Summarizes 861107 & 13 Telcons & Schedules Future Actions Re Updated Fire Protection Program & App R Safe Shutdown Confirmatory Program.Programs Generally Acceptable.Bnl Will Resume Review of Program During Wk of 870323
ML20209H740
Person / Time
Site: Peach Bottom  
Issue date: 02/03/1987
From: Clark R
Office of Nuclear Reactor Regulation
To: Bauer E
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
References
NUDOCS 8702060126
Download: ML20209H740 (3)


Text

3 FEB 1987 Dockets Nos. 50-277/228 DISTRIBUTION C Docket File NRC PDR L PDR Mr. Edward G. Bauer, Jr.

PD#2 Plant File Vice President & General Counsel RMBernero OGC-Bethesda Philadelphia Electric Company Edordan BGrimes 2301 Market Street JPartlow NThompson Philadelphia, Pennsylvania 19101 RClark SNorris ACRS (10)

Dear Mr. Bauer:

SUBJECT:

FIRE PROTECTION PROGRAM Re:

Peach Bottom Atomic Power Station, Units 2 and 3 Your letter of September 30, 1986 submitted an updated Fire Protection Program and Appendix R Safe Shutdown confirmatory program for Peach Bottom Units 2 and 3.

This submittal has been the subject of a number of discussions during the past several months between our staffs. The purpose of this letter is to sumarize these discussions and the schedule for future actions.

Our preliminary review of your submittal last fall found it generally acceptable.

To complete an in-depth review, we requested in the conference calls of November 7 and 13,1986 three items:

A set of large (roll size) P& ids for all systems used for safe shutdown methods A, B, C and D.

The EPM (Engineering Planning and Management, Inc) analyses of the Peach Bottom safe shutdown capability that were performed in the spring of 1986.

Procedures for any fire requiring utilization of alternative safe shutdown capability.

As requested, you sent a set of the P& ids to our contractor, Brookhaven National Laboratory (BNL). The EPM analyses which are available in your corporate office consist of about six large notebooks of material.

From the discussions with your staff, only a portion of the material is important to our review.

It was decided that the most feasible approach was for us to review the volumes in your corporate offices with your personnel available to explain the analyses. As a result of this review, we may request a copy of specific sections of the EPM analyses. With respect to the procedures, your approach has been to prepare symptomatic type procedures tied into the existing emergency procedures rather than event-type procedures. The procedures for safe shutdown trethods, A, B and C have been prepared and are available; the procedures for method D ore being written. The logical place to review the procedures is at the site.

(We appreciated your offer to bring the personnel and procedures to your corporate office if this would be more convenient to our review).

8702060126 070203 PDR ADOCK 05000277 F

PDR

]

i l.

' l l

Due to prior work commitments, our contractor (BNL) will not be available to resume review of your fire protection program until the week of March 23, 1987 at the earliest. We have tentatively established a schedule that we will be at your corporate offices on Tuesday March 24, 1987 to review the EPM analyses and at the Peach Bottom site on Wednesday and Thursday, March 25 and 26, 1987 to review the procedures, equipment locations, plant modifications being performed during the Unit 2 outage and other facets of your safe shutdown capability. To help us prepare for the site visit, your staff will investigate the feasibility of providing a draft copy of the procedures being prepared for alternate shutdown method D to our contractor about a week prior to the site visit.

Sincerely, Original signed W Richard J. Clark Richard J. Clark, Project Manager BWR Project Directorate #2 Division of BWR Licensing cc: See Next Page DB1: PD#2 DBL:PD Q

DBL

  • Fp' pb SterYtr#

RLlark(cd DP,tM Tler A/3 /87 02/0L/8 S./../87 OFFICIAL RECORD COPY

~

Mr. E. G. Bauer, Jr.

Peach Bottom Atomic Power Station, Philadelphia Electric Company Units 2 and 3 cc:

Mr. Eugene J. Bradley Mr. R. A. Heiss, Coordinator Assistant General Counsel Pennsylvania State Clearinghouse Philadelphia Electric Company Governor's Office of State Planning 2301 Market Street and Development Philadelphia, Pennsylvania 19101 Post Office Box 1323 Harrisburg, Pennsylvania 17120 Troy B. Conner, Jr., Esquire 1747 Pennsylvania Avenue, N.W.

Mr. Thomas M. Gerusky, Director Washington, D.C.

20006 Bureau of Radiation Protection Pennsylvania Department of Thomas A. Deming, Esquire Environmental Resources Assistant Attorney General Post Office Box 2063 Department of Natural Resources Harrisburg, Pennsylvania 17120 Annapolis, Maryland 21401 Mr. Albert R. Steel, Chairman Mr. R. Fleishmann, II, Manager Board of Supervisors Peach Bottom Atomic Power Station Peach Bottom Township R. D. #1 R. D. #1 Delta, Pennsylvania 17314 Delta, Pennsylvania 17314 Mr. G. M. Leitch, Superintendent Nuclear Generation Division b7-1 Philadelphia Electric Company 2301 Market Street Philadelphia, Pennsylvania 19101 Mr. Anthony J. Pietrofitta, General Manager Power Production Engineering Atlantic Electric Post Office Box 1500 1199 Black Horse Pike Pleasantville, New Jersey 08232 Resident Inspector U.S. Nuclear Regulatory Comission Peach Bottom Atomic Power Station Post Office Box 399 Delta, Pennsylvania 17314 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia Pennsylvania 19406

.