Log # TXX-6107 File # 10110 903.7 TEXAS UTILITIES GENERATING COMPANY B^t rMAY TOWER e est NORTH OLIVE ST9 TEST. L.B. 51. DALLAS. TEXA8 7MDB i
November 21, 1986 y
[a a As ce v
NOV 2 41986 l
Mr. Eric H. Johnson, Director Division of Reactor Safety and Projects u -
l U. S. Nuclear Regulatory Commission i
611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 SEISMIC AIR GAP DESIGN ADEQUACY SDAR: CP-86-55 (INTERIM REPORT)
Dear Mr. Johnson:
On August 14, 1986, we verbally notified your Mr. I. Barnes of a deficiency involving the seismic air gap design adequacy between the Auxiliary Building and Units 1 and 2 Containment Buildings. This is an interim report of a potentially reportable item under the provision of 10CFR50.55(e). Our last interim report was logged TXX-5011, dated September 12, 1986.
The specific deficiency involved recent calculations which indicated that a separation gap dimension should be greater than the existing design dimension during extreme high temperature conditions. Using more realistic data, this calculation was refined to demonstrate that the present gap is acceptable.
Review and evaluation of the refined calculations are scheduled for completion by February 20, 1987.
We anticipate submitting our next report no later than March 13, 1987.
Very truly yours, K
uf I
W. G. Counsil JCH/mlh c - NRC Region IV (0 + 1 copy)
Director, Inspection & Enforcement (15 copies)
U. S. Naclear Regulatory Commission Washington, D.C.
20555 8612010222 861121 gDR ADOCK 05000445 g g PDR.