ML20212G815

From kanterella
Jump to navigation Jump to search
Closes Concerns Raised by IE Bulletin 80-08, Exam of Containment Liner Penetration Welds, for Unit 2,per Exam of Welds Listed in .Unit 1 Welds Will Be Examined During Spring 1987 Maint/Refueling Outage
ML20212G815
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 02/27/1987
From: Gucwa L
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
RTR-NUREG-CR-3053 3237N, IEB-80-08, IEB-80-8, SL-2071, NUDOCS 8703050413
Download: ML20212G815 (1)


Text

C~

Georgi 2 Power CompW,

- 313 Piedmont Avenu2 Affantz, Georgia S0308 Telephona 404 S26-6526 Mailing Address:

Post Office Box 4545 :

Atlanta, Georgia 30302 GeorgiaPower ge uclear Safety 7j 3237N February 27, 1987 U. S., Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C.

20555 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 CLOSE0VT OF I&E BULLETIN 80-08 EXAMINATION OF CONTAINMENT LINER PENETRATION WELDS Gentlemen:

By letter dated August 8, 1986, Georgia Power Company (GPC) commit'ted to the NRC to perform nondestructive examination of certain containment penetration assemblies.

The letter delineated the specific penetrations which would allow for the closecut of NRC I&E Bulletin 80-08 and NUREG/CR-3053 fcr both Unit 1 and Unit 2, and indicated the examination would be performed during the next scheduled maintenance / refueling outage for the ' respective units.

During the Fall 1986 Hatch Unit 2 maintenance / refueling outage the welds for the containment liner penetrations listed in the August 8,1986 letter were examined.

No significant indications were observed.

GPC concludes that concerns raised by I&E Bulletin 80-08 are hereby closed for Hatch Unit 2.

The remaining containment liner welds in Hatch Unit 1 will be examined during the upcoming Spring 1987 maintenance / refueling outage.

If you have any questions in this regard, please contact this office at any time..

Sincerely, f7~~& -z L. T. Gucwa GKM/mb c: Georgia Power Company U. S. Nuclear Regulatory Commission Mr. J. P. O'Reilly Dr. J. N. Grace, Regional Administrator Mr. J. T. Beckham, Jr.

Mr. P. Holmes-Ray, Senior Resident

!!r. H. C. Nix, Jr.

Inspector - Hatch GO-NORMS Mr. G. Rivenbark, Licensing Project p

Manager I 6 8703050413 870227

{

DR ADOCK 0500 1