RECElVE0
!DC 2
Arizona Nuclear Power Project ess fpg g g g P.o. box 52034 e PHOENIX, ARIZONA 85072-2024 April 18,,1,,9.86 ANPP-36299aEEVB/SGB/98.05 Mr. John B. Martin, Regional Administrator Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek CA 94596-5368
Subject:
Palo Verde Nuclear Generating Station (PVNGS)
Unit 2 Docket-No. STN 50-529 (License NPF-46)
Initial Test Program File: 86-056-026
Dear Sir:
In accordance with PVNGS Unit 2 Facility Operating License NPF-46, License Condi-tion 2.C.(5), we are hereby submitting a change made to the Unit 2 Initial Test Program. The change involves a clarification of the review process for test proce-dures as described in Chapter 14 of the PVNGS Final Safety Analysis Report (FSAR).
This change is consistent with Section 6.0, Administrative Controls, of PVNGS Technical Specifications. A safety -review and evaluation has been performed, in accordance with 10 CFR 50.59.- and we have determined that there is not an unre-viewed safety question involved with making this change. The affected page of the FSAR is attached.
If you have any questions concerning this subject, please contact Mr. William F. Quinn of my staff at (602) 943-7200, extension 4087.
Very truly yours, 0
Ou u~
l E. E. Van Brunt, Jr.
Executive Vice President Project Director EEVB/SGB/rw Attachment.
cc:
E. A. Licitra A. C. Gehr R. P. Zimmerman J. Taylor, Office of Inspection and Enforcement 8604290127 860428 DR ADOCK 05000529 p
PDR l
fFeI
SPECIFIC INFORMATION TO BE INCLUDED IN FSAR 12l
-will be designated as the Test Director / Principal Startup 10l Engineer / Responsible Engineer.
The official copy of the test
. procedure shall.be availabl6 in'the test area during the performance of a preoperational or startup test.
The person 2
conducting the test is charged with responsibility for perform-ing the' test in accordance with the approved test procedure.
If, during the performance of the test, it is determined that the test cannot be conducted as written, it is-the responsi-bility of the person conducting the test to resolve the problem in accordance with approved administrative control procedures.
14.2.5 REVIEW, EVALUATION, AND APPROVA,L OF PHASE I THROUGH 8
PHASE IV TEST RESULTS Individual test results will be reviewed and approved as
]
2l provided in the Station Manual.
Completed procedures and test 11l reports will be reviewed for acceptance.
The specific 2l acceptance criteria for determining the success or failure of the test will be included as part of.the procedure and will be used during the r,3 view.
12l The Principal Startup Engineer / Responsible Engineer will present the cogneted test procedure and test report with 4
remarks and recommendations to the responsible Group Supervisor 12l as app' Top Mu,p e rvisor,Wil-1---re 'ew the completed p
4 procedure for conformance with testing requirements a ell as the c..a pto cEtance of the test results.
Following this review, for acce 3
^ specified procedure and t-he4-s test report will be submitted to the or either the Test Working Group or Test Results Review Group anda 12 j
Plant Review Board, for final review, evaluation, and approval 8l recommendation.
If the as-built configuration of a system i
~
apattl+ of demonstra ing i N g ity to meet the acf:ep nce i ering evaluation w b T'b M erformed.
criteria, an en g
Test results for each phase of the test program will be reviewed 4l ( and verified as complete (as required) and satisfactory before Remse /)s ale l Amendment 13 14.2-26 August 1984