ML20214V196

From kanterella
Jump to navigation Jump to search
Ack Receipt of 861013 & 1104 Responses to Violations & Deviations Noted in Insp Repts 50-445/86-01 & 50-446/86-01. Requests Addl Info Re Response to Items A,A.6 & A.3 of Notice of Violation & Items B & C of Notice of Deviation
ML20214V196
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/03/1986
From: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
References
NUDOCS 8612090567
Download: ML20214V196 (3)


See also: IR 05000445/1986001

Text

o

. .

DEC 3 1986

In Reply Refer To:

Dockets: 50-445/86-01

50-446/86-01

Texas Utilities Generating Company

ATTN: Mr. W. G. Counsil

Executive Vice President

400 North Olive, L.B. 81

Dallas, Texas 75201

Gentlemen:

Thank you for your letters dated October 13, 1986, and November 4, 1986, in

response to our letter dated August 29, 1986. As a result of our review, we

find we are in need of additional information with respect to Item A in the

Notice of Violation (N0V) and Items B and C in the Notice of Deviation (NOD).

NOV Item A: With respect to Item A.1, you did not provide the " Reason for

Violation" regarding your failure to implement the requirements of

Procedure CP-QP-16.3 for Deviation Reports (DRs) which were generated for

non-ASME components; e.g., HVAC equipment. Additionally, in regard to

" Corrective Action Taken," please confirm that the review of DRs was not

limited to just those associated with ASME equipment. With respect to Item A.4,

staff review of Procedure CP-QAP-16.1, Revision 25, finds that the document

literally requires that nonconforming items identified on nonconformance

reports (NCRs) are to be clearly identified with signs, barriers, and/or hold

tags. Accordingly, while we have no questions concerning the subsequent

revision made to this procedure, we do not concur with your stated reason for

disagreement with this finding. Therefore, please provide the information

required by the NOV for this item.

With respect to Item A.6, your response indicates that you have restricted

consideration of the violation to Comanche Peak Response Team (CPRT)

activities only. The fact that you acknowledged in the " Reason for Violation"

for Item A.3, the existence of conditions outside of CPRT activities which

were not documented on NCRs, supports the stated violation. Therefore, please

provide the information required by the NOV for this item.

N0D Item B: With respect to Items B.1, B.2, and B.3, pleate identify what

specific documented actions were taken to prevent recurrence for each of the

three stated examples.

N00 Item C: Please clarify whether surveillances and/or audits have

specifically addressed the work activities of the QA/QC engineer applicable to

this deviation.

RIV:CPRT /M [ DRSP

IBarnes:gb EHJohnson

// /2r/86 el' gv/v/86

8612090567 861203 /[OI l l

PDR ADOCK 05000445

G pop

_

.. .

Texas Utilities Generating Company' 2

We have no further questions regarding Items A.2, A.3, A.5, and B of the NOV -

and Item A of the N00. Your response to Item B in the NOV will be factored

into our inspection of ISAP VII.a.9 implementation, as it applies-to cable

procurement.

Please provide the supplemental information within 20 days of the date of this

letter.

Odginal signed By

E. H. Johnson .'- .

.

E. H. Johnson,' Director >

Division of Reactor Safety

and Projects -

...

,

cc.

Texas Utilities Electric Company - ,

ATTN: G. S. Keeley, Manager

Licensing i

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas 75201

Juanita Ellis

President - CASE

1426 South Polk Street

Dallas, Texas 75224

Renea Hicks

Assistant Attorney General

Environmental Protection Division

P. O. Box'12548

Austin, Texas 78711-2548

Administrative Judge Peter Bloch

U.S. Nuclear Regulatory Commission

Washington, D.C. 20555

Elizabeth B. Johnson

Administrative Judge

Oak Ridge National Laboratory

P. O. Box X, Building 3500

Oak Ridge, Tennessee 37830

(continuednextpage)

,

. .

'

c

Texas Utilities Generating Company 3

'

.

1

Dr. Kenneth A. McCollom- s

1107 West.Knapp i

Stillwater, Oklahoma 74075

~

.

,- -

' ' '

Dr. Walter H.-Jordan '

.

881 Outer Drive ,

0ak Ridge, Tennessee 37830 * ' -

A

Anthony Roisman,,Esq.

Executive Director

Trial Lawyers for Public Justice

2000 P. Street, N.W. Suite 611

Washington, D.C. 20036

Texas Radiation Control Program Director

bec to DMB (IE01)

bec distrib. by RIV:

  • RPB * MIS System
  • RRI-0PS *RSTS Operator
  • RRI-CONST *R&SPB
  • T. F. Westerman, RSB DRSP

V. Noonan, NRR R. Martin, RA

S. Treby, ELD *RSB

  • RIV File J. Taylor, IE
  • D. Weiss, LFMB (AR-2015) J. Conklin, IE
  • I. Barnes, CPTG
  • w/766

,

t

' '

Log # TXX-6070

f File # 10130

IR 86-01

i TEXAS LTILITIES GENERATING COMPANY IR 86-01

SKYWAY TOWER . 4Ee NORTH OLIVE STREET. I.B. OR . DALLAS, TEXAS 75301

November 4, 1986

-

rf , , , ;

"~

r,Vr,iff.=:n, .

NOV 6 1986

  • .

i.

Mr. Eric H. Johnson, Director

Division of Reactor Safety and Projects

U. S. Nuclear Regulatory Commission

611 Ryan Plaza Drive, Suite 1000

Arlington, Texas 76012

SUBJECT: COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446

SUPPLEMENTAL RESPONSE TO NRC NOTICE OF VIOLATION

AND NOTICE OF DEVIATION INSPECTION REPORT

NOS. 50-445/86-01 AND 50-446/86-01

Dear Mr. Johnson:

We responded to Inspection Report Nos. 50-445/86-01 and 50-446/86-01 on

October 13, 1986 (TXX-5048). In the response to Notice of Deviation, Item A

(445/8601-D-04), we stated that CPSES Engineering is still evaluating the

Notice of Deviation and the tests and requirements for the Auxiliary Feedwater

Pumps. In addition, we committed to provide a complete response by November

3, 1986.

NOTICE OF DEVIATION

ITEM A (445/8601-0-04)

A. FSAR Section 10.4.9.1 states that the Auxiliary Feedwater (AFW) System is

capable of supplying the minimum required flow to at least two steam

generators against a back pressure equivalent to the accumulation pressure

of the lowest set main steam safety valve plus the system frictional and

static losses.

FSAR Table 14.2-2, Sheet 51, Test Method No. 3 commits the applicant to

verify through preoperational testing that the hydraulic performance of

each AFW pump meets design requirements and is within limits assumed in

the appropriate accident analysis.

In deviation from the above, preoperational tests ICP-PT-37-01, " Auxiliary

Feedwater System (Motor Driven Pumps)," and ICP-PT-37-03, " Auxiliary

Feedwater System (Turbine Driven Pumps)," failed to test the AFW pumps

against a back pressure determined using main steam safety valve

accumulation pressure, but instead incorrectly used the safety valve iqi

pressure. This amounts to a less conservative 36 psi reduction in the

back pressure during this test. Consequently, the pump capacity data

recorded in the above completed test packages are incorrect for the

maximum back pressure test.

1

Qj gg a r>unsm or run tuma mnnic a>mn

Ice 211  % ay,

.

'

'.- 'TXX-6070

t November 4, 1986

Page 2 of 2

'a

RESPONSE TO ITEM A

1. Reason for Deviation

'

The acceptance criteria in the test procedures deviated from the design

limits described in FSAR Section 10.4.9.1 due to incomplete documentation

of the accident analysis assumptions. The acceptance criteria for the

test procedures were based on the acceptance criteria in FSAR Table 14.2-2

and Secticn 15.2 neither of which documented the 3% accumulation.

2. Corrective Action Taken

To ensure the adequacy of the Auxiliary Feedwater System, the test

procedures and data are being reviewed and evaluated.

The evaluation includes a review of the test objectives, acceptance

criteria, test methodology, and data. The results of this evaluation will

be attached to the Unit I test procedures and test data packages. The

Unit 2 test procedures will be revised to incorporate the evaluation

findings prior to the Unit 2 tests.

FSAR Table 14.2-2 and Chapter 15 will be revised to document the

appropriate acceptance criteria.

3. Action to Prevent Recurrence

The desigr; limits assumed in each accident analysis will be reviewed

against the FSAR Chapter 15 documentation and the FSAR corrected as

required. Any resulting FSAR changes will be reviewed against the

affected test procedures / test data packages and corrective action

documented as discussed above for the Auxiliary Feedwater System.

4. Qate of Full Como11ance

TUGC0 will be in full compliance prior to fuel load or we will submit a

specific request to load fuel with this deficiency outstanding.

Very truly yours,

bW

W. G. Counsil

RSB/amb

j c - Region IV (Original + 1 copy)

Director, Inspection and Enforcement (15 copies)

U. S. Nuclear Regulatory Commission

i Washington, D. C. 20555

Mr. V. S. Noonan

4

Mr. D. L. Kelley

. _ _

.. . - -._-- _ _ _ . . . -. . __ - _ _ _ _ -_ _. .. _-

r

. .

9 -

g

Log # TXX-5048

'

Filef 10130

TEXAS UTILITIES GENERATING COMPANY IR 86-01

es,w ve ma . a. ==,= ouve me a n . .*ua. rsma == 86-01

October 13, 1986

." E.".*d%2fL b@M MMT

Mr. Eric H. Johnson Director EIdE

Division of Reactor Safety and Projects J IL lg

U. S. Nuclear Regulatory Commission '

611 Ryan Plaza Drive, suite 1000

Arlington, Texas 76012

SUBJECT: COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET N0S. 50-445 AND 50-446

RESPONSE TO NRC NOTICE OF VIOLATION AND NOTICE OF DEVIATION

-

INSPECTION REPORT N05 : 50-445/86-01 AND 50-446/86-01

-

l

Dear Mr. Johnson:

We have reviewed your letter dated August 29, 1986, concerning the inspection

conducted by Mr. T.F. Westerman and other members of the Region IV Comanche

Peak Group during the period November 1, 1985, through January 31, 1986. This

inspection covered activities authorized by NRC Construction Permits CPPR-126

and CPPR-127 for Comanche Peak Steam Electric Station Units 1 and 2. Attached

to your letter was a Notice of Violation and Notice of Deviation.

We requested and received a two week extension in providing our response

during a telephone conversation on September 29, 1986.

- .

We hereby respond to the Notice of Violation and Notice of Deviation in the

atttchment to this letter.

Very truly yours,

e

W. G. Counsil

R$8/gj

Attachments

.

c-Region IV (Original + 1 Copy)

Director, Inspection & Enforcement (15 copies)

U.S. Nuclear Regulatory Commission

Washington, D.C. 20555

Mr. V.S. Noonan

Mr. D.L. Kelley

g/p /o .2.0~ 37Y /7FF

~ ~ ~ ~ ~ ~

_gyq Q

___ _ _ _ _ _

. o

. .

.

Attachment to TXX-5048 Page 1

October 13, 1986

HDIlGI QE VIOLATION  ;

ITEMS 81 THROUGH 81 (111/A101-y-11 AND 146/gigi-y-91)

A. Criterion XV of Appendix 8 to.10 CFR Part 50 requires that measures be

established to prevent the inadvertent use of nonconforming items, and  !

g that these measures include procedures for identification, documentation,

segregation, disposition, and notification to affected organizations. It

'

further requires that nonconforming items be reviewed and accepted,

rejected, repaired, or reworked in accordance with documented procedures.

E

i Section 15.0 of Revision 5 to ths TUGCo Quality Assurance Plan (QAP)

states, in part, "The identificati.'n, documentation, segregation, and

i disposition of nonconforming materials, parts, or components is outlined

in written procedures...." A nonconformance report is used to document

deficiencies unless another method is prescribed by a specific

procedure / instruction. Nonconformance reports . . . are made available to

TUGCo for evaluation ....(and) TUGCo QA assures that periodic evaluations

i of these reports are forwarded to TUGCo management identifying trends

adverse to quality."

,

'

Section 3.9 of Revision 3 to the TUGCo Operations Administrative Control

!

and Quality Assurance Plan states, in part, " Material, parts and

components which are determined to be nonconforming, shall be identified i
and re>orted. Nonconformance reports shall be prepared which identify and  ;

l descri>e the nonconformance, the disposition of the nonconformance, and '

j the . . . acceptability of the item after the disposition has been

completed . . . ." j

l Contrary to the above, established procedures for handling of I

nonconforming materials, parts, or components were not effectively

j

- - implemented as evidenced by the following observed conditions: j

i

h Deviation Reports (DRs) enerated by ERC to document nonconforming

conditions did not, in a 1 cases, result in the initiation of l

l nonconformancereports(NCRs)bytheTUGCoQA/QCCoordinatoras ,

'

'

required by Revision I to Procedure CP-QP-16.3 dated August 28, 1985.

h2 The TUGC0

Revision I to QA/QC Coordinator

Procedure CP-QP-16.3 failed

datedtoAugust

initiate28,

NCRs

1985,asforrequired numerousby

l

,

ERC identified out-of-scope observations which were subsequently

repaired or reworked.

h Nonconforming items identified by the TUGCo QC Ins ection Process

Control Group, and subsequently reworked and repal ed, were not

c documented on NCRs as required by Revision 9 of Procedure STA-405

i dated November 11, 1985, but rather on three-part office memos.

4. A large number of nonconforming items have not been physically

'

identified with signs, barriers, or hold tags as required by Revision

i 25 of Procedure CP-QAP-16.1 dated August 17, 1985.

--~ x

l

l I

!

L - ._

. .

. .

)

k(

Q

Attachment to TXX-5048 Page 2

October 13, 1986 .,/

y fept

fiQJEI Of VIOLATION

M A.1 THROUGH A.i (115/85.Q1-1-11 AliD 316/81M-1-91)-CQtiI'D

hDeficiencyNotifications(DNs),asrequiredbyRevision4ofProcedure

-

N61-1 dated December 10, iv65, are to be used only for documenting

deficient conditions identified during repair or replacement of

mechanical components previously accepted by TUGCo. However, numerous

instances have been identified where DNs have also been used to

imprope*1y document nonconformances and effect the issuance of work

i requests and work orders.

,

6. Failure to initiate required NCRs impacts on the validity of the

monthly trend analysis report required by Revision 1 of Procedure

. QI-QP-17.0-1. The report is required to contain potentially adverse

trands, which are based on the number of NCRs issued during the report

period,

ftESPONSE IQ M 81 IliBNiti A.1

1

1. Reason for Violation

Item 1 - The requirements of CP-QP-16.3 were not implemented for DRs .

[ generated when the component identified fell under the scope of ASNE

Section XI program.

Item 2 - CP-QP-16.3 R1 required an evaluation to be done on out-of-scope

observations to determine whether they warrant the issuance of an NCR.

, There have been instances where the evaluation did not require the

y ,

issuance of an NCR when in fact an NCR should have been issued.

G

Item 3 - TUGC0 QC Inspection Process Control Group, used IPC-3 which did

C"> not require that an NCR be issued when the inspectors noted a deficiency

that was out-of-scope from the inspector's checklist. Instead 3-part

, memos were used to notify personnel of deficiencies in order to effect

corrections _- x

Item 4 do not agree with the alleged' iolation because QP-QAP-16.1

R25 did not' require the~ application of f 1d tag in all cases. The items

~

I

were being controlled since whether or not hold tags were placed on the )

i

\ items, further processing of the items was controlled through work package

holds. However, a revision to CP-QAP-16.1 has been made which now

'

requires the placing of hold tags on nonconforming items where practicable

regardless of the stage of component processing. If a hold tag is not

placed, the initiator must provide a brief justification on the NCR.

'

Item 5 - This violation resulted from deviating from the requirements

contained within N61-1 dated 12/10/85. In several instances, DRs were

received from ERC (that were associated with the N61-1 program) and TUGCo

incorrectly used DNs to process these DRs.

wt c.e#rcek - TO G C o @C A or 6

7me

u>ere d eve Nel L ubll,5 , 3 y

un a ve's

y , n s c. &

~ _

d

. _ _ ~

_ _ - - -- . - . - - -- -

. .

. .

Attachment to TXX-5048 Page 3

October 13, 1986

,

d

RESPONSE IQ IIIt!181 THROUGH 81 IQtiI'Q

i

Item 6 - We disagree with this violation. Quality Instruction

QI-QP-17.0-1 " Preparation and Distribution of Trend Reports" contains

criteria for the identification of Potential Adverse Trends (PAT) during

the monthly NCR trend results evaluation. Since the objective of the

Trend Program is the timely identification of activities which may require l

corrective action, NCRs initiated per CP-QP-16.3 " Processing CPRT i

Deviation Reports /0ut of Scope observations" are excluded from the Trend

'

1

'

Program due to the inability to clearly identify current program

weaknesses based on analysis of deficiencies not related to present

conditions or requirements. In order to clearly exclude these NCRs from

trending, these NCR numbers are suffixed with an "X" and do not have a

specific Trend Code applied. Trend Reports provided for management review 1

therefore contain evaluation results pertinent to ongoing construction and

inspection / testing activities.

The CPRT Program Plan describes methods used by CPRT to develop, approve

and document corrective action for deviations or deficiencies identified

by CPRT. Methods used include identification of adverse trends through

the evaluation of related observations and/or deviations. For these

items, CPRT provides reports of adverse trends or areas requiring TUGCo- ,

management review and action as appropriate. '

2. Corrective Action Igkg8

Item 1 - A review of DRs received was conducted and NCRs were issued for

all DRs not previously documented on NCRs.

- .

Item 2 - CP-QP-16.3 R2 now requires that all out-of-scope observations be

documented on NCRs regardless of the described condition. All out-of-

scope observations have been reviewed to determine if NCRs were issued for

them. NCR0 have now been issued for all out-of-scope observations.

Item 3 - NCR E-86-200637 R3 was generated to disposition all items listed

on the 3-part menos.

Item 5 - Per CP-QP-16.3 R2, DNs may no longer be used to process DRs.

NCRs are used to document deficiencies regardless of the stage of

component processing. All previous DRs have been addressed as noted in

Item 1 above.

L

>

, - - - - _ . _ , - - _ - . - , . , . . . . - . . - , - - . _ , _ - _ ,

. .

. .

Attachment to TXX-5048 Page 4

October 13, 1986

RESPONSE IQ IIIH1 A.1 THROUGH 8 1 fallI'Q

3. Action in Prevent Recurrence

Item 1 - CP-QP-16.3 Rev. 3 was revised to delete the reference to N61.1.

This revision unequivocally requires that all DRs received be documented

in accordance with CP-QP-16.0 "Nonconformances" or CP-QAP-16.1 " Control of

Nonconforming Items".

Items 2 - Same as corrective action noted above.

Item 3 - The Inspection Process Control Program was replaced by the

Inspection Surveillance Program, which requires NCRs to be generated en

all deficiencies noted.

Item 5 - Same as corrective action noted above.

4. Qalg gf Egil comoliance:

Item 1 - CPSES is currently in full compliance.

Items 2 - CPSES is currently in compliance with CP-QP-16.3.

Item 3 - CPSES is currently in compliance with the Inspection Surveillance

Program.

Item 5 - CPSES is currently in compliance with the CP-QP-16.3.

- .

j

. . - . ,_ - _ - - , - - - . _ - __ _ , , , , _ . - - - - , . - - , _ - _ - , , . . - , . , - , - - , . _ - , - - - . , , - - - - - - _ _ . - - - , -m-.,-_

c ,

. .

. .

Attachment to TXX-5048 Page 5

October 13, 1986

NOTICE DE VIOLAIl0N

M A (115/Aln-Y-11 als 115/A691-Y-Ai)

B. Criterion V of Appendix B to 10 CFR Part 50, as implemented by Section

5.0, Revision 3, dated July 31, 1984, of the TUGC0 QAP, requires that

activities affecting quality shall be prescribed by and accomplished in

accordance with documented instructions, procedures, or drawings of a type '

appropriate to the circumstances.

Paragraph 6.15.1(t) of Gibbs and Hill Electrical Erection Specification

-

2323-ES-100, Revision 2, dated October 15, 1980, requires: (1) that

field tests shall be performed by the Contractor on all cable reels in

accordance with the manufacturer's recommendations, and (2) that the owner

will witness these tests.

Contrary to the above, the specified field tests of cable reels were -

neither prescribed by implementing procedures nor performed.

RESPONSE IQ M 3

It is our opinion that the conditions described in this Notice of

,

'

Violation item are not a violation. None cf the manufacturers that have

supplied cable reels to CPSES have recossended that any field tests be run

on cable reels.

CPSES procurement documents invoke and reference all applicable

'

specifications and/or testing which is required of our manufacturers. The

-

required certification / documentation is transferred to CPSES with the

shipment of cable and is reviewed for acceptability by receiving

inspection and quality control. Site procedures invoke additional 1

i

'

acceptance testing of the individual conductors and cables after '

'

installation. These tests are more stringent than testing in the bulk j

reel form.

The requirements in paragraph 6.15.1(t) of electrical erection

specification 2323-ES-100 are meaningless because no cable reel field

tests have been recommended and are redundant because all necessary

testing is already being accomplished by the manufacturer.

In order to eliminate this redundancy in the specification, the paragraph

in question was removed from the specification by design change DCA-24088

! issued January 24, 1986.

i

l

l

-, . . , , _ - - - . . . . _ . _ , .,_.__.-___ -___- , _. _

. .

.

.

Attachment to TXX-5048 Page 6

October 13, 1986

-

ff0I1G1 RE DEVIATION

1I15 A (lil/fdQ1-2-01)

A. FSAR Section 10.4.9.1 states that the Auxiliary Feedwater (AFW) System is

capable of supplying the minimum required flow to at least two steam

generators against a back pressure equivalent to the accumulation pressure

of the lowest set main steam safety valve plus the system frictional and

static losses.

FSAR Table 14.2-2, Sheet $1, Test Method No. 3 commits the applicant to

verify through preoperational testing that the hydraulic performance of

each AFW pump meets design requirements and is within limits assumed in

the appropriate accident analysis.

In deviation from the above, preoperational tests ICP-PT-37-01, " Auxiliary

Feedwater System (Motor Driven Pumps)," and ICP-PT-37-03, " Auxiliary

Feedwater System (Turbine Driven Pumps)," failed to test the AFW pumps

against a back pressure determined using main steam safety valve i

accumulation pressure, but instead incorrectly used the safety valve it.t '

pressure. This amounts to a less conservative 36 psi reduction in the

back pressure during this test. Consequently, the pump capacity data

recorded in the above completed test packages are incorrect for the

maximum back pressure test.

RESPONSE IQ IIEl$ &

CPSES Engineering is still evaluating the Notice of Deviation, the tests

and requirements for the Auxiliary Feedwater Pumps. We intend to provide

,

,

a complete response by November 3, 1986.

.

. - _ . . _ _ _ _ , _ _ . . _ _ . _ _ . , - _ _ . .,

- _ _ . - -. _ . . _ . . . .

l

.

.

. . .

Attachment to TXX-5048 Page 7

October 13, 1986

HQI1G1 QE DEVIATION

IIEH B.1 (115/1191-D-11) i

B. Section 4 of Revision 3 t'o CPRT Procedure CPP-009 states, in part, ,

" Qualified QA/QC Review Team personnel perform field inspections of j

)/ 3

specific hardware items and reviews of appropriate documents in accordance

with approved instructions ..."

In deviation from the above, the following example was noted where field l

reinspections were not performed in accordance with approved instructions:  ;

1. Attribute 1.f in Section 5.2.6.2 of Quality Instruction (QI) QI-025, ,

Revision 1, which states, in part, "All lines with operating temperatures '

below 2000F may be installed with a minimum of one inch clearance, I

includir.g insulation, with respect to other piping," was signed off as ,

acceptable by the ERC inspector for Verification Package No. I-M-LBCO-038.

However, independent inspection showed an existing clearance of 0.75 inch

between spool piece 2Q2 of drawing BRP-CS-1-SB-060 and the inspected line

at a point 12 inches above sleeve 3.

! RES2DNIE IQ IIEB 1 1

1. Reason f.g.t Deviation

'

ERC investigation confirmed the stated condition. A 0.75-inch clearance

existed between spool piece No. 2Q2 on Drawing BRP-CS-SB-060 at a point 12

inches above sleeve No. 3 on the inspected line. The ERC inspector

i

,

accepted this attribute when in fact a minimum 1-inch clearance was

,

,

required.

2. Corrective AGliGB Taken

i Deviation Report (DR) number I-M-LBC0-038-DR-1 was prepared on March 18,

1986, to document the existence of the pipe to pipe insulation clearance

of 0.75-inch. Nonconformance Report (NCR) number M-25226N was generated

as a result of the DR to disposition the above condition.

3. Action 12 Prevent Recurrence

In cases where inspector error was evident, the inspector and the lead

inspector or population engineer discussed specifics to determine why the

error occurred. Actions taken to address the error and preclude

recurrence typically included one or more of the following, as necessary:

0 Documented retraining of the inspector (s) to the pertinent Quality

Instruction (s),

O Clarification or revision of the Quality Instruction.

At the discretion of the lead inspector, formal and informal group

' meetings were held to discuss inspector errors on a generic basis. These

discussions allowed appropriate information to be disseminated to various  !

cognizant ERC inspectors.

,

, - - - ,

_ _

.

.

.

Attachment to TXX-5048 Page 8

October 13, 1986

RESPONSE IQ IIH R.1 f&fil'D

An Overview Inspection Program was implemented to reinspect a sample of

each Inspector's work. Action is ongoing to analyze the results of the

Overview Inspection Program, which includes pertinent inspector error data

fromothersources(i.e.,NRCinspections,etc.).

4. DalsgfEgilComo11ance

Corrective action will be completed commensurate with the final

disposition of nonconformance report M-25226N. Results of the Overview

Inspection Program are scheduled to be completed by October

31, 1986.

$

1

  • .

e

_ - - - . - _ -

- . .. - __ -- . ._

.

. .

Attachment to TXX-5048 Page 9

October 13, 1986

i

i

HQIlCE Of DEVIATION

IIEB 31 (115/A621-0-12)

B. Section 4 of Revision 3 to CPRT Procedure CPP-009 states, in part,

" Qualified QA/QC Review Team personnel perform field inspections of

specific hardware items and reviews of appropriate documents in accordance

with approved instructions

3 In deviation from the above, the following example was noted where field

reinspections were not performed in accordance with approved instructions:

2. Attribute 1.f in Section 5.2.6.3 of QI-025 Revision 1, which requires

that all lines with operating temperatures less than 2000F be installed

such that an air gap exists between the pipe, or pipe insulation, and

'

other objects, was signed off as acceptable by the ERC inspector for

Verification Package No. I-M-LBC0-144. However, independent inspection

identified a portion of a pipe support in contact with the insulation of l

.

the inspected line at approximately 14 feet south of the 760 bend in the

package.

RESPONSE IQ IIIM R.1

1. Reason Enr Deviation  !

ERC investigation confirmed the trapeze hanger is touching the insulation

on the inspected line. The ERC Inspector did not note this condition at

the time of his original inspection.

, 2.

,

Corrective Action Taken )

Deviation Report (DR) number I-M-LBC0-144-DR-3 was prepared on March 14, l

1986, to document the clearance deviation. Based in part on this DR, I

i Nonconformance Report (NCR) number M-23475N R-1 was generated to

,_

disposition this condition.

3. Action in Prevent Recurrence

In cases where inspector error was evident, the inspector and the lead

inspector or population engineer discussed specifics to deteraine why the

error ocurred. Actions taken to address the error and preclude recurrence

! typically included one or more of the following, as necessary:

0 Documented retraining of the inspector (s) to the pertinent Quality

Instruction (s),

o Clarification or revision of the Quality Instruction.

At the discretion of the lead inspector, formal and informal group

meetings were held to discuss inspectors error on a generic basis. These

discussions allowed appropriate information to be disseminated to various

cognizant ERC inspectors.

An Overview Inspection Program was implemented to reinspect a sample of

each Inspector's work. Action is ongoing to analyze the results of the

overview Inspection Program which includes partinent inspector error data

from other sources (i.e., NRC inspections, etc.).

. _ _ _ _ _ _ _ _ . . _ _ _ _ _ _ _ _ _ . _ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _

r i

.

. .

Attachment to TXX-5048 Page 10

October 13, 1986

RESPONSE IQ IIEB R.1 - CQlil'Q

4. DalgafEullComoliance

Corrective action will be completed coincident with final disposition of

NCR M-23475N R-1. Results of the overview Inspection Program are ,

scheduled to be completed by October 31, 1986.

.

9

- -  ;

l

. . _ _ _ .

. .

. .

Attachment to TXX-5048 Page 11

October 13, 1986

lfD11.([ DE DEVIATION

IIB 3,1 (ill/ASAl-D-11)

B. Section 4 of Revision 3 to CPRT Procedure CPP-009 states, in part,  !

" Qualified QA/QC Review Team personnel perform field inspections of

specific hardware items and reviews of appropriate documents in accordance

with approved instructions ...."

In deviation from the above, the following example was noted where field

reinspections were not performed in accordance with approved instructions:

3. Attribute 1.d in Section 5.2.4 of QI-025, Revision 1, which states, in

par', " Ensure that the actual piping dimensions are in agreement with

those shown on the piping isometric ....," was signed off as acceptable by

the ERC inspector on December 9,1985, for Verification Package No. I-M- l

LBCO-144. However, field survey acasurements taken by Brown & Root on

December 6, 1985, in response to an ERC request, showed the distance from

the end of the containment penetration at field weld 18-A to the working

point of the 760 bend as 10 feet 5 7/16 inches with respect to a  :

distance (with a tolerance of +2 inches) indicated by the applicable l

Isometric Drawing BRP-CC-1-RB-046 of 10 feet 8 1/8 inches. '

RESPONSE IQ IIM H.1

1. Egnga f.gr Deviation

'

An ERC investigation confirmed the stated condition. The difference

between the Brown and Root field survey results and the dimension shown on

- . the isometric drawing exceeds the +2 in. Tolerance. The ERC Inspector did

not note this condition at the time of his original inspection.

2. Corrective Action Taken

,

,

'

Deviation Report (DR) I-M LBCO-144 DR2 was prepared on March 14, 1986, to

document the tolereance deviation. Based in part on this DR,

Nonconformance Report (NCR) M-23475N R-1 L s generated to disposition this

condition.

3. Action in Prevent Recurrence

In cases where inspector error was evident, the inspector and the lead

inspector or population engineer discussed specifics to determine why the

arror ocurred. Actions taken to address the error and preclude recurrence

i typically included one or more of the following, as necessary:

l

l

0 Documented retraining of the inspector (s) to the pertinent Quality

'

Instruction (s),

l 0 Clarification or revision of the Quality Instruction.

At the discretion of the lead inspector, formal and informal group

meetings were held to discuss inspector error on a generic basis. These

discussions allowed appropriate information to be disseminated to various

engn bant ERC insoectors. j

__ _ . - . _ - - . _ _ - - _ _ - - - .- .

. . l

. .

Attachment to TXX-5048 Page 12

October 13, 1986

!

RESPONSE IQ 112 R.1 CQlfI'Q

An Overview Inspection Program was implemented to reinspect a sample of

each Inspector's work. Action is ongoing to analyze the results of the

Overview Inspection Program which includes pertinent inspector error data

from other sources (i.e., NRC inspections, etc.).

4. Q31ggfEgilComo11ance

Corrective action will ba completed coincident with final disposition of

NCR M-23475N R-1. Results of the Overview Inspection Program are

scheduled to be completed by October 31, 1986.

.

- , _ , _ , _v ._,__. _ _ _ y-, ,.-.__ _, _ - _ ., . ,m,.-- - y.., ,

- p

~-- -

r

. .

. .

Attachment to TXX-5048 Page 13

October 13, 1986

NOTICE QE DEVIATION

HEH B.i (fil/81Q1-D-D)

B. Section 4 of Revision 3 to CPRT Procedure CPP-009 states, in part,

" Qualified QA/QC Review Team personnel perform field inspections of

specific hardware items and reviews of appropriate documents in accordance

) with approved instructions..."

In deviation from the above, the following example was noted where field

reinspections were not performed in accordance with approved instructions:

4. Paragraph 6 on page 34 of Attachment 6.17 of QI-058 requires (for vendor

safety wiring of attachment bolts between the forward bracket assembly and

the snubber assembly) that the inspector shall verify that the lockwire is

not damaged. Independent inspection showed for Verification Package No.

I-5-PS42-021 that the inspection checklist was accepted.by the ERC

inspector despite the presence of a broken lockwire on the snubber adaptor

plate.

RESPONSE IQ U E5 B.i

1. Reason f.g.t Deviation

l

Inspection for damaged lockwire was not included as an attribute on the

QI-058 inspection checklist. However, Attachment 6.17 required that the

inspector verify that the lockwire is not damaged. Therefore, the ERC

inspector noted the broken lockwire as an out-of-scope observation in lieu

of an in-scope deviation.

'

2. Corrective Action Iaken

An out-of-scope observation (005) number 289 was generated on November 11,

,

1985. Subsecuently, Nonconformance Report (NCR) M-234474 was prepared and

I dispositionec to replace the broken lockwire on the snubber adapter bolts.

l

This action is addressed via TUGC0 work request No. 7288.

In order to clarify inspection requirements, QI-037 and QI-05S are

currently being revised to include the inspection of lockwire on snubber

adaptor plate bolts. In addition, 36 Verification Packages from the PS7N

population and 11 Verification Packages from the PS42 population have been

reinspected, via a supplemental inspection instruction, to verify that

-lockwires are installed and not damaged. This supplemental instruction

will be included in QI-037 and QI-058.

Further, a Hardware Validation Program (HVP) has been initiated based on

Corrective Action Requests (CAR) 65x through 69x. These CARS will be

dispositioned by TUGC0 by performing a 100% reinspection of pipe supports.

Many attributes will be examined including lockwire.

.. - .. - - - _ . - .__ - - - - . _ - . - - -

_ -

,

. .

. -

Attachment to TXX-5048 Page 14

.

October 13, 1986

RESPONSE IQ IIS R.i LQE'Q

3. Ard19A In finxant Recurrence

In addition to the lockwire reinspections required by supplemental

instructions to QI-037 and 058, inspection for lockwire on snubber adapter

plate bolts is required by the ISAP VII.c Quality Instructions QI-019 and

l

QI-029 under a separate attribute for safety wire.

TUGC0 Operations has issued procedures governing housekeeping and

inspection of plant systems, structures, components and equipment turned

over to Operations. These procedures are QAI-001, " Plant Housekeeping and

Equipment Inspection Plan", and STA-607, " Housekeeping Control". Part of

this monthly inspection requires the visual inspection for loose, damaged,

broken or missing parts / components on equipment.

4. DAtaaffullCompliance

Corrective action will be completed commensurate with the final

disposition of CARS 65x through 69x. ERC reinspection concerning the

aforementioned populations are complete. Revisions to QI-037 and QI-058

are scheduled to >e completed by October 31, 1986.

- -

, , , , - . - - - , , , - -

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

. .

. . . .

Attachment to TXX-5048 Page 15

October 13, 1986

NOTICE QE DEVIATION

II.Ett G (illi/AftQ1-D-18)

C. Section 4.0 of CPRT Project Procedure CPP-008, Revision 1, requires that

verification packages provide the information necessary to conduct

/ reinspections and document the results. Section 5.1.1 of this procedure

/( states, in part, "...Should an attribute appear on the generic checklist

J and not be applicable to the specific item, the engineer indicates "N/A"

and provides reasonable justification for the entry."

In deviation from the above, the engineer incorrectly indicated "N/A" for

attribute 1.e on the checklist for Verification Package No. I-M-LBCO-038.

As a result, this attribute, dealing with assuring branch connections were

in accordance with the piping isometric drawing, was not reinspected by

ERC. Independent inspection identified that the attribute was applicable

for Verification Package No. 1-M-LBC0-038 as evidenced by the observation

of the presence of a branch connection

l

RESPONSE IQ 111l[ L

1. Reason for Deviat. ion

l

ERC investigation confirmed that attribute 1.a in the ERC inspection

checklist had N/A incorrectly inserted by the QA/QC engineer, and thus was

not inspected. This attribute addresses assuring that brr ch connections

are in accordance with the piping isometric drawing. The existence of a

branch connection was confirmed on the piping isometric drawing bill of l

material,

'

,

5. Corrective Action Iaken

No corrective action has been planned for this deviation. The lack of

reinspection of one branch connection will not affect the final

conclusions drawn concerning branch connection installation. A

l statistically sufficient quantity of branch connections (approximately

! 115) have been inspected to permit the adequacy of branch connection

installation to be determined.

3. Action in Prevent Recurrence

The QA/QC engineer was instructed to take added precautions when

completing inspection checklists. Additionally, ERC inspectors have been

instructed to correct a checklist when an error '7 found or return the

list to the QA/QC engineer for correction. A mc.arandum dated May 28,

1986, confirmed the above instruction,

k _ __ - __ ---____-_ _

..

_.

,

,

l

. . ~

l

Attachment to TXX-5048 Page 16

October 13, 1986

RESPONSE IQ IIEB G [QNI'Q

In addition to the specific a'ctions identified above, the following

activities are ongoing on a generic basis to identify and correct

inspection, engineering or program deficiencies to insure compliance with  !

,

the Quality Assurance guidelines for the CPRT Program

1) Surveillances are scheduled and performed routinely of CPRT activities

per ERC-QA-15, " Performance of Project Surveillance". Specific

elements of the surveillance practice are:

'

0 Monitoring ongoing work to determine what activities have been

slanned, what activities are in process, and what activities have '

>een completed and accepted.

<

0 Verify the work is being accomplished in accordance with

requirements.

'

0 Determining when independent inspections should be made and

re. commending conduct of those inspections.

O Determining when direct observation of the work performance or

overview of inspections and tests should be.made and arranging for

the conduct of those observations.

O

Performing and documenting observations or witnessing of

inspections or tests performed by others.

- .

O Determining when special audits of quality assurance activities

should be performed.

O Initiating recommendations for corrective action based upon

observations.

These surveillances are performed through selected activities such as

monitoring of direct observation of work activities, quality trends,

etc. Surveillance activities and their results are recorded. If any

deviations are identified, the appropriate organization within ERC is

notified to correct the deviation and submit a report describing

corrective action taken or proposed. All deviations are logged and

tracked until closed.

2) Audits are performed per ERC-QA-18, " Administration of Quality

Assurance Auditing". These audits verify the adequacy of the ERC

'

Quality Assurance Program. Audit reports are prepared and if

deviations from the Program Plan or Procedures are identified, the

, audited organization is notified to correct the deviation, review

areas where similar deviations can occur and to initiate corrective

action. All deviations are tracked until closed.

4. Q31.g af Egil Comoliance

l Quality Assurance surveillances and audits consist of an ongoing program.

'

, _ _ _ _ _ _ _ _ _ _ _ . _ _ . . _ _ _ _ _ . _ _ _ _ _ _ . _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _