Forwards Petition Filed by Devine Under 10CFR2.206 on Behalf of San Luis Obispo Mothers for Peace.Board Notification Being Prepared & Attachments Being Reviewed to Determine Whether Petition Eligible for Release to Public
ML20212P672
Person / Time
Site: Diablo Canyon  
Issue date: 02/22/1984
From: Stephen Burns
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Cater C
NRC ATOMIC SAFETY & LICENSING APPEAL PANEL (ASLAP)
Shared Package
ML20212P606 List:
References
FOIA-84-741, FOIA-84-742 2.206, NUDOCS 8703160191
Download: ML20212P672 (1)


Text

.

p. ~%,,

!~

t UNITED STATES f

NUCLEAR REGULATORY COMMISSION f

WASHINGTON, D.C. 20555

" * " ~

February 22, 1984 Chris Cater, ASLAP Attached is a copy you requested of the petition filed by Mr. Devine on behalf of the San Luis Obispo Mothers for Peace.

The Comission referred the petition to the staff for consideration in accordance with 10 CFR 2.206.

~

The staff is preparina a Board notification on the petition and is reviewing the attachments to the petition to determine whether they can be publicly released or should be provided to the boards in camera.

The Board notification should be issued in the near. future.

/

Ste hen G. Burns r

Deputy Director Regional Operations and

' Enforcement Division, OELD

~

3 8703160191 870311 PDR FOIA DEVINEB4-741 PDR

,;,[/

. c,},

'~-

UNITED STATES NUCLEAR REGULATORY COMMISSION

\\;

/

May 8, 1984 MEMORANDUM FOR:

Harold R. Denton, Director Office of Nuclear Reactor Regulation FROM:

Richard Hoefling, Acting Director Regional Operations and Enforcement Office of the Executive Legal Director

SUBJECT:

MAY 3,-1984 2.206 PETITION FROM GAP RE: DIABLO CANYON By the enclosed Petition dated May 3,1984, Thomas Devine, on behalf of the Mothers for Peace and the Government Accountability Project submitted an additional request for action concerning the Diablo Canyon Nuclear Power Plant. The request augments its earlier _ requests and relies on allegations previously submitted as well as the infomation included with this Petition.

The Petition requests that any decision on ascension above 5% power be deferred until certain actions, to be ordered by the Comis-sion by May 11, 1984, are completed.

The actions recuested include:

1) additional re-evaluation of design, design control and construction activities under the direction of an independent third party; 2) a review of Diablo Canyon's character and competence by means of an independent management audit and OI investigation of intimidation and harassment; and 3) an investigation of possible misleading statements by the NRC staff to the Comdission during recent briefings.

Although no decision on whether the information submitted supports initiation of the requested actions is necessary by the May 11, 1984 dat,e specified in the Petition, an acknowledgement letter should be sent promptly.

We have enclosed a draft of such a letter for your use.

Please contact Karen Cyr of my office if you have any questions con-cerning this Petition and include James Lieberman on distribution for any future correspondence concerning this Petition, f.

j'E PAhard Hoefling, Acting Director Regional Operations and Enforcement Division Office of the Executive Legal Director Enclosured:

as stated See next page for cc's

~

$3 o

_ c

_7

..e,- i

- l cc w/o Petition:

D. Eisenhut, URR J. Martin, RV 1-T. Bishop, RV G. Knighton,flRR H. Schierling, i;RR.

E. Christenbury,' OELD

- L. Chandler,' ELD R. DeYoung, IE B. Hayes, 01 G. !!essenger, 01 A Distribution fiRC Central Burns info' Liberman info i

Hoefling chron Cyr chron LC/SC info Cunningham/Murray info.

ELD rdg ROED rdg J:pROED chron e

EDO # 14412 (reference EDOF 14334)-

L. Shollenberger, RV 1

~

!~

4 i.

6 4

i e:

9 e

<=

~

D R A.F T 9

^

Thcmas Devine, Esq.

Cccr.sel for itcthers for Peace Government Accountability Prcject Institute for Policy' Studies 1901 Q 5treet, N.W.

l!ashincton, D.C. 20009

Dear Mr. Devine:

This is to acknowledge receipt of your Petition, filed liay 3,1984,-pur-suant 'o.10 CFR 2.206 of the Commission's regulations.

You have requested t

that the Commission defer a_ny decisions on whether to permit the Diablo, Canyon Nuclear Power Plant to begin ascension'beyond 5% power until certain actions are completed.

Your request has been referred to the staff for consideration.

You have. requested that these actions be ordered by the Commission on or before liay 11, 1984 No decision on the authorization for the Diablo Canyon plant to go beyond 5% pcwer is currently scheduled.

We have begun an inquiry into the information ycu. have submitted to determine whether any of your requested actions should be taken.

Hcwever, ne decision or, whether they should be taken will be reached by liay 11, 1984, nor is such a decision by that date required or necessary. We will respond to the substance of your Petition within a reasonable time as provided in 10 CFR 2.206(b).

3 i

Harold R. Denton, Director Office of i:uclear Reactor Regulation 9