Requests Mod of 840614 Order Re Completion of Spds,Extending Date for Installation of Sys to Startup Following Unit 1, Cycle 9 Refueling Outage Currently Scheduled for Spring 1988
ML20210E473
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/18/1986
From: Tiernan J
BALTIMORE GAS & ELECTRIC CO.
To: Thadani A
Office of Nuclear Reactor Regulation
References
NUDOCS 8609250016
Download: ML20210E473 (2)


Text

._ __

B ALTIMORE GAS AND ELECTRIC CHARLES CENTER P. O. BOX 1475 BALTIMORE, MARYLAND 21203 JostPH A.TIERN AN WcE PRESIDENT NUCLEAR ENERGY September 18,1986 U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C. 20555 ATTENTION:

Mr. Ashok C. Thadani, Director PWR Project Directorate //8 Division of PWR Licensing-B

SUBJECT:

Csivert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 Request for Modification of June 14, 1984, Order Regarding the Safety Parameter Display System

REFERENCES:

(a)

Letter from 3. R. Miller, to A. E. Lundvall, Jr., Order Confirming Licensee Commitments on Emergency Response Capability Schedules (Generic Letter 82-33), dated June 14,1984 (b)

Letter from 3. A. Tiernan, to A. C. Thadani, Request for Modification of June 14,1984, Order, dated June 12,1986 Gentlemen:

Your Order of June 14,1984, (Reference a) confirmed our commitment to complete the Safety Parameter Display System (SPDS) on Unit I by October 1,1987, and on Unit 2 by October 1,1986. We request that both of these dates be extended to start-up following the Unit 1 Cycle 9 refueling outage currently scheduled for the spring of 1988.

On June 12th (Reference b) we reported that, due to problems with our plant computer supplier, we would not be able to meet our original commitment date for the Unit 2 SPDS and that our Unit i SPDS completion schedule was also in jeopardy.

We expended our best management and technical efforts, both in-house and at the suppliers' facility, to resolve the Unit I delays. Two of our computer specialists continue to work full-time with our supplier.

In addition, our Principal Computer Project Administrator, our Computer Maintenance Supervisor, members of his Unit, computer specialists at one of our coal-fired plants experienced with the type of computer being installed, and other specialists have made frequent trips to assist our supplier. We also restructured the project and focused our supplier's efforts on critical plant-operations sof tware when development slowed.

6609250016 860918 PDR ADOCK 05000317 p

PDR i 4

.=,

N Mr. Ashok C. Thadani September 18,1986 Page 2' Despite our efforts, we recently determined that the plant computer is of insufficient capacity to accommodate all necessary application programs. We met with our hardware vendor to try to solve the problem and stay on schedule, but we must now replace.this computer with one of larger capacity.

We are confident in our revised completion dates due to the material and personnel changes we have demanded of our supplier. Should you have any questions regarding this matter, please do not hesitate to contact us.

Very truly yours, M

JAT/ WPM / dim cc: