.2, Fsbruary 23, 1987
' Georgia Power Company-ATTN:
Mr. James P. O'Reilly Senior Vice President-Nuclear Operations P. O. Box 4545 Atlanta, GA 30302 Gentlemen:
Ha4
SUBJECT:
V0GTLE ELECTRIC GENERATING PLANT EXAMINATION REPORT +94/0L-86-02 The NRC administered examinations on October 21, 1986, November 12-13, 22-26, 1986, and December 1-5, 1986, to employees of your company who had applied for licenses to operate the Vogtle Electric Generating Plant.
At the conclusion of the written examination, a copy of the exam was left with your staff; at the conclusion of the site visit, preliminary findings on the operating examinations were discussed with those members of your staff identified in the Examination Report, Enclosure 1.
Copies of the written examination questions and answer key are included in this report as Enclosure 2.
Facility comments regarding the written examination are included in this report as Enclosure 3.
' In-accordance with 10 CFR 2.790(a), a copy of this letter and its enclosures will be placed in NRC's Public Document Room.
Should you.have any questions concerning this letter, please contact us.
Sincerely, (Original signed by V.L. Brownlee) i-Virgil L. Brownlee, Chief Reactor Projects Branch 2 DivisionofReactorProjects l
Enclosures:
l 1.
Exam Report 50-424/0L-86-02 l-2.
R0/SR0 Exam Questions & Answer Key l
3.
Facility Comments cc w/encls 1 & 3:
l-J. Badgett, Corporate Training Director G. Bockhold, Plant Manager cc w/encls 1, 2, & 3:
R. Rushton, Site Training Director i
bec w/encls:
(See page 2) l
(
um