ML20209D820

From kanterella
Jump to navigation Jump to search
Forwards Safety Insp Rept 50-271/87-06 on 870303-0406.No Violations Noted.Response to Violation Noted in Insp Rept 50-271/86-25 Re Failure to Complete Inservice Testing Reviewed.Violation Proper & Will Stand
ML20209D820
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 04/23/1987
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Murphy W
VERMONT YANKEE NUCLEAR POWER CORP.
Shared Package
ML20209D823 List:
References
NUDOCS 8704290369
Download: ML20209D820 (2)


See also: IR 05000271/1987006

Text

.

.

APR 2 31987

Docket No. 50-271

Vermont Yankee Nuclear Power Corporation

ATTN: Mr. Warren P. Murphy

Vice President and Manager of Operations

RD 5, Box 169

Ferry Road

Brattleboro, Vermont 05301

Gentlemen:

Subject: Inspection Report No. 50-271/87-06

This refers to the routine resident safety inspection conducted by Mr. W. J. Raymond

of this office on March 3 - April 6, 1987, at the Vermont Yankee Nuclear Power

Station, Vernon, Vermont. The inspection consisted of observation of activities,

interviews with personnel and document reviews. The results of the inspection are

described in the NRC Region I Inspection Report enclosed with this letter and were

discussed with Mr. J. P. Pelletier of your staff at the conclusion of the inspec-

tion.

We have also reviewed your response and the actions taken to correct the violation

brought to your attention in our letter dated February 6, 1987 (Inspection Report

86-25), concerning the failure to complete inservice testing in accordance with

ASME Section XI requirements. After reviewing the additional information provided

in your response, we concluded that our initial assessment was proper and will

therefore stand. This matter will be addressed further by separate correspondence

to determine what additional measures or actions may be required in addition to

those referenced in your March 12, 1987 letter.

Based on a discussion between our inspector and the Technical Support Superinten-

dent or. March 13, 1987, we note that you delayed the start of RHR wear ring in-

spections beyond March 1987 due to the need to process a relief request for meeting

the requirement of Technical Specification 4.7.A.3. This oral notification meets

your commitment as stated in our letter to you dated February 6,1987 transmitting

Inspection Report 86-25. We understand that the RHR pump inspections are now

scheduled to begin during the week of April 20, 1987. Should you plan further

delays in inspections of these pumps beyond April, 1987, please let me know, in

writing, including the basis for the delays.

Within the scope of this inspection, no violations were identified.

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice", a copy of this

letter and the enclosure will be placed in the NRC Public Document Room.

b$00$$73

-

9

-.

i

-

,

>.

,

  • -

Vermont Yankee Nuclear Power 2

Corporation APR 2 3137  !

1

Your cooperation with us is appreciated.

Sincerely,

Original Signed By

Edward C. Wenzinger, Chief

Projects Branch No. 3

Division of Reactor Projects

Enclosure: NRC Region I Inspection Report 50-271/87-06

cc w/ enc 1:

Mr. R. W. Capstick, Licensing Engineer

Mr. J. Gary Weigand, President and Chief Executive Officer

Mr. J. P. Pelletier, Plant Manager

Mr. Donald Hunter, Vice President

Mr. Cort Richardson, Vermont Public Interest Research Group, Inc.

Mr. Gerald Tarrant, Department of Public Service

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

State of New Hampshire

State of Vermont

NRC Resident Inspector

bcc w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

Section Chief, DRP

M. McBride, RI, Pilgrim

H. Eichenholz, SRI, Yahkee

V. Rooney, LPM, NRR

Robert J. Bores, DRSS

Raymon /meo Elsa er W nzin r

4/20/87

4lt } Q h*) $

OFFICIAL RECORD COPY

l

l