ML20207P269
| ML20207P269 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 12/31/1986 |
| From: | Andrews R OMAHA PUBLIC POWER DISTRICT |
| To: | Gagliardo J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| LIC-86-698, NUDOCS 8701150329 | |
| Download: ML20207P269 (2) | |
Text
-
Omaha Public Power District 1623 Harney Omaha. Nebraska 68102-2247 402/536-4000 December 31, 1986 LIC-86-698
$$$bb vj
>\\>.
L'"-2toa7
- t Mr. J. E. Gagliardo, Chief im
['
UO Reactor Projects Branch i
J U. S. iiuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011
References:
1.
Docket No. 50-285 2.
Inspection Report 50-285/86-14 dated July 3, 1986 3.
Letter from OPPD (R. L. Andrews) to NRC (J. E. Gagliardo) dated August 2, 1986 (LIC-86-393)
SUBJECT:
Additional Information Concerning Item 285/8614-01
Dear Mr. Gagliardo:
In Reference 3, the Omaha Public Power District responded to a violation on the failure to maintain cable and cable tray installations in accordance with design documentation. A series of corrective actions were provided, one of which was to implement a computerized cable and conduit schedule.
The implementation schedule given for this step was December 31, 1986. The purpose of this letter is to inform you of progress made to date, and to revise the implementation schedule accordingly.
At the present time, OPPD has a consultant assisting with this effort.
Software development is 80% complete. The cable data collection effort is 75% complete.
The cable routing data collection is 50% complete.
To date, approximately 2500 manhours have been expended on data collection and soft-ware development.
Because the data included in the program is safety related, an independent verification of data collection and data entry is being performed. Additionally, software development is being done in accordance with OPPD's software QA procedures.
These requirements have extended the expected implementation date from December 31, 1986, to j
March 31, 1987.
8701150329 861231 DR ADOCK 05000285 PDR i b fcoot G
/
4% Sl24 LIT ployfTWnt with LQUdl Opportunity Md@ f f9'idit*
y Mr. J. E. Gagliardo LIC-86-698 Page Two OPPD will continue toward resolution of this task.
If any additional delays are encountered, OPPD will keep your office informed.
If you have further questions concerning this matter, please do not hesitate to contact us.
Sincerely,
/
d
. L. Andrews
/s Division Manager Nuclear Production RLA/DJM:rge c: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Ave., N.W.
Washington, DC 20036 Mr. D. E. Sells, NRC Project Manager Mr. P. H. Harrell, NRC Resident Inspector Mr. W. Paulsen, NRC Project Manager
,,. -.