Requests Schedule for plant-specific Implementation of USI A-46, Seismic Qualification of Equipment of Operating Plants No Later than 871201,per Encl Granting 870410 Request for Schedular Relief
ML20214F489
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/14/1987
From: De Agazio A
Office of Nuclear Reactor Regulation
To: Shelton D
TOLEDO EDISON CO.
References
TASK-A-46, TASK-OR GL-87-02, GL-87-2, NUDOCS 8705260119
Download: ML20214F489 (2)


Text

,.. -. . . _ . . _ . . - . .

c <  :--- $ 1 .

~

. 5. 'f MAY 141987 ,-

.DockAtNo. 50-N6 - , 1

. Serial--No.'D-B 87-001~ , ,

~

,  : Davis-Bess'e Nuclear Power; Station ~,.

' Unit No. l' ' '

Mr. Donald C..Shelton- -

Vice. President, Nuclear ,

[ Toledo Edison. Company , ,

~ ,

-; EdisonjPlaza - Stop;712

'300 Madison Avenuec p s 5 Toledo, Ohiol 43652- '

Dear Mr. Shelton:

~

SUBJECT:

RELIEF FROM 60-DAY REPORTING. REQUIREMENT 0F GENERIC. LETTER 87 . ,

sGeneric Letter 87-02 was issued +on February 19,11987, to allfutili_ ties required -

to implement the,requireme'nts of USI'A-46,~ " Seismic Qualification of. Equipment ,

' ~

in' 0perating Plants,;" required all 'affected utilities to respond within 60 days.

Subsequently, the; Seismic Qualification _ Utilities Groupi.(SQUG) formally .

, -requested'an. extension of=the 60-day-reporting,requir.ements for utilities' who.

are members of the.SQUG. 'The extension.was granted by the-enclosed. letter' .

3 dated April-28,'1987, from Thomas = E. ' Murley,. Director, Office of Nuclear Reactor '

' Regulation,.to;Neil P._ Smith, Chairman, SQUG. -

Please; note that you should provide 'the. schedule for. plant-specific implementation l'

no later than December 1,.1987 3 The NRC staff will review'and evaluate the , ~

2 Lgeneric procedures by October.1, to allow each utility 60 days to prepare their

r_eplies to the generic letter. '

Sincerely,'

i. .

.jff'/~

l Albert ~W.'De Agazio, Project Manager Project Directorate III-l' Division.of Reactor Projects - III, IV,,V

-&-Special Projects'

~

Enclosure:

As stated Distribution .[

GN3g"o i NRC PDR LA:PD31 RSP PM:PD31:DRSP i- ' Local PDR- A. De'Agazio -RINGR :dlm- ADEAGAZIO L E.~ Jordan PD31 Plant File- 3 / / 87 g/jp/87

-G.'Holahan: R. Ingram' OGC J. Partlow '

ACRS-(10)_

i f

% h m

87052601.t9 870514 4-PDR ADOLK 050003464 ,

P PDR e

, .. P

Mr. Donald C. Shelton Davis-Besse Nuclear Power Station Toledo Edison Company Unit No. I cc:

Donald H. Hauser, Esq.

The Cleveland Electric Radiological Health Program Illuminating Company Ohio Department of Health P. O. Box 5000 1224 Kinnear Road Cleveland, Ohio 44101 Columbus, Ohio 43212 Mr. Robert F. Peters Attorney General Manager, Nuclear Licensing Department of Attorney Toledo Edison Company General Edison Plaza 30 East Broad Street 300 Madison Avenue Columbus, Ohio 43215 Toledo, Ohio 43652 Mr. James W. Harris, Director Gerald Charnoff, Esq. (Addressee Only)

Shaw, Pittman, Potts Division of Power Generation and Trowbridge Ohio Department of Industrial Relations 2300 N Street N.W. 2323 West 5th Avenue Washington, D.C. 20037 P. O. Box 825 Columbus, Ohio' 43216 Mr. Paul M. Smart, President Toledo Edison Company Ohio Environmental Protection Agency 300 Madison Avenue 361 East Broad Street Toledo, Ohio 43652 Columbus, Ohio 43266-0558 Mr. Robert B. Borsum President, Board of

f. Babcock & Wilcox County Commissioners of Nuclear Power Generation Ottawa County-Division Port Clinton, Ohio 43452 Suite 200, 7910 Woodmont Avenue Bethesda, Maryland 20814 State of Ohio Public Utilities Commission Resident Inspector 180 East Broad Street U.S. Nuclear Regulatory Commission Columbus, Ohio 43266-0573 5503 N. State Route 2 Dak Harbor, Ohio 43449 Regional Administrator, Region III i U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 l

+ _ . .

-+

/  %,, UNITED STATES i

! NUCLEAR REGULATORY COMMISSION g ,j mam oron.o.c.sessa i.

\*****/ APR 2 81987

,d

  • Mr. Neil P. Smith Chainnan .

Seismic-Qualification Utility Group l 801 18th Street, N.W.

Suite 300 Washington, D.C. 20006,

Dear Mr. Smith:

I have received jour letter dated April 10, 1987 requesting clarification of the 60-day reporting provisions of Generic Letter 87-02. In Generic Letter 87-02, the steff requested that each licensee subject to the USI A-46 equipment seismic adequacy verification requirements provide a schedule for implementation of the seismic verification within 60 days of receipt of the Generic Letter.

In your letter you stated that licensees who belong to the Seismic Qualification Utility Group (SQUG) will be unable to provide a schedule for implementation at this time because the generic implementation procedures are still under develepment by the SQUG and will not be finalized until the completion of seyeral trial plant reviews.

The staff hat / reviewed your request and concluded that it is appropriate to ,

extend the 60-day reporting provisions of Generic Letter 87-02 for SQUG licensees until the generic implementation procedures are better defined and the trial plant reviews are completed'. It is my understanding that-the SQUG generic implementation procedures should be essentially complete before October 1,1987. By that date at least two trial plant reviews will have been completed and the generic implementation procedures sufficiently defined and :l reviewed by NRC staff so'that licensees can plan and schedule their plant i specific reviews.

All licensees participating in the USI Ah6 SQUG implementation program should provide the schedule for plant specific implementation no later than

. December 1,1987. The NRC staff will review and evaluate the generic i procedures by October 1, to allow each utility 60 days to prepare their replies to the generic letter.

Sincerely, Thomas E. MurleyN.uwr Office. of Nuclear Reactor Regulation M.