Requests Util Submit Turbine Maint Program Based on NRC Approved Manufacturer Analyses of Probability of Missile Producing Turbine Failure within 3 Yrs of Issuance of Ol,To Reclassify Issue from Open to Confirmatory Item
ML20213E351
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/07/1983
From: Johnston W
Office of Nuclear Reactor Regulation
To: Novak T
Office of Nuclear Reactor Regulation
References
CON-WNP-0570, CON-WNP-570 NUDOCS 8303160021
Download: ML20213E351 (3)


Text

y o

h!M 7 19c3 DISTRIBUTION MTEB Reading File WPPSS Plant File Concurrences Docket Nos. 50-397 MEMORANDUM FOR:

Thomas M. Novak, Assistant Director for Licensing Division of Licensing FROM:

William V. Johnston, Assistant Director Materials, Chemical & Environmental Technology Division of Engineering

SUBJECT:

REQUEST FOR WASHINGTON PUBLIC POWER SUPPLY SYSTEM (WPPSS) AGREEMENT TO PROCEDURE FOR ESTABLISHING AN NRC APPROVED TURBINE MAINTENANCE PROGRAM Plant Name:

Washington Nuclear Project No. 2 Suppliers:

Westinghouse (Turbine)

Docket Number:

50-397 Responsible Branch & Project Manager:

LB #2; Rajender Auluck Reviewer:

J. O. Schiffgens Description of Task:

Required Commitment for WNP-2 Safety Evaluation Report Review Status:

Information Requested In order to reclassify the turbine missile issue from "open item" to

" confirmatory," we request that Washington Public Power agree to submit to the NRC a turbine maintenance program based on NRC approved manufac-turer's analyses of the probability of missile producing turbine failure within 3 years of obtaining an operating license.

If such a program is not received and approved by us within 3 years, the applicant is to inspect all LP turbine rotors during the second refueling outage.

We will provide a detailed evaluation on the issue assuming that the applicant has agreed to our request.

l William V. Johnston, Assistant Director Materials, Chemical & Environmental Technology Division of Engineering

Attachment:

Perry Turbine Maintenance cc:

See Page 2 y

r) /

1 4 Il )

Contact:

J. Schiffgens WM'IEB DE/MT DE'/MTEB DE/MC&ET X-28099 Ebkiffgens R)(Iecker BDLiaw WJohnston

, /' / /83 3'/ 4 /83 3/ /83 3/

/83 Nd TVI/.

/I 8303160021 83030 t

ADOCK 05000397

. uJ T. Novak,%

7 1953 cc:

R. Vollmer D. Eisenhuf.

T. Sullivan S. Pawlicki B. Youngblood R. Auluck B. D. Liaw W. Hazelton C. Cheng R. Klecker J. Schiffgens

7 ATTACHMENT TURBINE MAINTENANCE COMMITTMENT FOR WNP-2 TURBINE MISSILE ISSUE We have reviewed the WNP-2 facility with regard to the turbine missile issue and conclude that the probability of unacceptable damage to safety-related systems and components due to turbine missiles is acceptably

-7 low (i.e., less than 10 per year) provided that the turbine missile

-5 generation probability is maintained to be 10 per reactor year or less for the life of the plant by an acceptable maintenance program.

In reaching this conclusion, the staff has factored into consideration the unfavorable orientation of the turbine generator.

The staff considers the turbine missile issue as a confirmatory item if the applicant agrees to:

a) submit for NRC approvalr within three years of obtaining an operating license, a turbine system maintenance program based on the manu-facturer's calculations of missile. generation probabilities, or b) volumetrically inspect all low pressure turbine rotors at the second refueling outage and every other (alternate) refueling outage thereafter until a maintenance program is approved by the staff, and i

c) conduct turbine steam valve maintenance, (following initiation of power output) in accordance with present NRC recommendations-as stated in SRP Section 10.2 of NUREG-0800.

?

l

& nh

,(p q[9 UNITED STATES g

yjf,O4[g/,8

.- r g

. NUCLEAR REGULATORY COMMISSION

4 q E

WASHINGTON, D. C. 20555 t W4 X MAR 5 1983

%g - O f

....+

1 Docket No. :

S0-397 MEMORANDUM FOR:

A. Schwencer, Chief Licensing Branch No. 2, DL FROM:

R. Auluck, Project Manager Licensing Branch No. 2, DL

SUBJECT:

FORTHCOMING MEETING WITH WASHINGTON PUBLIC POWER SUPPLY SYSTEM (WPPSS)

DATE & TIME:

March 10,1983 10:00 am LOCATION:

Room 12309 MNLB Bethesda, MD PURPOSE:

Discuss Applicant's Estimated Plant Completion Date PARTICIPANTS:

NRC WPPSS D. Eisenhut D. Bouchey, et. al T. Novak A. Schwencer R. Auluck W. Lovelace R. Scroggins L. Barry k

b R. Auluck, Project flanager I

Licensing Branch No. 2 DL l

l cc:

See next page i

l i

l l

4;;;i,0vvV 830308 PDR ADOCK 05000397 i

A PDR

  • p st%q'o UNITED STATES

[Ifp,. y/.'l. Pj NUCLEAR REGULATORY COMMISSION

.j\\

c WASHINGTON, D. C. 20555 l

y9d/,/

FEB 17 1983 Docket No. :

50-397

}

MEMORANDUM FOR:

A. Schwencer, Chief k

Licensing Branch No. 2, DL FROM:

R. Auluck, Project Manager 1

Licensing Branch No. 2, DL

}

FORTHCOMING MEETING WITH WASHINGT0t.

P JBLh0WER

SUBJECT:

SUPPLY SYSTEM (WPPSS)

J DATE & TIME:

March 8,1983 1:00 pm LOCATION:

e

(

Phillips Building l

Bethesda, Maryland l

4 PURPOSE:

Discuss Applicant's EstinatIdJant Completion Date 1

PARTICIPANTS:

NRC WP D. Eisenhua

(

D.Aouchey, et. al T. Novak I

\\g A. Schwenct R. Auluck W. Love}eqe R. Scrchgins L. Bart R P.a hR.Auluck,ProjectManager j

Licensing Branch No. 2, DL See n c J i

a f

\\-

4 lt T304L50062-377

WNP-2 Mr. R. L. Ferguson Managing Director Washington Public Power Supply System P. O. Box 968 3000 George Washington Way Richland, Washington 99352 cc:

Nicholas Reynolds, Esquire Debevoise & Liberman 1200 Seventeenth Street, N. W.

Washington, D. C.

20036 Mr. G.E. Doupe, Esquire Washington Public Power Supply System P.O. Box 968 3000 George Washington Way Richland, Washington 99352 flicholas Lewi s, Chairman Energy Facility Site Evaluation Council Mail Stop PY-ll Olympia, Washington 98504 Roger Nelson, Licensing Manager

. Washington Public Power Supply System P.O. Box 968 Richland, Washington 99352 Mr. W.G. Conn, Sr. N/M Group Supervi sor Burns and Roe, Incorporated 601 Williams Boulevard Richland, Washington 99352 Mr. Richard Feil U.S.. NRC Resident Inspector WPPSS-2 NPS P.O. Box 69 Richland, Washington 99352 i

Dr. G.D. Bouchey Deputy Director, Safety & Security Washington Public Power Supply System P.O. Box 968,10 650,

Richland, Washington 99352 I

o IE0 I 7 l903 MEETING NDTICE DISTRIBUTION:

Date:

...e..:...,,,wr:.

NRC POR L PDR NSIC PRC LB#2' Reading NRC PARTICIPANTS:

E. Hyl to n D. Eisenhut Project Manager R. Auluck T. Novak H. Denton/E, Case A. Schwencer D. Eisenhut/R. Purple R. Auluck T. M. Novak*

W. Lovelace B. Youngblood A. Schwencer R. Scroggms L. Barry G. Knighton E. Adensam G. Lainas F. Miraglia J. P. Knight W. Johnston D. Mull er T. Speis

~

R. Houston L. Rubenstein

/~

~ ~ '

F. Schroeder M. Ernst J. Kramer NRR Division Directors" OELD Attorney paenn E. L. Jordan, DEQA:IE J. M. Taylor, DRP:IE Phi' lips Building Receptionist **

ACRS (.16)

Region y

Resident Inspector cc: Service List

  • 0nly if participant in meeting