|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:NRC TO PUBLIC ENTITY/CITIZEN/ORGANIZATION/MEDIA
MONTHYEARML20237G0421987-08-11011 August 1987 Responds to 870707 Appeal Re Denial of FOIA Request for Documents.Appeal Granted.Portions of Six Documents Re Insp Rept 50-424/86-91 Concerning Drug Abuse at Facility Previously Withheld Encl ML20235K1541987-07-14014 July 1987 Responds to Appeal of Denial of FOIA Request for Documents Re 861113 Insp Rept 50-424/87-90 Concerning Drug Abuse at Plant.Previously Withheld Info Will Continue to Be Withheld (Ref FOIA Exemption 6) ML20235D3791987-07-0101 July 1987 Final Response to FOIA Request for Documents Re Plant Fitness for Duty Program.Forwards App F & G Documents. Documents Also Available in Pdr.App G Documents Partially Withheld (Ref FOIA Exemption 6) ML20237D2881987-06-15015 June 1987 Responds to Request for Info Re Proposed Rule Changes Dealing W/Emergency Planning for Nuclear Power Plants.Rule Provides Criteria by Which NRC Can Evaluate Whether Util Emergency Plan Adequate in Absence of Local Participation ML20214B6881987-05-14014 May 1987 Partial Response to FOIA Request for Documents Re Plant anti-drug & Alcohol Program.Encl App C Documents Also Available in Pdr.App D & E Documents Partially & Completely Withheld (Ref FOIA Exemption 6),respectively ML20213G8501987-05-12012 May 1987 Responds to Expressing Concerns Re Licensing of Plant Prior to Completion of Required Safety Tests.Nrc Authorized Schedular Relief from Certain Tests Which Are Not Necessary to Ensure Safety ML20212P1601987-03-11011 March 1987 Partial Response to FOIA Request Re Insp Repts.Forwards App B Documents.App a & B Documents Available in PDR ML20207P7351987-01-14014 January 1987 Ack Receipt of Notifying NRC That Recipient Will Represent Georgians Against Nuclear Energy in Oral Argument Scheduled for 870121.Served on 870115 ML20214F1711986-11-20020 November 1986 Responds to FOIA Request for Documents Re Insp Repts 50-424/85-04 & 50-425/85-04.Forwards Portions of App a & B Documents.Documents Also Available in Pdr.Portions of App a & B Documents Withheld (Ref FOIA Exemptions 6 & 7) ML20197C4531986-10-23023 October 1986 Responds to Appeal of Denial of FOIA Request for Documents Re Allegations.Seven of 11 App D Items Forwarded & Available in Pdr.Portions of Items 4-7 Withheld (Ref FOIA Exemption 7) ML20210T0621986-10-0303 October 1986 Forwards Response to Applicant Motion to Strike Notice of Appeal of Campaign for Prosperous Georgia ML20204G5971986-08-0101 August 1986 Responds to to DOE Re Startup of Plant.Specific Info Available at Lpdr.Unit 1 Fuel Load Estimated for 861215.Following Preoperational Testing,Unit Ready for Commercial Operation About 6 Months After Loading Fuel ML20203C2951986-07-11011 July 1986 Further Response to FOIA Request for Documents Re NRC Investigation Into Complaints of Register,L Price & JB Register Concerning Improper Practices at Facilities.App D Documents Withheld (Ref FOIA Exemption 7) ML20198E2181986-05-22022 May 1986 Informs That Wf Lawless & Hm Deutsch Affiliation W/Georgians Against Nuclear Energy Must Be Established by 860605 Before Filing of Proposed Findings Re Contentions 7 & 10.5,in Response to 860314 Hearing,Acceptable.Served on 860523 ML20197E2381986-05-0202 May 1986 Further Response to FOIA Request for Records on Register, L Price & JB Register Complaints Re Alleged Illegal & Improper Procedures.Portions of App B Records & All App C Records Withheld (Ref FOIA Exemptions 6 & 7,respectively) ML20210K4521986-03-28028 March 1986 Partial Response to FOIA Request for Documents Re NRC Investigation Into Register,L Price & J Register Allegations of Illegal & Improper Procedures at Facilities. Documents on App a in PDR ML20141G4951986-03-25025 March 1986 Further Response to FOIA Request for Documents Re NRC Investigation of Allegations of Intimidation & Harassment of Inspectors by Pullman Power Products Employees.Forwards App D Documents.Documents Also Available in PDR ML20138R0621985-12-26026 December 1985 Returns 851220 Transmittal of 11 Page Unsigned Document Entitled, Analysis of ASLB 851212 Memorandum & Order.... Document Does Not Conform to NRC Rules of Practice & Is of No Use in Case.W/O Encl.Served on 851227 ML20134A5251985-10-28028 October 1985 Final Response to FOIA Request for Documents on 850726 Briefing by Util Re Readiness Review Program,Including Transcript of Briefing.App D Documents Withheld (Ref FOIA Exemption 5).Action on Request Complete ML20136D4051985-10-11011 October 1985 Final Response to FOIA Request for Five Categories of Documents Re Pollution Control Bonds for Plants.Forwards App E Documents.Documents Listed in App F & App E Available in PDR IA-85-599, Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5)1985-10-0303 October 1985 Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5) ML20138C1041985-10-0303 October 1985 Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5) ML20133Q1851985-07-11011 July 1985 Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl IA-84-430, Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl1985-07-11011 July 1985 Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl ML20210K4901985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl.Related Info Encl ML20210K4821985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & May Be Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl ML20210K4701985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & May Be Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl ML20126D8001985-02-28028 February 1985 Further Response to FOIA Request for Six Categories of Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle Nuclear Power Plant.App B Documents Forwarded & Available in Pdr.Review Continuing ML20197E2961985-02-26026 February 1985 Partially Withheld Ltr Re Abuse of Drug Screening Program & Const Deficiencies Discussed During Feb 1985 Telcons.Actions to Develop Facts & Circumstances of Encl Identified Concerns Initiated ML20197E2661985-02-26026 February 1985 Partially Withheld Ltr Re Abuse of Drug Screening Program & Const Deficiencies Discussed During Jan 1985 Telcons.Actions to Develop Facts & Circumstances of Encl Identified Concerns Initiated ML20125E3381985-02-19019 February 1985 Third Partial Response to FOIA Request for Six Categories of Documents Re Charleston,Sc Earthquake of 1886 & Seismic Design for Plant.Forwards App a Documents ML20214F5541984-11-0808 November 1984 Partially Withheld Memo Re QC Concerns at Plant.Notification If Concerns Not Completely or Accurately Reflected in Encl Requested.Complaint Re Discrimination Should Be Filed W/Dol. Related Info Encl ML20214F3911984-06-12012 June 1984 Partially Withheld Ltr Confirming Understanding of Concerns Re Deficiencies Concerning Case RII-84-A-0094.Notification If Concerns Not Completely or Accurately Reflected Requested.Records of 860531,0601 & 0608 Telcons Encl 1987-08-11
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20205B9601999-03-24024 March 1999 Seventh Partial Response to FOIA Request for Documents. Records in App N Already Available in Pdr.App O Records Being Released in Entirety & App P Records Being Withheld in Part (Ref FOIA Exemptions 7C,2 & 5) ML20205A2771999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Vogtle PPR on 990208.PPR for Plant Involved Participation of All Technical Divs in Evaluating Insp Results & Safety Performance Info for Period of Dec 1997 - Jan 1999 ML20207L8281999-03-0808 March 1999 Forwards Partially Withheld Insp Repts 50-424/99-01 & 50-425/99-01 & Notice of Violation ML20207J0431999-03-0303 March 1999 Forwards Insp Repts 50-424/98-10 & 50-425/98-10 on 981227- 990213.No Violations Noted.Licensee Conduct of Activities at Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices ML20203G5691999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Ltr Indicating No Candidates or Ltr Listing Names of Candidates for Exam ML20202H9691999-01-29029 January 1999 Forwards Safety Evaluation Authorizing Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant, Unit 1 ML20199J7931999-01-20020 January 1999 Forwards Insp Repts 50-424/98-09 & 50-425/98-09 on 981115-1226 at Vogtle Units 1 & 2.No Violations Were Identified.Conduct of Activities at Vogtle Was Generally Characterized by safety-conscious Operations ML20199K1381999-01-12012 January 1999 Informs That on 990117,Region II Implemented Staff Reorganization as Part of agency-wide Streamlining Effort, Due to Staffing Reductions in FY99 Budget.Organization Charts Encl ML20198S1601998-12-31031 December 1998 Forwards SER of Licensee Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Vogtle Electric Generating Plant Submitted on 970529. INEEL/EXT-98-01007 Rept Also Encl ML20199E4741998-12-23023 December 1998 Provides Summary of 981105 Training Managers Conference Held in Atlanta,Georgia.Conference Agenda,List of Conference Attendees,Presentation Slides & Preliminary Schedule for FY99 & FY00 Encl ML20199J9781998-12-22022 December 1998 Responds to 981209 Meeting Re Installation of Seismic Clips on Cutler Hammer Electrical Circuit Breakers.Forwards List of Attendees & Handouts ML20198F6711998-12-11011 December 1998 Forwards Insp Repts 50-424/98-08 & 425/98-08 on 980927-1114. No Violations Identified ML20198N9431998-12-10010 December 1998 Ack Receipt of Response, to NOV Issued on 980112 Re Surveillance Testing of Reactor Trip Sys P-4 Interlock Feature at Licensee Facility.Nrc Agrees That Surveillance Testing Not Required ML20196J2181998-12-0101 December 1998 Advises of Planned Insp Effort Resulting from 981102 Insp Planning Meeting.Historical Listing of Plant Issues Called Plant Issues Matrix & Insp Plan,Including Specific Insps Such as in Security & Radiological Protection Areas Encl ML20196J2581998-12-0101 December 1998 Confirms Arrangements Made Between J Bailey & B Holbrook, Re Info Meeting Scheduled for 990210 to Discuss Licensee Performance,New Initiatives & Other Regulatory Issues Pertaining to Listed Facilities ML20196B1231998-11-23023 November 1998 Confirms Telephone Conversation Between J Bailey & P Skinner on 981120 Re Info Meeting Which Has Been Scheduled for 981209 in Atlanta,Ga,To Discuss Issues Re Seismic Retainer Clips ML20196D4981998-11-13013 November 1998 Informs That on 981007,NRC Administered Gfes of Written Operator Licensing Examination.Copy of Answer Key & Master Bw/Pwr GFE Encl,Even Though Facility Did Not Participate in Exam.Without Encl ML20195B3391998-11-0909 November 1998 Forwards Partially Withheld Insp Repts 50-424/98-12 & 50-425/98-12 on 981005-09 (Ref 10CFR73.21).No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations & Sound Engineering ML20155H2501998-10-21021 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-424/98-05 & 50-425/98-05 Issued on 980723.Concluded for Reasons Stated That Example 2 Violation Occurred as Stated in NOV ML20155A7491998-10-15015 October 1998 Forwards Insp Repts 50-424/98-07 & 50-425/98-07 on 980816-0926 & Nov.Insp Generally Characterized by Safety Conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20155B7771998-10-0909 October 1998 Extends Invitation to Attend Training Manager Conference on 981105 in Atlanta,Georgia.Conference Designed to Inform Regional Training & Operations Mgt of Issues & Policies That Effect Licensing of Reactor Plant Operators ML20155B4621998-09-25025 September 1998 Discusses OI Investigation Which Completed on 980728. Investigation Reviewed Circumstances Surrounding Apparent Disabling of Fire Computer Trouble Alarm by Unit Shift Supervisor.Concludes Enforcement Discretion Warranted ML20153B0401998-09-17017 September 1998 Responds to 980904 e-mail Message Making Certain Observations Re Apparent Increase in Reactor Trips at Plant, Units 1 & 2.NRC Concluded That Licensee post-trip Reviews Adequately Conducted & That No Adverse Trends,Apparent ML20153B9311998-09-16016 September 1998 Forwards RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations, Responses for Plant,Units 1 & 2 ML20153F7081998-09-11011 September 1998 Provides Summary of 980909 Meeting Held to Discuss TS & Other Regulatory Issues Re Vogtle Electric Generating Plant. List of Meeting Attendees & Copy of Presentation Slides Encl ML20154C4871998-09-10010 September 1998 Forwards Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815 & Nov.One Violation Involved Failure to Implement Adequate C/As for Repeated Failures to Enter Applicable TS Limiting Conditions for Operation ML20151U7901998-09-0909 September 1998 Discusses 980615 Request for Exemption from Requirement of 10CFR73.55(e)(1) & (f)(1) to Provide Continuous Staffing of Plant CAS During Contingency Events.Request Denied ML20151S7291998-09-0202 September 1998 Discusses Evaluation of Util Response to GL 97-05 for Plant, Units 1 & 2.NRC Did Not Identify Any Concerns W/Sg Tube Insp Techniques Employed at Plant ML20239A4251998-08-27027 August 1998 Informs of Change Being Implemented by Region II Re Administrative Processing of Licensee Responses to Nov.Nov Responses Will Be Formally Ack as Part of Periodically Issued Integrated Insp Repts 1999-09-01
[Table view] |
Text
7 v
. ,~
UNITE 2 STATES
' ' '-y,/ free,{6 NUCLEAR REOULATCRY COMMisslON p REGlON80 g j 101 MARIETTA STREET.N.W.
ATLANTA. GEORGIA 30303
'*4,,,,, June 20, 1985 Ms. Leslie A. Price c/o Route 2, Box 265 Vidalia, GA 30474
^
Dear Ms. Price:
SUBJECT:
ALLEGATIONS REGARDING V0GTLE NUCLEAR PLANT, RII-85-A-0016 Enclosed please find the write up I made' regarding the interview I- had with you on May 23, 1985. I am forwarding a copy per your request.
The information will be provided to the Technical Staff for review and any follow up action. I would also like to advise you that there may be some., concerns which you reported that could be referred back to the licensee for follow up which would be subject to audit by the NRC.
Please review the. enclosed document and if there are any changes or corrections that you would like to make, please call me collect at 404/221-4193.
2.
I appreciate your cooperation and assistance in this matter. I'll be in touch with you regarding the resolution of your allegations, and if I can be of any assistance, please do not hesitate to contact me.
$4MD. SjG Bruno Uryc Inves tigation/Allega tion Coordinator
Enclosure:
Results of Interview, 8 pages w/atch 8604280327 860328 '
PDR FOIA FOWLERS 6-43 PDR
u s sucttaa etoutatoav coeurssros wacrem m ALLEGATION DATA FORM t1142: in.iewetion. en eeve se .ier RECEIVlN3 OFFICE Docket Number (if applicablel
' ';2*J' ,'.';;* '
'~J' voer a eso oo42 4 generic. wrie. GENERICS
~
- 2. Functional Areef al involved: onsite health and safaty ich.ca .ppropret. tionte.1 I operations _
construction __
offsite health and safety safeguards _ emergency preparedness other tspecifyl
- 3. D:scription: lAIBIOISIEl IOlFI IT1RIOldbl idE1T1EICtrit lolbil IPl
- "****'* IRio151RIANI IANIbl IClolMl&lTIRIOlc.frli 10141 ICI lolHic.EIRIMisl. I I I I I I I I I I I I IIIIII I I I I I I I I I 1.1 I I I I I I I I I I I I I I I
- 4. Scurce of Allegation: security guard contractor employee _
tcheck .pproprote t>o :
licensee employee ._ news media NRC employee ._._.
private citizen
.__ organization (specityl other (specify MM DD YY
- 5. Date Allegation Received:
anest two initi.i. .no s.. n. met 0
- 6. Name of Individual Receiving Allegation:
- 7. Office: g y ,
ACTION OFFICE in,.i swe insii.i. .no s.. n.m.:
3 , U R V, C .-
- 8. Action Office
Contact:
L C 3 S. FTS Telephone Number: Q v 7 _ g
- 10. Ctatus: - Open. If followup actions are pending or in progress tcheck onei Closed. If f ollowup actions are completed MM DD YY
- 11. Date Closed: g g
. h~\
12 a*=k':
(Lirrut to 50 cher.ctersi 1IIIIIIIIIIIIIIIIIIIIIIIII lIIl IIIIIIIIIIIIIIIIIIIIII Offic. Yr Numiset
- 13. Allegation Number: -
5 O O I 6
' ~
. . . Rcb M L
ACLU Amencan Civil 88 Walton Attanta.
Liberties Uruon Street. NW Georgia 30303 -
of Georgia Second Floor (404) 523 5398 For Release: For Further Information:
Monday, say 13, 1985 '
Gene Guerrero Office: 523-5398 10:00 A.M. Home: 523-3283 The American Civil Liberties Union announced this morning that it has filed a complaint with the U.S. Department of Labor on behalf of four former workers at Georgia Power. Company's nuclear P hnt Vogtle, under construction near Augusta, Georgia. The ACLU is asking federgi o((icials to order Georgia Power to discontinue use of a urinanalysis testing program. Under the program, anonymous tips of drug usage can be telephoned into a " hot line." Employees y turned in on the " hot line" are then required to submit to urinanalysis tests as are all new employees and non-construction personnel.
According to the ACLU complaint, " workers with a history of making known their opinions regarding quality concerns at the plant, were identified on the hot line." Two of the workers, Steve McNally and Billy Weatherford, had previously said they regarded such tests as an invasion of privacy and would refuse to submit to a urine test. They were turned into the hot line after filing safety-related complaints. Both were then fired wheh they refused to take th'e urinalysis test. Leslie Price worked as a quality control inspector. She had complained to the Nuclear Regulatory Commission regarding quality control violations. Once she was warned by 'a welder that she would be turned in on the hotline if she was too careful inspecting welds.
Soon her name was called in on the hot line and she was fired when A .
.. Nsws R21ocso, May 13, i985 Page Two company officials said the tests came out positive for drug usage.
James B. Register filed a quality concern regarding improper documentation of activities of the survey department. He was fired when his name was turned into the hot line and company officials said he failed the urinanalysis test. Susan Register filed complaints with the Nuclear Regulatory Commission. She was fired after'she was first unable to produce enough urine for a test and later refused to take a test.
In addition to filing the complaint on behalf of the five named workers, ACLU officials charged that the urinanalysis testing program has made agpy Plant Vogtle workers afraid to act on quality or safety concesns.**" Conscientious workers are afraid to file safety and quality control complaints for fear they will be turned in on the hot line," according to ACLU state director Gene Guerrero.
"We have received complaints from a number of workers at Plant Vogtle, including workers who have taken the test once and passeda but
~
fear that if they step out of line, the testing program will be used to discharge them," said Guerrero. " Ironically," Guerrero continued, "a program which purports to be about safety is having the opposite effect. The workers who complain to us are safety conscious. They know how dangerous a large construction site can be and they recognize the need for careful construction of nuclear i
plants. They are pro-nuclear power. They believe this program l adversly affects safety, and violates their right to be treated with respect and dignity on the j ob."
l 1
l- ,
May 13, 1985 Office of the Administrator of the Wage and Hour Division Employee Standards Administration U.S. Department of Labor -
STEVE McNALLY, BILLY WEATHERFORD, )
LESLIE PRICE, JAMES B. REGISTER, )
and SUSAN TILLER REGISTER, )
Petitio,ners )
)
vs. -
) COMPLAINT
. )
' )
GEORGIA POWER COMPANY, )
Respondent )
I. INTRODUCTIO,N 4
Petitioners Steve McNally, Billy Weatherford, Leslie Price,
~
James B. Registef and Susan Tiller Register file this complaint a .u.
. pursuant to the Energy Reorganization Act of 1974, 42 USC 5851; and 29 CFR Part 24.
1 In the spring of 1984, the Georgia Power Company implemented a drug policy at its nuclear Plant Vogtle construction site whereby workers can phone in on a " hotline" 4
anonymous allegations of drug abuse by other workers. The j caller may make any allegation, based on any motive; the accused party is never informed of the identity of his accuser.
Any accused worker is then forced to take an EMIT urinalysis
! screening test which purportedly picks up traces of drugs in the urine up to 39 days after ingestion. ,
Petitioners were reported on the company /s hotline or otherwise targeted to take the urinolysis screening test solely as a consequence of making complaints to company qua[ity f
assurance personnel and the Nuclear Regulatory Commission (NRC)
. - - . - , - , . . _ . _ , . . . . _ , _ _ _ _ _ _ , . . . _ . _ . _ _ _ , _ . _ , _ _ , _ . , _ , _ . . . _ , , , _ . . _ - . . _ . . . , _ , _ - - _ _ _ _ _ , _ , . . _ . . , . . _ _ ~ _ _ , , . _ _ _ . _ _ . , _ , _ _ . _ _ _ _ - - .
T staff in accordance with 10 CFR Part 59 Appendix B. Their complaints, which are further discussed below, concern inadequate documentation, falsifi' cation of records and other violations of the Atomic Energy Act. Petitioners Steve McNally, Billy Weatherford and Susan Tiller Register have been discharged as a result of refusing to take the urinalysis and petitioners Leslie Price and James B. Register have been discharged as a result of failing to pass the test.
Petitioners' complaints to quality assurance personnel and the Nuclear Regulatory Commission constitute protected activity under the Energy Reorganization Act of 1974, 42 USC 5851; Georgia Power's urinalysis program, as applied to petitioners, constitutes ditcrihination as prohibited by 42 USC 5851 and 29 CFR Part 24.
This discrimination continues as Georgia Power Company refuses to pay unemployment benefits to discharged petitioner Susan Tiller Register and refuses to allow petitione'rs Leslie Price and Susan Tiller Register to withdraw their contributions to the Company's saving plan program. The presence of Georgia Power attorney Chuck Whitney at a meeting between Petitioners, their attorneys and other workers opposed to the urinalysis program, including current Company employees as well as disc'iarged workers, in Augusta on April 18th, 1985 constitutes further discrimination, harassment and intimidation.
When Mr. Whitney initially attempted to enter the meeting room, he was told that his presence was inappr,opriate and unacceptable. He insisted on entering in order to assure those
present that the company would not retaliate against them for attending the meeting. Again he was asked to leave the room and finally did so. Mr. Whitney stood outside the meeting room for several minutes; he was finally picked up by a passing car. His remarks and presence in general further raised workers' anxiety and fear of discrimination, intimidation and harrassment.
As the Company had failed to post NRC Form 3 at readily accessible points at the construction site at the time petitioners were terminated, petitioners were unaware that this federal grievance procedure was avai1*able to them. Because petitioners were first informed of th,eir legal rights regarding this proceedinh ae 2 meeting with American Civil Liberties Union attorneys on April 18th, 1985, this complaint is timely filed.
II. DESCRIPTION OF PETITIONERS A. Steve McNally, 70 Washington St., Apt. $1, N6w London, CT. 96329, worked for nine months at Plant Vogtle as a quality control inspector. He has over ten years of experience in this field. In August 1984, Mr. McNally submitted a written quality concern in accordance with 19 CFR Part 50 Appendix B regarding management's attitude of production before quality to head quality control manager, Mike Upchurch. No action was taken regarding this concern. Mr. McNally continued to urge management, particularly assistant quality control manager Roy Page, to follow their own procedures involving the handling of cable reels and filling out EE-589 cable installation cards, as I
well as others. In the last week of November 1984, Page fired Mr. McNally for refusing to work unscheduled overtime without pay.This decision was overridden and Mr. McNally was rehired ;
the same week though he was given the next scheduled work week off without pay for insubordination.
In,early November, Mr. McNally was assigned to a problem-solving team by Mr.*Pinson, Georgia Power Company vice-president for site construction. The team's task was to identify quality problems, formulate solutions and present results to management. Team meetings were to start in December.
As a result of Mr. McNally's history of making quality assurance complaints, Fred Page, the new head quality control manager, direc$e( him not to attend the meetings and without authorization removed him from the problem-solving team. When the team leader informed Mr. Pinson of this, Mr. McNally was
) immediately reassigned to the team.
L On November 30, 1984, Mr. McNally notified a Nucl, ear Regulatory Commission investigator on-site that Georgia Power Company management was attempting to intimidate him into leaving his job for expressing his concerns regarding quality assurance. One week later Mr. McNally was transferred, without choice, from the electrical quality control department to the field engineering department. In mid-January of 1985, three quality control inspectors were called in on the hotline for suspected drug abuse. Mr. McNally, suspecting that he would be the next to be called in, asked Roy Page for a copy of the quality concern he had submitted in August 1984'. He also told
~
Page that he considered the test an invasion of privacy and would refuse to take the test in the event he was asked to. The following day, Mr.McNally's name was phoned in on the hotline.
He refused to take the urinalysis and was subsequently discharged on January 16, 1985.
B. Billy Weatherford, Box 1123, Clearwater, SC, 29822, has been employed at Plant Vogtle since 1977. He has worked in both the survey and mechanical sections at the plant. At the time he was discharged he, held the position of party chief and supervised a crew of four surveyors. In October of 1984 he reported to Ed Groover of the quality assurance division his
' concern that the lack of docimentatio6 of design changes in the e .s.
powerblock buildings would result in an open item in the event of a quality assurance audit of the field books.
Mr. Weatherford continually reminded the crews on other shifts of the necessity of proper documentation. The other party chief supervisors, particularly David Moncus, began to harass him and search for faults in his work. Moncus accused him of time theft but Mr. Weatherford was acquitted. He ;
reported to his supervisor, Herman Richards, that he was being harassed for insisting that work be done properly by the crews and predicted that he would be forced to take the urinalysis as a means of intimidation. Soon thereafter Mr. Weatherford was told by Moncus that his name had been phoned in on the hotline and thus he would have to take the urinalysis screening test.
Mr. Weatherford had stated publicly many times.before that he believed the drug test was a constitutional violation and that
- he would not take it. He did in fact refuse to take the urinalysis and walked off the site when he was ordered to do so. He was discharged by the Company on March 1st, 1985.
C. Leslie Price was employed for two and a half years as a civil quality control inspector at Plant Vogtle. On January 24, 1985 she contacted Bruno Uryc of the Nuclear Regulatory Commission staff about qual'ity assurance violations at the plant including falsification of soil density records during 1976-77, extensive honeycombing in the concrete of the control building on the north wall, the fact that Georgia Power Company was purposefully camouflaging the fact that workers were being terminated for drug abuse activity so that NRC would not force them to reinsRpch $the work performed by these individuals, and documentation problems in the quality assurance vault. On or about February 4th, she notified a welder that his welds were
? inadequate. He warned her that her pickiness might someday result in a hotline complaint. On February lith, she notified her supervisor, Allen Chestnut, that her party chief Charlie Bonnell was drunk on the job, performing his work inadequately and preventing other workers from performing their jobs. The following day she was ordered to take the urinalysis as a result of an alleged hotline complaint. She was subsequently discharged on February 12, 1985 for misconduct and violation of work rules. A Georgia Department of Labor administrative i hearing officer found that she had been discharged for being at work with drugs in her system.
l '
f D. James B. Register, Route 2, Box 265, Vidalia, GA 36474, t
is a surveyor with eleven years of experience in his field. He was employed at Plant Vogtle for almost three years as an instrument man in the survey department. On January 25, 1985, Mr. Register filed a quality concern on survey regarding the department's failure to follow its procedures regarding field work, documentation and harrassment of surveyors. On February 21, 1985 he was ordered to take the urinalysis as his name had allegedly been identified on the hotline. On February 27th he was discharged as a consequence of failing to pass the test.
E. Susan Tiller Register, Route 2, Box 265, Vidalia, GA 30474, was employed at Plant Vogtle for four and a half years.
Her last job title was that o,f Junior, Coordinator in the Mechanical DivisioW. Around the first of January 1985 she began hearing rumors that she had identified other workers as drug users on the hotline and was thus target for a hotline' call
" herself. Ms. Tiller was allegedly identified as a drug user on the hotline soon thereaf ter and was ordered to take *the urinalysis screening test. She was unable to produce enough urine for the test on January 22nd and on January 23rd. She refused to take the urinalysis again on January 24th and was discharged for insubordination, excessive absenteeism and unsatisfactory job performance. On January 24th she contacted Bruno Uryc of the Nuclear Regulatory Commission with her concerns regarding settling of the Auxiliary Building as a result of improper backfilling, protection by Georgia Power Company of certain employees who were not being required to take the urinalysis and problems with concrete in the turbine
e building resulting from walls being backfilled too soon. She also told Mr. Uryc that she was being harassed and intimidated for be'ing a suspected hotline accuser. On January 25th she was
{
discharged for insubordination, excessive absenteeism and unsatisfactory job performance.
II . CONCLUSION i Petitioners' complaints to quality assurance personnel and
, the Nuclear Regulatory Commission staff in accordance with company policy and 19 CFR Part 59 Appendix B constitute protected activity under the Energy Reorganization Act of 1974, 42 USC 5851; use of the hotline and urinalysis screening test
?.
as a means of pigoberging employees, including petitioners, who I have engaged in protected activity constitutes discrimination as prohibited by 42 USC 5851. Furthermore, the presence of Georgia Power's attorney, Chuck Whitney, at the April 18th meeting between workers and ACLU attorneys constitutes discrimination, harrassment and intimidation as well.
Thus, pursuant to 42 USC 5851 (b) (2) (B) , petitioners request reinstatement with full back pay in their former i positions at the Plant Vogtle facility. Furthermore, because 1 Georgia Power Company's drug testing program is both unreliable (l) and unconstitutional (2) and because a strong f
likelihood exists that other workers who have made quality assurance and safety complaints have been and will continue to be discriminated against by use of the hotline and urinalysis screening test, petitioners request that the use of the urinalysis be discontinued and that the Company reinstate, with
- full back 1
pay, all workers who have been discharged as a result of their refusal to take, or failure to pass, the urinalysis.
Petitioners request any other relief the board might deem appropriate.
. Respectfully submitted, May 13, 1985 Ralph Goldberg
-* 1133 Healey Building s .se 57 Forsyth St.
Atlanta, GA 29303 Gary Flack Laurie Fowler Attorneys for Petitioners e
J 1
The Syva Company's literature concedes that i ts test is only 954 accurate. A 1982 study by the Department of Defense and the Air Force, however, shows that the EMIT test produces up to 11.1 Percent unconfirmed, or false, positives. The Syva Company has found that 11 substances, including aspirin, can trigger false positives. See S. Clark et al., EMIT Cannaboid Assay: Clinical Study No. 74 Summary Report (Palo Alto: The Syva Company, 1989), pp. 22-24. Studies indicate that passive inhalation of marijuana by nonsmokers as well as substances produced by the human body.may also trigger false positives.
See P. Zeidenberg et al., " Marijuana Intoxication by Passive Inhalation: Documentation by Detection of Urinary Metabolites,"
American Journal of Psychiatry 134:1 at pp. 76-77 (January 1977).
2 The chilling effect of the hotline and urinalysis is apparent. Workers now fear to make their quality and safety concerns known in light of the hotline retaliation which might follow.
\ $
?~
O 9
9
. w .. _
- d..er11101 Zed f.or
. . m u- > s :
=
e o L .
Nunreliability
- j. . . . .
- w'fg,kA ,. vahnet.
=
m e
9
.s _ ,
t.anysi
. C' ,
. n. A u.
i
- 7. ,-Q.: i '
- By Charles Seabreek m wm.,
D *
- [- .g( 4%,
."._ Tream
'y d'"CY >
The reliabdity of drug screening tests. Uke ' i. - - % -
'" 7- * '"'
'thsee proposed by baseball enemhaiceer Peter , '
Discti,!
Uens: tog, is being lacrosslagly challenged for i , *. - , ' ,'1 C :
'. . . ' f. ~ .a , %.
at De thstr inabatty to consistanoy wenuly users of - - ' ~ ,
ilu d 4
'.~ -' ~ '
~
.~ ' '
Dodip ,
New used by the multary, pebile as-r4am '. ' -
and a number of corporations, some uriae tests -
anoa 5 taw n sama heared by some laborataries have been >- >V. ;' , .
wrseg op to too percent of the time, according
- ' ~- '~. .
.' 5. , -
to a recent report from the UA Centers for Diesase Control. -
g- t
'!he M said "arion .l [- ' --* b lb . .
p.,. _ ,,,,,
accumy of tat resets - coupled Em rapid Commissioner Peter Ueberroth has ordered drug tests for,all beschall personnel, twy co l lacreases la the use of the scrossing i., -h excePt major-league players days
- has emated a " crisis in drug tesun( la ths . Wdson, United States.
singer, a former administrator of the federal phetamines, cocaine, codeine and enorphine. aM "1%e h hatt people are going to be awful- Drug Enforcement Administration and now The testing programs have been used most P"50" ly, awfully for getting lato testing peo- president of a Chicago consulting firm that ad- widely in the military, prisons and drug abuse ple's artes for win a i
" says Dr. Arthur McBay, vises companies ce drug screening programs. treatment programs. lately, government agen- renstet eksf towie=ta- J =t for the state of North Caroll- But Ueberrows announcement comes at a cies, including the U S. Postal Service, have nas feo and a 'astsonal expert on tesung for mart- time when such tests are under increasing fire. started using the tests to screen job applicants son.
l The CDC report, published two weeks ago in and employees. Many of the Fortune 500 com-r j While'McBay applandes UeberreG's efforte the Journal of the American Medical Assoela- panies now perform similar drug tests. ,
professional baseball of drug abuse, he tion, found that more than a dozen private lab-that acy of the tests may spewn a eratories serv'ng 282 drug treatment centers "W thin a year or two, in order to get a et legal cha!)enges, as it already has around the nation had " false-positive *.* error good job, you are going to have to be drug- A"'S1' i i ladustrial and government work- rates of up to 46 percent when testlag for free," says Dr. Michael Walsh, chief of clinical rez is k '
WO"-
who ve been denia( employmset because awdadone and op to 37 percent wher> testing Institute and behavioral of Dnag Abuse. pharmacology at the National
Became of doubts about the reliability of A false-positive result :ndicates a sperson This may k Ge ddmate hb 'd' the tests, McBay sa he himself would reface has been taking a certain drug, when he has vice against drug abuse which casting this to cooperate if his vauhood depended on Ge act. ,
country untold hundreds of millicas of dollars The las
outcasne of the test. In the study, the researchers found that in lost prodoctivity, absenteelse from work season' The proposed screening program will in- sone of 12 laboratories could re!! ably test for and on-the-job accidents," he says' Tamp **
ciude aD ha** hall personnel - from owners to amphetamines 80 percent of the time - the But Walsh is also concerned that the tests consper. ,
sterstaries to 3.044 adsor league players. It rate the CDC considers "ecceptable.- often yleid inaccurate results. w' does not yet include majorleague players be- Only one of 11 tabs had " acceptable'* tests Because of the growing threats of lawsuits cause the plan must first be accepted by the .for cocaine and five of them were unable to de ' from peoons who claim they have been falsely sentenc '
Major IAngue Players Association Before drug lect traces of the drug in any of the arine sam- accused :of drug abuse, many companies are tasung for the players becomes mandatory. ' pies that actually contained it. oow rechecking the results of drug tests.
"ne basebaD car &*=t^=r is focusing'at- The lacrease in screening for 1111 cit drugs Since June, the Army has also been review.
Admits :
Niter a tenties an drug abuse, a major problem in this has coene about only dur:ng the past four or ing the cases of $1,000 soldiers or veterans who for the country,*and 18 is est is the tout laterest of the Ave years as new technology has made analysis may have been improperly disciplined on tookthe **g major lesgee players to resist his efforts to rid reliable and cheap. The tests can detect most basis o poorly administered tasts for ulegal oncenn sports of the problem,"jsays Peter B. Bee- drugs, heleding marijuana, barbituratas, am- drugs. players
-c _ _ - - . . . - . ~ . - _ . , . . _ , , . _ . , - . . . _ _ _ _ - - - -