In Reply Refer To:
il M Dockets:
50-313 50-368 Arkansas Power & Light Company ATTN: Mr. Gene Campbell Vice President, Nuclear Operations P. O. Box 551 Little Rock, Arkansas 72203
SUBJECT:
ACCEPTANCE OF CHANGES TO THE OPERATIONS QUALITY ASSURANCE PROGRAM MANUAL FOR ARKANSAS NUCLEAR ONE (ANO), UNITS 1 AND 2 Gentlemen:
We have reviewed the changes addressed in Revisions 7 and 8 of the QA program description for ANO, Units 1 & 2 and find that they continue to meet the requirements of 10 CFR 50, Appendix B; therefore, the changes are acceptable.
If there are changes to other operative QA commitments existing in docketed correspondence outside of the SAR QA program description, you are obligated to notify this office.
Implementing such changes should be based on 10CFR50.54(a)(3).
You are reminded that Unit 1 USAR Table 1-2 and Unit 2 USAR Table 3.2-6 are considered part of your Quality Assurance Program. Changes to these table are governed by 10 CFR 50.54(a)(3).
odginst s!gned BY E. H. Johnson Eric H. Johnson, Director Division of Reactor Safety and Projects cc:
J. M. Levine, Director Site Nuclear Operations Arkansas Nuclear One P. O. Box 608 Russellville, Arkansas 72801 Arkansas Radiation Control Program Director bcc distrib. by RIV:
RPB RRI R. D. Martin, RA R&SPB Section Chief (RPB/B)
D. Weiss, RM/ALF RIV DRSP RSB Project Inspector J. R. Boardman l-OS/RSBq?/
C/05/RSBM RSB DRSP %
JRBoardman:cnm DMHunnicutt REIreland EHJohnson l
3/6/87 3/13 /87 3 /13 / 8 7 3/lb/87 8703190254 870317 l