Forwards Request for Addl Info Re Review of Util Submittals Concerning Generic Ltr 83-28, Salem Atws. Licensee Response Should Confirm That Info Handling Sys Consists of Single,Concise Listing of All safety-related Components
ML20211N258
Person / Time
Site: Millstone Dominion icon.png
Issue date: 02/20/1987
From: Jaffe D
Office of Nuclear Reactor Regulation
To: Mroczka E
NORTHEAST NUCLEAR ENERGY CO.
References
GL-83-28, NUDOCS 8703020028
Download: ML20211N258 (3)


Text

n 3 ON ~

FEB 2 01987 Docket No. 50-336 9

Mr. Edward J. Mroczka, Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company P. O. Box 270 Hartford, Connecticut- - 06141-0270

Dear Mr. Mroczka:

We are continuing to' review your submittals concerning' Generic' Letter 83-28,

" Salem ATWS," for Millstone Unit 2.

In order to expedite our review,~we request that you respond to the enclosed questions within 60 days from receipt of this letter.

l This request for additional information affects_ fewer than 10 respondents; therefore, OMB clearance is not required under Pub. L.96-511.

Sincerely, nogtnaloWedW David H. Jaffe," Project Manager PWR Project Directorate #8 Division of PWR Licensing-B

Enclosure:

Request for Additional Information cc w/ enclosure:

See next page

?

DISTRTRIJ" ION ACRS-10 C Docket : p BGrimes NRC PDR JPartlow L POR DJaffe PBD-8 Rdg PKreutzer FMiraglia Gray File OGC-Bethesda NThompson EJordan AToalston

'i i

+

7 PBD PBD#k://

/

PBD#8hN zer DJaf

cF AThadant 87 2/bd/87 2RC/87

/ /.

k sf

~

0703020020 070220 PDR ADOCK 05000336 p

PDR

f

Mr. Edward J. Mroczka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 2 cc:

Gerald Garfield, Esq.

Mr. Stephen E. Scace Day, Berry & Howard Superintendent Counselors at Law Millstone Nuclear Power Station City Place P. O. Box 128 Hartford, Connecticut 06103-3499 Waterford, Connecticut 06385 Regional Administrator, Region I Mr. Wayne D. Romberg U.S. Nuclear Regulatory Commission Vice President, Nuclear Operations Office of Executive Director for Northeast Nuclear Energy Company Operations P. O. Box 270 631 Park Avenue Hartford, Connecticut 06141-0270 King of Prussia, Pennsylvania 19406 Mr. Char)es Brinkman, Manager Washington Nuclear Operations C-E Power Systems Combustion Engineering, Inc.

/ 7910 Woodmont Avenue

,t-Bethesda, Maryland 20814 Mr. Lawrence Bettencourt, First Selectman Tcwn,of Waterford j

Hall,of Records - 200 Boston Post Road V

Waterford, Connecticut 06385 i

Northeast Utilities Service Company ATTN:

Mr. Richard M. Kacich, Manager Generation Facilities Licensing Post Office Box 270 Hartford, Connecticut 06141-0270 Kevin McCarthy, Director 1

Radiation Control Unit Department of Environmental IJ Protection

-a J

State Office Building Hartford, Connect.icut 06106 i

tir. Theodore Rebelowski U.S.~

NRC P. O. Box 615 Waterford, Connecticut 06385-0615 Office of Policy & Management ATTN:

Under Secretary Energy Division 80 Washington Street Hartford, Connecticut 06106

\\,

i 3

f REQUEST FOR ADDITIONAL INFORMATION MILLSTONE, UNIT NO. 2 GENERIC LETTER 83-28

- 1.

Item 2.1 Reference the C-E "infobulletins" and the fact that return receipts are required for the bulletins.

2.

Item 2.2.1 The licensee's response does not confirm that the information handling system consists of a single, concise, unambiguous listing of all safety-related components and parts.

3.

Item 2.2.1.2 The licensee's response has not confirmed that the information handling system includes a list of safety-related equipment and that procedures exist which govern its development and validation.

~

4.

Item 2.2.1.3 The licensee's response has not confirmed that criteria and procedures exist which govern the use of the information handling system to determine that an activity is safety-related and what procedures for maintenance, surveillance, parts replacement and other activities defined in the introduction in 10 CFR 50, Appendix B, apply to safety-related components.

  • ~

5.

Item 4.5.2 In the November 8, 1983 response to GL 83-28 the licensee states that Millstone Unit 2 performs on-line testing of the Reactor Trip System.

However, the response also states that independent testing of the shunt and undervoltage attachments is performed at 18-month intervals; it is not clear from the response that the plant is designed to permit independent on-line verification of operability of the shunt and undervoltage attachments.