Forwards Summary of Changes to Plant Settlement Monitoring Surveying Procedure 1-PT-115 & Category I Structures- Settlement Monitoring Procedure 1-PT-112,per Aslab Decision ALAB-578
ML20214K545
Person / Time
Site: North Anna  
Issue date: 11/24/1986
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Rubenstein L
Office of Nuclear Reactor Regulation
References
86-733, ALAB-578, NUDOCS 8612020341
Download: ML20214K545 (2)


Text

s VINUINIA ELECTHIC AND PownH CoxiwNY Hiciswonni,ViuoisrA 23261 November 24, 1986 W.L. STEWART u,'

~.': ~..

Mr. Harold R. Denton, Director Serial No.86-733 Office of Nuclear Reactor Regulation N0D/GGH:vlh Attn: Mr. Lester S. Rubenstein, Director Docket Nos.

50-338 PWR Project Directorate No. 2 50-339 Division of PWR Licensing-A Licensing Nos. NPF-4 U. S. Nuclear Regulatory Conunission NPF-7 Washington, D. C.

20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS NO. 1 AND 2 IETTLEMENT MONITORING PROCEDURE REVISIONS Enclosed is a summary of changes to the North Anna Power Station Settlement Monitoring Surveying Procedure, 1-PT-115, and the Category I

Structures-Settlement Monitoring Procedure, 1-PT-112.

This information is being transmitted for your review pursuant to Atomic Safety and Licensing Appeal Board Decision ALAB-578.

If you have any questions, please contact us.

Very truly yours, 62A W. L. Stewart cc: Dr. J. Nelson Grace Regional Administrator NRC Region III Mr. J. L. Caldwell NRC Senior Resident Inspector North Anna Power Station Mr. L. B. Engle NRC North Anna Project Manager PWR Project Directorate No. 2 Division of PWR Licensing-A co\\

y.hz IfDCA - AdTS

  • 8612O20341 861124 i

PDR ADOCK 0500 8

$p P

SUfMARY OF CHANGES TO SETTLEMENT MONITORING PROCEDURES This summary provides notification, in accordance with Atomic Safety and Licensing Appeal Board Decision ALAB-578, that the Virginia Electric and Power Company has revised the Settlement Monitoring Surveying Periodic Test (PT)

Procedure (1-PT-115) and the Category I Structures - Settlement Monitoring Procedure (1-PT-112) for the North Anna Power Station. These procedures are used by Carrouth and Associates to monitor the settlement of Class I structures at North Anna and provide instructions for surveying to second order, Class II accuracy.

The changes to both procedures were necessary because settlement monitoring points

113, 141, 206, 207, 208, and 209 could no longer be used for surveying and had to be replaced with the associated redundant points.

Settlement monitoring points 113 and 141 were no longer accessible for reliable surveying due to plant modifications which have obstructed access to the points.

Settlement monitoring points 206, 207, 208, and 209 were fabricated from a corrosive material and they are deteriorating, making it desirable to survey the stainless steel redundant points instead.

In each case the redundant points are located on the same structure as, and in close proximity to, the original point.

The Bases section of NAPS Technical Specification 3/4.7.12 allows the establishment of alternate monitoring points.

Baseline elevations were established and added to 1-PT-112 for redundant settlement points 206R, 207R, 208R, and 209R corrected to May 1976. Baseline elevation for redundant settlement poirt 113R was established (corrected to July 1977) and the baseline elevation for redundant settlement point 141R was established (corrected to February 1979), and both elevations were added to 1-Pi-112.

The other changes made to these procedures were administrative in nature and do not affect the method of surveying.