marco Jg UNITED STATES g
NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 205S5
\\....+/
BALTIM0RE GAS AND ELECTRIC COMPANY DOCKET NO. 50-317 CALVERT CLIFFS NUCLEAR POWER PLANT UNIT N0. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 123 License No. DPR-53 1.
The Nuclear Regulatory Comission (the Comission) has found that:
A.
The application for amendment by Baltimore Gas & Electric Company (thelicensee)datedApril 14, 1986 as supplemented July 24, 1986, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Comission;
^'
C.
There is reasonable assurance (1) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.
l 8610100688 861006 PDR ADOCK 05000317 P
. E.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-53 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No.123, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
3.
This license amendment is effective as of the date of its issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/ (hk %
^^
.7 Ashok C. Thadani, Director PWR Project Directorate #8 Division of PWR Licensing-B
Attachment:
Changes to the Technical Specifications Date of Issuance: October 6, 1986
ATTACHMENT TO LICENSE AMENDMENT N0.123 FACILTIY OPERATING LICENSE N0. DPR-53 DOCKET N0. 50-317 Replace the following pages of the Appendix "A" Technical Specifications with the enclosed pages. The revised pages are identified by amendment number and contain vertical lines indicating the areas of change. The corresponding overleaf pages are provided to maintain document completeness.
Remove Pages Insert Pages 3/4 8-1 3/4 8-1 3/4 8-2 3/4 8-2 3/4 8-3 3/4 8-3 3/4 8-4 3/4 8-4 l
9 i
k
3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 1
3.8.1.1 As a minimum, the following A.C. electrical powe'r sources shall be OPERABLE:-
a?
Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system consisting of either:
1.
Two 500 kV offsite power circuits, or as necessary
\\
- 2. -
The 69 kV SMECO offsite power circuit described in the January 14, 1977 Safety Evaluation and one 500 kV offsite power circuit; and b.
Two separate and independent diesel generators (one of which may be a swing diesel generator capable of serving.either Unit 1 or Unit 2) with:
I 1.
Separate day fuel tanks containing a minimum volume of 375 gallons of fuel for each diesel generator, 2.
A common fuel storage system consisting of two independent storage tanks each containing a minimum volume of 18,250 gallons of fuel, and 3.
A separate fuel transfer pump for each diesel generator.
APPLICABILITY: MODES 1, 2, 3 and 4.
f ACTION:
i i
a.
With two offsite circuits of the above required A.C. electrical power i
sources inoperable, demonstrate the OPERABILITY of the remaining A.C.
sources by perfoming Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and 4.8.1.1.2.a.4 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless the diesel generators are already operating.
Restore at least two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
b.
With one diesel generator inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by perfoming Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, and Surveillance Requirement 4.8.1.1.2.a.4 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Restore i
two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
CALVERT CLIFFS - UNIT 1 r
3/4 8-1 Amendment No. 55,92 JJJ,l#N 123 1
.m ELECTRICAL POWER SYSTEMS I
LIMITING CONDITION FOR OPERATION (Continued)
ACTION:
(Continued) c.
With two offsite circuits and one diesel generator of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by'perfonning Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter and Surveillance Requirement. 4.8.1.1.2.a.4 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, unless the diesel generators are already operating. Restore at least i
one of the inoperable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Restore at least two offsite circuits i
and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from the time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
d.
With three of the above required offsite A.C. circuits inoperable.
l demonstrate the OPERABILITY of two diesel generators by performing l
Surveillance Requirement 4.8.1.1.2.a.4 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> unless the diesel generators are already operating;' restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be i
in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. With only one off-site source restored.. restore at least two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />' from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the follow-ing 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
e.
With two of the above required diesel generators inoperable, demonstrate i
the OPERABILITY of two offsite A.C. circuits by perfonning Surveillance l
Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable diesel generators to j'
OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
Restore at least two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in at least H0T STANDBY within
...h the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
f.
With one Diesel Fuel Oil Storage Tank inoperable, demonstrate the OPERABILITY of the remaining tank by:
- 1) perfonning Surveillance Requirement 4.8.1.1.2.a.2 (verifying 36,500 gallons) within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, and E) verifying the flow-path from the OPERABLE fuel oil storage tank to the diesel generators within one hour.
Restore two storage tanks to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least H0T STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
(NOTE:
If the tank is inoperable, maintain an 8,000 gallon alternate fuel source onsite.)
This Action Statement is not applicable for the following conditions:
- 1) when #21 Diesel Fuel Oil Storage Tank is inoperable during the period from April 1 through September 30 due to the higher probability i
CALVERT CLIFFS - UNIT 1 3/4 8-2 Amendment No. EE,#,JJJ,yyy,123 l
ELECTRICAL POWER SYSTEMS LIMITING CONDITION FOR OPERATION (Continued) of tornado occurrences during this time frame and 2) when two Diesel Fuel Oil Storage Tanks are inoperable. Action statement e is applicable for these conditions.
SURVEILLANCE REQUIREMENTS 4.8.1.1.1.
Each required independent circuit between the offsite transmission network and the onsite Class lE distribution system shall be:
a.
Demonstrated OPERABLE, as follows:
1.
For each 500 kV offsite circuit, at least once per 7 dais by verifying correct breaker alignments arid indicated power avail-ability.
2.
For the 69 kV SMECO offsite power circuit, within one hour of substitution for a 500 kV offsite power circuit, and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter during use by verifying correct breaker alignments and indicated power availability; and b.
Demonstrated OPERABL'E at least once per 18 months during shutdown by manually transferring unit power supply from the normal circuit to the alternate circuit.
4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:
At least once per 31 days on a STAGGERED TEST BASIS by:
a.
1.
Verifying the fuel level in the day fuel tank.
2.
Verifying the fuel level in the fuel storage tank.
3 3.
Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day tank.
4.
Verifying the diesel starts and accelerates to at least 900 rpm with generator voltage and frequency at 4160 1 420 volts and 60 1 1.2 Hz, respectively.*
5.
Verifying the generator is synchronized, loaded to > 1250 kW, and operates for > 60 minutes.
6.
Verifying the diesel generator is aligned to provide standby power to the associated emergency busses.
- All engine starts for the purpose of this Surveillance Requirement may be i
preceded by an engine prelube period and/or other wannup procedures reconmended by the manufacturer so that mechanical wear and stress on the diesel engine is minimized.
CALVERT CLIFFS - UNIT 1 3/4 8-3 Amendment No. JM,JJJ,777,123
ELECTRICAL POWER SYSTEMS
~
SURVEILLANCE REQUIREMENTS (Continued) 1 7.
Verifying that the automatic load sequencer timer is OPERABLE with' the interval between each load block within + 10% of its design interval.
b.
At least once per 92 days by verifying that a sample of diesel fuel from the fuel storage tank is within the acceptable limits specified in Table 1 of ASTM D975-81 when checked for viscosity, water and sediment.
c.
At least once per 184 days by verifying the diesel starts from ambient condition and accelerates to at least 900 rpm in < 10 seconds.
d.
At least once per 18 months by:
1.
Subjecting the diesel to an inspection in accordance with proce-dures prepared in conjunction with its manufacturer's recomenda-tions for this class of standby service.
2.
Verifying the generator capability to reject a load of > 500 hp without tripping.
3.
Simulating a loss of offsite power in conjunction with a safety injection actuation test signal, and:
a)
Verifying de-energization of the emergency busses and load shedding from the emergency busses.
b)
Verifying the diesel starts from ambient condition on the auto-start signal, energizes the emergency busses with pennanently connected loads, energizes the auto-connected emergency loads through the load sequencer and operates for
> 5 minutes while its generator is loaded with the emergency
- Toads, c)
Verifying that the high jacket coolant temperature and low jacket coolant pressure trips are automatically bypassed on a Safety Injection Actuation Signal.
4.
Verifying the diesel generator operates for > 60 minutes while loaded to > 2500 kW.
5.
Verifying that the auto-connected loads to each diesel generator do not exceed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 2700 kW.
CALVERT CLIFFS - UNIT 1 3/4 8-4 Amendment No. JJJ.//),123
~
c ue f
UNITED STATES y
') w g
NUCLEAR REGULATORY COMMISSION j
WASHWGTON D. C.20555 r,A...
~
~,...../
s I
BALTIM0RE GAS AND ELECTRIC COMPANY DOCKET N0. 50-318 CALVERT CLIFFS NUCLEAR POWER PLANT UNIT NO. 2 AMENDMENTTOFACILITYOP5RATINGLICENSE Amendment No.105 License No. DPR-69 1.
The Nuclear Regulatory Comission (the Comission) has found that:
A.
The application for amendment by Baltimore I!as & Electric Company (the licensee) dated April 14, 1986 as supplemented July 24, 1986, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Comission's rules and regulations set forth in 10 CFR Chapter I;.
B.
The facility will operate in confonnity with the application, the provisions of the Act, and the rules and regulations of the Comission; 1
,a C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulatiors and all. applicable requirements have been satisfied.
Y 4
___m_...--,-,--._.-.--.--..__.__--_,%..-_
__,.-__m..-_m..m..,___.-c.._,,.
2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.2 of Facility Operating License No. DPR-69 is hereby amended to read as follows:
2.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No.105, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
3.
This license amendment is effective as of the date of its issuance.
FOR THE NUCLEAR REGULATORY COMMISSION l
- f*{Y2A h]&
Ashok. Thadani, Director FWR Project Directorate #8 Division of PWR Licensing-B
Attachment:
Changes to the Technical Specifications Date of Issuance: October 6, 1986
I ATTACHMENT TO LICENSE AMENDMENT N0. 105 FACILTIY OPERATING LICENSE NO. DPR-69 DOCKET NO. 50-318 Replace the following pages of the Appendix "A" Technical Specifications with the enclosed pages. The revised pages are identified by amendment number and contain vertical lines indicating the areas of change. The corresponding overleaf pages are provided to maintain document completeness.
Remove Pages Insert Pages 3/4 8-1 3/4 8-1 3/4 8-2 3/4 8-2 3/4 8-3 3/4 8-3 3/4 8-4 3/4 8-4 a
i e
3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES
~
OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
~
a.
Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system consisting of either:
1.
Two 500 kV offsite. power circuits Dr as necessary 2.
The 69 kV SMECO offsite power circuit described in the January 14, 1977 Safety Evaluation and one 500 kV offsite power circuit; and b.
Two separate and independent diesel generators (one of which may be a swing diesel generator capable of serving either Unit 1 or Unit 2) with:
I 1.
Separate day fuel tanks containing a minimum volume of 375 gallons of fuel for each diesel generator, 2.
A common fuel storage system consisting of two independent storage tanks each containing a minimum volume of 18,250 gallons of fuel, and 3.
A' separate fuel transfer pump for each diesel generator.
APPLICABILITY: MODES 1, 2, 3 and 4.
ACTION:
WithtwooffsitecircuitsoftheaboverequiredA.C.electricalpower a.
sources inoperable, demonstrate the OPERABILITY of the remaining A.C.
sources by perfoming Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and 4.8.1.1.2.a.4 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless the diesel generators are already operating.
Restore at least two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
b.
With one diesel generator inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by perfonning Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, and Surveillance Requirement 4.8.1.1.2.a.4 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Restore two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
CALVERT CLIFFS - UNIT 2 3/4 8-1 Amendment No.6,40,73,94,)A3,105
ELECTRICAL POWER SYSTEMS LIMITING CONDITION FOR OPERATION (Continued)
ACTI_0N:
(Continued)
With two offsite circuits and one diesel generator of the above c.
required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by perfonning Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter and Surveillance Requirement 4.8.1.1.2.a.4 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, unless the diesel generators are already operating. Restore at least one of the inoperable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Restore at least two offsite circuits and two diesel generators to. OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from the time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
d.
With three of the above required offsite A.C. circuits inoperable, demonstrate the OPERABILITY of two diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. With only one off-site source restored, restore at least two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the follow-ing 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
With two of the above required diesel generators inoperable, demonstrate e.
the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hcur and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
Restore at least two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
f.
With one Diesel Fuel Oil Storage Tank inoperable, demonstrate the OPERABILITY of the remaining tank by:
- 1) perfonning Surveillance Requirement 4.8.1.1.2.a.2 (verifying 36,500 gallons) within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, and 2) verifying the flow-path from the OPERABLE fuel oil storage tank to the diesel generators within one hour.
Restore two storage tanks to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
(NOTE: If the tank is inoperable, maintain an 8,000 gallon alternate fuel source onsite.)
This Action Statement is not applicable for the following conditions:
- 1) when #21 Diesel Fuel Oil Storage Tank is inoperable during the period from April 1 through September 30 due to the higher probability CALVERT CLIFFS - UNIT 2 3/4 8-2 Amendment No. 49.73,pp,M8,105
ELECTRICAL POWER SYSTEMS
~
LIMITING CONDITION FOR OPERATION (Continued)
~
of tornado occurrences during this time frame and.2) when two Diesel Fuel Oil Storage Tanks are inoperablel Action statement e is applicable for these conditions.
SURVEILLANCE REQUIREMENTS 4.8.1.1.1.
Each required independent circuit between the offsite transmission network and the onsite Class lE distribution system shall be:
a.
Demonstrated OPERABLE, as fo.11ows:
1.
For each 500 kV offsite. circuit, at least once per 7 days by verifying correct breaker alignments and indicated power avail-ability.
2.
For the 69 kV SMECO offsite power circuit, within one hour of substitution for a 500 kV offsite power circuit, and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter during use by verifying correct breaker alignments and indicated power availability; and b.
Demonstrated OPERABLE at least once per 18 months during shutdown by manually transferring ur.!t power supply from the nomal circuit to the alternate circuit.
- 4. 8.1.1. 2 Each diesel generator shall be demonstrated OPERABLE:
At least once per 31 days on a STAGGERED TEST BASIS by:
a.
1.
Verifying the fuel level in the day fuel tank.
\\
2.
Verifying the fuel level in the fuel storage tank.
3.
Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day tank.
4.
Verifying the diesel starts and accelerates to at least 900 rpm with generator voltage and frequency at 4160 + 420 volts and 60 + 1.2 Hz, respectively.*
5.
Verifying the generator is synchronized, loaded to > 1250 kW, and operates for > 60 minutes.
6.
Verifying the diesel generator is aligned to provide standby power to the associated emergency busses.
t
- All engine starts for the purpose of this Surveillance Requirement may be preceded by an engine prelube period and/or other wannup procedures reconsnended by the manufacturer so that mechanical wear and stress on the diesel engine is minimized.
CALVERT CLIFFS - UNIT 2 3/4 8-3 Amendment No. 92,95,/[/,105 l
ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)
I 7.
Verifying that the automatic load sequencer timer is OPERABLE with the interval between each load block within + 10% of its design interval.
~
b.
At least once per 92 days by verifying that a sample of diesel fuel from the fuel storage tank is within the acceptable limits specified in Table 1 of ASTM D975-81 when checked for viscosity, water and sediment.
At least once per 184 days by verifying the diesel starts from ambient c.
condition and accelerates to at least 900 rpm in < 10 seconds.
d.
At least once per 18 months by:
1.
Subjecting the diesel to an inspection in accordance with proce-i dures prepared in conjunction with its manufacturer's recomenda-tions for this class of standby service.
2.
Verifying the generator capability to reject a load of > 500 hp without tripping.
3.
Simulating a loss of offsite power in conjunction with a safety injection actuation test signal, and:
a)
Verifying de-energization of the emergency busses and load shedding from the emergency. busses.
b)
Verifying the diesel starts from ambient condition on the auto-start signal, energizes the emergency busses with permanently connected loads, energizes the auto-connected l
l emergency loads through the load sequencer and operates for
> 5 minutes while its generator is loaded with the emergency Toads.
c)
Verifying that the high jacket coolant temperature and low Jacket coolant pressure trips are automatically bypassed on a Safety Injection Actuation Signal.
Verif' ing the diesel generator operates for > 60 minutes while 4.
y loaded to > 2500 kW.
5.
Verifying that the auto-connected loads to each diesel generator do not exceed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 2700 kW.
CALVERT CLIFFS - UNIT 2 3/4 8-4 Amendment No. H./l/}8,105 l