Monthly Operating Rept for Jan 1987
ML20211C799
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 01/31/1987
From: Bregni L, Lenart R
DETROIT EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NP870101, NUDOCS 8702200220
Download: ML20211C799 (5)


Text

- - _ _ _ _ _ _ _ _ - _ _ _ _

OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY L. P. Bregni

! DATE February 13, 1987 TELEPHONE (313)586-5313 OPERATING STATUS

1. UNIT NAME: Fermi 2 l Notes l
2. REPORTING PERIOD: January l l 3 LICENSED THERNAL POWER (NWt): 3292 l l
4. NAMEPLATE RATING (GROSS NWe): 1215 l l
5. DESIGN ELECT RATING (Net NWe): 1093 I I
6. MAX DEPENDABLE CAP (GROSS MWe): # l l 7 MAX DEPENDABLE CAP (Net NWe): # l l
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE y LAST REPORT, GIVE REASONS: None 9 POWER LEVEL TO WHICH RESTRICTED, IF ANY (NWe Net): 218.6
10. REASONS FOR RESTRICTION, IF ANY: Fermi 2 is in the startup test phase and is currently authorized to operate not in excess of 20% of rated thermal power. (Ref. J. G. Keppler letter of September 12, 1986)

THIS MONTH YR TO DATE CUMULATIVE

11. HRS IN REPORTING PERIOD 744 744 3,177.9
12. HRS REACTOR WAS CRITICAL 361.7 361.7 1,231.5
13. REACTOR RESERVE SHUTDOWN HRS 0 0 0

, 14. HOURS GENERATOR ON-LINE 54.1 54.1 183 6

15. UNIT RESERVE SHUTDOWN HOURS 0 0 0
16. GROSS THERMAL ENERGY GEN (NWH) 124,128 124,128 347,376
17. GROSS ELECT ENERGY GEN (NWH) 5,620 5,620 16,070
18. NET ELECT ENERGY GEN (NWH) -7,695 -7,695 -33,654
19. UNIT SERVICE FACTOR N/A N/A N/A
20. UNIT AVAILABILITY FACTOR N/A N/A N/A
21. UNIT CAP FACTOR (USING MDC NET) N/A N/A N/A
22. UNIT CAP FACTOR (USING DER NET) N/A N/A N/A
23. UNIT FORCED OUTAGE RATE N/A N/A N/A
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)

Maintenance Modification Outage, Completion of Test Condition 2,14 days

25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED

~

INITIAL CRITICALITY 06/20/85 06/21/85 INITIAL ELECTRICITY 10/01/86 09/21/86 COMMERCIAL OPERATION 05/01/87 0D0 kDO 5 0 341 n PDR '

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-341 i

UNIT FERMI 2 DATE February 13, 1987 COMPLETED BY L. P. Bregni TELEPHONE (313) 586-5313 MONTH January DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 95.3 17 0 2 80.9 18 0 3 0 19 0 4 0 20 0 5 59.5 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 c12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 68.3 16 0

- _ - - - _ - - _ - _ _ _ _ _ - - . - - _ _ - . _ - _ _ _ . _ _ . _ - . _ _ ~ _ _ . - _ . _ . . _ _ _ _ _ _ _ _ _ - - . -_- . _ _ _ - - _ - . _.

l0 UNIT SHUTDOMNS AND POMER REDUCTIONS DOCKET NO. 50-341 DATE February 13. 1987.

UNIT NAME Fermt 2 COMPLETED BY L. P. Bregni TELEPHONE (313)586-5313 REPORT MONTH January i I I I I i l l METHOD OF l LER SYS COMP l CAUSE & CORRECTIVE i li NO. l DATE TYPE DUR REASON SHUTTING DOWN l NO. CODE CODE L ACTION TO PREVENT  ;

l (1) (HRS) (2) THE REACTOR (4) (S) RECURRENCE i l (3) 1 87-01 , 870108 ! F l 382.3 l A 2 N/A CC PIPEXXA . Shut down to inspect and repair l l l l l melds on instrument taps attached l to the main steam Ilnes. Outage l l scope was expanded to include work 3 l on the Control Center HVAC l l chiller.

l l I I (1) F: FORCED (2) REASON: (3) METHOD: (4) EXHIBIT G - INSTRUCTIONS S: SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA 8 - MAINTENANCE OR TEST 2 - MANUAL SCRAM ENTRY SHEETS FOR LICENSEE C - REFUELING 3 - AUTOMATIC SCRAM EVENT REPORT (LER) 8ILS D - REGULATORY RESTRICTION 4- CONTINUED (NUREG-0161)

E - OPERATOR TRAINING & LICENSE EXAMINATION 5 - REDUCED LOAD F - ADMINISTRATIVE 9 - OTHER

, G.- OPERATIONAL ERROR (EXPLAIN) 7 H - OTHER (EXPLAIN) (5) EXHIBIT I - SAME SOURCE

OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY L.P.Bregni DATE February 13, 1987 TELEPHONE (313)586-5313 _

OPERATING STATUS

1. UNIT NAME: Fermi 2 l Notes l
2. REPORTING PERIOD: December l l 3 LICENSED THERMAL POWER (MWt): 3292 l l
4. NAMEPLATE RATING (GROSS MWe): 1215 l l S. DESIGN ELECT RATING (Net MWe): 1093 l l
6. MAX DEPENDABLE CAP (GROSS MWe): # l l 7 MAX DEPENDABLE CAP (Net MWe): # l l
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE

~IAST REPORT, GIVE REASONS: None 9 POWER LEVEL TO WHICH RESTRICTED, IF ANY (HWe Net): 218.6

10. REASONS FOR RESTRICTION, IF ANY: Fermi 2 is in the startup test phase and is currently authorized to operate not in excess of 20% of rated thermal power. (Ref. J. G. Keppler letter of September 12, 1986)

THIS MONTH YR TO DATE CUMULATIVE

11. HRS IN REPORTING PERIOD 744 2,433 9 2,433.9
12. HRS REACTOR WAS CRITICAL 308.9 869.8 869.8
13. REACTOR RESERVE SHUTDOWN HRS 0 0 0
14. HOURS GENERATOR ON-LINE 33 7 129.5 129.5 1h.UNITRESERVESHUTDOWNHOURS 0 0 0
16. GROSS THERMAL ENERGY GEN (HWH) 55,680 223,248 223,248
17. GROSS ELECT ENERGY GE4 (HWH) 2,810 10,450 10,450
18. NET ELECT ENERGY GEN (MWH) -8,693 -25,959 -25,959
19. UNIT SERVICE FACTOR N/A N/A N/A
20. UNIT AVAILABILITY FACTOR N/A N/A N/A
21. UNIT CAP FACTOR (USING MDC NET) N/A N/A N/A
22. UNIT CAP FACTOR (USING DER NET) N/A N/A N/A
23. UNIT FORCED OUTAGE RATE N/A N/A _

N/A

24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)

None

25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 'N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY 06/20/85 06/21/85

! INITIAL ELECTRICITY 10/01/86 09/21/86 f COMMERCIAL OPERATION 05/01/87 l

I

~

EN0ld7" February 13, 1987 Detroit r.,-4 2 NP870101 Edison EEE " c:1.

U. S. Nuclear Regu'latory' Commission Attention: Document Control Desk washington, D.C. 20555

Reference:

Fermi 2 NRC Docket No. 50-341 A NRC Operating License No. NPF-43

Subject:

Monthly Operating Status Report for Januarv. 1987 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for January, 1987. This report includes the Operating Data Report, Average Daily Unit Power Level, and the Summary of Unit Shutdowns and Power Reductions identified in NRC Regulatory Guide 1.16 and Fermi 2 Technical Specification 6.9.1.6.

This report also includes a revised Operating Data Report sheet for December, 1986. The report has been revised to correct the value for Hours Generator On-Line.

If you have any questions, please contact us.

Sincerely,

,}-

( R. S. Lenart Plant Manager Enclosure cc: J. R. Eckert D. R. Hahn J. G. Keppler W. G. Rogers J. J. Stefano G. C. Wright 'f

.