George S. Thomas woo heederW Nuclear Roducnon N:w Hampshire Yankee Division NYN-87057 April 23, 1987 l
United States Nuclear Regulatory Commission l
Washington, DC 20555 Attention: Document Control Desk t
References:
(a) Facility Operating License NPF-56, Docket No. 50-443 (b) USNRC Letter. Dated March 23, 1987, " Inspection Report No. 50-443/87-08", Thomas T. Martin to Robert J. Harrison Subj ect : Response to Inspection Report No. 50-443/87-08 Centlemen In accordance with the requirements of the notice of violation identified in Reference (b), enclosed please find our response to that violation.
Should you have any questions concerning our response, please contact Mr. Warren J. Itall at (603) 474-9574, extension 4046.
Very truly yours, d
Geo e S. Thomas Enclosure cct Regional Administrator U. S. Nuclear Regulatory Commission - Region I 631 Park Avenue King of Prussia, PA 19406 l
Mr. A. C. Corne NRC Senior Resident Inspector Seabrook Station Seabrook, Nil 03874 0704290232 070423
/
I'DH ADUCK 00000443
//'89 0
PDH
/\\ f P.O. Box 300. Seabrook. NH 03874. Telephone (603) 474 9574 l
.___,m__._
._-..- __.______,_____ _ __~ -....--
ENCLOSURE TO NYN-87057 NHY RESPONSE TO NOTICE OF VIOLATION Notice of Violation 87-08-01 Technical Specification Section 6.7.1 requires in part that, written procedures be established, implemented, and maintained covering Emergency Plan implementation.
Emergency Plan implementing procedure ER-1.0, " Classification and Notification of Emergencies at Zero Power", Revision 1, requires in part that notifications of the state authorities of both New Hampshire and Hassachusetts be completed within 15 minutes after the declaration of an Unusual Event.
Contrary to the above, on February 11, 1987, an Unusual Event was declared at 3:30 p.m., however, Massachusetts was not notified until 4:00 p.m., 30 minutes af ter declaring the Unusual Event.
Response
The fact that the Commonwealth of Massachusetts was not notified within 15 minutes after the declaration of the Unusual Event is correct. The delay in notification of the Commonwealth of Massachusetts was due to the uncertainty of the Commonwealth's participation in the emergency planning efforts for l
Seabrook Station.
~
Aa a result of an inittal assessment of activities associated with the declaration of the Unusual Event on February 11, 1987, the following actions l
were implemented:
- 1) Hanagement directives were provided to all Shift Superintendents 1
that, when procedures require the declaration of an emergency class, 1
the State of New Hampshiro and the Commonwon1th of Hannachusetts shall be notified within the required time frame.
i I
l
- 2) An internal evaluation of the activities surrounding this event was j
initiated. The results of this evaluation have been compiled into a f
management report with specific recommendations concerning the 1
event. This report has been issued to all managers who have direct responsibility for the specific recommendations.
continuing review of activities surrounding this event resulted in the i
followir.g additional corrective actions:
i l
- 1) Emergency Response Proceduren have been reviewed and, where necessary, revined to improve guidance to operators in clansification j
of emergencies, notiftention of required organizations and i
termination of emorgencies.
I j
- 2) Training will bo provided for all Shift Superintendents Unit Shift Supervisors, and Operations Management. The training will emphasize the requirements of Emergoney Hosponse proceduren for clannification 4
of an emergency, notification of required organisations, and termina-3 I
tion of the emergency. Tho training is ncheduled to begin in April, 1987, concurrent with tho next 6 week nogment of operator requalift-
{
cation training, and is expected to be completed by June 15, 1987.
l
}
I i
- - - - -