4-P. O. BOX 14000, JUNO BEACH, FL 33408-0420 4!!y/
w 3
FEBRUARY 231987 L-87-78 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:
Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Select System Assessment Progress Summary The January 1987 progress summary of the Phase li Select System Assessment is attached for the information of the Region 11 Staff.
Should there be any questions on this information, please contact us.
Very truly yours, C.O.W l
Group ce President Nuclear Energy l
COW /PLP/gp Attachment cc:
Dr. J. Nelson Grace, Regional Administrator, Region 11, USNRC Senior Resident, USNRC, Turkey Point Plant l
l l
5 0
% 0ggo!K 5
R 0
t i
. PLPl/025/1 an FPL Group company L
P. Pace PTNE-87-092 Attachment SELECT SYSTEM ASSESSMENT JANUARY 1987, PROGRESS Reconstitution of Design Basis Engineering review of the revised versions of the reconstituted design bases is ongoing. Comment receipt and resolution is scheduled for completion during February.
Preparation and issuance of the Chemical and Volume Control System (Emergency Boration) draft reconstituted design basis was performed on schedule (2/2/87 issue).
Walkdowns One hundred and twenty-four (124) of three hundred and six (306) small bore piping and tubing walkdowns are complete.
One hundred and thirteen (113) of one hundred and eighty-two (182) breaker list walkdowns are complete.
Note that two walkdown packages were added this period to the previcusly reported one hundred and eighty (180).
One hundred and nine (109) of one hundred and fifty-one (151) P&ID walkdowns are complete SEG Comprehensive Review Items identified in the SEG Phase II Report have been incorporated, where appropriate, on the applicable Select System Punchlist, for tracking purposes.
Other Significant Progress
- Completed various ICW NCRs
- Modified MSI procedure
- Rebuilt SI pump rotating element
- Replaced ICW check valves MWDisk/DAC#1/#030/C g
!