MAR 211986
Docket No. 50-271
Vermont Yankee Nuclear Power Corporation-
ATTN:
Mr. Warren P. Murphy
Vice President and Manager
of Operations
RD 5, Box 169
Ferry Road
Brattleboro, Vermont 05301
Gentlemen:
Subject:
Systematic Assessment of Licensee Performance (SALP) Report No.
50-271/85-99
This refers to the evaluation we conducted of the activities at the Vermont Yankee
Nuclear Power Station for the ' period of November 1,1984
-October 18, 1985 and
discussed with members of your staff on January 10, 1986 at a meeting in Vernon,
Vermont. The list of meeting attendees is attached as Enclosure 1.
The NRC Region
I SALP Report is provided as Enclosure 2.
Our letter of December 31, 1985 (En -
closure 3) forwarded the SALP Board Report and solicited comments within 30 days
of our meeting.
As discussed during the January 10 meeting and subsequently docu-
mented in your February 12, 1986 letter (Enclosure 4), you provided additional
comments on our report.
With respect to your comment on Section IV.A.1, Operations, as you noted, the AEOD
evaluation of LER quality has been discussed extens~ively with our SeniorLResident
Inspector by VY personnel; this evaluation was only a minor factor in our overall
evaluation of this functional area. Your comments on Section IV.B.1.2, Radioac.tive
Waste Management and Effluent Controls, and Section IV.E.1, Emergency Preparedness,
regarding points requiring clarification have been reflected in our amended report
(Pages 13 and 22); they did not directly affect oar. ratings in these areas.
l
Similarly, we welcome your comments regarding the Emergency Preparedness rating
'
and your general comments; however, they also do not directly affect our ratings.
Our overall assessment of your facility concludes that performance remained gen-
erally consistent throughout this assessment period as compared to the past as-
sessment period.
Although performance in each functional area is at_least satis-
factory, we know that Vermont Yankee shares our goal of even higher performance
levels.
In order to achieve such goals, we continue to urge VY management to be
more aggressive in self evaluation, and more open and receptive to opportunities,
whether identified internally or by external organizations, for further improvement.
We consider that our meeting and subsequent interchange of information were bene-
ficial and improved mutual understanding of your activities and our regulatory
program.
8603270195 860321
ADOCK 05000271
O
I
t
_
.. -
-
-
. . . - . .
. _ _ _
___
_.
.s
-
,
,
,
.
Vermont Yankee Nuclear Power
2
Corporation
MAR 21 m
No reply to this letter is required.
Your actions in response to the NRC System-
atic Assessment of Licensee Performance will be revlewed during future inspections
of your licensed facility.
Your cooperation is appreciated.
Sincerely,
Original ' signed by
Thomas E. Murlet
Thomas E. Murley
-Regional Administrator
Enclosures:
1.
SALP Management Meeting Attendees
2.
NRC SALP Report, Vermont Yankee Nuclear Power Station, December 2, 1985
3.
NRC Region I Letter, T. Murley to W. Murphy, December 31, 1985
4.
Vermont Yankee Letter, W. Murphy to T. Murley, February 12, 1986
cc w/encls:
l
R. W. Capstick,~ Licensing Engineer
W. F. Conway, President and Chief Executive Officer
J. P. Pelletier, Plant Manager
Donald Hunter, Vice President
Cort Richardson, Vermont Public Interest Research Group, Inc.
Public Document Room (PDR)
Local Public Document Room (LPDR)
.
Nuclear Safety Information Center'(NSIC)
NRC Resident Inspector
State of New Hampshire
State of Vermont
Chairman Palladino
l
Commissioner Roberts
Commissioner Asselstine
Commissioner Bernthal
Commissioner Zech
- )
\\1
[
r.
.e...,
. ,.
.
.
Vermont Yankee Nuclear Power
3
MAR 21 M
-
Corporation
bec w/encls:
Region I Docket Room (with concurrences)
Management Assistant, DRMA (w/o encl)
Section Chief, DRP
M. McBride, RI, Pilgrim
H. Eichenholz, SRI, Yankee
V. Rooney, LPM, NRR
T. Murley
K. Abraham (2 copies)
D. Holody
J. Taylor, IE
Division Directors
Branch Chiefs
SALP Management Meeting Attendees
t
lF I:RA
.(
i-
R
R
P
R
$Tripp/meo
W N inger
.Stdf tecki
All
l ey -
34/86
(
/g gb
J f/
@
OFFICIAL RECORD COPY
. - -
-
,
. . , _ . . . . - - . . -
. . - - . - -
. . . - . . . .
. . . - . - - - -
- - - - - . - , - - . . .
,
-
-
,
0
l
,
.
-
J
ENCLOSURE 1
JANUARY 10, 1986 SALP MANAGEMENT MEETING ATTENDEES
1.
Licensee Attendees
W. Conway, President and CEO
W. Murphy, Vice President and M00
l
J. Pelletier, Plant Manager
W. Wittmer, Manager, Recirculation Pipe Project
G. Johnson, Operations Supervisor
i
H. McBrien, Director of Communications
D. Reid, Operations Superintendent
R. Wanczyk, Technical Services Superi'ntendent
M. Metell, Engineering Support Supervisor
S. Miller, Engineering Manager, Yankee Nuclear Services Division
,
E. Jackson, Assistant to President
R. Leach, Chemistry and Health Physics Supervisor
R. Spinney, Training Manager
J. Sinclair, Assistant to Vice President (Operations)
8. Buteau, Reactor and Computer Engineering Supervisor
R. Lopriore, Maintenance Supervisor
D. Bauer, State Liason
W. Daley, Assistant to Vice President (Admin / Finance)
R. Ludwick, Operations Support Manager
P. Donnelly, Maintenance Supervisor
J. Gianfrancesco, Construction Superintendent
2.
NRC Attendees
i
T. E. Murley, Regional Administrator
R. W. Starostecki, Director, Division of Reactor Projects
D. Muller, Director, BWR Project Directorate #2, NRR
E. C. Wenzinger, Chief, Projects Branch No. 3
L. E. Tripp, Chief, Reactor Projects Section 3A
W. J. Raymond, Senior Resident Inspector
V. Rooney, Licensing Project Manager
T. B. Silko, Resident Inspector
1
.
. .
.
.
. .
.