Text
-
MAY 231986 Docket Nos.: 50-416 DISTRIBUTION:
and 50-417
' Docket File; BGrimes NRC PDR JPartlow Local PDR LKintner Mr. Oliver D. Kingsley, Jr.
PD#4 Rdg P0'Brien Vice President, Nuclear Operations RBernero ACRS (10)
Mississippi Power and Light Company Young, OELD CGoodman P.O. Box 23054 EJordan Jackson, Mississippi 39205
Dear Mr. Kingsley:
SUBJECT:
GRAND GULF NUCLEAR STATION (GGNS) UNITS 1 AND 2 - SHIFT TECHNICAL ADVISOR STAFFING By letter dated April 10, 1986, Mississippi Power and Light Company requested approval of a change to its commitment regarding the assignment of shift technical advisors to operating shifts. During its review of this submittal, the NRC staff found that additional information as described in the enclosure is needed to complete its review.
In order to meet the schedule for review of this licensing action you are requested to provide the information identified in the enclosure by June 15, 1986.
If you cannot meet this date, please advise me within 7 days of receipt of this letter.
The reporting and/or recordkeeping requirements contained in this letter affect fewer than ter, respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely,
%fnal signed by Lester L. Kintner, Project Manager BWR Project Directorate No. 4 Division of BWR Licensing
Enclosure:
As stated i
cc w/ enclosure:
See next page l
l l
j0FC :PD#4 L
- PD#4: DBL
[:
f----:----------f.-----------:------------:------------:------------:-----------
lNAME :LK ner l-----:-------/dn:WButler DATE :503/86
- 5/2786 B606120003 860523 PDR ADOCK 05000416 l
P PDR
!(pa arc o
q'o UNITED STATES
' g
' g NUCLEAR REGULATORY COMMISSION E
WASH WGTON, D. C. 20555 8
(
o
\\..... p#
MAY 2 31986 Docket Nos.: 50-416 and 50-417 Mr. Oliver D. Kingsley, Jr.
Vice President, Nuclear Operations Mississippi Power and Light Company P.O. Box 23054 Jackson, Mississippi 39205
Dear Mr. Kingsley:
SUBJECT:
GRAND GULF NUCLEAR STATION (GGNS) UNITS 1 AND 2 - SHIFT TECHNICAL ADVISOR STAFFING By letter dated April 10, 1986, Mississippi Power and Light Company requested approval of a change to its commitment regarding the assignment of shift technical advisors to operating shifts. During its review of this submittal, the NRC staff found that additional information as described in the enclosure is needed to complete its review.
In order to meet the schedule for review of this licensing actior,you are requested to provide the information identified in the enclosure by June 15, 1986.
If you cannot meet this date, please advise me within 7 days of receipt of this letter.
The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, S-Lester L. Kintner, Project Manager BWR Project Directorate No. 4 Division of BWR Licensing
Enclosure:
As stated cc w/ enclosure:
See next page e
4 Mr. Oliver D. Kingsley, Jr.
Mississippi Power & Light Company Grand Gulf Nuclear Staiten cc:
Robert B. McGehee, Esquire The Honorable William J. Gaste, Jr.
Wise, Carter, Child, Steen and Caraway Attorney General P.O. Box 651 Cepartment of Justice Jackscn, Mississippi 39205 State of Louisiana Baton Rouge, Louisians 7C804 Nicholas S. Reynolds, Esquire Bishop, Liberman, Cook, Purcell Office of the Governor and Reynolds
. State of Mississippi 1200 17th Street, N.W.
Jackson, Mississippi 39201 Washington, D. C.
20036 Attorney General Mr. Ralph T. Lally Gartin Building Manager of Quality Assurance Jackson, Mississippi 39205 Middle South Services, Inc.
P.O. Box 61000 Mr. Jack McMillan, Director New Orleans, Louisiana 70161 Division of Solid Waste Management Mississippi Department of Natural Mr. Larry F. Dale, Director Rescurces Nuclear Licensing and Safety Bureau of Follution Control Mississippi Power & Light Company Post Office Box 10385 P.O. Box 23054 Jackson, Mississippi 39209 Jackson, Mississippi 39205 Alton B. Cobb, M.D.
Mr. R. W. Jackson, Project Engineer State Health Officer Bechtel Power Corporation State Board of Health 15740 Shady Grove Road P.O. Box 1700 Gaithersburg, Maryland 20877-1454 Jackson, Mississippi 39205 Mr. Ross C. Butcher President Senior Resident Inspector Claiborne County Board of Supervisors U.S. Nuclear Regulatory Commission Port Gibson, Mississippi 39150 Route 2, Box 399 Port Gibson, Mississippi 39150 Mr. Ted H. Cloninger Vice President, Nuclear Engineering l
Regional Administrator, Region II and Support U.S. Nuclear Regulatory Commission, Mississippi Power & Light Company 101 Marietta Street, N.W., Suite 2900 Post Office Box 23054 Atlanta, Georgia 30323 Jackson, Mississippi 39205 Mr. J. E. Cross Grand Gulf Nuclear Station Site Director Mississippi Power & Light Company P.O. Box 756 Port Gibson, Mississippi 39150 Mr. C. R. Hutchinson GGNS General Manager Mississippi Power & Light Company Post Office Box 756 Port Gibson, Mississippi 39150 l
ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION RELATING TO A PROPOSED CHANGE TO A COMMITMENT OF MISSISSIPPI POWER AND LIGHT COMPANY GRAND GULF NUCLEAR STATION By letter dated April 10, 1986, Mississippi Power and Light Company (MP&L) requests approval to place the Grand Gulf Nuclear Station (GGNS) Shift Technical Advisors (STAS) on a rotation different frca that of the operations shift rotation. Currently GGNS is committed to a " team concept" where the STA is assigned to each of five orerating shifts at GGNS. The connitment, made in a letter dated November 21,1983 from 0. D. Kingsley of MP&L to J. P. O'Reilly of NRC, stated that the STAS will be assigned to a particular shift and will train on the training rotation with that shift as appropriate.
In compliance with the commitments MP&L made, the STAS have been assigned to a particular shift and the STAS have remained with that shift.
However MP&L is now requesting to depart from the " team concept" and allow the STAS to be on a different shift rotation. This departure would allow MP&L to use a much larger or smaller number of STA qualified engineers to participate in the STA shift rotation.
In order that the staff can evaluate this proposed departure, MP&L needs to address the " Policy Statement On Engineering Expertise On Shift." The Policy Statement became effective on October 28, 1985 and presents the policy of NRC with respect to engineering expertise on shift. Specifically, Option 2 of the Policy Statement (GGNS, we believe follows Option 2) states that the dedicated STA thould assume an active role in shift activities.
For example, the STA shnuld review plant logs, participate in shift turnover activities, and maintain an awareness of plant configuration and status. Therefore, we request that the licensee address how the STA will assume an active role in shift activities.