Amends 104 & 94 to Licenses DPR-39 & DPR-48,respectively, Permitting one-time Extension of Outage Time from 7 to 21 Days on Diesel Generator 0 for Unit 2 Spring 1987 Refueling Outage Maint & Mod,Per 10CFR50,App R
ML20213G608
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/08/1987
From: Muller D
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20213G575 List:
References
NUDOCS 8705180366
Download: ML20213G608 (7)


Text

o *, %q'o UINTED STATES g

NUCLEAR REGULATORY COMMISSION n

h WASHileGTON, D. C. 20586 s.,.....j COMMONWEALTH EDIS0N COMPANY DOCKET NO. 50-295 ZION NUCLEAR POWER STATION, UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.104 License No. DPR-39 1.

The Nuclear Regulatory Comission (the Comission) has found that:

A.

The application for amendment by Comonwealth Edison Company (the licensee) dated February 10, 1987, complies with the standards 4

and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (1) that the activities authorized by this amendment can be conducted without endangering the health andsafetyofthepublic,and(ii)thatsuchactivitieswillbe conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the comon defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-39 is hereby amended to read as follows:

h[g5gDO 3

P

-2 (2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.104, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment is effective as of the date of its issuance.

FOR THE NUCLEAR REGULATORY COMMI ON

//

d Daniel R. Muller, Director Project Directorate III-2 Division of Reactor Projects - 111, IV, V and Special Projects

Enclosure:

Changes to the Technical Specifications Date of Issuance: my 8,1987

  • [ha a80g%,

WINTEJ STATES f,

g

~,

NUCLEAR REGULATORY COMMISSION g

wAsumaTom, o. c. zones 9,

a

%, *... /

COMMONWEALTH EDISON COMPANY DOCKET NO. 50-304 ZION NUCLEAR POWER STATION, UNIT 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 94 License No. DPR-48 1.

The Nuclear Regulatory Comission (the Comission) has found that:

A.

The application for amendment by Comonwealth Edison Company (the licensee) dated February 10, 1987, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Comission; C.

There is reasonable assurance (1) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; D.

The issuance of this amendment will not be inimical to the comon defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-48 is hereby amended to read as follows:

i

)

i

, (2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 94,are hereby incorporated in the license.

The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment is effective as of the date of its issuance.

FOR THE NUCLEAR REGULATORY C ISSION

~

4

  • J Daniel R. Muller, Director Project Directorate III-2 Division of Reactor Projects - III, IV, Y and Special Projects

Enclosure:

Changes to the Technical Specifications Date of Issuance:

May 8, 1987

.' /-

'o untTED STATES

[

',g NtJCLEAR REGULATORY COMMISSION j

wAamwoTom, p. c. seems

\\,*... /

ATTACHMENT TO LICENSE AMENDMENTS AMENDMENT NO. 104 FACILITY OPERATING LICENSE NO. DPR-39 AMENDMENT NO. 94 FACILITY OPERATING LICENSE NO. DPR-48 DOCKET NOS. 50-295 AND 50-304 Revise Appendix A as follows:

Remove Page Insert Pages 255a 255a 255b l

l

Y a

c.

E For a 21 day period during the Unit 2 Spring 1987 refueling outage, f,

with Unit 2 in Mode 5 or 6. only two diesel generators (IA. IB) are required to satisfy the standby AC onsite power requirements for z

?

Unit I as specified in Sections 3.15.1.B. 4.15.1.B.2. 3.15.2, and 4.15.2.

The surveillance testing specified in 4.15.1.B.2 will be 3

perfomed on diesel generators IA. IB. 2A, and 2B isenediately prior to removal of "O" diesel generator from service. During the 21 day period, diesel generators IA. IB. 2A, and 25 will be verified (1) operable at least once per day. The surveillance frequency for diesel generators IA and IB will remain as specified in the Zion Confir1matory Order of February 29, 1980. In the event that diesel generator IA or IB becomes inoperable. Ur.it I will be brought to Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Mode 5 within the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

l Should 2A and 28 diesel generators become inoperable during the 21.

day outage on "0" diesel generator, the ACTION statements on the table on page 255b shall apply.

l (1)

The tem verify as used in this context means to administratively check by exaulning loss or other information to determine if certain I

components are out-of-service for maintenance or other reasons. It does not mean to perform the surveillance requirements needed to demonstrate the OPERABILITY of the components.

l l

255a 2704K

~

i y

Unit 1 Unit 2 n

5 Diesel Generator O

1A IB O

2A 2B h

Bus 147 148 149 247 248 249 e

Service Water PP 1A IB IC 2A 2B 2C Comp. Cool PP OE OD OC 08 OA ACTION O Diesel Cen.

00S Operable operable 00S Operable Operable No LCO.

No additional surveillance.

IA Diesel Cen.

003 Inop Operable DOS Operable Operable Unit 1 Mode 3 within 12 hrs. Mode 5 additional 30 hrs.

IB Diesel Cen.

00S Operable Inop OOS Operable operable Unit 1 Mode 3 within 12 hrs.

Mode 5 additional 30 hre 1A & IB Diesel Cen 003 Inop Inop OOS Operable Operable Inunediate Shutdown 2A Diesel Cen.

00S Operable Operable 005 Inop Operable No LCO No additional surveillance 28 Diesel Cen.

00S Operable Operable OOS Operable Inop 5o LCo. No additional surveillance 2A & 2B Diesel Cen 005 Operable Operable DOS Incy Inop Unit 1 operation 7 days.

Test IB & IC SWPp's and OD & OC CC pps daily.

ACTION STATEMENTS FOR 21 DAY PERIOD OF "0" D/C OUTACE (SPRING 1987) 255b