Interim Deficiency Rept CP-86-52 Re Cable Tray Splices/ Connections.Initially Reported on 860725.Testing Program Initiated to Evaluate Conditions.Next Rept Will Be Submitted by 861212
ML20211F700
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/21/1986
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
.EFR-861021-1, CP-86-52, TXX-6053, NUDOCS 8610310230
Download: ML20211F700 (2)


Text

" DALLAS-SLIC TEL No.

214 979 8700 Oct 21.86 17:29 P.04 Lo

  1. TXX-6053 P'

F1 e # 10110 Q

903.11 TEXAS UTILITIES GENERATING COMPANY SEYWAY TOWER. e00 NOttTH OLtys evaart Lp, es. DatJ.A4 PEXA0 f6868

  • E^,", Lf?.Unt,

%[@@[MOWIMf !

'li j j i i

Mr. Eric H. Johnson, Director gggg

. ii Division of Reactor Safety and Projects 1

/

j 1 U. S. Nuclear Regulatory Commission i

1 611 Ryan Plaza Drive, Suite 1000 j

Arlington, TX 76012

SUBJECT:

COMANCHE FEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 CA8LE TRAY SPLICES / CONNECTIONS SDAR: CP-86-52 (INTERIN REPORT)

Dear Mr. Johnson:

On July 25, 1986, we verbally notified your Mr. I. Barnes of a deficiency involving the splices / connections used for cable trays in Units I and 2.

This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e). We have submitted an interim report logged TXX-4981, dated August 22, 1986.

This issue was identified during as-built activities for the Unit 2 Cable Tray Hangers. We have established that splices / connections used for some tray types and sizes were not installed in accordance with specified splice patterns as defined by the cable tray manufacturer or approved design change documents.

I Although the deviations do not appear to impair the functional capability of the trays, steps are being taken to provide a more definitive determination.

A testing program is being initiated to evaluate these conditions. Completien of this testing is estimated for mid November,1986.

Evaluation of test results and identification of corrective actions, if required, will be performed at that time.

puo 188 n 88688 6 j

S PDR i

A NV80KM D9 TEMAS L73UTERC KLECTRIC COM9ANY D

I DALLAS-SLIC TEL No.

214 979 8700 Oct 21.86 17:29 P.05 7

TXX-6053 October 21, 1986 Page 2 Sased upon this schedule we anticipate submitting our next report by December 12, 1986.

Very trul yours, b

W. G. Counsil By:

G.S. Keeley 7

Manager, Nuclear LicVnsing JCH/amb c-NRCRegionIV(0+1 copy)

Director, Inspection & Enforcement (15 copies)

U. S. Nuclear Regulatory Commission Washington, D.C.

20555 e