Forwards Summary of 860812 Meeting W/Util at Region II Ofc Re Raychem Electrical Splice Installation,Per Insp on 860721-25.List of Attendees Also Encl
ML20209G442
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 08/29/1986
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
References
NUDOCS 8609120473
Download: ML20209G442 (5)


Text

(cicR y

I AUG 2 91986

\\ Georgia Power Company ATTN: Mr. J. H. Miller, Jr.

Presider t P. O. Box 4545 Atlanta, GA 30302 Gentlemen:

SUBJECT:

MEETING

SUMMARY

- V0GTLE FACILITY - DOCKET N0. 50-424 This refers to the technical meeting conducted at your request in the NRC Region II Office on August 12, 1986.

This meeting was held to brief the NRC on the Vogtle Raychem electrical splice installations.

This meeting was held to provide the NRC staff additional technical information pertaining to questions raised during our inspection on July 21-25, 1986, on the Raychem electrical splice installations.

It is our opinion that this meeting was beneficial and has provided a compre-hensive overview of the Vogtle Raychem Splice Installations, specifically, the material presented.

These in-depth presentations will better enable the NRC to conduct its evaluations of this item.

i In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC public Document Room.

Should you have any questions concerning these matters, we will be pleased to discuss them.

Sincerely.

Original Signed by Roger D. Walker Roger D. Walker, Director Division of Reactor Projects

Enclosures:

1.

List of Attendees 2.

Meeting Summary cc w/encls:

NJ. P. O'Reilly, Senior Vice President Nuclear Operations NR. E. Conway, Senior Vice President &

Project Director D. O. Foster, Vice President, Project Support

\\/P.D. Rice,VicePresident, Project Engineering g,

(cc w/encls cont'd - see page 2) g 8609120473 860829 l

PDR ADOCK 05000424 pp l

0 PDR

$66 Georgia Power Company 2

gg g 9 (cc w/encls cont'd) g/R. H. Pinson, Vice President, Project Construction

/J.T.Beckham,VicePresident&

General Manager - Operations

/R.A. Thomas,VicePresident, Licensing VD.S. Read,GeneralManager, f Quality Assurance VC. W. Hayes, Vogtle Quality d.AssuranceManager C. Ramsey, Manager -

. Readiness Review dG.B.Bockhold,GeneralManager, Nuclear Operations 5/ L. Gucwa, Manager, Nuclear Safety and Licensing

/M.H.Googe, Project Construction Manager V'E. D. Groover, Quality Assurance Site Manager -

d. Construction J

A. Bailey, Project Licensing Manager VG. F. Trowbridge, Esq., Shaw, Pittman, Potts and Trowbridge dB.W. Churchill,Esq.,Shaw, 4.Pittman, Potts and Trowbridge E

L. Blake, Jr., Esq., Shaw,

, Pittman, Potts and Trowbridge W.E. Joiner,Troutman, Sanders, Lockerman and Ashmore dJ.G.Ledbetter, Commissioner, Department of Human Resources

/C. H. Badger, Office of Planning d.and Budget D Kirkland, III, Counsel, Office of the Consumer's Utility Council 40.C.Teper,GeorgiansAgainst Nuclear Energy dM.B.Margulies,Esq., Chairman, Atomic Safety and Licensing Board i

Panel 4Dr. O. H. Paris, Administrative Judge Atomic Safety and Licensing Board Panel AG. A. Linenberger, Jr., Administrative Judge Atomic Safety and Licensing Board Panel B. P. Garde, Citizens Clinic, Director Government Accountability Project (bcc w/encls - see page 3)

-Georgia Power Company 3

AUG 2 91986

/ccw/encls:

E. Reis, ELD d)M. Miller,NRR

,d. M. Hill, IE V

dW.Brach,ED0

. Sinkule, RII E. Christnot, RII NRC. Resident Inspector

  • Document Control Desk State of Georgia RII fg, V RII Mb p.

RIL I

RI

$4s m eistnotew MSinkule m nion ur-lee R iker 8/ '7/86 8/3 /86 8/ /86 8/jp86 8/jg/86 8p/86 3

ENCLOSURE 1 LIST OF ATTENDEES Vogtle Technical Meeting August 12, 1986, at 9:30 a.m.

U. S. Nuclear Regulatory Commission Representatives - Region II V. Brownlee, Chief, Projects Branch 3 M. V. Sinkule, Chief, Projects Section 3C T. Conlon, Chief, Plant Systems Section, DRS H. Livermore, Senior Resident Inspector - Construction, DRP Section 3C E. Christnot, Project Engineer, DRP Section 3C A. Ruff, Plant Systems Section Engineer, DRS M. Hunt, Reactor Inspector, Plant Systems Section, DRS N. Merriweather, Reactor Inspector, Plant Systems Section, DRS Georgia Power Company Representatives D. O. Foster, Vice President-Project Support, Georgia Power Company (GPC)

C. Hayes, Quality Assurance Manager, Plant Vogtle B. Harbin, Manager Quality Control - Construction, Plant Vogtle A. Harrelson, Electrical Discipline Manager - Construction, Plant Vogtle C. Justice, Nuclear Operations Maintenance Foreman, Plant Vogtle S. Pietrzyk, Assistant Project Engineer, BPC0 S. Hayter, Electrical Group Supervisor, BPC0 K. Baker, Nuclear Products Manager, Raychem-Menlopark, CA D. Scheafbauer, District Sales Manager, Raychem-Atlanta, GA i

ENCLOSURE 2 Meeting Suninary On August 12, 1986 GPC technical personnel met with NRC Region II technical personnel to discuss the Raychem electrical splice installations at the Vogtle facility. The following subjects were covered:

1.

The total number of splices involving breakout boots (both 3-way and 4-way);

2.

The training of craft personnel, field engineers, and quality control inspectors in the design and installations of Raychem electrical splices; 3.

Quality Assurance Department involvement in the Raychem splice installations.

l Based on GPC's technical briefing of the topics mentioned above, it was evident that GPC is very much involved in identifying the impact on hardware as a result of field installed 3-way and 4-way Raychem splices.

The applicant stated that additional information for NRC review would be available within six weeks.