Monthly Operating Repts for July 1999 for Catawba Nuclear Station,Units 1 & 2
ML20210S289
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 07/31/1999
From: Robert Williams
DUKE POWER CO.
To:
Shared Package
ML20210S279 List:
References
NUDOCS 9908180057
Download: ML20210S289 (6)


Text

Operating Data Report Docket No. 50-413 Date Aunust 12.1999 Completed By Roner Williams

< . Telephone 704-382-5346 Operating Status

1. Unit Name: Catawba 1
2. R: porting Period: July 1,1999. July 31,1999
3. Licensed Thermal Power (MWt): 3411 Notes:
  • Nameplate
, 4. %meplate Rating (Gross MWe)
1305
  • Rating (GrossMWe) l 5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power
7. Maximum Dependable Capacity (Net MWe): 1129 factor per Page 111,
8. lf Changes Occured in Capacity Ratings (items Number 3-7) Since Last Report, Give Reasons: 6.
9. Power level To Which Restricted, if Any (Net MWe):

~ 10. Reason for Restrictions, if any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 5087.0 123504.0
12. Number of Hours Reactor was Critical 744.0 4333.1 98543.7
13. Reactor Reserve Sh'u tdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 4315.3 97104.1
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2533176 80627103 384885307 l

= 17. Gross Electrical Energy Generated (MWH) 897068 5148836 112883973 l

18. Net Electrical Energy Generated (MWH) 850284 4872696 106315063

.19. Unit Service Factor 100.0 84.8 78.6 !

20. Unit Availability Factor 100.0 84.8 78.6
21. Unit Capacity Factor (Using MDC Net) 101.2 84.8 76.1 j

' 22. Unit Capacity Factor (Using DER Net) 99.8 -83.7 75.2 l

23. Unit Forced Outage Rate 0.0 0.0 7.0
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each) i
25. If Shutdown At End Of Report Period, Estimated Date of Stantup
26. Units in Test Status (Prior to Commercial Operation) -

Forcast Achieved initial Criticality i Initial Electricity Commercial Operation l

l PDR ADOCK 05000413 R PDR 3A - 8/12/99

1 f

o

_ 1 e

g - -

a -

P '

e c

n m a

e r

r c

r S u

c

/

e ip n o r i R T au t

t n l a n e u i v n t n

e a r o P

o MC - -

t n 2 4 i

o t

c m A a r

e c v S i

/)

t c ipn e ri r

r Tl ap o c x C d l iaE t

d ou a n

a e

ht n m e a uth toe(r s

u a

MMAO

) - - -

C 2

( 1 35 t

r 9 de po 9 s e .

S 9 nR o N 1 e

ic n N t

y W l u

L ev O J E D  :

I H h b T fo/ X t n n N

H S O d R o n o i t

o -

M he w M a T in t

T o e I

N R Md

)

t u

h t

m a

x U O 2 h r E P ( S o e E f s )

R n n e i a

c n s i l p

o s e L

/ x a g g E e a n ( )

R

)

t u in e rroian ia v 1

( O r T aE ir t l r p x r t r n t ois oE t (

o s a n a r r ir e ii. uro o e pd pt meh mH N OA OO - -

D - -

9 s EFGH _

9 _

9 m 6 d .

ia 4 e .

eMl 1

1

. l l

3 5-u _

2 i d 3 b a 1 t W 2 8

p ue i

yF h c )

n s T r 3 1 w 4 ta n e u - S i a

n 4- F - l 0 a u o 0

- p _

5 C A R7 S x n E t s o .

OEEYE

(

e r T e i t

c NMTBN A O e l i

u r o

i t

r s

e TA DDE H EN P D t

a f t

a ec r

y K n na gro CIT TE EL e n nt ON LE y n mei o p t lel a DU r s iuiun g u L

P T a a e q af e e m

RE MRR M o O N m u ) - - - -

C S 1

( ABCD

6 8 MONTHLY REFUELING INFORMATION REOUEST

1. Facility name: _ Catawba Unit 1 2 Scheduled next refueling shutdown: October 2000
3. Scheduled restart following refueling: November 20QQ THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

~ 5. Scheduled date(s) for submitting proposed licensing action and supporting information.

6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 191 '

(b) in the spent fuel pool: IM

8. Present licensed fuel pool capacity: Mll  ;

Size of requested or planned increase: _-- i

9. Projected date oflast refueling which can be accommodated by present license capacity: '

November 2009 I

DUKE POWER COMPANY DATE: August 12.1999 Name of

Contact:

R. A. William < Phone: (7041- 382-5346 4

Operating Data Report I Docket No. 50-414 Date Aucust 12.1999 Completed By Rocer Williams

. ,' Telephone 704-382-5346 Operatinst Status

1. Unit Name: Catawba 2
2. Reporting Period: July 1,1999-July 31,1999
3. Licensed nermal Power (MWt): 3411 Notes:
  • Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power
7. Maximum Dependable Capacity (Net MWe): 1129 factor per Page 111,
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons: G-M20.
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions,if any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 5087.0 113520.0
12. Number of Hours Reactor was Critical 744.0 4152.1 91879.2
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 4084.4 90537.3
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Hermal Energy Generated (MWH) 2534158 94444016 375993951
17. Gross Electrical Energy Generated (MWH) 902006 4964990 105020696
18. Net Electrical Energy Generated (MWH) 857690 4680062 99081682
19. Unit Service Factor 100.0 80.3 79.8
20. Unit Availability Factor 100.0 80.3 79.8
21. Unit Capacity Factor (Using MDC Net) 102.1 81.5 77.2
22. Unit Capacity Factor (Using DER Net) 100.7 80.3 76.2
23. Unit Forced Outage Rate 0.0 19.7 8.2
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If Shutdown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A 8/12/99

1 f m o 2 1 1

/

_  : 8 e

g -

a -

  • c P
  • 3 e

c n m e a r

r c r

u S

/

c e

p n R . ir io t T au t n l a n

- e ui v t e

r n n a o P

o MC - -

t n 2 4 i

o t

c m A a r

e c v S p )n i /

t c

e i ri r

r Tl a o cpx C d l iaE t

d n

a h t

o an moe(r u

e e a uth t s

u a

MMAO

) - - -

C 2

( 1 35 t

r 9 d o p

9 e S 9 s nR eo .

1 W e

. c n N t

M l y

u i

L ev O J E D  :

T H h U T fo/ X t n n N o H O d R o n i o

S M t a

T M he wo t n T e i I

N R Md

)

t u

h t

m a

O x U 2 h r E P

E

( S f

o e s )

R n n e

c i

a n s i lp o

s e L

/ x a g g E e a n ( )

R t u ian ev roi n

) i r a 1

( O r T aE it r lp r x r

oi t

s troE (

n t a n a r o s i r t

a u o e me r ir e pd pt h r o u H N OA OO D - - - -

9 s EFGH 9

9 m 6 d 1

i a 4 d e

. l 3 e lu 2 2 l i 5- e cr d a 1 W 2 p o e )

4 b t r 38 yF h n 1 w s

u e T - Sc i a

4- ta g g 4-0 a u o 0 F - l p

5 CAR 7 S x n E

(

t s i o

- OEEYE eT e t c

NMTBN A O e l r

u r o i

r t

s i

e TA DDE H EN P t

D a fa e c

r n na gryo t

K CIT TE e ON EL  :

n o melia nnt DU LE y r p t el u L

P T a s iuiun g a

e q af e e m

M N o

m RE-MRR - - -

O u )

C S 1

( ABCD _

> : ,, o, l MONTHLY REFUFi ING INFORMATION REOUEST I

Facility name: Catawba Unit 2 1.

L 2. Scheduled next refueling shutdown: March 2000 l

l 3. Scheduled restart following refueling: April 2000 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

I i

l 4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

l If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

' 5. Scheduled date(s) for submitting proposed licensing action and supporting information.

l l 6. Important licensing considerations (new or different design or supplier, unreviewed design or

' )

performance analysis methods, significant changes in design or new operating procedures).

7. Number of Fuel assemblies (a) in the core: 191 (b) in the spent fuel pool: 6M
8. Present licensed fuel pool capacity: 1418 Size of requested or planned increase: _-
9. Projected date oflast refueling which can be accommodated by present license capacity:

May 2012 DUKE POWER COMPANY DATE: Aunust 12.1999 Name of

Contact:

R. A. Williams Phone: (704)- 382-5346 1

l I

..