: The NRC inspector reviewed Procedure 20, " Class 1

Exposed Conduit System Installation," Revision 15, and compared

it to the requirements of S&L Standard EB 146,." Standard

Specification for the Installation of Seismic Category

1 Conc'uit Systems Containing Class IE Cable," dated April 23,

1986. The NRC inspector noted that there were several instances

where a S&L drawing was referenced as the installation criteria

rather than Standard EB146.

However, the Electrical Specification,

Paragraph 304, states that the S&L drawings take precedence over

S&L Standards.

Conclusions: During a review of Standard EB-146 and

Procedure 20, it was observed that there were several instance

where a drawing was referenced instead of Standard EB-146.

However, S&L drawings take precedence over S&L Standards. No

violations or deviations were identified.

(79) Concer'n: During core drilling, there were numerous rebars

70

cut / hit in "Q" wall and many were not reported to S&L.

NRC Review: The NRC inspector reviewed approximately 100 cored

hole reports (CHR).

For all safety-related CHRs that indicated

a rebar cut / hit, an NCR was prepared if the cut / hit rebar was

not permitted by the field change request (FCR) and/or core

drilling request (CDR). Even though an NCR was not required, a

copy of all safety-related and non-safety-related CHRs were

forwarded to S&L for their review. During this inspection, the

NRC inspector selected 10 CHRs for "Q" wall where rebar was

cut / hit and verified that S&L was plotting / recording the cut / hit

rebar on the appropriate "Q" wall (a safety related wall)

location.

In addition, the NRC inspector also selected five

cut / hit rebar NCRs on "Q" wall and verified that they were

.

properly plotted / recorded.

No deficiencies were identified.

Conclusions: Cut / hit rebars were being preperly documented by

S&L. No violations or deviations were identified.

(80) Concern:

Procedure 21, " Cored Hole Requests and Inspections,"

states that "no items may be installed in a cored hole until

HECo receives a completed CHR signed-off by CECO PCD."

How can

CECO sign-off (accept) a CHR with an open NCR against the cored

hole?

NRC Review: The NRC inspector reviewed Procedure 21 and

interviewed CECO PCD engineers. CECO PCD engineer's signature

on a cored old report (CHR) is the licensee's approval for " Work

May Proceed." If an NCR is prepared on the cored hole due to a

rebar being cut / hit, the NCR tracks the deficiency. Therefore,

a cored hole with a cut / hit rebar would not be " accepted" until

the NCR was properly closed.

Conclusions: CECO PCD engineer's signature on a CHR is the

licensee's approval for " Work May Proceed." The proper closure

of the NCR would be the acceptance of the cored hole with

identified deficiencies. No violations or deviations were

identified.

(81) Concern: At final turnover to CECO, did the electrical raceway

hangers meet the latest S&L drawings?

NRC Review: The NRC inspector reviewed the inspection,

reinspection and overinspection history of the raceway hangers

at the Byron Station. As a result of the NRC team inspection

(See NRC Inspection Report 454/82005; 455/82004), a major

reinspection program was initiated at Byron Station (See Paragraphs

5.a(56) and (57) for similar concerns).

This reinspection

program included a reinspection of raceway hangers. The Following

is a general sequence of events as relating to the raceway

hanger, reinspection program:

71

-

.

.-_.

__ -

._.

.--

-_--.

--

HECo NCR 407, dated February 11, 1982, documented that

cable pan hanger inspections were inadequate. A sample

inspection was performed on 20% of the total hangers in

each of the six drawing areas with a 26% reject rate. The

corrective action was to perform a 100% reinspection of

i

all cable pan hanpers. This NCR was closed on June 9,

>

1982, before the reinspection was completed.

HECo NCR 407R was initiated on December 3, 1982 to track

the reinspection program.

NRC Inspection Reports 454/82017; 455/82012 issued an

Unresolved Item pending final review of NCR 407.

NRC Inspection Report 454/83048 provided a status of NCR

407/407R.

NRC Inspection Reports 454/84027; 455/84019 issued an NRC

violation for inadequate inspections in conjunction with

NCR 407R. As a results, 345 previously accepted cable

tray hangers were reinspected and 129 were found defective

and 19 were classified as indeterminate because they were

inaccessible for reinspection. To document these

deficiencies, HECo prepared NCR 989 and DRs 4921-4928,

4930, 4932, 4934-4937, 4943, 4945-4948, 5003, 5007,

5013-5017, 5019, and 5022-5032.

NRC Inspection Reports 454/84047, 455/84041 closed the

Unresolved Item identified in IE Inspection Reports

454/82017; 455/82012.

l

NRC Inspection Reports 454/84069; 455/84047 closed the

l

violations identified in IE Inspection Reports 454/84027;

l

455/84019.

During the review of this concern, the NRC inspector was provided

copies of various memorandums between Ceco and HECo. The following

is a general description of these memorandums:

QA/QC Memorandum 897, dated July 1,1983, from a HECo QC

lead inspector to the HECo QA/QC Manager identified

certain pan hanger attributes that were not being

inspected; e.g., gusset plate size, fit-up gap, and locus of

working points.

QA/QC Memorandum 1173, dated February 22, 1984, from a

HECo QC inspector to the HECo QC Supervisor identified

that " Prior to February 13, 1983, pan hangers were in most

cases not inspected per detail."

J

72

-

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

QA/QC Memorandum 1230, dated March 23, 1984, from HECo

QA/QC Department to CECO PCD project electrical supervisor

stated, "HECo QC has reviewed all detail connections on

the 0-3200 series drawings. Attached is a copy of each

detail including the items that have not been inspected."

The attachments to this memorandum listed the following

types of items as not being inspected plate sizes;

DV-161 stiffners; fit-up gap; I beam size; bolt hole

dimensions; bent plate size; locus of working points; etc.

NOTE: The same types of discrepancies were

previously identified by the NRC.

Fit-up (91); plate

size (17); wrong connection detail (7); welding;

missing bolts (See Inspection Reports 454/84027;

455/84019). This inspection was conducted between

April 24 and May 11, 1984

CECO letter dated July 16, 1984, transmitted HECo QA/QC

Memorandum 1230 to S&L for review.

S&L letter to CECO, dated October 2,1984, documented the

results of S&L's inspection program and analysis of

uninspected items identified in HECo QA/QC Memorandum

1230. The following are excerpts from the S&L letter:

80 randomly selected supports were inspected.

-

pre-approved checklist were utilized.

-

engineering evaluation included observed discrepancies

-

and Byron QC Inspector Reinspection Program.

engineering evaluation finds that the corresponding

-

strength reduction in the connections is within the

specified design limits.

the quality of cable tray support connection work is

-

adequate through out the plant for both Units 1 and 2.

Based on the NRC inspector's review of the S&L inspection program

and their engineering evaluation, S&L's evaluation was adequate

to accept the hangers installed to date.

CECO letter from the PCD Project Electrical Supervisor to

the HECo QA/QC Manager, dated October 8, 1984, transmits

the S&L letter (October 2,1984) to HECo and states,

"This review has been completed and as identified in

reference (b) above (S&L letter of October 2, 1984), the

quality of the cable tray support connection work is

adequate throughout the plant for both Units 1 and 2.

73

-

.

.

.

-

-

_ . - - .

-_

__

_

cut / hit in "Q" wall and many were not reported to S&L.

NRC Review:

The NRC inspector reviewed approximately 100 cored

hole reports (CHR).

For all safety-related CdRs that indicated

a rebar cut / hit, an NCR was prepared if the cut / hit rebar was

not permitted by the field change request (FCR) and/or core

drilling request (CDR). Even though an NCR was not required, a

copy of all safety-telated and non-safety-related CHRs were

forwarded to S&L for their review. During this inspection, the

NRC inspector selected 10 CHRs for "Q" wall where rebar was

cut / hit and verified that S&L was plotting / recording the cut / hit

rebar on the appropriate "Q" wall (a safety-related wall)

location.

In addition, the NRC inspector also selected five

cut / hit rebar NCRs on "Q" wall and verified that they were

properly plotted / recorded. No deficiencies were identified.

Conclusions: Cut / hit rebars were being properly documented by

S&L. No violations or deviations were identified.

(80) Concern: Procedure 21, " Cored Hole Requests and Inspections,"

states that "no items may be installed in a cored hole until

HECo receives a completed CHR signed-off by CECO PCD." How can

Ceco sign-off (accept) a CHR with an open NCR against the cored

hole?

NRC Review: The NRC inspector reviewed Procedure 21 and

interviewed CECO PCD engineers.

CECO PCD engineer's signature

on a cored old report (CHR) is the licensee's approval for " Work

May Proceed." If an NCR is prepared on the cored hole due to a

rebar being cut / hit, the NCR tracks the deficiency. Therefore,

a cored hole with a cut / hit rebar would not be " accepted" until

the NCR was properly closed.

Conclusions: Ceco PCD engineer's signature on a CHR is the

licensee s approval for " Work May Proceed." The proper closure

i

of the NCR would be the acceptance of the cored hole with

identified deficiencies.

No violations or deviations were

identified.

(81) Concern: At final turnover to CECO, did the electrical raceway

hangers meet the latest S&L drawings?

NRC Review: The NRC inspector reviewed the inspection,

reinspection and overinspection history of the raceway hangers

at the Byron Station. As a result of the NRC team inspection

(See NRC Inspection Report 454/82005; 455/82004), a major

reinspection program was initiated at Byron Station (See Paragraphs

5.a(56) and (57) for similar concerns). This reinspection

program included a reinspection of raceway hangers. The Following

is a general sequence of events as relating to the raceway

hanger reinspection program:

,

74

. . , . .

.. . . -

- _ _ _ . _ _

. - . - -

attributes discussed in Memorandum 1230 on future work."

However, an ECN, FCR, or drawing revision was not issued to

delete the requirements to install / inspect cable tray hangers in

accordance with the design documents. QA/QC Memorandum 1631

documents that the HEcc QA/QC Manager provided a verbal directive

not to inspect pan hanger connections per details specified on

S&L drawings (Des.ign Documents).

The licensee was informed that failure to assure that changes

to documents, such as instructions, procedures, and drawings

are reviewed and approved by the same organizations that

performed the original review and approval is an example of

a failure to implement Criterion VI of 10 CFR 50, Appendix B

(454/86031-15; 455/86017-15).

(82) Concern:

Procedure 10 has been revised to reduce inspection

requirements.

NRC Review: The NRC inspector reviewed HECo Procedure 10,

" Class 1 Cable Installation," Revisions 19 through 24 (current

revision). During this review, the following procedure

differences were noted:

Between Revision 19, (February 14,1983) and Revision 22

(January 3, 1985) only minor changes were made to the

HP-105 form (Cable Installation Inspection Checklist), the

requirement to list the DR number (s), if applicable, was

added.

Between Revision 22 and Revision 23, (March 20, 1985) a

major change was made to the HP-105 form. The following

inspection attributes were celeted in Revision 23:

-

Cables below top edge of pan, neat, flat and parallel.

-

Half-rounds and edge protectors in place.

No sharp edges.

-

i

No damage or deformity to cables.

-

-

No obvious violations of minimum bend in pan.

<

-

Cables in pan protected from work in progress in area.

-

No scaffold on pan in run.

l

-

Embed conduit swabbed and acceptable.

!

Cable ends were sealed.

-

Minimum bend not exceeded (coiled cables).

-

75

-

.

- =-_ -

_

-

Cable routing acceptable.

-

-

Cable free of damage.

Cable coiled properly.

-

The following inspection attributes were added in Revision 23:

-

Conduit reports HP-204, HP-205 and HP-206 complete and

on file.

-

Hangers installed and conduit properly attached.

-

Conduit size is as specified in Exhibit K (Cable

Tension Calculation).

'

,

-

Installed junction boxes are as specified on

Production Installation Reports.

-

Exhibit K attached to HP-105.

A new section was added for Cable Rework.

-

Revision 24 (October 18,1985) deleted the first three

inspection attributes that we added in Revision 23. No

inspection attributes were added in Revision 24.

During a tour of the plant by the NRC inspector, no discrepancies

were identified that resulted from the reduced inspection

i

criteria discussed above. The electrical construction activities,

as of this inspection, are essentially complete at the Byron

i

Station. However, it is the NRC inspector's understanding that

HECo's contract has been extended through December 1987 to

perform maintenance and modification work activities as directed

by the licensee. Based on this extension of contract, the

licensee was requested to evaluate HECo Procedure 10, Revision

22, 23 and 24, and provide justification for the deletion of the

'

j

above listed inspection attributes.

Conclusions: A review of Procedure 10, Revisions 19-24,

'

indicated that inspection attributes were deleted from the cable

installation procedure. During a tour of the plant, the NRC

inspector did not identify any violations that resulted from

the deletion of these inspection attributes. Construction is

essentially complete at Byron, however, HECo's contract has

been extended. Based on this extension of contract, the

licensee was requasted to provide justification for the

deletion of inspection attributes from Procedure 10.

Pending a

review of this justification, this item is unresolved

(454/86031-11; 455/86017-11).

(83) Concern: The only corrective action cn minimum cable bend

radius violations is to straighten the cable.

These violations

are never evaluated.

76

. , -

,

. - - . - -

.

-

--

=

NRC Review: The NRC inspector reviewed HECo Procedure ;0,

" Class 1 Cable Installation." Paragraph 5.1.45 of this procedure

states, "QA/QC Department will conduct an evaluation against the

criteria of Exhibit G and if required, QA/QC will generate a DR

or NCR, as applicable, per Procedure 6." Exhibit G states,

" Commonwealth Edison Company (PCD) shall be notified by DR or

NCR if: A kink or twist is found that is caused by compressing a

loop to less than the minimum bending radius." As stated in

Procedure 10, "HECo shall document all minimum cable bend radius

violations on an NCR or DR."

The NRC inspector reviewed two CECO NCRs (F-873 and F-878) that

identified c*hle bend radius violations. The disposition on

these NCRs seates, " Retrain the affected cables such that the

bending radius is equal to or greater than the minimum specified

training radius." However, the violations identified on these

NCRs were evaluated by S&L and the Okonite Company (cable

manufacture). The NRC inspector was also provided a copy of

a CECO internal letter, dated April 16, 1982, that provided

guidelines for field examination of suspected nonconforming

cable bending radius. This letter states in part:

" Power Cable, Medium Voltage - Above 600V. (Sky, 8kv and 16kv)

.

Dispositioned on a case-by-case basis via CECO.

Nonconformance Report.

Power, Control and Instrumentation Cable, Low Voltage -

Under 600V.

'

Cable is to be accepted if the (MBR) Minimum Bend Radius

was exceeded under the following conditions:

(a) MBR violation did not occur when the cable was under

pulling tension.

(b) Visual inspection of the cable indicates that tnere is

no rippling, tearing or stretching of the cable jacket

or significant deformation of the cable at the point

where the MBR was exceeded (both inner and outer radius).

(c) The copper conductor had not been bent 180' and/or

crushed severely such as to cause the copper conductor

to be permanently crimped and/or penetrate the

insulation or strands to be broken.

(d)

If the cable has been handled roughly but the visual

inspection indicates no damage, construction or

quality control may request that conductor continuity

be verified.

C' ables not meeting the above criteria will be repulled/

abandoned.

77

.

-.

_ _ . _ _

In all instances where the MBR has been exceeded, the cable

installation will not be deemed acceptable unless the cable

is retrained and left in an unstressed condition (final

radius equal to or greater than MBR)."

The licensee was requested to provide justification for not

documenting all violations of minimum cable bend radius on NCRs.

Conclusions:

The NRC inspector identified two NCRs identifying

cable bend radius violations where the disposition was to retrain

the cables. These violations had been evaluated by S&L and the

cable manufacturer. There is a CECO letter that limits the

conditions under which an NCR is required for cable bend radius

violations. The licensee was requested to provide justification

for not documenting all bend radius violations on NCRs.

Pending

a review of this justification, this item is unresolved

(454/86031-12; 455/86017-12).

(84) Concern: Battery cables for safety-related diesel driven pumps

were received non-safety-related and installed in a

safety-related system.

NRC Review: The NRC inspector reviewed NCR 1741 and Project

Specification F/L 2891.

During a review of the specifications,

it was determined that Paragraph 206 imposes the following IEEE

Standards on the vendor, Stewart and Stevenson, Inc.:

IEEE 308, " Criteria for Class 1E Electric Systems for

,

Nuclear Power Generating Stations."

IEEE 323, " Standard for Qualifying Class 1 Electric

Equipment for Nuclear Power Generating Stations."

IEEE 344, " Standard for Seismic Qualification of Class 1

Electric Equipment for Nuclear Power Generating Stations."

Form EM-29115 was attached to and was a part of Specification

F/L 2891. Section 9.1 of this form requires flame tests be

conducted on cables per IEEE 383-1974. Section 11.3 of EM-29115

requires thermal and radiation tests be conducted per IEEE 383-1974 and IEEE 323-1974

The only amendment (1) to

Specification F/L 2891 was dated June 27, 1983. This amendment

did not revise nor take exception to any of the above listed

paragraphs or IEEE Standards.

In accordance with Specification F/L 2891, the subject battery

cables are installed at the Byron and Braidwood Stations in

conjunction with safety-related diesel driven Auxiliary

Feedwater Pumps and Essential Service Makeup Water Pumps. The

requirements for these battery cables was re-affirmed in an S&L

letter (F. G. Gogliotti) to Steward and Stevenson (S&S) (H. M.

Arbuckle) requesting S&S submit a supplementary proposal for

the battery cables. This letter specified that the cables were

78

Class 1E and must be qualified to IEEE 323-1974. S&S

supplementary proposal letter of February 18, 1982, stated that

the battery cables would be furnished in accordance with

Military Specification M-5086A. S&L letter to S&S, dated

February 19, 1982, authorized S&S to proceed with the delivery

of the battery cables. A 500' reel of 1/c, #4/0, 600V battery

cable was received at Byron Station on MRR 51998 dated June 1,

1982. A S&L letter to the Byron QA Superintendent (CECO),

dated October 11, 1982,' stated that no quality control

documentation was required for the material (battery cable)

furnished on MRR 51998. On May 6, 1985, an additional 200'

of battery cable was ordered on Material Services Request 79551

(P0 501632). This additional battery cable was received on MRR

58918, dated June 26, 1985. On October 29, 1985, HECo prepared

NCR 1741 to document the lack of adequate documentation for the

battery cable received on MRR 58918. The disposition on NCR

1741 states, " CECO MSR 67395 written to change QA requirements

on MSR 79551." This change made the battery cables a " Commercial

Grade" item. A review of Table 3.11-1 of the Byron /Braidwood

FSAR indicates that the applicable items associated with the

Auxiliary Feed Water Pumps (diesel driven) would be qualified

to IEEE 323. However, the NRC inspector was informed that this

information had been revised by a later submittal to the NRC

(NRR).

It is the inspector's understanding that FSAR Table

3.11-1 will be revised / deleted based on this later submittal of

the Byron /Braidwood Equipment Environmental Qualification Report.

Conclusions: The NRC inspector's review of Project Specification

F/L 2891, NCR 1741, applicable Material Receiving Reports,

applicable Material Service Requests, and Chapter 3 of the

Byron /Braidwood FSAR, verified that " Commercial Grade" battery

cables were used in conjunction with the diesel driven Auxiliary

Feedwater Pumps. Table 3.11-1 of the FSAR indicates these

cables would be qualified to IEEE-323. However, a later

submittal of the Byron /Braidwood Equipment Environmental

Qualification (EQ) Report revised the information contained in

Table 3.11-1 of the FSAR. It is the inspector's understanding

that Table 3.11-1 will be revised / deleted based on the latest

EQ report.

Pending a review of the revised FSAR (Table 3.11-1

and the applicable paragraphs), this item is unresolved

(454/86031-13; 455/86017-13).

b

Licensee Actions on Suspected Drug Use

Concern: On June 24, 1986, NRC's Region III Office received an

allegation that 13 named current or former employees of a known site

contractor used drugs at a party attended by the alleger. Additionally,

the alleger stated that these individuals used drugs in the Byron

Station parking lot during lunch hour.

The contractor performs

electrical installation / modification work on Unit 2, which is under

construction, and modification work on Unit 1, which is operating.

The NRC's Region III office notified the licensee of the allegation

and provided a list of the 13 names.

79

.

.-

Licensee Action:

In keeping with the licensee's established drug

awareness program, the current employees (9) were interviewed by Byron

Station Management. The nine employees were relieved of all duties,

their photo identification security badges and access key-cards were

revoked, and access to Byron Station denied pending the outcome of

CECO's investigation.

In keeping with CECO procedures, the nine employees provided an

observed urine specimen, at a local medical facility, for analysis.

After drug testing, four individuals showed positive results for THC

(active ingredient of marijuana) and were subsequently terminated.

The other five individuals were returned to duty after testing showed

no evidence of drug usage.

The remaining four named individuals who are no longer employed at

Byron Station will be tested for drug usage if and when they are

scheduled for re-employment.

In addition to the drug testing, the

licensee conducted a search of the electrical contractor's office

facilities and the parking lot utilized by construction personnel.

This search was conducted with trained dogs.

No drugs were found

during the search.

The four individuals that were terminated had been employed as QC

inspectors for the electrical contractor.

The licensee initiated a

sample reinspection of these four individuals' work. This reinspection

was performed by Pittsburgh Testing Laboratory (PTL) with the following

results:

Inspector "A",

99 items reinspected with zcro rejects.

Inspector "B",113 items reinspected with one rejectable attribute

(slag inclusion in a weld). The weld was subsequently repaired.

Inspector "C", 149 items reinspected with zero rejects.

Inspector "D", 104 items reinspected with zero rejects.

, The one unacceptable seld was considered to be an isolated case.

Conclusions: This allegation was substantiated, in part, in that four

of the nine named individuals showed positive results when tested for

drugs.

The termination of the four individuals testing positive was

in keeping with CECO procedures. The past work of these four

individuals was found to be adequate based on a sample reinspection of

their work. No violations o deviations were identified.

,

80

_ ._

__

_

6.

Onen-Items

Open items are matters which have been discussed with the licensee, which

will be reviewed further by the inspector, and which involves some action

on the part of the NRC or licensee or both. An open item disclosed

during this inspection is discussed in Paragraph 5.a(77) of this report.

7.

Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, violations, or

deviations.

Unresolved items disclosed during this inspection are

disclosed in Paragraphs 5.a(82), 5.a(83), and 5.a(84) of this report.

8.

Meetings with the Licensee

a.

During a meeting with licensee personnel in the NRC's Region III

Office on July 2, 1986, the findings to date of this special

inspection were discussed. As a result of this meeting, the

licensee initiated CECO QA Audit 6-86-201 which involved approximately

36 man weeks of audit / inspection effort. This audit resulted in Ceco

QA issuing five findings (violations), four observations, and two

open items.

b.

During a meeting with licensee personnel in the Region III Office on

October 1,1986, the licensee briefed Region III on the results of

their investigation of the alleged forged inspection reports. See

Paragraph 5.a(76) above for the results of the licensee's investigation.

9.

Exit Interview

The Region III inspector met with licensee representatives (denoted under

Paragraph 1) at the conclusion of the special inspection on October 22,

1986. The inspector summarized the scope and findings of the inspection

and also discussed the likely informational content of the inspection

report with regard to documents or processes reviewed during the

inspection.

The licensee was also informed that potential enforcement

options were being considered.

The licensee acknowledged this information and did not identify any such

document or processes as proprietary.

Attachment:

Cross Reference: Violation to Report Detail.

I

81

-

-

_ _ _ _ _ _ . , _ - _

. - .

_.

___

- - _ _

.

.

. _ .

.

_.-

_ _ _

_ _ . . - . _ .

_

BYRON STATION-

REPORT NO. 454/86031; 455/86017L

Cross Reference:

Violation to Report Details

Y

Item

Criterion

. Paragraph

Violation

'

A1

10CFR21

5.a(15)

Failure to impose on site-contractors (U1, U2)

B1

I

5.a(6)

Lack of freedom to verify inspection (U1~, U2)

B2

II

5.a(14).

Failure to indoctrinate / train QA/QC personnel

(U1,U2)

,

II

5.a(54)

Failure to assure QA/QC personne1'are

properly qualified / certified (U1, U2)

.

B3

III

5.a(11)

Failure to assure that design changes were

approved by original design organizations.

'

(U2)

III

5.a(41)

Failure to assure use-as-is dispositions on

DRs/NCRs are approved by original design

organization. (U2)

.

a

B4

V

5.a(15)

Failure to follow procedures-(Unit 1 turnover).

<

l

(U1)

}

V

5.a(15)

Failure to have a proceduralized system

for Byron construction to notify Byron

Operations of deficiencies that could

i

impact safe operations. (U1)

i

V

5.a(51)

Failure to assure that activities affecting

quality are accomplished in accordance

-

with approved instructions. (U2)

V

5.a(53)

Failure to assure that activities affecting

quality are prescribed by documented

'

procedures. (U2)

B5

VI

5.a(81)

Failure to assure that activities affecting

,

quality are accomplished in accordance

with approved procedures (working to

verbal / memo instructions). (UI, U2)

,

B6

X

5.a(48)

Failure to assure that inspections are

j _

performed to verify conformance to design

.

(inspections not performed per CECO

i

directions). (U1)

'

B7

XIV

5.a(15)

Failure to establish a system to accurately

status inspections to preclude bypassing

,

required inspections. (U1, U2)

i

B8

XV

5.a(11)

Failure to assure that nonconforming items

are reworked in accordance with NCR/DR

program. (U2)

'XV

5.a(22)

Failure to control nonconforming items to

'

prevent their inadvertent use. (U2)

!

i

i

.

_

-, ._ _

__

. .

. ~

. -

- .

.

.

. . .

-

-

l

B9

XVI

5.a(15)

Failure to assure that conditions adverse to

quality were promptly identified and

corrected.(U1)

XVI

5.a(26)

Failure to assure that conditions adverse to

quality were promptly identified and

corrected.(U2)

XVI

5.a(28)

Failure to assure that corrective action to

prevent recurrence is complete prior to

closing the NCR. (U2)

XVI

5.a(39)

Failure to assure that conditions adversd

to quality were promptly identified and

corrected. (U1)

XVI

5.a(41)

Failure to assure that conditions adverse

to quality are determined and corrective

s

action taken to preclude repetition. (U2)

/

XVI

5.a(81)

Failure to assure that conditions adverse

to quality were promptly identified and

corrected.(U1,U2)

B10

XVII

5.a(47)

Failure to maintain sufficient records to

furnish evidence of qualifications of

personnel. (UI, U2)