Advises That Util 861105 Schedular Commitments Re Compliance w/10CFR50.62 by End of Second Refueling Outage Acceptable. Review Will Be Completed within 6 Months of Receipt of Plant Specific Info Addressing 14 Items from Safety Evaluation
ML20209C409
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/21/1987
From: Doolittle E
Office of Nuclear Reactor Regulation
To: Mroczka E
NORTHEAST NUCLEAR ENERGY CO.
References
NUDOCS 8702040265
Download: ML20209C409 (4)


Text

.

JAN 2119@

. Docket No.:

50-423 Mr. E. J. Mroczka Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company Post Office Box 270 Hartford. Connecticut 06141-0270

Dear Mr. Mroczka:

SUBJECT:

Mil.l. STONE NUCl. EAR POWER STATION, UNIT NO. 3 ATWS RUI.E-IMPI.EMENTATION Pl.AN

REFERENCE:

1.etter from J. F. Opeka to V. S. Noonan, Millstone Nuclear Power Station, Unit No. 3 ATWS Rule - Implementation Plan, dated November 5, 1986.

In your letter dated November 5, 1986, you stated your intention to comply with the requirements of 10 CFR 50.62 for Millstone Unit 3 by the end of the second refueling outage, scheduled to begin during the third quarter of 1989.

You also stated your intention to submit the plant specific information addressing each of the fourteen items contained in the Staff's Safety Evaluation in the first quarter of 1988.

We have reviewed this information and find the schedular commitments acceptable, although we recognize that implementation will not be complete before the Staff's July 1,1989 pro.jected completion date. The staff expects to complete its review within 6 months of the date of receipt of the plant specific information, addressing each of the fourteen items contained in our Safety Evaluation.

If you have any questions, please contact me at (301) 492-8379.

Sincerely, f$

Elizabeth I.

Doolittle, Pro.iect Manaaer PWR Pro.iect Directorate No. 5 See Previous Concurrence cc: Jerry Mauck Distribution 5 ccket:Filey B. Grimes E. Jordan 0

NRC PDR J. Partlow OEI.D l.ocal PDR N. Thompson M. Rushbrook PD#5 R/F E. Doolittle ACRs (10)

V. N nan 6t?

CA Jttle:ss oa l

1/k/87 1/g/87 1/g/87 2040265 870221 p

ADOCK 05000423 i

PDR

.~

JAM 21 W Docket No.:

50-423 Mr. E. J. Mroczka Senior Vice President Nuclear Engineering and Operations-Northeast Nuclear Energy Company Post Office Box 270

-Hartford, Connecticut- 06141-0270

Dear Mr. Mroczka:

SUBJECT:

MII.I. STONE NUCI. EAR POWER STATION, UNIT NO. 3 ATWS RUI.E-IMPLEMENTATION Pl.AN

REFERENCE:

I.etter from J. F. Opeka to V. S. Noonan, Mill tone Nuclear Power Station, Unit No. 3 ATWS Rule - Implem ntation Plan, dated November 5, 1986.

In your letter dated November 5,1986, you stated your intention to comply with the requiremer.ts of 10 CFR 50.62 for Millston Unit 3 by the end of the second refueling outage, scheduled to begin durin the third quarter of 1989.

You also stated your intention to submit the plan, specific information addressing each of the fourteen items contained in the Staffs Safety Evaluation in the first ouarter of 1988.

We have reviewed this information and find t e schedular commitments acceptable, although we recognize that imp smentation will not be complete before the Staffs July 1, 1989 pro.iected ompletion date. The staff expects to complete its review within 6 months o the date of receipt of the plant specific information, addressing each o the fourteen items contained in our Safety Evaluation.

If you have any questions, please c ntact me at (301) 492-8379.

Sincerely, is Elizabeth L. Doolittle, Project Manager PWR Project Directorate No. 5 Division of PWR I.icensing-A cc: Jerry Mauck Distribution

/

B. Grimes E. Jordan

/J.Partlow Docket File OELD NRC PDR

/

i.ocal PDR N. Thompson M. Rushbrook l

PD#5 R/F E. Doolittle ACRs (10)

V n

l AD/PWR-A DIR:PD#5 tie:ss ERossi VSNoonan 1/j87 1/ /87 1/ /87 l-i

a M

D UNITED STATES I

E

  1. 'n NUCLEAR REGULATORY COMMISSION
E WASHINGTON, D. C. 20555 C,

,e

\\....+*#,

agg g 1 W Docket No.:

50-423 Mr. E. J. Mroczka Senior Vice President Nuclear Engineerino and Operations Northeast Nuclear Energy Company Post Office Box 270 Partford, Connecticut 06141-0270

Dear Mr. Mroczka:

SUBJECT:

Mill. STONE NUCl. EAR POWER STATION, UNIT NO. 3 ATWS RUI.E-IMPl.EMENTATION Pl.AN

REFERENCE:

letter from J. F. Opeka to V. S. Noonan, Millstone Nuclear Power Station, Unit No. 3 ATWS Rule - Implementation Plan, dated November 5, 1986.

In your letter dated November 5, 1986, you stated your intention to comply with the requirements of 10 CFR 50.62 for Millstone Unit 3 by the end of the second refueling outage, scheduled to begin during the third ouarter of 1989.

You also stated your intention to submit the plant specific information addressing each of the fourteen items contained in the Staff's Safety Evaluation in the first quarter of 1988.

We have reviewed this information and find the schedular commitments acceptable, although we recognize that implementation will not be complete before the Staff's July 1,1989 pro.iected completion date. The staff expects to complete its review within 6 months of the date of receipt of the plant specific information, addressing each of the fourteen items contained in our Safety Evaluation.

If you have any questions, please contact me at (301) 49P-8379.

Sincerely.

Elizabe L. Doolittle, Project Manaaer PWR Project Directorate No. 5 Division of PWR l.icensing-A cc: Jerry Mauck

~

l Mr. J. F. Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 3 cc:

Gerald Garfield, Esq.

Ms. Jane Spector Day, Berry & Howard Federal Energy Regulatory Commission City Place 825 N. Capitol Street, NE Hartford, Connecticut 06103-3499 Room 8608C Washington, D.C.

20426 Mr. Maurice R. Scully, Executive Director Mr. Kevin McCarthy, Director Connecticut Municipal Electric Radiation Control Unit Energy Cooperative Department of Environmental Protection 268 Thomas Road State Office Building Groton, Connecticut 06340 Hartford, Connecticut 06115 Robert W. Bishop, Esq.

Corporate Secretary Northeast Utilities Post Office Box 270 Hartford, Connecticut 06141 Thomas Shedlosky Senior Resident Inspector Office U. S. Nuclear Regulatory Commission Millstone III P. O. Box 811 Niantic, Connecticut 06357-08.

Mr. Michael L. Jones, Manage ~r Project Management Department Massachusetts Municipal Wholesale Electric Company Post Office Box 426 ludlow, Massachusetts 01056 Regional Administrator U. S. NRC, Region I C31 Park Avenue King of Prussia, Pennsylvania 19406 l

Mr. Karl Abraham l

Public Affairs Office, Region I I

U. S. Nuclear Regulatory Commission, King of Prussia, Pennsylvania 19406 i

l l

l l

l

-