Provides Disposition of Human Factors Findings Re Technical Support Ctr (Tsc).Resolution of Findings Not Practical within Constraints of Existing TSC Size.Const Schedule for Larger TSC Will Be Provided by 870701
ML20207Q560
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 01/19/1987
From: Leblond P
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
2592K, NUDOCS 8701270546
Download: ML20207Q560 (2)


Text

r

,_a-7"N r

./

/

\\ CORNROnwealth EclisOn

(

_ f Cne First Nabonel Plaza, Chcago, ll5nois

\\,

/ Address Reply to: Post Omco Box 767

%/ Chcago, Illinois 60690 0767 January 19, 1987 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Zion Nuclear Power Station Units 1 and 2 Emergency Response Facilities NRC Docket Nos.50-295 and 50-304 References (a): October 31, 1986 letter from P. C. LeBlond to H. R. Denton (b): June 12, 1984 letter from S. A. Varga to D. L. Farrar (c): June 22, 1984 letter from R. N. Cascarano to H. R. Denton

Dear Mr. Denton:

Reference (a) transmitted to the NRC a copy of Commonwealth Edison Company's " Final burrimary Report of the Human Factor Review for the Zion Station Emergency Response Facilities". This document was provided in response to the commitments made in references (b) and (c).

Reference (a) also stated that the human factors findings regarding the Technical Support Center (TSC) were undergoing additional evaluations to determine the appropriate resolutions. This letter is providing the disposition of these findings regarding the TSC.

The report transmitted with reference (a) identified a number of findings regarding the overall size of Zion's TSC.

This issue has been carefully reviewed since the issuance of reference (a).

The conclusion of this review is that the resolution of these findings is not practical within the constraints of the existing TSC's size. Therefore, Commonwealth Edison Company intends to construct a new, larger TSC for Zion Station.

The overall design process has been initiated for this effort. The' specific human factors concerns discussed in reference (a) will be incorporated into the new TSC design effort as part of the design's human factors review.

8701270546 870119

'0 PDR ADOCK 05000295 iQ F

PDR

\\

r

, s.

o' Mr. H. R. Denton January 19, 1987 This construction project is a major undertaking and will involve substantial amounts of preplanning, financial analysis and interface with numerous contractors. Therefore, Conunonwealth Edison Company will develop a construction schedule and provide it to the NRC by July 1, 1987.

Please address any further questions you may have regarding this issue to this office.

Very truly yours, e.,

P. C. LeBlond Nuclear Licensing Administrator la cc: Zion Resident Inspector J. A. Norris - NRR Regional Administrator - RIII 2592K

.