| ML20209E599 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 06/14/1985 |
| From: | Brownlee V NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Kelly R GEORGIA POWER CO. |
| Shared Package | |
| ML20209E604 | List: |
| References | |
| NUDOCS 8507110640 | |
| Download: ML20209E599 (3) | |
See also: IR 05000424/1985021
Text
_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
OCCcict(
.
.
.
<
.
JUN 14 1985
Georgia Power Company
/ ATTN: Mr. R. J. Kelly
Executive Vice President
P. O. Box 4545
Atlanta, GA 30302
i
Gentlemen:
{
I
'
SUBJECT:
REPORT NOS. 50-424/85-21 AND 50-425/85-21
On May 7 - June 7. 1985, NRC inspected activities authorized by NRC Construction
Permit Nos. CPPR-108 and CPPR-109 for your Vogtle facility. At the conclusion of
l
the inspection, the findings were discussed with those members of your staff
I
identified in the enclosed inspection report.
Areas examined during the inspection are identified in the report. Within these
areas, the inspection consisted of selective examinations of procedures and
representative records, interviews with personnel, and observation of activities
in progress.
Within the scope of the inspection, no violations or deviations were identified.
Should you have any questions concerning this letter, please contact us.
Sincerely,
l5l %yi L. amnkse
Virgil L. Brownlee, Chief
Reactor Projects Branch 2
Division of Reactor Projects
Er> closure:
Ir.spection Report Nos. 50-424/85-21
and 50-425/85-21
cc w/ encl:
(See page 2)
8507110640 850L.4
ADOCK 05000424
[FO/
G
-
/ I
_ _ _ _ _ _ _ _ .
_---
-
_ - - .
JUN 14 196
.
.,
.
,
Georgia Power Company
2
cc w/ enc 1:
/ R. E. Conway, Senior Vice President
Nuclear Power
/0. O. Foster, Vice President and
. General Manager Vogtle Project
/H.H. Gregory,III, General
Manager, Vogtle Nuclear Construction
vG. Bockhold, Jr., Vogtle Plant Manager
/ L. T. Gucwa, Chief, Nuclear Engineer
sRuble A. Thomas, Vice President -
Licensing Vogtle Project
VEd Groover, Quality Assurance
Site Manager
/C. W. Hayes, QA Manager
/J. T. Beckham, Vice President and
General Manager - Operations
/J. A. Bailey, Project Licensing
Manager
/ George F. Trowbridge, Esq.
Shaw, Pittman, Potts and Trowbridge
/ Bruce W. Churchill, Esq.
Shaw, Pittman, Potts and Trowbridge
dErnest L. Blake, Jr., Esq.
Shaw, Pittman, Potts and Trowbridge
/ James E. Joiner, Troutman, Sanders,
Lockerman and Ashmore
JJames.G. Ledbetter, Commissioner
/ Department of Human Resources
/ Charles H. Badger, Office of
Planning and Budget, Management
Review Division
/ eppish Kirkland, III, Counsel
D
Office of the Consumer's Utility
/ Council
/ Douglas C. Teper, Georgians Against
Nuclear Energy
>
J aurie Fowler, Legal Environmental
L
Assistance Foundation
,
vTim Johnson, Executive Director
Educational Campaign for a Prosperous
/Morton B. Margulies, Esq. , Chairman
Administrative Judge, Atomic Safety
and Licensing Board Panel
VDr. Oscar H. Paris, Administrative Judge
, Atomic Safety and Licensing Board Panel
sGustave A. Linenberger, Jr., Administrative
' Judge, Atomic Safety and Licensing Board
Panel
bec w/ enc 1:
(See page 3)
..
c. -
_
'
T-
JUN 141985
..
, , ,
Georgia Power Company
3
bec w/ enc 1:
E. Reis, ELD
M. Sinkule, RII
vNRC Resident. Inspector-
Document Control Desk
State of Georgia
e
t
RI
RI
ankin:bhg
inkule
6/if/85
6/IS/85
,
%
%