Notifies That Commission Has Approved Recommendation to Approve Request from Util for Extension of 851130 Deadline for Completion of Equipment Qualification Program
ML20207P325
Person / Time
Site: 05000000, Shoreham
Issue date: 11/14/1985
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Dircks W, Plaine H
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO), NRC OFFICE OF THE GENERAL COUNSEL (OGC)
Shared Package
ML20205M922 List:
References
FOIA-86-810 NUDOCS 8701150412
Download: ML20207P325 (1)


Text

ACTION - Denton, NRR

[meeg'o,,

UNITED 5TATES CyS: Dircks y

NUCLEAR REGULATORY COMMISSION Roe

' y WASHINGTON, D.C. 20ssa Rehm o

Stello S* * *l * /

uGCunnine: ham Murley oniCE or mE RCaruso November 14, 1985 SECRETARY Taylor MDORANDW FOR: ~

William J. Dircks Executive Director for Operations Herzel H.E. Plaine

)

9 General Counsel 1 )

FRCH:

Sanuel J. Chilk, Secre g

2-SUBJEcr SECY-85-336 - DNIBONMD TNL QUALIFICATION (EQ) EXTDSION OF THE NOVENBER 30, 1985 DEADLINE FOR SHOREHAM NUCLEAR POWER STATION

'Ihis is to advise you that the Camission (with all Ccmnissioners agreeing) has approved your reu.. dation to approve the request frcn Iong Island Lighting Ccmpany for an extension in the Nevernber 30, 1985, deadline for ocmpletion of their equipnent qualification program.

Mr. John Iecoard, Jr. was advised by letter (attached) on Novernber 14, 1985 of this result.

The staff should proceed to issue the appropriate license amendments to extend the dadline to D-=nhar 31, 1985.

(ID0/NRR)

(SECY Suspense: 11/30/85)

Attachment:

As stated I

cc: Chairman Palladino Ca missioner Roberts Cm missioner Asselstine Camissioner Bernthal Ccamissioner Zech g,.d Off. EDO OPE j

m=....v.g.......,,[j~,,,,

Dato.....d.,

\\

8701150412 870115 PDR FOIA WILLIAM 86-810 PDR