Summary of 861113 Meeting in Region II W/Util,Bechtel & Southern Co Svcs Re Implementation of 10CFR50,App R Fire Protection,In Preparation for Special Insp Scheduled for 861215-19.Attendance List Encl
ML20214V921
Person / Time
Site: Hatch  
Issue date: 11/20/1986
From: Madden P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20214V893 List:
References
NUDOCS 8612100007
Download: ML20214V921 (3)


Text

r~

ENCLOSURE MEETING

SUMMARY

Licensee: Georgia Power Company Facility: Hatch Units 1 and 2 Docket Nos.:

50-321 and 50-366 License Nos.: DPR-57 and NPF-5 A meeting was held in the NRC Region II Office on November 13, 1986, to discuss the implementation of 10 CFR 50 Appendix R Fire Protection, in preparation for the special inspection at Hatch Units 1 and 2 scheduled for December 15 - 19, 1986.

The licensee presented copies of the following preaudit information requested by Region 11 staff:

1.

Piping and instrumentation (flow) diagrams for hot shutdown and cold shut-down systems, and alternative or dedicated shutdowns.

! j ; I... + t j ll @qnt layout and equipment location drawings which identify the

2. i 8 I heatiops of, hetl shutdown.and cold shutdown equipment.

3.

Plaqt, layout drawings which identify fire area delineation and fire protec-

, i tHn equipment locations.

! ;!l,7

,it,i Layou~t drawings which identify the locations of emergency lighting units.

4.

5.

Associated circuit analysis methodology.

l 6.

Plant operating procedures and shutdown path (flow) diagrams which describe emergency hot and cold shutdown from emergency control stations outside and independent of the control room, and shutdown operations which utilize alternative or dedicated shutdown capability.

I 8612100007 861128 7

PDR ADOCK 05000321 fl F

PDR

}

=-

Enclosure 2

7.

Electrical raceway drawings which identify the cable routing of power, control, and instrumentation circuits for those plant systems necessary to achieve hot shutdown and for those systems necessary to achieve and maintain cold shutdown.

5 ll ZD h P.A. M @ en

/

Date'

Attachment:

Attendance List i

l f Ih'I 5*

  • IfI l fif'!'?

iIs*

.*;e

't.

e

ATTACHMENT ATTENDANCE LIST Attendance at the GPC/NRC meeting on November 11, 1986 at the NRC Region 11 office.

Georgia Power Company P. E. Fornel, Appendix R Project General Manager J. D. Heidt, Nuclear Generation Engineer S. C. Hart, Appendix R Engineering Manager R. F. Mayhew, Procedure Engineer D. E. McAfee, Senior Fire Protection Engineer Bechtel G. M. Cooper, Electrical Engineer Southern Company Services R. C. Bunt, Mechanical Engineer P. D. Grisson, Nuclear Analysis Engineer i:

ijt{l il![i i..teill '-lltI+i.et.6{lle lllii

  • ~

NRC Region 11 T. E. Conlon, Chief, Plant Systems Section (PSS) i

,I i,

+';i*

R. H. Bernhard, Test and Startup, Test Programs <Section

'l

P. J. Fillion, Electrical, PSS i+'

P. M. Madden, Fire Protection, PSS J. E. Menning, Reactor Inspector, Materials and Processes Section W. H. Miller, Fire Protection, PSS G. R. Wiseman, Fire Protection, PSS