Application to Amend Licenses NPF-4 & NPF-7,changing Tech Spec 3/4.3.1, Reactor Trip Sys Instrumentation to Modify Surveillance Frequencies & out-of-service & Test Times for Selected Functional Units Per Generic Ltr 83-28.Fee Paid
ML20210F653
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 01/30/1987
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20210F657 List:
References
86-655, GL-83-28, NUDOCS 8702110129
Download: ML20210F653 (3)


Text

a.

VINGINIA ELECTRIC AND Powen COMPANY Rzenxoxn,VINGINIA 20261 W. L. Srawrar Vaca Passapawr Nuctaan oramarsons January 30, 1987 United States Nuclear Regulatory Commission Serial No.86-655 Attention: Document Control Desk N0/EJL:jmj Washington, D.C.

20555 Docket Nos.

50-338 50-339 License Nos.

NPF-4 NPF-7 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 PROPOSED TECHNICAL SPECIFICATIONS CHANGES Pursuant to 10 CFR 50.90, the Virginia Electric and Power Company requests an amendment, in the form of changes to the Technical Specifications, to Operating License Nos. NPF-4 and NPF-7 for North Anna Power Station Units 1 and 2.

Our letter dated November 18, 1985 (Serial No.85-695) regarding your request for additional information for Generic Letter 83-28 item 4.5.3 outlined our plan to propose changes to the Technical Specifications that would modify the surveillance intervals associated with several of the reactor trip functions.

This is the follow-up to that letter.

We are proposing changes to Sections 3/4.3.1, Reactor Trip System InFtrumentation. The proposed changes modify the surveillance frequencies, and allowable out-of-service and test times for selected reactor trip system instrumentation functional units.

These changes take advantage of those provisions of WCAP-10271 and Supplement I which have been approved on a generic basis in the NRC's SER issued in March, 1985. The changes have been prepared in accordance with the guidance provided in the letter from Mr. L. D.

Butterfield (WOG) to you dated May 16, 1985 and your letter to Mr.

Butterfield dated July 24, 1986. We would like to have these changes approved by May 15, 1987 with implementation within the next sixty days.

The proposed changes to the Technical Specifications are provided in Attachments 1 and 2 for Units 1 and 2 respectively. A discussion of the proposed changes to the Technical Specifications is provided in Attachment 3.

In accordance with 10 CFR Part 170 an Application Fee of $150 is also enclosed.

M 8702110129 870130 8gb&

PDR ADOCK 05000338 gggg37 P

PDR

+

--.-s

This ' request has been reviewed and approved by the Station Nuclear Safety and Operating Committee and the Safety Evaluation and Control ~ Staff.

It has been determined that this change does not pose an unreviewed safety question as defined in 10 CFR-50.59 and does not pose a significant hazards consideration as defined in 10 CFR 50.92.

If you have any questions, or need additional information to process this request, please contact us.

Very truly yours, k

L.

W. L. Stewart Attachments:

1.

Proposed Technical Specifications Changes for North Anna Unit 1.

2.

Proposed Technical Specifications Changes for North Anna Unit 2.

3.

Discussion of Proposed Changes.

4.

Application Fee.

cc:

U. S. Nuclear Regulatory Commission 101 Marietta Street, N.W.

Suite 2900 Atlanta, CA 30323 Mr. J. L. Caldwell NRC Senior Resident Inspector North Anna Power Station Mr. Charles Price Department of Health 109 Covernor Street Richmond, Virginia 23219

COMMONWEALTH OF VIRGINIA )

)

CITY OF RICHMOND

)

The foregoing document was acknowledged before me,-in and for the City and Commonwealth aforesaid, today_by W. L. Stewart who is Vice President - Nuclear Operations, of Virginia Electric and Power Company. He is duly authorized to execute and file the aforegoing document in behalf of that Company, and the' statements in the document are true to the best of his knowledge and belief.

Acknowledged before me this d day of d/k/ m so, 19 E.

My Commission expires:L /[N/,gm f25 1994.

/

b*E A $90 Notary Public

~

i (SEAL) i

_-