Other: A04824, Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided, A07296, Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 880712, B11677, Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment, B12922, Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 880729, B12980, Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage, ML20151A460, ML20210A244, ML20211B373
|
MONTHYEARB11677, Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment1985-09-0909 September 1985 Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment Project stage: Other A04824, Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided1985-10-11011 October 1985 Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided Project stage: Other ML20211B3731987-02-12012 February 1987 Provides Info Re Implementation Schedules for Compliance W/Requirements of ATWS Rule (10CFR50.62).NRC Should Be Contacted 30 Days After Ltr Receipt Re Implementation Schedules Using Guidance Provided Project stage: Other A06368, Responds to NRC 870212 Request for Addl Info Re Implementation Schedule for Compliance W/Requirements of ATWS rule,10CFR50.62.Mods Will Be Completed by End of Cycle 10 Refueling Outage Scheduled to Begin in June 19891987-03-19019 March 1987 Responds to NRC 870212 Request for Addl Info Re Implementation Schedule for Compliance W/Requirements of ATWS rule,10CFR50.62.Mods Will Be Completed by End of Cycle 10 Refueling Outage Scheduled to Begin in June 1989 Project stage: Request ML20210A2441987-05-0101 May 1987 Reconfirms 851011 Proposed Design Mods to Address 10CFR50.62 Requirements,Per 870319 Commitment to Reevaluate Design.Mods Will Be Installed by Cycle 10 Refueling Outage in June 1989. Review of Mods Requested by 870901 Project stage: Other B12922, Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 8807291988-05-27027 May 1988 Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 880729 Project stage: Other A07296, Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 8807121988-06-27027 June 1988 Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 880712 Project stage: Other ML20151A4601988-07-11011 July 1988 Forwards Responses to Questions on Proposed ATWS Mods,Per NRC 880608 Request.Spare Parts Will Be Kept for All Dss/Atws Mitigating Sys Actuation Circuitry Components Project stage: Other B12980, Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage1988-07-25025 July 1988 Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage Project stage: Other 1987-05-01
[Table View] |
Text
5
)
General offices
.I[,,7.".'. ~,, ""
P.O. Box 270 HARTFORD CONNECTICUT 06141-0270 a
g (203) 665-5000 awar iuma ranaov-=
May 1, 1987 Docket No. 50-336 AO6368 Re: 10 CFR 50.62 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.
20555 Gentlemen:
Millstone Nuclear Power Station, Unit No. 2 ATWS Rule, 10 CFR 50.62 In a letter dated March 19, 1987(1)
Northeast Nuclear Energy Company (NNECO) provided the NRC Staff with additional information with regard to the schedule for implementation of the ATWS rule, 10 CFR 50.62, at Millstone Unit No. 2.
In addition, Reference (1) stated that NNECO would be re-evaluating the design of those modifications being proposed to address the requirements of10CFR50.62atMillgoneUnitNo.2,asdescribedinaletter 1985' NNECO stated that by April 30, 1987, dated October 11, we would inform the Staff of the results of that re-evaluation.
Accordingly, NNECO has reviewed our proposed modifications as outlined in Reference (2) and have decided to reconfirm our design as described in that letter.
As stated in Reference (1),
NNECO intends to proceed with the installation of these modifications with the expectation of bringing Millstone Unit No.
2 into full compliance with 10 CFR 50.62 by the end of the Cycle 10 refueling outage currently scheduled to begin in June, 1989.
As such, Reference (1) requested that the NRC Staff complete their review of our proposed design and respond to NNECO with any comments no later than September 1,
1987.
This will help to ensure that the implementation schedule as proposed above will l
not be adversely impacted.
1)
E.J.Mroczka letter to U.S.
Nuclear Regulatory Commission, dated March 19, 1987," Implementation Schedule for ATWS Rule".
2)
J.F.Opeka letter to E.J. Butcher and J.A.Zwolinski, dated October 11, 1985,"ATWS Rule Schedule Required by 10 CFR 50.62(d)".
8705050043 870501 0
DR ADOCK 0500 6
i g
e-U.S. Nuclear Regulatory Commission A06368/Page 2 May 1, 1987
]
If you have any questions, please contact us.
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY W
tcc
~
E.J.Mr zka O
Senior Vice President n-
- .. -.By: R.P.Werner Vice President cc:
W.T. Russell, Region I Administrator D.H.Jaffe,NRC Project Manager, Millstone Unit No. 2 T.Rebelowski, Resident Inspector, Millstone Unit Nos. I and 2
..