ML20210A686

From kanterella
Jump to navigation Jump to search
Responds to Re Proposed Action Statement for SCR Relays.Allowable out-of-svc Time Limit of 48 H Acceptable to Permit Repair of Inoperable Relay.Proposed Action Statement Should Be Revised as Listed
ML20210A686
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 12/06/1985
From: Miraglia F
Office of Nuclear Reactor Regulation
To: Enos J
BABCOCK & WILCOX OPERATING PLANTS OWNERS GROUP
Shared Package
ML20209E108 List:
References
GL-85-10, NUDOCS 8512130559
Download: ML20210A686 (1)


Text

/

'/

UNITED STATES NUCLEAR REGULATORY COMMISSION aI wAswmoTow.o. c.zosss e

....*/

December 6,1985 Mr. J. Ted Enos, Chairman ATWS Standing Committee B&W Owners Group Suite 220 7910 Woodmont Avenue Bethesda, Maryland 20814

Dear Mr. Enos:

SUBJECT:

GENERIC LETTER 85-10 TECHNICAL SPECIFICATIONS FOR B&W RTBs In response to your letter of October 9,1985, the NRR staff has reviewed the S&W Owner's Group proposed Action Statement for SCR relays.

Based on its review, the 'NRR staff concluded that 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is an acceptable allowable out-of-service time' limit to permit the repair of an inoperable SCR relay in Tieu of having to place in trip all SCR relays associated with one channel. However it should be explicitly clear that if two or more SCR relays are inoperable, all SCR relays associated with that channel shall be,

placed in trip within one hour consistent with the guidance provided in Generic Letter 85-10. Accordingly, your proposed Action.',tatement should be revised as follows:

With the number of operable SCR relays one less than the total number of SCR relays it. a channel, restore the inoperable SCR relay to operable status in 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or place the SCRs associated with the inoperable relay in trip in the next hour. With two or more SCR relays inoperable, place all SCR relays associated with that channel in trip in the next hour.

In sumary, if the proposed action statement is revised as indicated above the staff would find it acceptable for B&W plant Technical Specifications of the Oconee design.

kal I