ML20210K923

From kanterella
Jump to navigation Jump to search
Forwards Unit 1 Cycle 12 Startup Rept for Criticality,Zero Power Physics Testing & Power Escalation Testing Per Section 6.9.1.1 of Plant TS
ML20210K923
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 08/14/1997
From: Barron H
DUKE POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20210K927 List:
References
NUDOCS 9708200167
Download: ML20210K923 (2)


Text

___

gi e

f Duke Power Company A iM, Zwy Comp 9

~

~

McGuirr Nuclear Station

      • MG0lVP 12700 Hager Ferry Rd.

Huntersville. NC 28078-9340 H. B. Barron Vice besident, McGuirr VM) 8754800 omcr Nuclear Generation Departonent GM) 8754800 ux August 14,. 1997 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555

Subject:

McGuire Nuclear Station Docket No. 50-369 Unit 1, Cycle 12 Startup Report

_ Attached is the.McGuire Nuclear Station Unit 1 Cycle 12 l Startup Report for Criticality, Zero. Power Physics Testing,~

l and Power Escalation Testing as required by Section 6.9.1.1 l- of the McGuire Technical Specifications. This report is l' submitted due to the installation of replacement steam generators which meet the criteria of Technical Specification 6.9.1,1(4).

= Questions concerning this report should be directed to Kay Crane, McGuire Regulatory Compliance at (704) 875-4306.

Very truly_yours,

/k H.-B.-Barron, Vice President McGuire Nuclear Station pa w ,

9708200167 970814 PDR ADOCK 05000369 P PDR

'10C2Ob liihitiRltiti !iiiii 4

1

l U. S. Nuclear Regulatory Commission Document Control Desk August 14, 1997 Page 2 cc: Mr. Luis A. Reyes U. S. Nuclear Regulatory Commission, Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, GA 30303 Mr. Victor Nerses, Project Manager Office of Nuclear Reactor Regulation l U. S. Nuclear Regulatory Commission i Mail Stop, 14H25, OWFN Washington, D.C. 20555 Mr. Marvin Sykes Senior Resident Inspector (Acting)