'O S
PHILADELPHIA ELECTRIC COMPANY 23o1 M ARKET STREET P.O. BOX 8699 PHILADELPHIA, PA.19101 4215)841-4000 September 18, 1986 Docket Nos. 50-277 50-278 Director Office of Inspection & Enforcement US Nuclear Regulatory Commission Washington, DC 20555 Attention:
Document Control Desk
SUBJECT:
Revision to Peach Bottom Atomic Power Station Monthly Operating Report Gentlemen:
Attached are twelve copies of revised Operating Data 1
Sheets Reporting Items 20 through 26 of the Monthly Operating Report for Peach Bottom Units 2 and 3 for the month of August, 1986.
This revision is necessary because the Docket Numbers on the upper right corner were transposed.
The correction has been identified in the right-hand margin with a vertical bar.
Please update your copies of the report with the revised sheets.
We regret any inconvenience this error may have caused.
Very truly yours,
~
. M. Alden Engineer-In-Charge Licensing Section Nuclear Generation Division LLM:vdw 8609290135 860931 PDR ADOCK 05 27 Attachment R
cc:
Dr.
T.
E. Murley, NRC Mr.
T.
P. Johnson, Resident Inspector Mr. Stan P. Mangi, Dept. of Envir. Resources Mr.
P. A. Ross, NRC (2 copies)
G.
E. Gears, NRC Project Manager
/pf Mr. Thomas Magette, Maryland Power Plant Siting J"
INPO Records Center L
._.