AUG 2 71986
Docket Nos. 50-424, 50-425
License Nos. CPPR-108 CPPR-109
Georgia Power Company
ATTN: Mr. J. H. Miller, Jr.
President
P. O. Box 4545
Atlanta, GA 30302
Gentlemen:
SUBJECT: NRC INSPECTION REPORT NOS. 50-424/86-66 AND 50-425/86-31
This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by
M. D. Hunt on July 21-25, 1986.
The inspection included a review of activities
authorized for your Vogtle facility.
At the conclusion of the inspection, the
findings were discussed with those members of your staff identified in the
enclosed inspection report.
Areas examined during the inspection are identified in the report. Within these
areas, the inspection consisted of selective examinations of procedures and
representative records, interviews with personnel, and observation of activities
in progress.
Within the scope of the inspection, no violations or deviations were identified.
I
Your attention is invited to unresolved items identified in the inspection
report. These matter will be pursued during future inspections.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and its enclosure
will be placed in the NRC Public Document Room.
Should you have any questions concerning this letter, please contact us.
Sincerely,
Virgil L. Brownlee, Chief
Reactor Projects Branch 3
Division of Reactor Projects
Enclosure:
NRC Inpsection Report
cc w/ enc 1:
(See page 2)
860912O272 860027
ADOCK 0S00
4
\\ \\
.na\\
.
'
. . .
.
,
"
.
Georgia Power Company
2
AUG 2 71986
c w/ encl:
J. P. O'Reilly, Senior Vice President
/NuclearOperations
VR. E. Conway, Senior Vice President &
j Project Director
VD. O. Foster, Vice President, Project
/. Support
P
D. Rice, Vice President, Project
/. Engineering
R
H. Pinson, Vice President, Project
_ j Construction
v J. T. Beckham, Vice President &
General Manager - Operations
. A. Thomas, Vice President,
Licensing
D. S. Read, General Manager,
Quality Assurance
/ C. W. Hayes, Vogtle Quality
Assurance Manager
/W.C.Ramsey, Manager-
Readiness Review
/G.B.Bockhold,GeneralManager,
Nuclear Operations
/L. Gucwa, Manager, Nuclear Safety
and Licensing
/M. H. Googe, Project
j Construction Manager
/ E. D. Groover, Quality
Assurance Site Manager -
/ . Construction
J
A. Bailey, Project Licensing
Manager
/G.F.Trowbridge,Esq.,Shaw,
/ Pittman, Potts and Trowbridge
V B. W. Churchill, Esq., Shaw,
/ Pittman, Potts and Trowbridge
V E. L. Blake, Jr., Esq., Shaw,
/.Pittman,PottsandTrowbridge
J
E. Joiner, Troutman, Sanders,
/ Lockerman and Ashmore
V J'. G. Ledbetter, Consnissioner,
j Department of Human Resources
V C. H. Badger, Office of Planning
/ a6d Budget
VD. Kirkland, III, Counsel,
Office of the Consumer's Utility
/D.C.Teper,GeorgiansAgainst
Council
Nuclear Energy
(cc w/ encl cont'd - see page 3)
,
-
'
.
.
Georgia Power Company
3
cc w/ encl cont'd)
. B. Margulies, Esq., Chairman,
Atomic Safety and Licensing Board
Panel
Dr. O. H. Paris, Administrative Judge
Atomic Safety and Licensing Board
Panel
G. A. Linenberger, Jr., Administrative Judge
Atomic Safety and Licensing Board
/ Panel
V B. P. Garde, Citizens Clinic, Director
Government Accountability Project
)ccw/ encl:
V E. Reis, GS0
/ . M. Hill, IE
. Miller, NRR
W. Brach, ED0
J.Sinkule,RII
7E.Christnot,RII