ML20209D469

From kanterella
Jump to navigation Jump to search
Requests Delay in Due Date for Response to Generic Ltr 86-06 Re Implementation of TMI Action Item II.K.3.5, Automatic Trip of Reactor Coolant Pumps, Until Jul 1987.Delay Caused by C-E Owners Group Failure to Provide Required Info
ML20209D469
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/20/1987
From: Andrews R
OMAHA PUBLIC POWER DISTRICT
To: Paulson W
Office of Nuclear Reactor Regulation
References
TASK-2.K.3.05, TASK-TM GL-86-06, GL-86-6, LIC-87-255, NUDOCS 8704290290
Download: ML20209D469 (1)


Text

Omaha Public Power District 1623 Harney Omaha, Nebraska 68102 2247 402/536-4000 April 20, 1987 LIC-87-255 Mr. W. A. Paulson, NRC Project Manager PWR Project Directorate #8 Division of PWR Licensing - B U.S. Nuclear Regulatory Commission Washington, D.C. 20555

References:

1.

Docket No. 50-285 2.

Generic Letter 86-06, Implementation of TMI Action Item II.K.3.5, " Automatic Trip of Reactor Coolant Pumps", dated May 29, 1986.

3.

Letter from OPPD (R. L. Andrews) to NRC (F. J. Miraglia) dated August 21, 1986. (LIC-86-419)

Dear Mr. Paulson:

SUBJECT:

Request for Delay to Provide Response Related to Generic Letter 86-06 The Omaha Public Power District (OPPD) was requested by Reference 2 to develop schedules for submittal of information requested in Section IV, Appendix A, of the safety evaluation for the Combustion Engineering Owners Group (CE0G) submittals on Reactor Pump Trip.

By Reference 3, OPPD committed to provide the information by April 1987.

The April date was predicated on the completion of tasks by the CE0G to develop information vital to our response.

OPPD has been informed that the work by the CE0G was not completed in the first quarter of 1987 as anticipated. The CE0G information required to prepare our response will not be available to OPPD until the end of the second quarter of 1987. Accordingly, OPPD respectfully requests that the April 1987 date for submittal of information requested by Generic Letter 86-06 be revised to July 1987.

Please contact us if you have questions.

Sincerely 0704290290 870420 PDR ADOCK 05000285 R. L. Andrews P

PDR Division Manager Nuclear Production RLA/me O

l c:

LeBoeuf, Lamb, Leiby & MacRae QO J. E. Gagliardo, NRC Chief, Reactor Projects Branch t'

gQ P. H. Harrell, NRC Senior Resident Inspector assua emamumeng opponunau

_.