ML20214P042

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-482/86-18
ML20214P042
Person / Time
Site: Wolf Creek 
Issue date: 11/25/1986
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Koester G
KANSAS GAS & ELECTRIC CO.
References
NUDOCS 8612040059
Download: ML20214P042 (1)


See also: IR 05000482/1986018

Text

_

s; . ..

NOV 2 61986

cIn Reply Refer To:

Docket: STN 50-482/86-18

Kansas Gas and Electric Company

ATTN: Glenn L. Koester

Vice President - Nuclear

P. O. Box 208

Wichita, Kansas

67201

Gentlemen:

Thank you for your ' letter of November 5,1986, in response to our letter and

- Notice of Violation dated October 6,1986. We have reviewed your reply and find it

responsive to the concerns raised in our Notice of Violation. We will review

the implementation of your corrective actions during a future inspection to

determine that full compliance has been achieved and will be maintained.

Sincerely,

N *.nal Egned by)

n. E. HALL"

J. E. Gagliardo, Chief

Reactor Projects Branch

cc:

Kansas Gas and Electric Company

ATTN: Otto Maynard, Manager

of Licensing

P. 0.' Box 309 (Sharp Road)

Burlington, Kansas

66839

Forrest Rhodes, Plant Superintendent

Wolf Creek Generating Station

P. O. Box 309

Burlington, Kansas

66839-

Kansas Radiation Control Program Director

8612040059 861125

bec to DMB (IE01)

PDR

ADOCK 05000482

G

PDR

bec distrib by RIV:

RPB

Myron Karman, ELD, MNBB (1)

RRI

R. D. Martin, RA

Section Chief (RPB/B)

DRSP

R&SPB

R. P. Warnick, RIII

RIV File

Resident Inspector, RIII

MIS System

RSB

RSTS Operator

D. Weiss, LFliB (AR-2015)

RIV:R

C:RPB/

. C:RPB #I

'

RPMul

s

DRHun

/ JEGagliardo

\\\\

11/p/86

11/JS/.6

11/M/86

\\\\

l

.

o , .

KANSAS GAS AND ELECTRIC COMPANY

THE ELECTRC COMPANr

GLENN L KOESTER

November 5, 1986

" " " " * ~ ' " " " "

TM@MDUC

Mr. E. H. Johnson, Director

Division of Reactor Safety and Projects

NOV I 3 IE

U. S. Nuclear Regulatory Commission

Region IV

-

l

611 Ryan Plaza Drive, Suite 1000

Arlington, Texas 76011

KMLNRC 86-206

Re:

Docket No. STN 50-482

Subj:

Response to Inspection Report STN 50-482/86-18

Dear Mr. Johnson:

This letter is written in reponse to your letter of October 6,

1986, which

transmitted

Inspection Report STN 50-482/86-18.

As requested,

the

violations (482/8618-01 and 02) identified in the Inspection Report are

being addressed in four parts.

(a) The reason for the violation if admitted;

(b) The corrective steps which have been taken and the results

achieved;

(c) Corrective steps which will be taken to avoid

further

violations; and

(d) The date when full compliance will be achieved.

Violation (482/8618-01): Failure To Comply With

Licensee's

Temporary

Modification Procedure

Finding:

Technical Specification (TS) 6.8.1 requires that, " Written procedures shall

be established,

implemented, and maintained covering .

a.

The

.

.

applicable procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Revision 2, February 1978."

amt n 1

0-

-

201 N. Market - Wichta, Kansas - Mail Address: PO. Box 208 I Wictuta, Kansas 67201 - Telephone: Area Code (316) 261-6451

.

.

s .

.

Mr. E. H. Johnson

November 5, 1986

KMLNRC 86-206

Page 2

Appendix A of RG 1.33, Revision 2, February 1978, states that "The following

safety-related activities .

should be covered by written

.

.

.

.

.

procedures . . 1.c.

Equipment control (e.g.,

locking and tagging) and "1.d

Procedure Adherence and Temporary Change Method."

Administrative

Procedure

(ADM)02-101,

Revision

15,

" Temporary

Modifications," has been established and implemented in accordance with the

above TS to control temporary modifications to ensure an accurate control of

station equipment is maintained and to ensure the return of a system to its

permanent configuration.

Section 6.1.1.1 of ADM 02-101, Revision 15, May 27, 1986, states that, "The

type of temporary modification shall be indicated in the activity to be

performed block.

Information to be recorded in Section D and on each

temporary modification tag should be as follows:

Lifted lead-cabinet name/ location,

terminal block number and

terminal number, wire number, and tag number."

Section 6.1.6.1 of ADM 02-101, Revision 15,

May 27,

1986,

states

that, ". . .

After the tag (s) are placed, the installer will sign

the tag (s),

initial the appropriate space on the temporary

modification order, and sign Section B, installed by."

Section 6.1.6.2 of ADM 02-101, Revision 15,

May 27,

1986, states

that,

"

The person performing the independent verification

.

.

.

will sign the tag (s),

initial the appropriate space on the

temporary modificatien order,

and sign Section B,

independent

verification by."

ADM 01-001,

Revision 12,

" Introduction To Wolf Creek Generating

Procedures," has been established and implemented in accordance

with the above TS to establish the administrative controls required

of

various

organizations

to

carry

out

their

assigned

responsibilities.

Section 4.2.4 of ADM 01-001,

Revisio1 12,

April 1,

1986, states

that,

"Those participating in any activity shall be made aware of,

and use, proper and current instructions, proc 9dures, drawings, and

engineering

requirements

for

performing

the

activity

as

applicable."

Contrary to the above,

on August 5,

1986,

the NRC inspector reviewed

Temporary Modification Orders 86-72KC and 86-81KC.

The NRC inappctor

observed that ADM 02-101 had not been followed in that the required

_

O

_

, . .

- - - -

o

,

. $ .

Mr. E. H. Johnson

November 5, 1986

KMLNRC ~ 86-206

Page 3

information for a lifted lead had not been recorded in Section D of

Temporary Modification Order 86-81KC, and that Temporary Modification Tag

86-72-KC-01 had been hung but the appropriate space on the temporary

modification

order

was

missing

initials for tag installation and

verification.

The NRC inspector also observed that ADM 01-001 had not been

followed in that Temporary Modification Order 86-72KC, prepared on July 10,

1986, used out-of-date ADM 02-101,

Revision 14,

versus the then current

Procedure ADM 02-101, Revision 15, May 27,1986.

Reason For Violation If Admitted:

The information for the lifted lead that was not recorded in Section "D" of

Temporary Modification Order (TMO) 86-81KC and the TM0 Tag 86-72-KC-01 that

was hung with the appropriate space on the TM0 missing initials for tag

installation and verification were due to failure to follow procedure by

station personnel.

TM0 86-72KC being prepared using an out-of-date ADM 02-001 was due to

failure to follow procedure by station personnel.

Corrective Steps Which Have Been Taken and Results Achieved:

TMO 86-81KC,

Section

'D' was corrected to include the required information.

TM0 86-72KC was corrected to include the initials for tag installation and

verification.

Revision 15 to ADM 02-101 did not create any changes to the TM0 fo rms.

Therefore the information on the out-of-date Revision 14 form was the same

as would have been entered on the Revision 15 form.

Management has stressed the importance of attention to de tail to the

Supervisory personnel in attendance at several of the daily status / schedule

meetings.

Corrective Steps Which Will Be Taken To Avoid Further Violations:

A copy of the violation and this response will be placed in Operations ,

Maintenance,

and Instrument & Control Required Reading to ensure personnel

are cognizant of the importance of following procedures.

The Date When Full Compliance Will Be Achieved:

Full compliance will be achieved by November 30, 1986.

.__ x

. _ _ _

-.

_ _ _ _ _

.

.

>.a

e

Mr. E. H. Johnson

November 5, 1986

KMLNRC.86-206

Page 4

' Violation (482/8618-02): Pailure To Lock Valve In Accordance With Procedure

Pinding:

TS 6.8.1

requires that,

" Written procedures shall be established, and

maintained covering .

a.

The applicable procedures recommended in

.

.

Appendix A of RG 1 33, Revision 2, February 1978."

Appendix A of RG

1 33,

Revision 2,

February 1978, states that,

"The

following . . . safety-related activities . . . should be covered by written

procedures . .

1.c. equipment control (e.g., locking and. tagging)."

Checklist CKL AL-120, Revision 8,

" Auxiliary Peedwater Normal Lineup," has

been established and implemented in accordance with-the above TS.

Checklich

A of CKL AL-120 requires, in part,

that the handwheels to Valves AL HV-006,

AL HV-008, AL HV-010 and AL HV-012 be lockwired in the neutral positions.

Contrary to the above, on August 20, 1986, the NRC inspectors observed that

3 out of the 4 turbine driven auxiliary feedwater pump (TDAPWP) discharge

valve handwheels were in the required neutral position but were not properly

lockwired. Valve ALHV-006 had its lockwire broken and twisted back together,

ALHV-008 was not lockwired, and ALHV-010 was lockwired so loosely that the

valve could be operated.

Reason For Violation If Admitted:

Pailure to properly lockwire valves ALHV-006,

ALHV-008 and ALHV-010 was-due

to operations personnel failure to follow procedure.

Corrective Steps Which Have Been Taken and Results Achieved:

Valves ALHV-006, 008 and 010 have been properly lockwired in the neutral

position in accordance with Checklist 'A' of CKL AL-120.

Administrative

Procedure ADM 02-102,

" Control of Locked Component Status" has been revised

'

to

provide a distinct blue valve tag for a Locked Neutral Valve.

Surveillance Test procedure, STS AL-103, " Turbine Driven Auxiliary Peedwater

Pump Inservice Pump Test" has been modified by Temporary Precedure Change

No. MA 86-0434 to open and lockwire the valves in the neutral position.

.

.

u

.s

.

Mr. E. H. Johnson

November 5, 1986

KMLNRC 86-206

Page 5

Corrective Steps Which Will Be Taken To Avoid Further Violations:

A copy of this violation and response has been placed in Operations Required

Reading to ensure operations personnel are aware of the requirement for

properly lock-wiring required valves.

The Date When Full Compliance Will Be Achieved:

Full compliance has been achieved.

If you have any questions concerning this matter, please contact me or Mr.

O. L. Maynard of my staff.

Very truly yours,

Glenn L. Koester

Vice President - Nuclear

ocs P0'Connor (2)

JCummins

JTaylor

.