Submits Response to GL 98-01,Suppl 1 Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701. Disclosure Encl
ML20209B357
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 06/28/1999
From: Scherer A
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-98-01, GL-98-1, NUDOCS 9907060421
Download: ML20209B357 (4)


Text

/

A. Edward Scherer

~ gpa spumtRN CAtifORMA

,,,, J EDISON An LD/SO V IVf1RMTIOV4L*' Company

  1. =bom i l

June 28,1999 U.S. Nuclear Regulatory Commission ,

Attention: Document Control Desk  !

Washington, D.C. 20555 Gentlemen:

Subject:

Docket Nos. 50-361, and 50-362 Response to Generic Letter 98-01, Supplement 1

" Year 2000 Readiness of Computer Systems at Nuclear Power Plants" San Onofre Nuclear Generating Station, Units 2 and 3

Reference:

Generic Letter 98-01, Supplement 1, " Year 2000 Readiness of Computer ,

Systems at Nuclear Power Plants," issued May 11,1998. l The purpose of this letter is to respond to the Nuclear Regulatory Commission's request for information regarding Year 2000 readiness at nuclear power plants. Generic Letter 98-01 requested a response on the status of facility Y2K readiness by July 1,1999.

On January 14,1999, the Commission issued Supplement 1 to Generic Letter 98-01 to modify the request for information in the original generic letter.

The Supplement stated:

"In responding to this supplement to GL 98-01, the addressee should confirm Y2K readiness of the facility with regard to those systems within the scope of the license and NRC regulations, and those systems required for continued operation of the facility after January 1,2000. For those systems which are not Y2K ready as of July 1,1999, the addressee should provide a status and completion schedule for achieving readiness by the year 2000."

in response, Southern California Edison is voluntarily reporting facility readiness as outlined in Supplement 1 to Generic Letter 98-01. Enclosed is the Year 2000 Readiness Disclosure for San Onofre Units 2 and 3, reporting the status of facility readiness. This 34 disclosure is submitted under the guidelines of the " Year 2000 Information and I Readiness Disclosure Act"(Public Law 105-271). /

~

9907060421 990628 PDR ADOCK 05000361 p PDR

/O P. O. Box 128 San Clemente. CA 92674-C128 949 368-7501 Fax 949 36&7575

. 1 Document Control Desk Generic Letter 98-01, Supplement 1 is not applicable to San Onofre Unit 1 because Unit 1  ;

has permanently ceased operations and SCE has certified that fuel has been permanently i removed from the reactor.

If you have any further questions on this subject, please feel free to call me or Jack  :

Rainsberry at (949) 368-7420.

l l

Sincerely,

,, 41 l

l l

cc: E. W. Merschoff, ft jonal Administrator, NRC Region IV l J. A. Sloan, NRC m- tior Resident inspector, San Onofre Units 2 & 3 )

L. Raghavan NRC Froject Manager, San Onofre Units 2 and 3  !

Nuclear Energy Institute

I l

ENCLOSURE Year 2000 Readiness Disclosure l

l

l Year 2000 Readiness Disclosure l This Year 2000 readiness disclosure is made for San Onofre Units 2 and 3 under the " Year 2000 Information and Readiness Disclosure Act" (Public Law 105-271).

This disclosure addresses the Y2K readiness ~of the facility with regard to those systems within the scope of the license, NRC regulations, and other systems required for continued operation of the facility after January 1,2000. A facility that is "Y2K Ready" has followed a prescribed program to identify and resolve Y2K issues so the facility can operate reliably while meeting commitments.

San Onofre Nuclear Generating Station has conducted a Year 2000 readiness program similar to that outlined in Nuclear Utility Year 2000 Readiness. NEl/NUSMG 97-07. The program applies to software, hardware and firmware whose failure due to a Y2K problem J would prevent the performance of the safety function of a structure, system or component. I Additionally, the program applies to any software, hardware, or firmware whose failure due to a Y2K problem would prevent continued operation of the nuclear facility well beyond December 31,1999. The facility pro 0 ram also includes identifying and, where appropriate, remediating embedded systems. The program provided for risk management efforts and development of contingency plans for key rollover dates.

The Y2K readiness program has been completed for those systems required for operation of San Onofre Units 2 and 3. Southern California Edison believes that San Onofre Units 2 and 3 are "Y2K Ready." Further, contingency plans have been developed to mitigate the impact )

of Y2K-induced events at key rollover dates.